Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sri Jayanth Balakrishna vs Sri B Pradeep
2025 Latest Caselaw 5964 Kant

Citation : 2025 Latest Caselaw 5964 Kant
Judgement Date : 29 May, 2025

Karnataka High Court

Sri Jayanth Balakrishna vs Sri B Pradeep on 29 May, 2025

Author: M.G.S.Kamal
Bench: M.G.S.Kamal
                         -1-




  IN THE HIGH COURT OF KARNATAKA AT BENGALURU

       DATED THIS THE 29TH DAY OF MAY, 2025

                      PRESENT

       THE HON'BLE MRS JUSTICE K.S.MUDAGAL

                         AND

        THE HON'BLE MR JUSTICE M.G.S.KAMAL

       REGULAR FIRST APPEAL NO.1473 OF 2012
                       C/W
       REGULAR FIRST APPEAL NO.1922 OF 2012

IN R.F.A. NO. 1473 OF 2012

BETWEEN:

SRI. JAYANTH BALAKRISHNA
S/O (LATE) JUSTICE H.G. BALAKRISHNA
RETD. JUDGE, HIGH COURT OF KARNATAKA
AGED ABOUT 54 YEARS
NOW R/O 1362, 3RD CROSS
JUDICIAL LAYOUT, GKVK POST
BANGALORE - 560 065.
                                         ... APPELLANT

(BY SRI. JAYANTH BALAKRISHNA PARTY-IN-PERSON-PH)

AND:

SRI. B. PRADEEP
AGED ABOUT 51 YEARS
PROPRIETOR OF POOJA CONSTRUCTIONS
R/O NO.9, 4TH MAIN ROAD
S.S. ASHRAM ROAD, HEBBAL
BANGALORE - 560 024.
                                       ... RESPONDENT

(BY SRI. VENKATESH R. BHAGAT., ADVOCATE-VC)

    THIS REGULAR FIRST APPEAL IS FILED UNDER SECTION
96 OF CPC., AGAINST THE JUDGMENT AND DECREE DATED
                           -2-




21.05.2012 PASSED IN O.S.NO.915/2002 ON THE FILE OF THE
XIX ADDITIONAL CITY CIVIL AND SESSIONS JUDGE
BANGALORE CITY, DISMISSING THE SUIT FILED FOR
RECOVERY OF MONEY.

R.F.A. NO.1922 OF 2012

BETWEEN:

SRI. B. PRADEEP
AGED ABOUT 52 YEARS
PROPRIETOR OF POOJA CONSTRUCTIONS,
R/O NO.9, 4TH MAIN ROAD,
S.S. ASHRAM ROAD, HEBBAL
BANGALORE-560 024.
                                           ... APPELLANT

(BY SRI. VENKATESH R. BHAGAT., ADVOCATE)

AND:

SRI. JAYANTH BALAKRISHNA
S/O LATE JUSTICE H.G. BALAKRISHNA,
RETD. JUDGE
AGED ABOUT 54 YEARS
R/AT NO.1411, 8TH MAIN,
JUDICIAL LAYOUT,
BANGALORE - 560 065.
                                       ... RESPONDENT

(BY SRI. JAYANTH BALAKRISHNA (PARTY-IN-PERSON)(PH)

     THIS REGULAR FIRST APPEAL IS FILED UNDER SECTION
96 OF CPC., AGAINST THE JUDGEMENT AND DECREE DATED
21.05.2012 PASSED IN O.S.NO. 915/2002 ON THE FILE OF THE
XIX ADDITIONAL CITY CIVIL AND SESSIONS JUDGE,
BANGALORE, DISMISSING THE SUIT FOR RECOVERY OF
MONEY.

     THESE REGULAR FIRST APPEALS HAVING BEEN
RESERVED FOR JUDGMENT COMING ON FOR PRONOUNCEMENT
THIS DAY, M.G.S. KAMAL J., DELIVERED/PRONOUNCED THE
FOLLOWING:
                                  -3-




CORAM:      HON'BLE MRS JUSTICE K.S.MUDAGAL
            AND
            HON'BLE MR JUSTICE M.G.S.KAMAL

                           CAV JUDGMENT

(PER: HON'BLE MR. JUSTICE M.G.S.KAMAL)

These regular first appeals are by the plaintiff as well as

by the defendant being aggrieved by the judgment and decree

dated 21.05.2012 passed in O.S.No.915/2002 on the file of XIX

Additional City Civil and Sessions Judge, Bangalore City

(hereinafter referred to as 'trial Court') by which the trial Court

has dismissed the suit of the plaintiff and has also rejected the

counterclaim set up by the defendant.

2. Parties are referred to as per their original rankings in

the suit.

3. Brief facts of the case of the plaintiff:

Plaintiff filed the above suit for judgment and decree

directing the defendant to pay Rs.17,48,000/- together with

the cost, current and future interest @ 18% per annum

contending inter-alia that;

(a). Plaintiff being desirous of putting up a residential building on his property bearing No.1411, 8th main, Judicial Layout, Opp. Jakkur Flying School, Bangalore, had engaged services of one Mr.Suresh

Babu, Engineering Consultant as an architect for the project, who as agreed had obtained and furnished all engineering details, drawings, permissions and sanctions from the Local Authority for the purpose of construction of a residential building measuring 5,275 sq. ft.

(b). The said architect had floated tenders for turnkey construction consisting of works. The estimated cost of construction that was submitted by the architect prior to the commencement of the project was Rs.37,63,000/- while the total cost of construction estimated by the architect including plumbing and electrical work was Rs.42,43,000/.

(c). In response, three contractors had submitted their tenders. That though one M/s.Rashmi Construction was the lowest bidder, the architect finally recommended defendant as a contractor on the premise that the said M/s.Rashmi Construction had withdrawn the tender and of the remaining two, defendant was the lowest. Plaintiff accordingly accepted the recommendation.

(d). That the defendant and the said architect had earlier jointly worked on several other projects. The plaintiff from the inception had found that there was a collusion between the architect and the defendant with an intention to defraud the Plaintiff.

(e). The plaintiff paid an advance of Rs.4,00,000/-

on      25.01.1999   to     the    defendant           for   the





commencement           of     the     work.     The      defendant

presented the first bill dated 23.04.1999. The architect had verified the measurement at the site and had certified the same and on his certification, the plaintiff made payment to avoid any delay in the work.

(f). That the second bill dated 28.03.2000 was presented after a gap of 11 months for a huge sum of Rs.27,70,000/-. By this time, the plaintiff had suspected the bonafides of both the architect and the defendant. Prior to submission of second bill, the plaintiff had requested the architect to physically verify the said bill at the construction site making necessary inspections, measurements and discussions together with the plaintiff and until then the said bill shall not be certified. The architect in collusion with the defendant had certified the second bill within 15 days for a sum of Rs.29,70,000/- while the first bill which was only for a smaller sum of Rs.4,80,000/-, had been certified after more than one and a half months of its presentation. The Plaintiff had no other option but to pay the said second bill amount.

(g) Subsequently on a separate physical verification of the measurements of the site, the plaintiff found that the quantity of the work actually done was far less than what was noted in the bill. The quality of the work was inferior and contrary to the specification. Upon being questioned by the plaintiff

about impropriety, the architect had asked the plaintiff to engage the services of some other architect. As such, the contract between the plaintiff and the architect stood terminated during the month of April 2000. Plaintiff had accordingly approached another architect to execute the work.

(h). Defendant had raised the third bill dated 06.08.2000 for Rs.14,20,000. The plaintiff paid the amount towards the said bill.

(i). Plaintiff terminated the service of defendant after realizing the fraud that was played on him by the defendant in collusion with the said Architect.

(j). Defendant had received a sum of Rs.13,10,000/-

in excess from the plaintiff compared to what the defendant was legitimately entitled for the work executed. That the defendant did not execute any tender work with respect to woodwork, paving and flooring, painting works. 50% of the miscellaneous work were not performed by the defendant under the miscellaneous category. The defendant had also removed several tender item works and had billed them at a higher rate as non-tender items without the knowledge of the plaintiff. In addition, defendant had also performed certain non-tender works which he had submitted as a part of the bill.

(k). It was agreed between the plaintiff, defendant and the architect that with regard to non-tender item works site observation and rupee rate analysis based

on the prevailing market rate would be applied. That the non-tender items claimed by the defendant in the bill were not discussed by the plaintiff, architect and defendant.

(l). Plaintiff had engaged the services of one Mr.D.Ranganath, independent Civil and Structural Consultant and Chartered Engineer and Valuer of M/s.Ranganath and Associates to assess the quality and quantity of the construction carried on by the defendant. That since the said architect and the defendant refused to co-operate with said Mr.Ranganath, he proceeded to prepare the report and submitted the same to the plaintiff, pointing out the glaring examples of inferior quality of work carried out by the defendant, such as incorrect execution of the reinforced concrete slab casted on the terrace to carry the overhead water tank; introduction of a beam contrary to the design, which was demolished and redone as per the revised design with the architect's structural engineer and was checked by M/s.Ranganath and Associates; faulty waterproofing of the ceiling with more than 250 cement grouting holes drilled in an unsuccessful attempt to rectify the leakage in the rooms; billing for such quantities and 23 bags of cement which were done only to correct his inferior quality of workmanship.

(m). Plaintiff had taken up remainder of the construction, repair and corrective work incurring additional expenses.

(n). The plaintiff paid an aggregate sum of Rs.47,18,000/- as against Rs.48,74,706/- raised by the defendant. M/s.Ranganath and Associates in its report had found that there was excess billing. The plaintiff on receipt of said report had issued a legal notice dated 15.03.2001 along with a summary of the comparative statement calling upon the defendant and the architect to make good atleast Rs.15,40,000/-, which included interest on excess payment amount of Rs.11,54,000/-, retention amount of 2% of the final bill and the cost of corrective repairs of Rs.70,500/-.

(o). In addition, plaintiff also sought for the reimbursement of monthly rental of Rs.15,000/- from the period between August 2000 and August 2001 aggregating in a sum of Rs.1,60,000/-.

Thus, in total, the claim of the plaintiff was Rs.17,48,000/- with interest at 18% thereon.

4. Case of the defendant:

(a). Defendant filed written statement contending that the suit was bad for non-joinder of necessary party for not arraying the architect. It is contended that it was the father of the plaintiff who being the owner of the property and relative of the defendant

had persuaded the defendant to take up the construction work and accordingly the defendant filed his tender. Considering the track record of the defendant and his quoted rates being the second least, he was awarded the work.

(b). That the tender furnished by the defendant towards the cost of construction of 5,275 sq. ft. of building in respect of the items mentioned in paragraph No.3 of the plaint was for Rs.37,12,662/-

and it did not cover the construction of swimming pool, servant quarters and high compound wall of 3.5 meters.

(c). The plaintiff had agreed that he would take care and that it would be his responsibility to co-ordinate with the agencies with regard to the supply of materials for wood work, paving and flooring and Painting. The responsibility of the defendant was to supply the steel grills for the window frames as per the necessary designs. In respect of paving and flooring, necessary materials like sand, cement and white cement were to be supplied by the defendant and the cost in respect of which would be reimbursed by the plaintiff.

(d). The allegation of defendant earlier working with the architect has been denied. Allegation of collusion and fraud are specifically denied. It is contended that the Plaintiff who himself is a civil Engineer was personally supervising the construction of the

- 10 -

proposed residential building and was issuing instructions during the entire process of construction.

(e). Receipt of Rs.4,00,000/- on 28.01.1999 towards mobilization advance to be deducted in the running bills in the prorata basis of 10% of each running bills is admitted.

(f). That the architect had given the working plan to the defendant on 28.01.1999. That the defendant had taken up the earthwork for the foundation and had completed 50% of the bed concrete work. Plaintiff, architect and the owner of the building had instructed the defendant to stop the ongoing work abruptly, as the City Municipal Authorities had declined to approve the plans submitted. That the plaintiff and his architect had issued fresh excavation drawings prepared as per the approved plan. As such, excavation work that had already been done had to be filled and the ground required to be cleared for fresh marking. Due to change in the excavation drawing placement of column, the excavation of foundation carried earlier got displaced and the bed concrete could not be retrieved. Defendant had brought this to the notice of the Plaintiff, his father and also the architect who had assured of reimbursement of the cost of the work to be carried out.

- 11 -

(g). Plaintiff and the architect went on changing the designs and drawings after execution of the work at their convenience. The floor levels in the living rooms and adjacent area were changed twice after plinth and later again after the brickwork. The defendant had dismantled the construction portion and reconstructed from the lower level to the foundation as instructed. In view of this, defendant had prepared a detailed list of work carried out due to the necessary changes in the specification and drawings duly measured and noted by the architect in the presence of the plaintiff and acknowledged by the architect. In addition to the above, there were major deviation and changes in excavation, bed concrete for foundation and flooring, foundation, basement, flints and brickwork.

(h). That the defendant had explained to the architect and the plaintiff at the time of joint measurement about the increase in the quantity due to the above-mentioned changes and also due to the changes in the drawings and both of them had agreed to approve the cost of minor changes affected which are mentioned in the running bills and agreed to reimburse the cost of major changes at a later date.

(i). The first bill was submitted on 23.04.1999 for Rs.4,80,000/-. The architect had certified the said bill on 15.06.1999. The plaintiff was making payment after assessment of the value the work

- 12 -

carried out after necessary consultation with the architect.

(j). The allegation that defendant presented the second bill on 28.03.2000 for Rs.29,70,000/- is incorrect. Defendant had submitted the bill for Rs.34,58,696/- to the architect which comprised the cost of civil work to the extent of Rs.32,33,426/- which is inclusive of the first running bill amount of Rs.4,81,175/-. Second bill amount of Rs.27,51,700/- and Rs.2,25,270/-, amount spent or given on instruction of the plaintiff.

(k). That the architect on receipt of second bill had passed Rs.32,27,847/- which is inclusive of first bill certified earlier. The plaintiff was liable to pay Rs.29,71,351/- towards certification of second bill towards the civil work and other payments as detailed.

(l). The allegation of plaintiff suspecting the bonafides of the defendant and the architect are denied. That the plaintiff himself was personally supervising the entire project all through and the detailed verification of the second bill was carried out in the presence of the plaintiff, architect and his assistant and the engineers of M/s. Pooja Construction. Only after proper measurements, inspection, verification and discussion of the architect and the plaintiff, the bill was certified by the architect with a clear direction of certification for

- 13 -

making payments. Allegations that the architect had certified the bill for Rs.29,70,000/- sitting in the office and in collusion with the defendant is denied as false.

(m). Delay in certifying the first bill after a period of one and a half month was due to change in the excavation, foundation and basement, change in the level of the floor and change in the height of the compound wall which were done pursuant to the instruction given by the architect and the plaintiff.

(n). Second bill presented and it was passed for the payment after following all the procedures in the presence of the plaintiff. That the bill amount was paid by the plaintiff without raising any objection as the defendant had executed the work to the fullest satisfaction of the plaintiff, the owner and the architect.

(o). That the plaintiff had collected the third and final bill on 06.08.2000 for Rs.14,21,629/- along with necessary enclosure from the defendant's office and 08.08.2000 along with architect's copy stating that he would hand over the third and final bill to the architect for necessary verification. Plaintiff did not inform regarding the termination of service of the architect. The third and final bill presented by the defendant was for Rs.14,21,629/- which included Rs.92,189/- amount spent or given on the instructional plaintiff.

- 14 -

(p). The total amount payable by the plaintiff to the defendant after deducting necessary advance and 2% security deposit was Rs.11,60,283/-. The plaintiff paid Rs.10,55,000/- towards the balance amount pending which is inclusive of sale of his car to the defendant for Rs.3,50,000/-. The plaintiff was liable to pay the balance of Rs.2,28,706/- which he assured to the defendant to clear it by the earliest date possible.

(q). The plaintiff requested the defendant in the month of September, 2000 to construct the eastern side compound wall and requirement for installation of computerized electronic gate and reconstruction of platform for water tank to hold 3,000 liters.

(r). As per the details provided, the said work for construction of the compound wall and the concrete platform was carried out in the month of September, 2000. The plaintiff is liable to pay in all Rs.4,88,255/-. Inspite of repeated requests and demands, the same was not paid. Surprisingly the plaintiff issued a letter dated 06.03.2001 after the lapse of 7 months intimating termination of the contract, only with an intention to deprive the legitimate amount payable by him. There were no work pending as on the date of closing of contract and while issuing final bill.

(s). The defendant has sent a reply along with the additional bill as detailed above.

- 15 -

(t). All the works have been executed as per the instructions of the plaintiff and the architect. The non-tender item works carried out after necessary approval of the architect and only after acceptance of the rate analysis given by the defendant the work has been done and bills were raised. Construction of swimming pool was taken up along with construction of servants quarters though they were not part of the tender. The said works were taken up as per the details provided by the architect in the presence of the plaintiff with an understanding that the defendant is going to execute the works on the basis of unit rate submitted and as per the rate analysis. The final bill was raised after entire work of construction was over. The last payment made by the plaintiff was on 02.11.2000 for Rs.2,00,000/-. Instead of making the balance payment, the plaintiff got issued a termination notice on 06.03.2001 that the contract was closed on 08.08.2000 by submitting the final bill.

(u). The defendant came to know about the consultation with M/s. Ranganath and Associates only when he received a notice from the plaintiff on 06.3.2001. The said M/s. Ranganath and Associates has neither consulted nor sought any clarification from the defendant till this date.

(v). The allegations regarding 250 grouting is denied. The plaintiff instead of following the design given by the consultant, he himself adopted his own

- 16 -

method resulting leakage in the sloping slabs. Therefore, at the request of the plaintiff and the architect grouting was done at that area to prevent leakage. Hence the bill has been raised for those works. The comparative statement as stated in the plaint is not based on the actual facts and only to oblige the plaintiff, M/s. Ranganath & Associates have prepared the report. Hence, defendant is not liable to pay any amount as claimed. On the other hand, the plaintiff himself is due to this defendant as narrated above.

Thus, apart from seeking dismissal of suit, had also sought for allowing of the counterclaim of Rs.4,88,255/- to be made by the Plaintiff with cost and interest at 18% per annum from the date of counterclaim till realization.

5. Based on the aforesaid pleading the trial court framed the following issues:

ISSUES:

'' 1. Whether the plaintiff proves that the defendants are liable to pay a sum of Rs.17,48,000/- along with interest at 18% p.a. from the date of suit till the date of realization?

2. Whether the plaintiff further proves that there is cause of action as alleged?

3. Whether the defendant proves that the plaintiff is liable to pay a sum of Rs.4,88,255.24 paise as counter claim?

4. Whether the plaintiff is entitled for the decree sought?

- 17 -

5. Whether the defendant is entitled for the counter claim sought?

6. What decree or order?''

Evidence and witnesses:

6. Plaintiff examined himself as PW.1 and four additional

witnesses as PW.2 to PW.5 and exhibited 62 documents as

Ex.P1 to Ex.P62.

7. The defendant examined three witnesses including the

architect as DW1 to DW3 and exhibited 41 documents, marked

as Ex.D1 to Ex.D41.

8. A Court Commissioner, namely Dr. B.R.Srinivasamurthy

has been examined as CW.1 and three documents have been

marked as Ex.C1 to Ex.C3.

9. The Trial Court on appreciation of the pleadings,

evidence and the documents dismissed the suit of the plaintiff

and also rejected the counterclaim of the defendant. Being

aggrieved by the same, plaintiff is before this Court in

RFA No.1473/2012, while the Defendant is before this Court in

RFA No.1922/2012.

10. Plaintiff has filed three applications in I.A.Nos.1/2022,

2/2022, 1/2023 under Order 41 Rule 27 seeking to produce

additional documents. He has also filed an application in

- 18 -

I.A.No.1/2024 under Section 151 of CPC seeking restitution.

Objection statements have been filed by the defendant to

I.A.No.1/2024.

Submissions of the plaintiff:

11. The plaintiff-party-in-person, apart from reiterating

the contents of the appeal memo, synopsis, revised synopsis

and citations, submitted;

(a). That the Trial Court has failed to appreciate the opinion and report of the Court Commissioner and Engineer. Since, the nature of the work entrusted to the Court Commissioner involved, technical specialization and competence in the field of construction and since the trial Court lacked the competence and expertise, it ought not to have declined to accept the ''expert's opinion''.

(b). That the Court Commissioner in his report has referred to the memo of instructions issued by the parties, tender documents, working drawings, bills, field book, physical measurements, meetings and discussions made by the parties and their respective counsel and only thereafter he has determined excess bills on certain disputed items of civil works in a sum of Rs.13,15,729/-.

(c). The Trial Court failed to apply the law laid down by this Court while rejecting the report of the Court

- 19 -

Commissioner. In that, as held in the case of Ashwatthamma Vs. Ramakka reported in 2011 (1) KCCR 387 ''if Court has not been satisfied with the expert's opinion, it was incumbent on the Court to have appointed another Commissioner in a serious dispute, such as this''.

(d). That PW.2, who is an independent civil and structural consultant and chartered engineer and valuer appointed by the plaintiff had sought information from defendant and the architect through written communications by the plaintiff as per Ex.P24 and Ex.P24A, Ex.P25 and Ex.P25A before independently assessing estimated quantities and amount for civil constructions which show excess billing of Rs.14,66,980/- together with cost of repair work in a sum of Rs.70,500/-. That the defendant refused to participate in the measurement of the work, despite he having been intimated regarding the scheduling of the meetings for the said purpose. That the trial Court grossly erred in not relying upon his evidence.

(e). PW.3, who supplied carpentry wood material and fabricators for window frames has deposed that delay in defendant supplying the metal grills as agreed which resulted in delay in completion of construction. That the trial Court has not taken his evidence into consideration.

- 20 -

(f). PW.4 is a neighbor who has deposed that the plaintiff was absent from the construction site and he had at the request of the plaintiff initially rendered assistance in the construction activities.

(g). PW.5 is the power of attorney holder of landlord of the house in which the plaintiff and the family members resided during the period of construction. Thus the trial Court has failed to appreciate the evidence of these two witnesses.

(h). That the plaintiff had sought enforcement of his rights by terminating the agreement which was tainted by fraud and misrepresentation on the part of the defendant which could not be discovered by the plaintiff with ordinary diligence. The trial Court ought to have awarded un-liquidated damages which the plaintiff had suffered on account of fraud and misrepresentation played by the defendant during the performance of the contract. That since the contract was rendered void by the plaintiff by his communication as per Ex.P34(b) which is admitted by the defendant, the plaintiff is liable to pay only for the work which is satisfactorily executed and properly accounted for as determined by independent agency as that of PW-2.

(i). That as per the Judgment of the Apex Court in the case of Avital Post Studioz Limited and others Vs HSBC PI Holdings (Mauritius) Ltd., and others reported in (2021) 4 SCC 713, it has

- 21 -

been held that "thus the fraud that is practiced during the performance of the contract, may be governed by the tort of deceit which would lead to damages but not rescission (cancellation of contract itself)."

(j). That the trial Court failed to apply the aforesaid principles of law while dismissing the suit.

(k). That the defendant has used lower inferior quality of material but however billed at the tender quality and price as seen at Ex.P27(a) and Ex.P31(a) and the defendant has admitted in his deposition to this effect. That though the defendant claims escalation in price of cement during construction and had sought for reimbursement, cost of cement had actually fallen below the tender price as evidenced at Ex.P27(a) and Ex.P42 and Ex.P45.

(l). That the defendant had billed in excess for other item works, non existent 2000 sq. ft. of 5.5" thick ceiling slab, non existent 1300 running feet of typical RCC beam and non existent 180 running feet of 9"

thick brick solid wall. The said findings have been brought on record by the Engineering consultant which has not been appreciated by the trial Court.

(m). That trial Judge had expressed his displeasure in the open Court as he was directed by this Court to dispose of the matter within two months by an order passed in W.P.No.41347/2011, filed by the plaintiff.

- 22 -

(n). The Trial Court failed to appreciate the facts and circumstances of the case and conduct of the defendant during the process of performance of contract.

(o). That though the defendant had made a counter claim, he has not discharged his burden of proof in respect thereof thereby disentitling him for any relief. Hence, sought for allowing of the appeal of the plaintiff and dismissal of the appeal filed by the defendant.

Submission on behalf of defendant:

12. Per contra, Sri. Venkatesh Bhagat, learned counsel

appearing for defendant who is appellant in RFA No.1922/2022

justifying the dismissal of the suit submitted:

(a). That the plaintiff has not produced the terms of the contract which he had allegedly entered into with the defendant.

(b). That the entire basis of the case of the plaintiff is the report which he had got prepared and obtained through PW-2 prior to filing of the suit. The said report was prepared behind the back of the defendant. That the same cannot be the basis for the suit.

(c). That PW-2 and the Court Commissioner-CW-1 both admitted regarding conducting of inspection and

- 23 -

submitting the report without notifying the defendant.

(d). That the trial Court erred in coming to the conclusion of defendant not making out a case for consideration of counter claim only on the ground that the defendant had not specified the amount due in respect of each bill and that he had received full payment against the said bills. That the said finding of the trial Court is contrary to the records made available.

(e). That the trial Court though had taken note of the fact that a sum of Rs.1,23,423/- being retention amount at the rate of 3% of the running bills and 2% of the final bills were retained by the plaintiff in terms of the tender condition, however has lost sight of the fact the same had to be refunded after lapse of six months from the date of submission of final bill or the first monsoon whichever was earlier.

(f). That though the trial Court had taken note of the fact that a sum of Rs.22,736/- had not been paid by the plaintiff towards the cost of execution of base slab and eastern side compound wall, erred in rejecting the said claim. That the trial Court erred in concluding that the said amount was covered in the final bill.

(g). The trial Court erred in denying the claim of Rs.2,36,842/- being the charges in respect of the works pertaining to alteration, addition and

- 24 -

reconstruction on the premise that the claim in respect of the said work had been submitted to the architect instead of submitting the same to the plaintiff which is contrary to the terms of the agreement. Hence, sought for dismissal of appeal filed by the plaintiff and allowing of the appeal filed by the defendant.

13. Heard and perused the records.

14. Plaintiff has filed the above suit seeking recovery of a sum of Rs.17,48,000/- together with current and future interest @ 18% per annum, alleging and claiming;

(a) "Fraud and misrepresentation" by the architect and the defendant from the inception and during the continuance of the contract;

(b) "Excess billing" in sum of Rs.13.10 lakhs by the defendant compared to what he is entitled for the work he has executed;

(c) "Inferior quality of construction" by the defendant in introducing a beam on his own which was demolished and redone. Faulty waterproofing of ceiling, by drilling more than 250 cement grouting holes and billing for such quantities including cost of 23 bags of cements.

(d) "Reimbursement of additional cost" incurred by the plaintiff towards corrective remedial work in a sum of Rs.70,500/-.

- 25 -

(e) "Reimbursement of monthly rentals" paid by the plaintiff in respect of rented premises occupied by him due to delay in completing the work between the period August 2000 and August 2001 amounting to a sum of Rs.1,65,000/- together with interest at 18% thereon.

Defendant on the other hand has sought for a counterclaim in a sum of Rs.4,88,255/- together with interest @ 18% per annum towards refund of retention amount, cost of construction of base slab and eastern side compound walls, charges towards alteration, addition and reconstruction.

16. Points that arise for consideration are:

"1. Whether the applications in I.A.Nos.1/2022, 2/2022 and 1/2023 filed by the Plaintiff deserves to be allowed?

2. Whether the Plaintiff has proved that the contract has been rendered void on account of fraud on the part of the Architect and the Defendant by wrongly certifying first and second bills?

3. Whether the Plaintiff has proved that there is excess billing by the Defendant in respect of quantities, and as such he is entitled for refund of Rs.13.10 lakhs with interest at 18% p.a.?

4. Whether the Plaintiff has proved that he is entitled for Rs.70,500/ towards reimbursement cost of repair work?

5. Whether the Plaintiff has proved that he is entitled for Rs.1,65,000 together with interest at 18% p.a. towards reimbursement of rental for delay in completion of work by the Defendant?

6. Whether the Defendant has proved that he is entitled for counter claim of Rs.4,88,255/- together with interest at 18% p.a.?

7. Whether the trial Court is justified in dismissing the suit of the Plaintiff and counter claim of the Defendant?"

8. Whether I.A.No.1/2024 deserves to be allowed?"

- 26 -

ANALYSIS:

Regarding Point No.1:

17. Plaintiff has filed I.A.No.1/2022 under Order 41 Rule

27(1) (aa) of Code of Civil Procedure seeking to produce certain

documents namely:

(a). A letter dated 04.07.1996 issued by one Mr.Syed Noorul Ameen to one Mr.R.Chaitanya Kumar.

(b). A letter dated 04.07.1996 issued by one Mr.Syed Noorul Ameen to one Mr.R.Chaitanya Kumar.

(c). A receipt dated 10.12.1999 executed by one Mr.R.Chaitanya Kumar.

(d). Lease Agreement dated 04.07.1996 entered into between Mr.Syed Noorul Ameen and Mr.R.Chaitanya Kumar.

18. In the affidavit accompanying the application the

plaintiff has deposed that since he is seeking costs and

damages from the defendant towards the rental amount paid

by him in respect of rented premises occupied by him during

the construction period, the aforesaid documents now sought to

be produced are necessary to prove and justify his claim. That

- 27 -

since he was away from India during 2009 to 2014 and his

personal belongings including all documents were kept in

separate storage, he could not have access to the same.

Hence, seeks for allowing of the said application for production

of the aforesaid additional documents.

19. I.A.No.2/2022 is filed by the plaintiff under Order 41

Rule 27 CPC seeking to produce:

(i) Postal receipts

(ii) True copy of the communication dated 09.04.2012 addressed to the Hon'ble Chief Justice, High Court of Karnataka, complaining against the Presiding Officer of the CCH-18, Bangalore City Civil Court.

(iii) True copy of the communication dated 09.04.2012 addressed to the Administrative Judge, High Court of Karnataka, complaining against the Presiding Officer of the CCH-18, Bangalore City Civil Court.

(iv) Petition under Section 24 of CPC.

20. In the affidavit accompanying the application the

plaintiff has deposed that at paragraph Nos.42 and 43 of the

appeal memo he has stated regarding inexplicable delay caused

by the Presiding Officer of XIX Additional City Civil and Sessions

- 28 -

Judge, Bangalore in passing the Judgment and decree in the

suit and also regarding he being infuriated on receiving

direction from this Court to expedite the disposal of the case

and that he had declared in the open Court that he would pass

adverse Judgment against the plaintiff for having sought the

direction. That though the plaintiff had offered to have the

building re-measured by the joint inspection of both the plaintiff

and defendant, the same was declined. That upon the advice

of his counsel on record he had communicated to the Chief

Justice and Administrative Judge of this Court appraising them

about the abuse of Court process. That upon the further advice

of his another counsel he had prepared a transfer petition

under Section 24 of Code of Civil Procedure. However, the

same could not be filed during April-May 2012 Court Holidays.

That before he could file the said application the suit had been

dismissed. Hence, the said documents are necessary to

support and justify his allegations of abuse of court process and

mal-administration and miscarriage of justice.

21. I.A.No.1/2023 is filed by the plaintiff under Order 41

Rule 27 read with Section 151 CPC seeking permission to

produce following documents:

- 29 -

(a) Notice dated 22.09.2007 issued by Assistant Commissioner, Commercial Taxes, (Transition)-2, Bangalore under Section 11 of the Right to Information Act, 2005 addressed to M/s.Pooja Constructions.

(b) Order dated 18.10.2007 passed by the Assistant Commissioner, Commercial Taxes, under Section 7 of the Right to Information Act, 2005.

(c) Notice dated 21.07.2008 issued by Assistant Commissioner, Commercial Taxes, (Transition)-2, Bangalore under Section 11 of the Right to Information Act, 2005 addressed to B.Pradeep, M/s.Pooja Constructions.

(d) Order dated 02.08.2008 passed by the Assistant Commissioner, Commercial Taxes, under Section 7 of the Right to Information Act, 2005.

(e) "True reproduction" of the extract of KST records pertaining to M/s.Pooja Constructions.

22. In the affidavit accompanying the aforesaid

application it is contended that the excess bill raised by the

defendant included work allegedly executed beneath and above

the ground in the course of erecting the foundation for the

house construction during February-March 1999. That the

defendant has pleaded to have completed entire earth

excavation for the foundation and had laid 50% of the bed

- 30 -

concrete which had to be demolished and re-laid during 15

days following 28.01.1999. Therefore to find out the aforesaid

unjustified billing, the Plaintiff had written to the Commercial

Tax Department seeking records submitted by the defendant

for the financial years 1998-1999 and 1999-2000 which are the

relevant years for construction, claim and counter claim and

plaintiff found that the defendant was not registered as a

contractor to the Karnataka State Commercial Tax Department

at the time of construction of his residence. That the

Karnataka State Commercial Tax Department declined to issue

the documents as sought for on the objections of the defendant

regarding matter being sub-judice. That subsequently plaintiff

was permitted to inspect the records in person. That during

the inspection plaintiff learnt that there were no relevant

documents regarding expenditure of labour, material

purchased, demolition etc., in respect of which inflated claims

were made. That though defendant during his cross

examination as DW-1 had admitted that he had no difficulty in

producing the records, he had failed to do so. As such, the

aforesaid documents were required to strengthen the case of

the appellant.

- 31 -

23. It is settled law that production of additional evidence

can be permitted only if party seeking production satisfies the

requirement contemplated under Order 41 Rule 27 CPC which

are extracted hereunder:

27. Production of additional evidence in Appellate Court.--(1) The parties to an appeal shall not be entitled to produce additional evidence, whether oral or documentary, in the Appellate Court. But if --

(a) the Court from whose decree the appeal is preferred has refused to admit evidence which ought to have been admitted, or

1(aa) the party seeking to produce additional evidence, establishes that notwithstanding the exercise of due diligence, such evidence was not within his knowledge or could not, after the exercise of due diligence, be produced by him at the time when the decree appealed against was passed, or

(b) the Appellate Court requires any document to be produced or any witness to be examined to enable it to pronounce judgment, or for any other substantial cause,

the Appellate Court may allow such evidence or document to be produced, or witness to be examined.

(2) Wherever additional evidence is allowed to be produced by an Appellate Court, the Court shall record the reason for its admission.

24. The reasons assigned at paragraph No.4 of the

affidavit accompanying the application in I.A.No.1/2022 seeking

to produce documents pertaining to rental arrangements reveal

that the said documents were not known and available to the

- 32 -

plaintiff during the course of the trial and before passing of the

Judgment and decree. At paragraph No.6 of the affidavit it is

deposed that subsequent to the year 2015-16 when he made

enquiry with PW-5, he was able to procure the originals of the

said documents. No where in the affidavit is there a mention

as to any effort having been made by the plaintiff or PW-5

regarding search made by them of the aforesaid documents. No

details as to the specific period when the plaintiff was away

from India is provided either. That apart perusal of the said

document would only indicate that by a letter dated 04.07.1996

one Mr.Syed Noorul Ameen has given his consent for use of his

rented premises and fixtures by the guests of one

Mr.R.Chaitanya Kumar. However, it states that the liability of

payment of rents would be of the said Mr.Chaitanya Kumar.

The rental agreement dated 04.07.1996 is though between the

said Mr.Noorul Ameen and Mr.Chaitanya Kumar, it is signed

only by Mr.R.Chaitanya Kumar and there is no signature of the

lessor. The reasons assigned in the affidavit apart from being

not satisfactory, the documents now sought to be produced are

not be required for adjudication of the lis between the parties.

25. Application in I.A.No.2/2022 is seeking production of

communications dated 09.04.2012 by the plaintiff to the Chief

- 33 -

Justice and the Administrative Judge of this Court and the

application along with the affidavit filed under Section 24 of the

CPC. As already noted above, additional evidence/documents

are expected to be pertaining to the dispute between the

parties. Documents sought to be produced under this

application in I.A.No.2/2022 are with regard to the allegations

made against the Presiding Officers of the trial Court. Even

those complaints/petitions were not personal to apply logical

conclusion. Therefore are not germane to the merits of the

appeal.

26. I.A.No.1/2023 is seeking to produce certain notices

issued under section 11 of the Right to Information Act and the

order under Section 7 of the said Act declining to issue the

information sought for by the Plaintiff. The ''true reproduction''

statement produced as document No.2 to the said application

neither being a certified nor an authenticated copy issued by

the Authority, cannot be taken on record.

27. For the reasons assigned in this judgment concerning

the issue on merits of the case, the said documents sought to

be produced are of no avail for the purpose determination of

the actual dispute between the parties. Hence, the applications

- 34 -

in I.A.Nos.1/2022, 2/2022 and 1/2023 are rejected, point No.1

is answered accordingly.

Regarding Point No.2:

28. Genesis of the case of the plaintiff is excess billing

tainted with elements fraud allegedly played on him by the

architect and Defendant from the inception and during the

performance of the contract and that such fraud has rendered

the contract void entitling the plaintiff for damages.

29. Necessary therefore to refer to relevant provision of

law in this regard before proceeding on the merits of case.

Section 17 in the Indian Contract Act, 1872

17. 'Fraud' defined.--

'Fraud' means and includes any of the following acts committed by a party to a contract, or with his connivance, or by his agent', with intent to deceive another party thereto or his agent, or to induce him to enter into the contract:--

(1) the suggestion, as a fact, of that which is not true, by one who does not believe it to be true;

(2) the active concealment of a fact by one having knowledge or belief of the fact;

(3) a promise made without any intention of performing it;

(4) any other act fitted to deceive;

(5) any such act or omission as the law specially declares to be fraudulent.

- 35 -

Explanation.--Mere silence as to facts likely to affect the willingness of a person to enter into a contract is not fraud, unless the circumstances of the case are such that, regard being had to them, it is the duty of the person keeping silence to speaks, or unless his silence, is, in itself, equivalent to speech.

30. It is a settled position of law that Fraud like any other

charge of a criminal offence whether made in civil or criminal

proceedings must be established beyond reasonable doubt. It

cannot be based on suspicion and conjuncture. (ALN

Narayanan Chettiyar V. Official Assignee reported in AIR

1941 P.C.93)

31. Except making general allegation of `collusion' and

`fraud' between the architect and the defendant there is no

specific details provided by the plaintiff. The said architect has

not been made party to the suit.

32. Fraud and it's particulars are required to be pleaded

in terms of order VI Rule 4 CPC which reads as follows:

4. Particulars to be given where necessary.- In all cases in which the party pleading relies on any misrepresentation, fraud, breach of trust, wilful default, or undue influence, and in all other cases in which particulars may be necessary beyond such as are exemplified in the forms aforesaid, particulars (with dates and items if necessary) shall be stated in the pleading.

- 36 -

32. Admittedly plaintiff himself is a Civil Engineering

graduate. Defendant -Pradeep, admittedly is his cousin and

they know each other since their childhood. In the cross

examination the plaintiff has categorically deposed that he has

selected the contractor and there was no say of Architect in

selection process of the contractor and that he had the final say

in the matter. This deposition completely rules out any element

of inducement or deceit in plaintiff awarding the contract to the

defendant. In the light of this admitted aspect of the matter the

averments made in the plaintiff to make believe that the

selection of contractor-defendant was at the sole choice of the

architect and that the plaintiff had no role to play runs contrary

to his own deposition.

33. Further admittedly there is no written agreement

between the Plaintiff and the Defendant providing the details of

the terms and conditions of the contract. From the contents of

the plaint and written statement, the undisputed facts which

emanate are that the Plaintiff had initially engaged the services

of Architect namely Mr.Suresh Babu, who was required to

obtain and provide all required clearances, detailed estimation,

specifications apart from negotiating the price and finalizing the

drawings. He was also required to supervise the contractor,

- 37 -

check on the quality and quantity of work being executed,

check the bills against the work executed and provide

certification. There is no dispute of the fact the construction

work was commenced upon the designs, drawings,

specifications and plans drawn, approved and cleared by the

said Architect. The rates were specified in respect of tender

items. There is also no dispute of the fact that apart from

tender items there were also certain non-tender items within

the scope of the contract. Rates in respect of non-tender items

were however subject to discussion.

34. Exhibit P27 (A) - " Schedule of Quantities " submitted

by the Defendant and accepted by the Plaintiff showing the

quotations for civil construction. The other admitted documents

which are part the transactions are:

1. Exhibit P1 original sanction plan prepared by the Architect.

2. Exhibit P3 ground floor working plan dated 12.02.1999.

3. Exhibit P4 central line column footing excavation plan and foundation details dated 09.02 .1999.

4. Exhibit P5 electrical layout for ground floor plan dated 25.02.1999.

5. Exhibit P6 toilet details.

6. Exhibit P7 east side and north side elevation cornice and pilaster details dated February 1999.

- 38 -

7. Exhibit P8 west side south side details-A and B dated February 1999.

8. Exhibit P9 plan for front portion and steps.

9. Exhibit P10 ground floor plan for workers quarters dated 25.07.1999.

10. Exhibit P11 first floor plan for workers quarters dated 25.07.1999.

11. Exhibit P12 drawings of underground storage tanks.

12. Exhibit P13 sectional drawings for swimming pool retaining wall.

13. Exhibit P14 ground floor ceiling slab and beam reinforcement details dated 10.05.1999.

14. Exhibit P15 first floor working plan.

15. Exhibit P16 first floor lintel details.

16. Exhibit P17 first floor roof slab beam and reinforcement details dated 01.09.1999 Exhibit P18 electrical layouts for the first floor plan dated 30.03.1999.

17. Exhibit P19 terrace floor plan.

18. Exhibit P20 water tank bottom slab details dated 23.05.2000.

19. Exhibit P21 staircase plan dated 08.07.1999

20. Exhibit P22 carpentry detail 1 dated 29.03.2000

21. Exhibit P23 Carpentry Details 1 dated 03.03.2000.

- 39 -

35. It is not the case of the plaintiff that these suit

documents were either created or thrusted upon him by the

architect and the defendant.

36. There is no dispute of the fact that plaintiff had

initially paid Rs.4,00,000/- towards the mobilization funds

enabling the defendant to commence the construction. There is

also no dispute of the fact that the first bill dated 23.04.1999

was raised by the defendant for Rs.4,88,086/- of which a sum

of Rs.4,81,725/- was certified by the architect after inspection

and measurement of the work at the site and that upon such

certification the plaintiff paid the said sum of Rs.4,81,725/-.

37. The second bill dated 28.03.2000 was raised for

Rs.29,07,000/- which was also certified by the said architect

and the same has been paid by the plaintiff.

38. It is during this period the plaintiff again has

apparently entertained suspicion about the architect and the

defendant having played fraud on the plaintiff resulting in

plaintiff terminating the services of said architect.

39. The third and the Final Bill dated 06.08.2000 has been

raised by the defendant for a sum of Rs.14,21,629.25 and

- 40 -

submitted directly to the plaintiff of which plaintiff has paid a

sum of Rs.11,28,000/- without even reference of the architect.

40. The plaintiff claimed to have terminated the services

of the Defendant after payment of the third bill. The plaintiff

has provided the details of payments made to the defendant

which are as under:

 Sl.    Details                     Date          Amount
 No.
 a.     Advance paid before         25.01.1999    Rs.4,00,000/-
        commencement      of
        work
 b.     First Bill                  23.04.1999    Rs.3,55,000/-
 c.     Second Bill                 28.03.2000    Rs.25,20,000/-
 d.     Third Bill                  06.08.2000    Rs.5,48,000/-
 e.     Subsequent        to        -             Rs.5,80,000/-
        06.08.2000    up  to
        02.11.2000
        Total amount paid           Rs.47,53,000/-



41. The aforesaid amount apparently included value of

personal car of the plaintiff which was given to the defendant

during the year 1999 in a sum of Rs.3,50,000/-.

42. Thus, essentially an approximate sum of

Rs.48,15,000/- being the aggregate of first, second and third

(final) bill amounts has been paid by the plaintiff as on August,

2000 and it is only thereafter the plaintiff in furtherance to his

suspicion of the architect and the defendant playing fraud on

- 41 -

him terminated the services of the architect and the defendant

and has sought the services of independent engineer

Sri.D.Ranganath to assess the quantity and quality of the work

carried out by the defendant. There is specific admission by the

plaintiff, that except for a brief period of 60 days, he was in

India and he being a Civil Engineer was often visiting the site.

Thus when he had purportedly entertained the doubt, suspicion

about the bonafides of the defendant and the architect, and

when he already being advised by an independent Consultant

and Engineer, he cannot be heard to say that he did not

supervise and inspect the work by himself and that he was the

victim of collusion and fraud played on him by the architect and

defendant.

43. Another aspect of the matter is that in terms of

Section 19 of the Indian Contract Act, 1872 a contract which is

induced by fraud is not void but only voidable at the option of

the party defrauded. It merely gives an option to the party

defrauded to avoid the contract on he discovering the fraud.

Defrauded party being entitled to rescind the contract on the

allegation of fraud cannot rescind it in part, it has to rescinded

in its entirety. If he elects to continue the contract even after

noticing the fraud, his election determines his right. In the

- 42 -

instant case plaintiff was allegedly being suspicious from the

inception. He claims to have terminated the services of the

architect after clearing of the Second bill. But continued the

work and the contract with the defendant thereafter. He

purportedly terminated the contract with defendant after

payment of third and final bill.

44. When the plaintiff has neither specifically pleaded nor

proved the elements of fraud as contemplated under Section 17

of the Contract Act allegedly noticed by him from the

"inception" and "during the performance of the contract", and

he having elected to allow the defendant to complete the work

by purportedly extending the time, his contention of he being

entitling for damages on rescission the contract on account of

Fraud cannot be countenanced.

45. Point No.2 is answered accordingly.

Regarding Point No.3:

46. Plaintiff after terminating the services of both the

architect and the defendant, engaged the services of an

Engineering Consultant namely Mr.D.Ranganath of

M/s.Ranganath and Associates, independent Engineering

Consultants a Chartered Engineers and Registered Valuer to

- 43 -

assess and assist in determining the "quantity" and "quality" of

the work executed by the defendant. The said consultant stated

to have prepared report dated 15.03.2001 and the revised

summary of comparative statement dated 30.04.2001

produced as Ex.P33. In terms of which the said consultant

stated to have found that the defendant had raised "Excess

Billing" and the plaintiff had made "excess payment" in a sum

of Rs.13,10,274/.

47. Appointing and engaging the services of the aforesaid

engineering consultant by the plaintiff is after the alleged

termination of services of the architect and the defendant. It is

an unilateral act. The inspection and verification by the said

Consultant was in absence of any participation either of the

architect or the defendant and based only on the information

and instruction of the plaintiff. Except the Comparative

Statement of Bills as per Ex.P33 there is no other material

produced to support and justify the calculation made by the

said engineering consultant. Thus the entire basis of the claim

under the said heading is the report of the said consultant.

48. Said Mr.D.Ranganath has been examined by the

plaintiff as PW2. The said witness has deposed that he had

accompanied the plaintiff to the site during the year 1999 and

- 44 -

had suggested for an RCC beam to be introduced connecting

two extremes of the flat roof area above the first floor roof. The

said witness has stated that he had observed structural

deficiency in the roof slab provided over the staircase leading to

second floor. He has further deposed that again during June

2000, plaintiff had approached him seeking his assistance in

assessing and arriving at a quantum of work executed and

billed by the defendant as he had suspected correctness of

quantities and the quality. He stated to have visited the site for

actual measurement and assessment of work executed. The

basis of assessment and quantification are working drawings,

site log book that were made available to him by the plaintiff

and the actual measurement of work taken by him at the site.

49. In the cross-examination the said witness has

admitted that he has valued the building as per the

methodology prescribed in Bureau of Indian Standard and on

inspecting the same at the spot. He has further deposed that all

the information was given to him by the plaintiff in the absence

of the contractor and the architect. With reference to Ex.D7

which is a document pertaining first floor slab and

reinforcement details, he has admitted that the structural

engineer has made endorsement on the said document

- 45 -

regarding excess reinforcement and that if there was any

excess reinforcement of steel, the same was not brought to his

knowledge and he has not referred to the same in his report.

He has further deposed that he has taken into consideration

only the drawings that were made available and if at all there

was any excess steel used he has not taken the same into

account.

50. Admittedly the defendant had no say in the statement

prepared by the PW2. When the contract was awarded by the

plaintiff to the defendant based on the tender document and bill

of quantities as per Ex.P27(a) there is no justification for

Plaintiff to have relied upon the report of the consultant

prepared on the basis of specification given by the Bureau of

Indian Standard, Architectural working drawings, structural

drawings and site book/log book that too in the absence of any

participation in the said process either by the defendant or the

architect. In the absence of any other material evidence being

produced by the plaintiff or by the said PW2 regarding basis on

which the comparative statement of bills, quantities and rates

were prepared the evidence in this regard is hardly of any use

to the plaintiff.

- 46 -

51. The Trial Court by order dated 26.11.2005 had

appointed one Dr. B. R. Srinivas Murthy, Professor Emeritus

Indian Institute of Science, Department of Civil Engineering, as

the Court Commissioner, who has been examined as CW.1

plaintiff and the defendants had furnished their memo of

instructions. Three documents have been marked through the

commissioner, viz., covering letter Ex.C1, report Ex.C2 and

detailed estimates, preparation and comparative statement of

bill of quantities Ex.C3.

52. The plaintiff had furnished a memo with following

points/instructions for the consideration of the court

commissioner ;

(a) to inspect evaluate and report as to the condition, status, quality of work done and quantities of the work done in the pond called swimming pool on the south side of the building site and the extent of work yet to be done to complete the same;

(b) to inspect evaluate and report as to the condition, status, quality of work done and quantities of the work done in sump tank on the north south east and west side of the building;

(c) to inspect evaluate and report as to the condition, status, quality of work done and quantities of the work done for the entire residential building and appurtenances within the confines of the compound wall (compound wall inclusive) in the said property;

- 47 -

53. While answering the point (a) the Commissioner

has found that though there is no tender specification with

regard the finishing of the swimming pool, since the work

of swimming pool is incomplete and all the executed items

have directly applicable tender rates, to the extent of the

work completed tender rates have been directly applied to

compensate the partially completed work.

54. While answering the point (b) the commissioner

has found that sump with brick masonry wall is a tender

item and the quoted rate is cost per litre. The rate for

sump with RCC wall with all other specification remaining

the same no different estimation of quantities was

required. However as regards reinforced concrete (RCC)

sump tank on the north, east and west side of the building,

the commissioner has found that the data rate derived and

applied by the defendant to be erroneous and the

commissioner has worked on the same based on the

tender rates for the brick masonry and cost per litre.

55. While answering the point (c) the commissioner

has found that in the first meeting it was agreed upon to

consider only the disputed items and the detailed

- 48 -

estimation has been made by the commissioner in respect

of all the disputed items.

56. The defendant had given the following eleven points

in his memo of instructions;

a) To verify and quantify the cost due to stoppage of work, rectification and removal of the earlier completed work as per the working drawing dated 28.01.1999 with regard to the center line marking, excavation, column footing and foundation and later repetition of the same work based on working drawings dated 09.02.1999 which were a mirror image of the earlier working drawing mentioned;

b) To verify and quantify the cost due to the repetitive change in floor level of the living room after completion of necessary work at each level and compare the existing level of flooring to the working drawings.

c) To quantify the cost due to change in the specification of the compound wall after bed concrete in relation to tender items.

d) To verify and quantify the cost due to the alteration and removal. and construction of T. MBmasonry of 9" and 4.5" brick wall like cancellation of niches, removal of reconstruction of wall at various parts of building and changing the clear height after necessary construction

e) Verification of the working plan with the existing structure in relation to volume of alteration being carried out quantifying the value of work, which was carried out earlier as per the working drawings and later removed or altered on the instruction of the owner and the Architect.

f) Verify the rate analysis for non-tendered items which is based on practiced principle of deriving the rates for non-tendered item from the rate of similar class of

- 49 -

work specified in the tender and approved by the Architect and owner before execution.

g) To verify the thickness of RCC slab, quantity of beams/ lintel, concealed beam at various level and points as mentioned in the working drawings and quantify the value.

h) to verify the causes of delay due to non-completion of work with the different agency or non-supply of material and uncertain on the part of the owner in finalizing the brand for the works, which is in the scope of the owner like plumbing, woodwork, flooring, front gate, finishing and electrical work etc.

i) To verify items which was decided at the later stage of construction, by the owner and his Architect like sloping slab, double height slab, providing skylight, servant quarters, window elevation design, and other various special works etc., neither mentioned in the tender schedule nor furnished the said drawings or specification at the time of tender which is executed and categorized under the non-tender item considered under the non-tender items or tender items

j) To verify and quantify the value of the work carried out on the instructions of the owner and his Architect and which is not in the drawings, like top room on the II floor, additional beam providing attic at office room and providing secret Godrej locks in the walls of the bedrooms, which is evident in its existence.

k) To verify and quantify the building materials supplied to owner of the work comes under his spare of activities like flooring and painting etc

57. In response to the points (a) and (b), the

Commissioner has found that cost due to stoppage of work

could not be assessed as no evidence in that regard was

- 50 -

produced by the defendant. However, the Commissioner has

found that by the time the first bill that was produced by the

defendant, entire foundation work for the main building was

complete along with the completion of majority of the

compound wall foundation work and that the first bill had

included items of alterations and additions up to that level.

Similarly, the second and the final bill included items for

alteration additions. As such, the claim for the said work that is

alteration, addition etc., after the final bill which the defendant

could not explain for non inclusion in the earlier bills and the

work done/losses/cost claimed after issuance of the third bill

and final were not acceptable.

58. In response to the point (c), the Commissioner has

found that since the tender document contains the rate for

change specification item, the derived rate to the defendant for

this item has been allowed by the Commissioner.

59. The commissioner in response to the points (d) and

(e) has found that there are minor deviation in construction of

various items from the working drawings such quantities ought

to have been included in the running bills since the defendant

had billed several such items in the three running bills it was

construed that all such items have been covered. No specific

- 51 -

quantity of item involved was brought to the notice of the

Commissioner;

60. In response to the point (f) the Commissioner has

stated that non-tender quantities rate analysis has been

examined and the same has been furnished in the enclosure

and have been included in the estimate prepared by him.

61. In response to point (g) the Commissioner has stated

that the estimate prepared by him covers all the items as per

the drawing site notes etc. Commissioner has found no

justifiable records are furnished to claim the delay and hence

no comments on point No.(h)

62. In response to point (i) and (j) the Commissioner has

found that it is normal in the building construction practice

wherein changes are made during the construction from the

tender drawings and even from the working drawings to suit

the site conditions and impact of the same were covered in the

running bills by the defendants. Relevant items have been

covered in the detailed estimate prepared by the commissioner.

The Commissioner has not advert to point (k) holding the same

to be not relevant for his action.

- 52 -

63. In conclusion, the Commissioner has found that the

Defendant had made materially significant tabulation errors

such as double billing of some items, lesser deduction of

quantities of beams and lintels in pertinent items and use of

non-tender rates for tender rates in certain instances. Thus, the

commissioner has found that there has been a total excess

billing for the disputed items. In which the defendant has billed

an amount of Rs.37,46,250/-, while according to the

Commissioner's estimate it ought to have been Rs.24,30,522/-.

Thereby there is an excess billing of Rs.13,15,729/-.

64. It is settled position of law that report and the

evidence collected by the Commissioner form part of the record

of the suit. It is also settled position of law that Commissioner's

report does not automatically become ipso facto evidence but

merely a piece of evidence required to be considered and

assessed by the court by taking into account the totality of

circumstances and other material evidence on record rather

than placing undue reliance thereon. [Praga Tools

Corporation Limited Vs. Mahboobunnissa Begum (2001)

6 SCC 238].

65. Except Ex.C1 to Ex.C3, the Court Commissioner has

not produced any other documents. The Court Commissioner in

- 53 -

his deposition has admitted that he has checked the

measurement according to the drawings that were made

available. He has also admitted that when he checked the

measurement defendant was not there. He has also admitted

that he has not given any notice to the defendant. He has

admitted that he has not recorded measurement on any of the

papers. He also admitted neither of the parties has given list of

the disputed items. He has admitted that Ex.D1 consisting of

11 pages was prepared at the instruction of plaintiff by

independent Engineer. He has further admitted that he has not

produced the details given by the plaintiff to the Court and that

Ex.D1 is only the list of disputed items and that he has not

prepared list of disputed items. In other words the even the

Court Commissioner has proceeded to assess the quantity and

quality based on the unilateral report of PW-2.

66. He has further admitted that the thickness of the bed

concrete is taken from the drawings and that he has not

excavated the section to verify the thickness of the bed

concrete. That, for ascertaining the thickness of the plinth

concrete one has to measure it by cutting the section physically

which he has not done. He has also admitted that the thickness

of the plinth concrete and the bed concrete are not designed

- 54 -

parameters. Though the court commissioner has admitted that

the contractor has to execute the work as per the designs and

instructions given by the architect and the structural engineer,

has however pleaded his ignorance if in the instant case there

was any change in the plan. He has also pleaded his ignorance

regarding change of plan of position of the columns. He has

admitted that he prepared Ex.C3 after comparing the running

bill and the final bill. He has admitted that he has not included

the bed concrete which was destroyed in view of change of plan

as it was not brought to his notice that there was a change of

plan and there was already a bed concrete and it was removed

by placing the new bed concrete.

67. He admits that the running bills were approved by the

architect but he has not been able to seek clarification from the

architect in this regard. He also admits that he has not

measured the entire constructed area of the building he also

not able to say the total constructed area of the said building.

He admits that he has not mentioned the thickness of the plinth

concrete used in the building as well as the plinth concrete of

the compound wall thickness. He has deposed that he has

taken into account the footing of the column concrete as per

- 55 -

the drawings, but he is not aware if the architect had advised

to change the footing of the column concrete thickness.

68. He has also deposed that as the building was already

constructed and that to know about the measurement referred

to it was required to be opened and that he has not randomly

checked the thickness of the lintel concrete used in the

building. He has also not measured the thickness of sajja. He

cannot exactly say the thickness of sajja and he has not

measured the thickness of sajjas as the finished worked are

required to be demolished. He admits that he has not

mentioned the thickness of attice. He also admits the arches

constructed are in steel covered by concrete. He has pleaded

his ignorance with regard to the thickness of the attice. He has

also pleaded his ignorance that there was a change in the

drawing from 3 thickness to 5 thickness of attice and he has

not measured the thickness of attice. He admits that in all there

are 11 projections given to outside wall, thickness of which is

18 X 5.5 inches and the set 11 projections are not in the

drawings and that he has not mentioned the said 11 projections

in his calculations.

69. Though he admits that there is a gutter around the

building, he cannot say if there is an all-round steel used for

- 56 -

construction of gutter, but he has prepared his report based on

the drawings but he has not mentioned the change in the

design of drawings.

70. He is unable to say that as per the instruction of the

structural Engineer there are concealed beams in the roof and

he cannot say that there is no drawing of concealed beams with

him. He admits that in the drawings there is no mention of

thickness of plinths and that he has not mentioned the plinth

thickness as executed by the contractor.

71. He has admitted that he was expected to carry out

factual aspect of constructed area, however he has done

wherever it was possible and wherever it was not possible he

has taken the assistance of general principles. He has admitted

that whenever there was a deviation in construction at the

instance of the owner, that amount was to be paid by the

owner to the contractor. He also admits that in the running bill

the work executed by the contractor as per the instructions of

the owner deviating from the original plan has been calculated

and approved by the Architect. He also admits that at the time

of executing non-tendered items rate analysis is prepared and

allowed. He also admits that after verifying the rate analysis

and the running bills the owner has made the payment of first

- 57 -

and second bill. He has deposed that he has taken the steel

reinforcement as per the drawings. He also admits in the

document there is no specific quantity mentioned. He admits

that he has not given the calculation sheet regarding plastering

work. He further admits that item number 31A was prepared by

his student on his instruction. That his students assisted him in

programming the C schedule work.

72. From the aforesaid deposition of the CW1 it is clear

that he has merely relied upon the document such as plans,

drawings and designs and the comparative statement prepared

by the PW2 to arrive at his report. He did not physically

measure all the items personally. In that view of the matter

commissioners report cannot be accepted as the substantial

piece of evidence justifying the claim of the plaintiff.

74. PW1 in his evidence has admitted that the defendant

had executed non-tender item works namely, swimming pool,

sump tank, spiral staircase, sloping roof, double height slab,

waterproof plastering, screed finishing, compound wall, window

grill, arch beam, curved slab, fixing of window and door frames,

different types of cornices, providing and laying of terracotta

tiles. He has also admitted that the defendant has executed

the work as per the direction of the architect. He has further

- 58 -

admitted that through the said architect he got appointed one

structural engineer. He has also admitted that his building is

having built up area of 6,166 square feet as against 5,275

square feet. He has admitted grouting of slope roofing was

done by the defendant as per the direction of the architect,

though he had suggested that it should be done at the cost of

the defendant. He admits that he has not produced the list

before the court showing the items of inferior quality in entire

building. He also admits that in the tender notification there

was no mention of time stipulation but it was a verbal

agreement. He admits exhibit P13 is the sketch pertaining to

the swimming pool and the entire reinforcement of exhibit P13

is changed. He further admits Sajja is not the same form as

shown in Exhibit P16 (a) and the design is changed pertaining

to the Sajja.

75. Though in the plaint as well as in the evidence the

Plaintiff has made efforts to contend that it was obvious from

the architect's certification of the bills raised by the defendant

with regard to non-existent huge quantities of brick, steel etc.,

there is no acceptable reasons assigned by the plaintiff to have

proceeded to clear the first and second bill upon the

certification made by the architect. Further, when even

- 59 -

according to the plaintiff he had terminated the services of the

Architect, there is no whisper as to what prompted him to clear

the third and final bill during August 2000 when the defendant

had submitted the third bill directly to the plaintiff. This is

under the teeth of allegation of plaintiff having found excess

billing quantity and inferior quality with the aid of third party

consultant. Nothing prevented the plaintiff to withhold the third

bill for Rs.14,20,000/- until he ascertained quantity and quality

of the work. The third bill was admittedly raised after

completion of all the work and paid of. It is paid after

purported termination of contract with the defendant.

76. This conduct of the plaintiff would only indicate that

the Plaintiff had been satisfied himself with regard to the work

carried out by the defendant and only thereafter had made the

payment. This is in the absence of any compelling

circumstances even as pleaded by the plaintiff to make the

payment of the first and second bill raised by the defendant.

Also pertinent to note that even according to the deposition of

the plaintiff, defendant had refused to continue to work on and

after August, 2000 and had vacated the site with lock, stock

and barrel.

- 60 -

77. Defendant on the other hand has examined himself

as DW-1 reiterating the contents of the written statement. He

has produced documents marked as Ex.D9 to Ex.D35. In the

cross examination though pointed questions have been asked

with reference to the contents of paragraph 37 of the affidavit

evidence of the plaintiff, nothing has been elicited to indicate

incompletion of the work as sought to be made out. Though in

the cross examination plaintiff himself has admitted, that

swimming pool amongst others was a non-tender item work,

defendant has been posed questions to suggest that he has

claimed Rs.7,54,730/- while the cost of construction of the

swimming pool was Rs.2,91,250/- thereby the defendant had

charged an excess of Rs.5,00,000/-. Defendant has

categorically deposed that he has constructed the swimming

pool as per the design and instructions given by the Architect of

the plaintiff and as per the rate analysis approved by the

architect of the plaintiff. Though it is suggested that as per the

Commissioner's report the defendant has added extra work

done in the bills than the actual same has been specifically

denied by the witness. Thus, nothing significant has been

elicited from the said witness to sustain the suit claim. Also

pertinent to note that there has been no suggestions denying

- 61 -

the change in the designs, specifications, alteration, demolition

of the work.

78. Architect -Suresh Babu has been examined as DW-3.

In his affidavit evidence the said witness has deposed in detail

regarding his role and involvement in the process of

construction. He has specifically deposed that though he had

suggested the owner of the property to appoint an Engineer to

supervise the day-to-day construction activities as per the

construction practice, the plaintiff had agreed to supervise the

day-to-day work as he was a qualified Engineer and did not

have any other work and to concentrate on the work by

himself. He has also deposed that he had prepared a plan for

submission of obtaining sanction and grant of licence but the

owner and the plaintiff had insisted to change the plan as per

requirement which was rejected. The defendant had

commenced the work as per the working plan on 28.01.1999.

That since the earlier plan was rejected, he prepared modified

plan in conformity with the CMC Regulations. By the said time

defendant had carried out certain portion of work which

required to be stopped, cleared and redone involving

duplication and modification of work of bed concrete. He has

affirmed that he thoroughly and properly verified the physical

- 62 -

measurements taking proper care and caution which has been

cross checked by the plaintiff. He has also deposed that during

the construction lot of changes in the working drawings were

effected as per the requirement of owner and the Plaintiff

deviated from the working drawings. At paragraph No.11 of his

affidavit evidence said witness has given the list of

modifications affected with regard to working drawings.

79. The witness has also deposed that as and when the

defendant submitted rate analysis for work that were not

mentioned in the tender or for items modified due to change in

the specification he had detailed discussion with the plaintiff

and finally the rates were approved after effecting certain

reductions. He has also deposed that plaintiff along with the

defendant and the Engineer were involved in the process of

measurement of each item and gave clarifications for certain

items in the bill as mentioned in paragraph No.15 of his

affidavit. He has also deposed regarding certain arithmetical

errors found in second bill in a sum of Rs.14,000/-, which was

informed to the plaintiff. He has deposed regarding the

inclusion of claim for reimbursement of cost incurred by the

defendant due to change in the design and specification,

particularly with regard to roof slab, double height roof slab

- 63 -

which after consultation with the Plaintiff were cleared for

payment.

80. He has also deposed that construction of swimming

pool was neither mentioned in the tender nor drawn in the

working plans issued to the defendant. Owner and the plaintiff

had insisted of getting the work done by defendant. The

defendant had submitted rate analysis and after negotiation

involving the plaintiff, it was approved for Rs.5.25 per litre.

The swimming pool was constructed for Rs.1,26,090/- litre

capacity. Nothing significant has been elicited in the cross

examination of the said witness discrediting his deposition.

81. From the deposition of Plaintiff, PW1, PW2 and the

Commissioner-CW1 as well as the depositions of DW1 and

DW3, it is clear that there have been changes and variations in

the designs, drawings and the actual construction. It is also

brought on record that the actual constructed area is more than

what was initially conceptualized. PW2 and the Commissioner

have deposed that they were neither informed by the Plaintiff

regarding particulars of changed designs/drawings nor they

have physically verified the actual constructed area by the

Defendant.

- 64 -

82. In the absence of specific details as to the excess

quantities allegedly billed by the defendant specifically with

reference to changed actual contractual area, merely based on

the comparative calculation made by the PW2 and the

Commissioner CW1, admittedly on the basis of designs and

drawings and the information provided by the plaintiff without

measuring the actual constructed area, it cannot be accepted

that defendant has made excess billing of the quantities.

83. The evidence of defendant examined as DW1 and the

evidence of architect examined as DW2 has stood the test of

cross examination and would indicate that the plaintiff was

throughout involved in the process of construction, change,

modification, alteration, discussion and finalisation of the rate

analysis.

84. Plaintiff has thus failed to prove that there was

excess billing of quantities by the defendant resulting in plaintiff

being entitled for refund of Rs.13.10 lakhs with interest at

18%. Point Nos.2 and 3 are answered accordingly.

Regarding point No.4:

85. The plaintiff has claimed a sum of Rs.70,500/-

towards reimbursement of cost incurred by him for carrying out

- 65 -

remedial work. At paragraph No.37 of his affidavit evidence he

has enlisted 15 items of work allegedly remained incomplete as

on the date of closing of the contract and issue of final bill

requiring remedial work. He has however not given the details

of the contractor or the person through whom he caused

execution of such remedial/repair work. Though the plaintiff

has produced photographs to indicate unfinished work as on

the date when the defendant had vacated the site the same is

not sufficient enough to come to the conclusion that it required

repair/remedial work as alleged. Ex.P29 and P29(a) are the

quotations purportedly received by the plaintiff from other

contractor for implementing corrective civil work. However,

nothing is brought on record regarding plaintiff actually having

got the work executed through the said contractor. In the

absence of acceptable evidence in this regard the claim of the

plaintiff under this head cannot be accepted.

Regarding point No.5:

86. The plaintiff has sought reimbursement of

Rs.1,65,000/- with interest at 18% p.a. being the rental paid

by him to the landlord of the premises occupied by the plaintiff

during the period of construction and delayed period. Plaintiff

has got examined one Syed Mohiuddin PW-5 in support of his

- 66 -

claim. Necessary to note that admittedly there was no

agreement between the plaintiff and the defendant regarding

stipulation of time for completion of the construction or the

time was the essence of contract. The final bill was raised by

the defendant during August 2000 which has been received

directly by the plaintiff. Plaintiff has admittedly paid the

substantial portion of the said bill between August and

November 2000. The plaintiff has neither indicated nor

produced any acceptable evidence regarding any agreement or

understanding requiring the defendant to pay and reimburse

the rentals on and after September 2000 to the end of August

2001. In the absence of any agreement in that regard and in

the absence of plaintiff producing acceptable evidence of he

having carried out the repair work after August 2000 when he

terminated the service of the defendant, there is no basis for

plaintiff to claim reimbursement of the monthly rentals. The

claim of the plaintiff under the said head is therefore rejected.

Regarding point No.6:

87. Defendant in his counter claim has claimed

Rs.4,88,255.24 to be payable by the plaintiff. The said amount

includes a sum of Rs.1,05,283.28 being balance payment

against first, second and third/final bill; a sum of

- 67 -

Rs.1,23,423.02 towards accumulated security deposit which

was deducted as per the tender details; Rs.22,736.74 towards

additional bill for construction of base lab and east side

compound wall; Rs.2,36,812.20 being cost of correction,

demolition, construction due to the changes in specification and

design etc., as per the representation given to the architect.

Admittedly first and second bill were certified for payment by

the architect and were paid accordingly by the plaintiff. In

other words the certification of bill has been made after

carrying out the verification and measurement of the work

done. The third and final bill was submitted by the defendant

directly to the plaintiff which has been paid by the plaintiff.

There is nothing on record brought in by the defendant to show

that there was any agreement or assurance by the plaintiff to

pay sum of Rs.1,05,283.28 being the balance amount payable

in respect of the said three bills. The defendant has received

the certified amount in respect of first and second bill and the

amount paid by the plaintiff in respect of third and final bill

without any protest or demur. As regards Rs.1,23,423.02

being purported accumulated security deposit as per the tender

details no evidence is produced in this regard. There is no

mention regarding this aspect of the matter in the bills that

were certified by the architect.

- 68 -

88. Once the defendant admittedly completed the

construction and submitted his final bill during August 2000

which even according to him included tender and non-tendered

items of work as well as reimbursement of cost of construction

due to change in specification and design it cannot be accepted

that plaintiff was due and liable to pay Rs.22,736.74/- and

Rs.2,36,812/- towards construction of base slab and east side

compound wall and the cost of correction and demolition and

reconstruction etc. Nothing prevented the defendant to include

the said items in the final bill if at all there were any such dues.

The claim/demand for the aforesaid amounts has been raised

by the defendant admittedly after issuance of notice by the

plaintiff. As such, the defendant is not entitled for the counter

claim raised in the written statement.

Regarding Point No.7:

89. The trial Court on appreciation of oral and

documentary evidence has declined to accept the case of the

plaintiff. The trial Court has extensively adverted to the

deposition of the Court Commissioner examined as CW-1 and

his report at Ex.C1 to C3. It has taken note of the fact that the

Court Commissioner had carried out the work assigned to him

without notice to the defendant and in his absence. It has also

- 69 -

taken note of the fact the defendant was not given fair

opportunity by the Commissioner during the process of

verifying and examining the work. It has taken into

consideration the admitted errors committed by the

Commissioner in not carrying out the measurement of certain

items physically and also causing certain measurements to be

carried out, calculation sheet to be prepared by the

Commissioner through his students. Thus, the trial Court has

found several discrepancies in the estimate made by the

Commissioner and has thus declined to rely upon his evidence.

90. As regards the evidence of PW2 the trial Court has

found that the said witness had followed the specifications

given by Bureau of Indian Standards without providing any

further details. The trial Court has also found that the said

witness had not referred to all the relevant documents but had

relied upon only few drawings and designs to prepare the

comparative statement. Even the said witness has admitted to

have prepared the report without any notice to the defendant.

As such, the trial Court has declined to accept the evidence of

PW2. Since the only evidence was of PW1, the trial Court has

found the same to be self serving oral testimony containing

- 70 -

several admissions on the issues and equally controverted by

the evidence of DW1.

91. Similarly the trial Court has declined to accept the

counter claim raised by the defendant for want of evidence and

also in view of defendant personally collecting the amounts in

respect of three bills indicating he either having given up or

adjusting the claim for balance amount.

92. This Court does not find any fault or irregularity in

the trial Court appreciating the evidence and declining claim of

both the plaintiff and the defendant and consequently

dismissing the suit and rejecting the counter claim. Point No.7

is answered accordingly.

93. For the aforesaid reasons and analysis this Court is of

the considered view that no grounds are made out by the

Plaintiff as well as the Defendant warranting interference by

this Court. Consequently the appeal filed by the Plaintiff in RFA

No.1473/2012 as well as appeal filed by the Defendant in RFA

No.1922/2012 are dismissed. Judgment and decree dated

21.05.2012 passed in O.S.No.915/2002 is confirmed.

- 71 -

POINT No.8:

I.A.No.1/2024 filed under Section 151 CPC seeking

restitution. In view of the conclusion arrived at on point Nos.2

to 5 in the negative, I.A.No.1/2024 does not survive for

consideration and same is rejected.

Sd/-

(K.S.MUDAGAL) JUDGE

Sd/-

(M.G.S. KAMAL) JUDGE SBN/RL/RU

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter