Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Janashakthi Welfare Layout ... vs The Chief Secretary
2025 Latest Caselaw 5961 Kant

Citation : 2025 Latest Caselaw 5961 Kant
Judgement Date : 28 May, 2025

Karnataka High Court

Janashakthi Welfare Layout ... vs The Chief Secretary on 28 May, 2025

                              -1-




     IN THE HIGH COURT OF KARNATAKA AT BENGALURU

           DATED THIS THE 28TH DAY OF MAY, 2025

                            PRESENT

       THE HON'BLE MR. N. V. ANJARIA, CHIEF JUSTICE

                              AND

           THE HON'BLE MR. JUSTICE K. V. ARAVIND

        WRIT PETITION No.10527 OF 2024 (GM-RES-PIL)

BETWEEN:

1.      JANASHAKTHI WELFARE LAYOUT ASSOCIATION (R),
        No.17,11TH CROSS,
        BASAVANAPURA MIAN ROAD,
        K.R. PURAM,
        BENGALURU-560036.
        RERPESENTED BYITS PRESIDENT,
        SRI.M.R. MAHANTESH,
        MOBILE No. 9845049535,
        PAN No. AFPPM6020C
        EMAIL: [email protected]
                                            ...PETITIONER

(BY SRI VASANTHAPPA, ADVOCATE)

AND:

1.     THE CHIEF SECRETARY,
       GOVERNEMENT OF KARNATAKA,
       VIDHANASOUDHA,
       BENGALURU 560 001.

2.     THE COMMISSIONER
       BBMP, N.R. SQUARE,
       HUDSON CIRCLE,
       BENGALURU 560 027.

3.     CHIEF EXECUTIVE ENGINEER
       BBMP, HOYSALANAGAR,
                           -2-




     K.R PURAM,
     BENGALURU 560 036.

4.   THE CHIEF EXECUTIVE ENGINEER,
     STORM WATER DRAINANGE,
     JAYANAGAR SHOPPING COMPLEX,
     BENGALURU 560 098.

5.   THE ASSISTANT WARD EXECUTIVE ENGINEER,
     BBMP,
     BENGALURU 560 027.

6.   SRIPAD OWNERS ASSOCIATION,
     9TH CROSS, BASAVANAPURA MAIN ROAD,
     K R PURAM,
     BENGALURU 560 036.
                                          ...RESPONDENTS

(BY SMT. NILOUFER AKBAR, AGA FOR R1;

SRI N.R. JAGADEESHWARA, ADVOCATE FOR R2 TO R5; SRI MOHAMMED MOIN ULLA, ADVOCATE FOR SRI M. MUNIRAJA, ADVOCATE FOR R6)

THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO ISSUE A WRIT OF MANDAMUS DIRECTING THE RESPONDENTS TO COMPLETE THE RETAINING WALL, LEFT OUT AT THE DEAD END OF THE 10TH CROSS, S.R. LAYOUT, BASAVANAPURA MAIN ROAD, K.R PURAM, BENGALURU-560036 AND WITH FURTHER DIRECTION TO THE RESPONDENT BBMP NOT TO PUT UP CULVERT/BRIDGE NEAR 10TH CROSS, S.R LAYOUT, BASAVANAPURA MAIN ROAD, K.R PURAM BENGALURU-560036.

THIS WRIT PETITION HAVING BEEN HEARD AND RESERVED FOR JUDGMENT, COMING ON FOR PRONOUNCEMENT THIS DAY, JUDGMENT WAS PRONOUNCED AS UNDER:

CORAM:        HON'BLE THE CHIEF JUSTICE MR. JUSTICE
              N. V. ANJARIA
              and
              HON'BLE MR. JUSTICE K. V. ARAVIND

                         C.A.V. JUDGMENT

              (PER: HON'BLE MR. JUSTICE K. V. ARAVIND)

Heard learned advocate Mr. Vasanthappa for the petitioner,

learned Additional Government Advocate Smt. Niloufer Akbar for

respondent No.1, learned advocate Mr. N.R. Jagadeeshwara for

respondent Nos.2 to 5 and learned advocate Mr. Mohammed Moin

Ulla for learned advocate Mr. M. Muniraja for respondent No.6.

2. The present writ petition, styled as a public interest litigation,

has been filed seeking a direction to the respondent-authorities not

to proceed with the construction of a bridge at the end of 10th

Cross, S.R. Layout, Basavanapura Main Road, K.R. Puram,

Bengaluru, and further to direct them to complete the construction

of a retaining wall of uniform height, measuring 15 feet, near the

10th Cross.

2.1 The averments made in the petition disclose that the

petitioner is a registered association formed by the residents of

10th, 11th, and 12th Cross, Basavanapura Main Road, K.R. Puram,

Bengaluru, with the objective of addressing common grievances

and promoting mutual cooperation among the residents.

2.2 It is stated that a Storm Water Drain (SWD) runs adjacent to

the 10th, 11th, and 12th Cross. The entire area, including the portion

in question, experiences flooding during the monsoon season. It is

further averred that such flooding is attributable to the poor

maintenance of the SWD. To address this issue, the Government

proposed the construction of a retaining wall with a 'U'-shaped

storm water drainage system, with a view to prevent flooding during

the monsoons. Taking into account the flow of water and the

geographical conditions of the area, a retaining wall of 15 feet in

height was constructed.

2.3 It is alleged that, at the instigation of respondent No.6, the

Bruhat Bengaluru Mahanagara Palike (BBMP) halted the

construction of the retaining wall at a height of 4 feet adjacent to

the 10th Cross. It is further alleged that respondent No.6 is

attempting to obstruct the construction of the retaining wall in order

to facilitate the construction of a bridge across the SWD to provide

access to respondent No.6 apartment from the 10th Cross.

2.4 It is contended that if the height of the retaining wall is

reduced to 4 feet, the very purpose of constructing the wall with a

height of 15 feet would be defeated, as such reduction would result

in the diversion of water flow into the residential areas through the

10th Cross.

3. Respondent Nos.2 to 5 - BBMP have filed a memo dated

24.08.2024 enclosing a technical report. As per the said report, the

SWD has been developed to connect Devasandra Lake to

Seegehalli Lake via S.R. Layout. The report states that the

construction of the retaining wall, measuring 15 metres in length,

remains incomplete due to the request made by respondent No.6

for access through the 10th Cross by reducing the height of the

retaining wall.

3.1 It is further stated in the report that the height of the retaining

wall on the upstream side is 3 metres, and on the downstream side

is 3.5 metres. The report opines that the request of respondent

No.6 to construct a crossover/culvert across the SWD at the exit of

the 10th Cross is unscientific. For such construction, the height of

the retaining wall would have to be reduced to 1.10 metres, which,

if done, would lead to flooding and over-spillage of water, thereby

adversely affecting the surrounding areas. The report also notes

that the sanctioned plan issued by the Assistant Director, K.R.

Puram, provides access to S.R. Layout through the 9th Cross, and,

therefore, a crossover/culvert through the 10th Cross is

unwarranted.

4. Respondent No.6 has filed a Statement of Objections

contending that the width of the Storm Water Drain (SWD) has

been increased from 6 feet to 15 feet, and, as a consequence, the

height of the retaining wall as proposed by the BBMP is

unwarranted. It is further stated that the apartment complex of

respondent No.6 houses more than 70 families, and if the

construction of a crossover/culvert at the exit of the 10th Cross is

not permitted, the said families would be deprived of access to the

apartment. It is also contended that the decision of the BBMP to

construct a high retaining wall, as well as the averments made in

the present public interest litigation, are unscientific.

5. Learned advocate Mr. Vasanthappa, appearing for the

petitioner, submits that the BBMP has constructed a 'U'-shaped

Storm Water Drain (SWD) with a retaining wall of 14 feet in height.

It is submitted that if a crossover/culvert is to be constructed at the

end of the 10th Cross, it would have to be constructed at ground

level, thereby necessitating a reduction in the height of the

retaining wall to 4 feet. It is contended that, considering the flow of

water during the monsoon season, the BBMP has constructed a

retaining wall of 14 feet height to facilitate the safe passage of

storm water from Devasandra Lake to Seegehalli Lake.

5.1 It is further submitted that any reduction in the height of the

retaining wall to 4 feet for the purpose of constructing a crossover

at the exit of 10th Cross would result in water flow beyond 4 feet

entering the residential area, thereby causing flooding. The learned

counsel submits that respondent No.6 apartment has an

independent access, and that the request for construction of a

crossover at the exit of 10th Cross is only for the purpose of

obtaining an additional access. It is submitted that, as per the

revenue and BBMP records, respondent No.6 does not have any

sanctioned access through the 10th Cross. It is further alleged that

the demand for construction of a crossover at the said location is

being pursued by exerting political pressure.

6. Learned advocate Mr. N.R. Jagadeeshwara, appearing for

respondent Nos.2 to 5, submits that the Storm Water Drain (SWD)

connecting Devasandra Lake and Seegehalli Lake via S.R. Layout

was developed with side retaining walls of a height ranging from 3

to 3.50 metres, in order to prevent flooding and over-spillage of

water during the monsoon season. It is submitted that, if the

crossover as sought by respondent No.6 is to be constructed, the

height of the side retaining wall would have to be reduced to 1.10

metres.

6.1 It is contended that any reduction of the retaining wall height

below 3 to 3.50 metres would result in storm water entering the

residential areas near the 10th Cross. It is further submitted that the

height of the retaining wall was determined on the basis of a

scientific study, and any reduction thereof would be scientifically

unsound and would likely result in flooding. It is also submitted that

respondent No.6 has an independent access and that the proposed

crossover is unnecessary.

7. Learned advocate Mr. Mohammed Moin Ulla, appearing for

learned advocate Mr. M. Muniraja on behalf of respondent No.6,

submits that prior to the development of the Storm Water Drain

(SWD), its width was 6 feet, and it has now been increased to 15

feet. It is contended that, in view of this increase in width, the

construction of side retaining walls with a height of 14 feet is not

only unnecessary but also unscientific. It is further submitted that

the residents of the apartment complex belonging to respondent

No.6, comprising approximately 70 families, would be deprived of

access if the proposed crossover at the exit of 10th Cross is not

permitted.

8. Having considered the submissions of the learned advocates

for the parties and upon perusal of the material on record, it is not

in dispute that the Storm Water Drain (SWD), including the side

retaining wall between Devasandra Lake and Seegehalli Lake

passing through S.R. Layout and the location in question, has been

constructed. The averments made by the petitioner, as well as

respondent Nos.2 to 5 and respondent No.6, clearly indicate that

the SWD has been constructed with side retaining walls of a height

ranging between 3 metres and 3.50 metres.

9. It is also evident that a portion of the side retaining wall,

measuring approximately 15 metres in length near respondent

No.6 apartment and at the exit of the 10th Cross Road, remains

incomplete. The reason for the incompletion appears to be the

request made by respondent No.6 for construction of a

crossover/culvert at the said location. The petitioner has objected

to the construction of the crossover, contending that if the height of

the retaining wall is reduced to accommodate the crossover, it

would result in flooding of the residential area situated along 10th

Cross Road. In contrast, respondent No.6 contends that, in view of

- 10 -

the increase in the width of the SWD from 6 feet to 15 feet, the

existing height of the retaining wall (3 to 3.50 metres) is excessive

and unnecessary.

10. Respondent Nos.2 to 5 - BBMP have submitted a technical

report, which states that in order to construct the proposed

crossover, the height of the retaining wall would need to be

reduced to 1.10 metres. The report further indicates that such a

reduction would result in flooding and over-spillage of water into the

adjoining residential area along 10th Cross Road. The technical

report categorically states that reducing the height of the side

retaining wall would be unscientific and would likely lead to

flooding.

11. The factual matrix as presented in this petition, along with the

rival contentions advanced by the parties, gives rise to two principal

issues for consideration. Firstly, whether the residents of

respondent No.6 apartment would be denied access in the event

the proposed crossover at the exit of 10th Cross is not constructed.

Secondly, whether it is feasible and appropriate to reduce the

height of the retaining wall to facilitate such construction.

- 11 -

12. In light of the rival contentions, respondent No.6 was

afforded an opportunity during the course of the hearing to produce

documents establishing the existence of access to the land on

which respondent No.6 apartment is constructed through the 10th

Cross. Learned advocate for respondent No.6 filed a memo dated

04.04.2025, enclosing a conversion order dated 27.02.2012,

photographs, and the building sanction plan issued by the BBMP.

However, the learned advocate for respondent No.6 was unable to

identify or demonstrate the existence of a road through the 10th

Cross connecting to respondent No.6 apartment.

13. Conversely, the photographs annexed to the memo confirm

the flooding of the 10th Cross, which lends support to the contention

of the petitioner. Furthermore, the scientific report submitted by

respondent Nos.2 to 5 BBMP establishes that respondent No.6

apartment has an independent access road. This evidence

effectively negates the claim of respondent No.6 that there exists a

road through the 10th Cross providing access to their apartment.

14. According to the technical report submitted by respondent

Nos.2 to 5 BBMP, the Storm Water Drain (SWD) between

Devasandra Lake and Seegehalli Lake via S.R. Layout was

developed with side retaining walls maintained at a height ranging

- 12 -

from 3 metres to 3.50 metres to prevent flooding and over-spillage

of water into the adjoining residential areas during the monsoon

season. The report states that the retaining wall height has been

consistently maintained throughout the length of the SWD between

Devasandra Lake and Seegehalli Lake. The construction of the

proposed crossover, as per the report, would necessitate a

reduction in the height of the retaining wall to 1.10 metres. Such a

reduction would give rise to two significant anomalies. Firstly, it

would render the construction of the retaining wall, maintained at a

height of 3 metres to 3.50 metres throughout the length of the

SWD, purposeless. Secondly, the flow of water exceeding the

height of 1.10 metres would enter the residential area through the

10th Cross, resulting in flooding and over-spillage of water in the

surrounding locality. This would defeat the very purpose of

constructing the SWD and retaining walls at a height exceeding 3

metres.

15. The technical report further states that, as per the building plan

approved by the Assistant Director of Town Planning, K.R. Puram,

respondent No.6 apartment has its entry and exit through 9th Cross,

S.R. Layout, Basavanapura Main Road, Bengaluru. Considering

that respondent No.6 has a planned entry and exit, the proposed

- 13 -

crossover through 10th Cross would constitute an alternative

access, which, however, comes at the risk and cost of potential

flooding and over-spillage of water towards the 10th Cross. The

construction of the side retaining wall to a height exceeding 3

metres has been identified by the technical experts as the only

viable solution to prevent flooding. In light of the foregoing and

considering all aspects, it is difficult to accept the contention of

respondent No.6 that the height of the retaining wall is unscientific.

16. Having considered the factual aspects and the documentary

evidence on record, the Court is persuaded to entertain this public

interest litigation and to issue appropriate directions.

17. Respondent Nos. 2 to 5 are hereby directed to complete the

construction of the Storm Water Drain, including the side retaining

wall, to the prescribed height of 3 metres to 3.50 metres as

planned, particularly in the pending stretch of approximately 15

metres near Sripada Apartments at the exit of 10th Cross Road

connecting Basavanapura Main Road, Bengaluru.

18. Considering the importance of the issue and the imminent

approach of the monsoon season, the aforesaid exercise shall be

completed within six weeks from the date of this order.

- 14 -

19. With the above observations and direction, writ petition is

disposed of.

Sd/-

(N. V. ANJARIA) CHIEF JUSTICE

Sd/-

(K. V. ARAVIND) JUDGE

MV

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter