Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Executive Engineer vs Abhiram Infra Projects Private Limited
2025 Latest Caselaw 10832 Kant

Citation : 2025 Latest Caselaw 10832 Kant
Judgement Date : 28 November, 2025

[Cites 0, Cited by 0]

Karnataka High Court

Executive Engineer vs Abhiram Infra Projects Private Limited on 28 November, 2025

                                            -1-
                                                    NC: 2025:KHC:49600-DB
                                                       WA No. 1549 of 2024


                HC-KAR




                    IN THE HIGH COURT OF KARNATAKA AT BENGALURU

                         DATED THIS THE 28TH DAY OF NOVEMBER, 2025

                                         PRESENT

                      THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE

                                           AND

                          THE HON'BLE MR. JUSTICE C.M. POONACHA

                           WRIT APPEAL NO. 1549 OF 2024 (GM-TEN)

               BETWEEN:
               1.   EXECUTIVE ENGINEER
                    KARNATAKA URBAN WATER SUPPLY
                    AND DRAINAGE BOARD
                    (KUWS & DB)
                    M.G. ROAD, RAVINDRA NAGAR
                    HASSAN - 573 202
                    KARNATAKA

               2.   KARNATAKA URBAN WATER
                    SUPPLY AND DRAINAGE BOARD
                    (KUWS & DB)
                    M.G. ROAD, RAVINDRA NAGAR
Digitally           HASSAN - 573 202
signed by
AMBIKA H B          ALSO AT:
Location:           #5, JALABHAVAN, 1ST STAGE
High Court          1ST PHASE, BTM LAYOUT
of Karnataka        BANNERGHATTA ROAD
                    BANGALORE - 560 029
                    (REPRESENTED BY EXECUTIVE ENGINEER)
                                                             ...APPELLANTS
               (BY SRI VEERESH R. BUDIHAL, ADVOCATE)

               AND:
               1.   ABHIRAM INFRA PROJECTS PRIVATE LIMITED
                    A COMPANY INCORPORATED UNDER
                                 -2-
                                           NC: 2025:KHC:49600-DB
                                            WA No. 1549 of 2024


 HC-KAR



     THE COMPANIES ACT, 1956
     HAVING ITS OFFICE AT
     C-81, FLAT No.402
     SRI JYOTHI NILAYAM
     MADHURA NAGAR
     HYDERABAD - 500 038
     TELANGANA INDIA
     (REPRESENTED BY ITS AUTHORIZED
     REPRESENTATIVE
     S. VENKATA RAMANA REDDY)

2.   M/S AXIS BANK LIMITED
     HAVING BRANCH AT:
     6-3-879/B, G. PULLA REDDY BUILDING
     GREENLANDS
     BEGUMPET ROAD
     HYDERABAD - 500 016
     (REPRESENTED BY ITS
     BRANCH MANAGER)
                                         ...RESPONDENTS
(SRI. ROHAN VEERANNA TIGADI, ADVOCATE FOR C/R-1)

     THIS WRIT APPEAL IS FILED UNDER SECTION 4 OF THE
KARNATAKA HIGH COURT ACT PRAYING TO SET ASIDE THE
ORDER DATED 27.08.2024 PASSED BY THE LEARNED SINGLE
JUDGE OF THIS HON'BLE COURT IN WRIT PETITION No.18245/2021
(GM-TEN) AND FURTHER TO DISMISS THE SAID WRIT PETITION &
ETC.

    THIS APPEAL, COMING ON FOR ORDERS, THIS DAY,
JUDGMENT WAS DELIVERED THEREIN AS UNDER:

CORAM: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
       and
       HON'BLE MR. JUSTICE C.M. POONACHA

                       ORAL JUDGMENT

(PER: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE)

1. For the reasons stated in the application - I.A No.1/2025, the

same is allowed. The delay in filing the recall application is

NC: 2025:KHC:49600-DB

HC-KAR

condoned. Since the office objections have been cured, the order

dated 24.04.2025 dismissing the appeal is recalled. The appeal is

restored to its file. Accordingly, I.A No.2/2025 is allowed.

2. Issue notice. Mr. Rohan Veeranna Tigadi, learned counsel

accepts notice for respondent No.1.

3. The appellants have filed the present appeal impugning an

order dated 27.08.2024 passed by the learned Single Judge in

Writ Petition No.18245/2021 (GM-TEN).

4. The said petition was preferred by respondent No.1 [the

Contractor] seeking return of the original Performance Bank

Guarantee dated 28.06.2019 for a sum of Rs.1,41,25,600/- and

the original Additional Performance Bank Guarantee dated

28.06.2019 for a sum of Rs.52,20,000/-. Additionally, the

Contractor also prayed for refund of the bid security amount of

Rs.35,32,000/- along with interest at the rate of 18% per annum

from 04.01.2019 till the date of realisation.

5. The controversy involved has arisen in the following factual

context:

NC: 2025:KHC:49600-DB

HC-KAR

6. The appellants had invited tender on 01.03.2014 for the

purpose of executing the work of laying of sewer network with

construction of manhole chambers, construction of 2.64 MLD

capacity Sewerage Treatment Plant and 0.15 KLD capacity septic

tank with allied components, providing and laying of sewer lines

across railway track and national highway under the Underground

Development Scheme at Birur Town, Hassan, [hereafter referred

to as "Birur Project"]. The Contractor has furnished his bid

pursuant to the said notice. The said bid was accepted in terms of

a letter of acceptance dated 03.11.2014 and the contract for

executing the said work was awarded to the Contractor at a price

of Rs.23,54,25,125/-. Thereafter, on 01.12.2014, the parties

entered into a formal agreement setting out the terms and

conditions of the contract.

7. There is no dispute that the Contractor successfully executed

the Birur Project and discharged his performance and obligations.

The appellants also cleared the Contractor's final bill. However,

the appellants failed to return the bank guarantees and refund the

bid security amount. Admittedly, the said amount was required to

be refunded to the Contractor as it had successfully completed the

NC: 2025:KHC:49600-DB

HC-KAR

Birur Project. The concerned officers of appellant No.2 authority

had also recommended return of the bank guarantees and the bid

security furnished by the Contractor.

8. Notwithstanding the above, by a letter dated 06.09.2019, the

appellants communicated their decision not to release the bank

guarantees on the ground that the Contractor had been awarded

another contract in respect of UGD scheme to be constructed by

the Contractor at Chikkamagaluru [Chikkamagaluru Project]. It is

stated that in terms of the said contract, the Contractor was

required to furnish a bank guarantee which the Contractor had

furnished but, the same had expired on 14.11.2014. The

appellants thus, decided to withhold return of the Performance

Bank Guarantees and the bid security furnished in relation to the

Birur Project on the ground that the bank guarantee given for

Chikkamagaluru Project had expired.

9. It is the appellant's case that in terms of the contract entered

into between the parties in respect of the Chikkamagaluru Project,

the appellants could retain the said bank guarantees. The

appellants relied on clause 49.4 of the contract relating to

NC: 2025:KHC:49600-DB

HC-KAR

Chikkamagaluru Project. The said clause as set out in the

impugned judgment is reproduced below:

"49.4 Contractor's Failure to Carry out Instructions

In case of default on the part of the Contractor in carrying out such instructions within a reasonable time, the Employer shall be entitled to employ and pay other persons to carry out the same and if such work is work which, in the opinion of the Engineer, the Contractor was liable to do at his own cost under the Contract, then all costs consequent thereon or incidental thereto shall, after due consultation with the Employer and Contractor, be determined by the Engineer and shall be recoverable from the Contractor by the Employer and may be deducted from any monies due or to become due to the Contractor and the Engineer shall notify the Contractor accordingly, with a copy to the Employer."

10. The learned Single Judge found that recourse to clause 49.4

was not available as there was no material placed on record to

substantiate that any amount was determined as recoverable from

the Contractor by the Engineer.

11. The learned counsel appearing for the appellants specifically

contends that the only question to be considered is whether the

appellants could withhold any amount payable to a person under a

contract on account of debts owed by the said person in relation to

another contract. He submits that the impugned judgement would

NC: 2025:KHC:49600-DB

HC-KAR

set an erroneous precedent, which would curtail the right of the

appellants to withhold the amounts notwithstanding that the person

to whom the amounts are payable owes a debt to the appellants.

12. In our view, the said question does not arise in the present

appeal. The learned Single Judge has allowed the writ petition on

the finding that there was no material to indicate that any

determined debt was owed by the Contractor to the appellants.

The petition was not allowed on the basis of any general

proposition as canvassed by the learned counsel for the

appellants.

13. The learned counsel for the appellants fairly states that the

same be clarified that the impugned order has been rendered in

the facts of the present case. We have no hesitation in accepting

the said request.

14. In view of the above, we dispose of the present appeal by

clarifying that the impugned order has been rendered by the

learned Single Judge in the given facts of the present case.

NC: 2025:KHC:49600-DB

HC-KAR

15. The pending interlocutory applications also stand disposed

of.

Sd/-

(VIBHU BAKHRU) CHIEF JUSTICE

Sd/-

(C.M. POONACHA) JUDGE

AHB

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter