Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Torrent Solar Power Private Limited vs Power Grid Koppal Gadag
2025 Latest Caselaw 11398 Kant

Citation : 2025 Latest Caselaw 11398 Kant
Judgement Date : 15 December, 2025

[Cites 19, Cited by 0]

Karnataka High Court

Torrent Solar Power Private Limited vs Power Grid Koppal Gadag on 15 December, 2025

Author: M.Nagaprasanna
Bench: M.Nagaprasanna
                             1



Reserved on   : 26.11.2025
Pronounced on : 15.12.2025

  IN THE HIGH COURT OF KARNATAKA DHARWAD BENCH

           DATED THIS THE 15TH DAY OF DECEMBER, 2025

                            BEFORE

           THE HON'BLE MR. JUSTICE M. NAGAPRASANNA

           WRIT PETITION No.104896 OF 2025 (GM - RES)


BETWEEN:

TORRENT SOLAR POWER PRIVATE LIMITED
SAMANVAY, 600, TAPOVAN, AMBAVADI
AHMEDABAD, GUJARAT - 380 015.
REPRESENTED BY ITS
AUTHORISED SIGNATORY
MR. V. BALASUBRAMANIAN.
                                                ... PETITIONER

(BY SRI K.N.PHANINDRA, SR.ADVOCATE A/W
    SRI SANTOSH KUMAR B.MALLIGAWAD, ADVOCATE
    SRI SUNAYANA BASU MALLIK AND
    SRI ARFATU AZAM, ADVOCATES)

AND:

POWER GRID KOPPAL GADAG
TRANSMISSION LIMITED
B-9, B-9 QUTAB INSTITUTIONAL AREA
KATWARIA SARAI,
NEW DELHI - 110 016.

ALSO AT:
                            2




FIRST FLOOR, PLOT NO.7 AND 8
DAMBAL LAYOUT
GADAG
KARNATAKA - 582 103.

                                           ... RESPONDENT

(BY SRI PRAMOD NAIR, SR. ADVOCATE FOR
    SRI M.S.HALLIKERI, ADVOCATE)


      THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO I. ISSUE A
WRIT ORDER OR DIRECTION OF MANDAMUS OR IN NATURE OF
MANDAMUS DIRECTING THE RESPONDENT TO RE-ROUTE THE
EXTRA HIGH VOLTAGE ("EHV") LINES WITHOUT INTERRUPTING
ANY WORK, ERECTIONS, ETC. WITHIN THE DISTANCE OF 227
METERS OF THE PETITIONER'S LAND PARCELS AS PER MINISTRY
OF NEW AND RENEWABLE ENERGY ("MNRE") GUIDELINES AT WTG
LOCATIONS AS PER COORDINATES MOREFULLY DETAILED IN THE
MAP/SKETCH (ANNEXURE-R); II. ISSUE A WRIT ORDER OR
DIRECTION OF CERTIORARI OR IN THE NATURE OF CERTIORARI
QUASHING THE SETTING ASIDE THE LETTERS DATED. 01/04/2025
BEARING REFERENCE NUMBER SRTS-II/PKGTL/GADAG TLC/2024-
25/273 (ANNEXURE-S), THE LETTER DATED. 07/02/2025 BEARING
REFERENCE        NUMBER      PKGTL-GADAG/TLC/TORRENT/255
(ANNEXURE-P) SENT BY THE RESPONDENT TO THE PETITIONER
ASKING TO RELOCATE THE WTG LOCATIONS ALONG WITH THE
CONNECTED COMMUNICATION DATED. 06/02/2025 (ANNEXURE-
N); III. ISSUE A WRIT ORDER OR DIRECTION OF MANDAMUS OR
IN THE NATURE OF MANDAMUS RESTRAINING THE RESPONDENT
FROM ISSUING ANY DIRECTIONS TO, OR OTHERWISE IN ANY
MANNER SEEKING TO COMPEL A CHANGE IN THE WTG LOCATIONS
AND FURTHER RESTRAIN THE RESPONDENT FROM IN ANY MANNER
INTERFERING WITH THE BUSINESS AND ACTIVITIES/PROJECT OF
THE PETITIONER.
                                   3



     THIS WRIT PETITION HAVING BEEN HEARD AND RESERVED
FOR ORDERS ON 26.11.2025, COMING ON FOR PRONOUNCEMENT
THIS DAY, THE COURT MADE THE FOLLOWING:-


CORAM:       THE HON'BLE MR JUSTICE M.NAGAPRASANNA

                              CAV ORDER



      The petitioner is at the doors of this Court seeking the

following reliefs:


      "i.    Issue a writ order or direction of mandamus or in the
             nature of mandamus directing the Respondent to re-route
             the Extra High Voltage ("EHV") Lines without interrupting
             any work, erections, etc. within the distance of 227
             meters of the Petitioner's land parcels as per Ministry of
             New and Renewable Energy ("MNRE") Guidelines at WTG
             Locations as per coordinates morefully detailed in the
             map/sketch (Annexure-R)

      ii.    Issue a writ order or direction of certiorari or in the
             nature of certiorari quashing and setting aside the letters
             dated 01/04/2025 number reference bearing by SRTS-
             II/PKGT L/Gadag TLC/2024-25/273 (Annexure- S), the
             letter dated 07/02/2025 bearing reference number
             PKGTL-Gadag/TLC/Torrent/255         (Annexure-P)      sent
             Respondent to the Petitioner asking to relocate the WTG
             Locations along with the connected communication dated
             06/02/2025 (Annexure-N);

      iii.   Issue a writ order or direction of mandamus or in the
             nature of mandamus restraining the Respondent from
             issuing any directions to, or otherwise in any manner
             seeking to compel a change in the WTG Locations and
             further restrain the Respondent from in any manner
             interfering with the business and activities/Project of the
             Petitioner; and
                                         4




       iv.    Pass such orders as this Hon'ble Court may deem just and
              proper in the facts and circumstances of the present writ
              petition."


       2. Facts in brief, germane, are as follows:


       2.1.   The     petitioner   -    Torrent     Solar   Power   Pvt.   Ltd.,

(hereinafter referred to as the 'Company' for short) is a Company

established in the year 2020, as an integrated power utility, having

its   business   or    interest    in       power   generation,   transmission,

distribution and supply of power cables and operates wind power

generation projects at various places. The respondent is the Power

Grid Koppal Gadag Transmission Ltd., (hereinafter referred to as

the 'Power Grid' for short) a wholly owned subsidiary of the Power

Grid Corporation of India. Power Grid is incorporated as a special

purpose vehicle of the Government of India for transmission.                 In

the years 2021-2022, the petitioner is said to have conducted a

deliberation with the Ministry of New and Renewable Energy

(MNRE) for setting of 300.3 MW. Wind power project, which is

proposed to be established in the villages of Yalaburga and Koppal

Taluk of Koppal District. After the deliberations, it transpires that
                                 5



the petitioner submits an application to the Karnataka Renewable

Energy Development Limited (KREDL) as per the MNRE guidelines,

requesting for allotment of 300.3 MW. wind power project under the

Inter-State Transmission System (ISTS) category at various places.



      2.2. Pursuant to the said deliberation, the petitioner is said to

have prepared a detailed project report for the project for the

purpose of enquiry or investigation into the feasibility of the project

and is submitted to KREDL. The particulars of the locations and the

project including the latitude and longitude of the land requirement,

the tentative survey numbers, the tentative village names, the

height of the wind mast for each proposed site and the tentative

project schedule are said to have been submitted by the petitioner.


      2.3. The Government, in terms of its order dated 23-02-2022,

accorded an in-principle approval to the project of the petitioner by

issuance of a Government order, pursuant to which, the petitioner

enters into an agreement with KREDL, agreeing to complete the

project by 22-02-2028. Between 27-04-2023 and 29-11-2023, the

petitioner secured conversion of agricultural lands into non-
                                6



agricultural purposes, as obtaining under Section 95 of the

Karnataka Land Revenue Act, 1964, for the purpose of the limited

use as industrial wind mills. On 13-12-2023, the Government of

India is said to have granted prior approval to the respondent -

Power Grid under Section 68(1) of the Electricity Act, 2003

(hereinafter referred to as the 'Act' for short) for installation of

overhead transmission lines under the transmission scheme for

integration of renewable energy zone.


      2.4. A power purchase agreement is entered into between the

petitioner and the Solar Energy Corporation of India (SECI), for

buying wind power from petitioner as an intermediary procurer as

per the tender. The petitioner while conducting the foundational

drilling work for the purpose of wind turbine generation at the

proposed project site, officers of the respondent are said to have

approached the petitioner and asked the petitioner to stop erecting

the Wind Turbine Generators (hereinafter referred to as the 'WTG'

for short) at some of the survey numbers acquired by the

petitioner, as they were falling near the line corridor of respondent

within 100 meters distance in Survey No.202/2 which was not
                                   7



permissible in law. The impugned communication then comes about

on 06-02-2025 through the electronic mail, that the petitioner was

conducting work near the transmission lines of the respondent,

thereby the request was made to stop such work.                Another

impugned letter springs on the next day i.e. 07-02-2025, with the

same intent of stopping the work. A joint inspection is conducted on

28-03-2025, which results in the third impugned letter that there

were    discrepancies   against       each   of   the   WTG   locations.

Communications galore between the two, all of which go unheeded

and the present petition is preferred.



       3. Heard the learned senior counsel Sri K.N.Phanindra,

appearing for the petitioner and the learned senior counsel

Sri Pramod Nair, appearing for the respondent.



       4. The learned senior counsel Sri K.N.Phanindra appearing

for the petitioner, would vehemently contend, that the proposed

Extra High Voltage (EHV) lines of the respondent are against the

Central Electricity Authority (Measures Relating to Safety and

Electricity Supply), Regulations 2023 (hereinafter referred to as the
                                  8



'Regulations' for short). He would place reliance upon Regulation 63

of the said regulations to contend that overhead transmission lines

or EHV lines, shall, as far as possible, not pass over or adjacent to

any existing building. The windmills proposed to be erected at the

WTG locations fall within the definition of 'building' under the

explanation to Regulation 63 of the said regulations. Therefore, he

would submit that the construction work of the respondent is in

violation of transmission planning norms and the request for

realignment of EHV lines is in tune with the manual of transmission

planning criteria.   It is his further submission that the petitioner

falls within the ambit of infrastructure projects as envisaged by the

State Government in its infrastructure policy.       The respondents

have violated the Telegraph Act, 1885 and Works of Licensees

Rules, 2016. He would seek to place reliance upon the judgment of

the Apex Court in the case of POWER GRID CORPORATION OF

INDIA LTD., v. CENTURY TEXTILES AND INDUSTRIES LTD.,

[(2017)5    SCC      143]   to   contend   that   while   laying   down

transmission lines buildings should be avoided.
                                9



      5. Per contra, the learned senior counsel Sri Pramod Nair,

representing the respondent contends that the WTG locations, as

approved by KREDL in terms of the Government Order dated

23-02-2022 were situated at a safe distance of more than 227

mtrs. from the transmission line corridor.    The petitioner has also

unilaterally shifted the WTG locations subsequently on its own,

creating a conflict with the respondent's transmission lines.     Had

the petitioner not shifted the three contested WTG locations, there

would not have been any conflict. For the act of the petitioner, it

cannot now seek alteration of its tower locations. The petitioner has

also failed to furnish any revised approval from KREDL or MNRE for

shifting the WTG locations. It is the case of the respondent that one

of the villages where petitioner claim to have purchased land is not

present in the KREDL approval order dated 23-02-2022.              The

respondent has completed foundation works at all three locations

and the towers are also erected.       At this stage, if the prayer is

granted, it would negatively impact the petitioner's own project,

since any power generated by the petitioner cannot be transmitted

without transmission infrastructure created by the respondent. The

respondent's   transmission    lines   have    been   finalized   after
                                    10



considering various factors, including KREDL approval in favour of

the petitioner for establishment of WTG lines.      The respondent's

project serves a larger public purpose and is a part of the Interstate

Transmission Network envisaged to strengthen the National Grid.

Any order to shift the lines would create huge dent to public

purpose and to various power generators. He would seek dismissal

of the petition.


      6. I have given my anxious consideration to the submissions

made by the learned counsel for the respective parties and have

perused the material on record.



      7. The afore-narrated facts are not in dispute. The only issue

that falls for consideration is:


      "Whether there is any illegality or arbitrariness in the

act of the respondent establishing its transmission lines

warranting interference at the hands of this Court?"



      8.   The petitioner makes an application before the KREDL, as

per the guidelines, requesting for allotment of 300.3 MW. of wind
                                 11



power project under the ISTS category at various villages.         The

application of the petitioner submitted to KREDL reads as follows:


     "Dear Sir,

     Karnataka has emerged as the hub for the investments in the
     Green Energy Sector thanks to the kind support and co-
     operation in creating a conducive environment for the
     Renewable sector in the state. The State Government has been
     in the forefront in resolving the problems faced by the
     Renewables and in securing the Investor's interest and
     increasing investment in the Sector.

     To capitalize this occasion and opportunity provided by the
     Govt. of Karnataka through the RE Policy 2009-2014, We, M/s.
     Torrent Solar Power Pvt. Ltd is a Special Purpose Vehicle
     (SPV) created by M/s. Torrent Power Limited through its
     Indian subsidiary to develop, execute, manage and run 300.3
     MW wind power generation plant at various villages of Nittali,
     Benakal, Gavarhal, Chendoor, Arken, Budsettinhal, Kinnal,
     Mudapur, Chikbeedinhalu, Kalkera Hatti, Kamanur, Karadıgudda,
     Hanmanhatti,       Honhunashi,    Kudri,    moti,   Mangalore,
     Bhairanayakanhallı,       Balapura,      Kavalkere,   Kadrali.
     Hirebeedinhalu, Muthal, Sirur, Bedwatti, Yadiapur. Budgumpi,
     Balgera, Tipparasanhalu, Kakkıhalli, Kuknoor, Kuknoor Talulk,
     Koppal District in Karnataka.

     The Site has been identified as ideally suited for the
     development of wind farm based on wind data published by
     NIWE for this regime. As the proposed site is nearer to the
     NIWE wind mast at TARLAKATTI of 100m the annual wind speed
     recorded at 100m height is 6.68 m/s and the extrapolated wind
     at 130m is 7.2m/s the recorded wind speed and frequency
     distribution have indicated that the proposed site is eminently
     suitable for good generation of electricity.

     M/s. Torrent Solar Power Pvt. Ltd is SPV of M/s. Torrent Power
     Limited which has expertise in developing Wind power projects,
     intends to develop 300.3 MW of Wind Power projects with an
     approximate investment of Rs. 2500 Crores. The project during
                              12



the implementation will create significant direct and indirect
employment opportunities and add 300.3 MW of Green power in
the state. We have selected the proposed site based on the
analysis of the Wind, site topography, elevation and the
availability of land for wind farming and its proximity to the grid.
The tentative villages for the proposed project are Nittali,
Benakal, Gavarhal, Chendoor, Arkeri, Budsettinhal, Kinnal
Mudapur, Chikbeedinhalu, Kalkera Hatti, Kamanur, Karadigudda,
Hanmanhatti,        Honhunashi,     Kudri      moti,    Mangalore,
Bhairanayakanhalli, Balapura, Kavalkere, Kadrali Hirebeedinhalu
Muthal, Sirur, Bedwatti, Yadiapur, Budgumpi, Balgera,
Tipparasanhalu, Kakkihalli, Kuknoor, Koppal District."

                        ....    ....     ....

1.    Tentative WTG Geographical latitude and longitude
      of 91 Nos WTG locations in DMS is (Degree Minutes
      and seconds) is attached as follows.

      WTG coordinates for 300.3MV with --- Nos WTG
      locations

                        ....    ....     ....

2.    Tentative extent of private land required for 300.3
      MW Project.
      Approximate land required for one WTG is roughly 156 X
      156 meters which shall cover activities such as casting
      the foundations, erection of DP Structures, Breaker yards,
      Metering yards and additional area for assembly,
      positioning of cranes for erection and other electrical
      infrastructure.   Area    required    for  internal  roads
      approximate width 6 meters to 8 meters and area for
      overhead transmission lines would be additional. Thus,
      the total areas for installation of 300.3 MW Wind project
      works out to be around 750 acres (approximate
      estimation subject to variation). However, the extent of
      land may vary during land acquisition considering the site
      dynamics

3. Tentative Survey nos and Village names and taluk The
   tentative villages for the proposed project are Nittali,
                                       13



        Benakal, Gavarhal, Chendoor Arkerı, Budsettinhal,
        Kinnal, Mudapur, Chikbeedinhalu, Kalkera Hatti,
        Kamanur, Karadigudda, Hanmanhatti, Honhunashi,
        Kudri moti, Mangalore, Bhairanayakanhalli, Balapura,
        Kavalkere, Kadrali, Hirebeedinhalu, Muthal, Sirur,
        Bedwatti,     Yadiapur,      Budgumpi,      Balgera,
        Tipparasanhalu, Kakkihalli, Kuknoor, Koppal District
        Karnataka."

                                                          (Emphasis added)

Tentative extent of private land required for the aforesaid project

was indicated in the application including the geographical latitude

and longitude coordinates of 91 WTG locations in DMS (Degree

Minutes and seconds). In terms of the order dated 23-02-2022, the

Government accords approval to the project of the petitioner. The

approval reads as follows:


     "ಪ ಾವ ೆ:
                ೕ ೆ   ಓದ ಾದ   ಕಮ    ಸಂ ೆ   (1)ರ   ಪತ ದನ ಯ    ವ ವ ಾಪಕ      ೇ ಶಕರು,
     "ೆ.ಆ$.ಇ.&.ಎ(. ರವರು ಸ"ಾ ರ"ೆ) ಸ*+,ರುವ ಪ ಾವ ೆಯ*+ M/s Torrent Solar Power Private
     Limited ರವರು "ೊಪ.ಳ 0 ೆ+ಯ ಯಲಬು3ಾ      ಮತು "ೊಪ.ಳ 4ಾಲೂ+ಕುಗಳ ಕೂಕನೂ$, ಮ ಾ6,
     ಹಂ9 ಾ:, ಕ ೆ)ೕರ, ಬು$ ;ೆ<6 ಾಳ,    =ಾ6*, ಕ>)ಹ?@,, ಗವರAಾಲ, Bಪ.ರ ಾ ಾಲ, ಚಂದೂ$,
     Dೆನಕ(, ಯ&EಾಪFರ, Dೆಡವ<6 ಬHಹ<6 ಬುದುಗುಂI, Jರೂ$, ಆ"ೇ H, ಮಂಗಳK$, ಮೂತ(,
     LMೇNಡ ಾ( ಕ ಾ *, > ಾOಲ, 9ಕ)Nದ ಾ(, ತಲಕP ಪFರ, AೊP ಹು O ಯಲ          QೕH, ಹನಮP
     ಹ<6 ಮತು ಕುR Sೕ< 3ಾ ಮಗಳ*+ 300.3 ಮ.Tಾ . ಾಮಥ ದ ಪವನ Vದು W Xೕಜ ೆಯ ಕುHತು
     VಸZತ Xೕಜ ಾ ವರRಯನುO ತEಾH,, "ೆ ಡ( 3ೆ ಸ*+,ರುವF ಾ[ Aಾಗೂ ಸದH Xೕಜ ೆ\ಂದ
     ಉ4ಾ.ದ ೆEಾಗುವ Vದು ತನುO "ೇಂದ ಸ"ಾ ರದ Power Grid Corporation of India Limited
     (PGCIL) ನ Vದು W ಪ ಸರಣ _ಾಲ"ೆ), _ೋ&,, Aೊರ Mಾಜ ಗ?3ೆ SECI N&`ಂa / ಮೂರ ೇ ವ >3ೆ
     Inter State Transmission System (ISTS) ಮು ಾಂತರ Vದು W ಸರಬMಾಜು bಾಡುವ ವಗ ದ&
     ಪFB Vಂc ಟDೈ P 3ೆ 4 ಎಕMೆಯಂ4ೆ Footprint basis            ೆ>)ೕಕH, ಜfೕನುಗಳನುO
                                     14



ಉಪXೕ[ಸುವFದು          ಮತು      ಪವನ      Vದು W      ಘಟಕಗಳ         ಅಂತರವನುO             MNRE
ಸು4ೋ ೆ/bಾಗ ಸೂ9ಯಂ4ೆ        ಅಳವ&ಸುವಂ4ೆ       ಷರತುಗಳನುO       Vj,,    ಹಂ9"ೆ        ೕಡುವಂ4ೆ
"ೋHರುವF ಾ[ B?,ರು4ಾMೆ.

            M/s Torrent Solar Power Private Limited ಕಂಪ ಯು R ಾಂಕ: 28.07.2020 ರಂದು
 ೋಂ ಾವkೆ3ೊಂ&ದುl ಇದರ       ೋಂ ಾ\ತ ಕmೇHಯು ಗುಜMಾW ನ ಅಹಮ ಾDಾn ನ*+
 ಾIತ3ೊಂ&ರುತ ೆ.      ಸದH   ಕಂಪ ಯು      M/s   Torrent   Power    Limited        ರವರ    ಅಂಗ
ಸಂ ೆEಾ[ರುತ ೆ. M/s Torrent Power Limited ರವರ            ೆo ವW    R ಾಂಕ: 31.03.2021ರ
ಅಂತ "ೆ) ರೂ.10,251.23 "ೋ<ಗpಾ[ರುತ ೆ ಎಂದು mಾ=ೆ c ಅ"ೌಂ=ೆಂo ರವರು ದೃsೕಕರಣ
ಪತ ವನುO ೕ&ರು4ಾMೆ.

              ೕ ೆ ಓದ ಾದ ಕ ಮ ಸಂ ೆ (2) ರ ಹಂ9ಕ ಸfB ಸtೆಯು M/s Torrent Solar Power
Private Limited ರವರು "ೊಪ.ಳ 0 ೆ+ಯ ಯಲಬು3ಾ             ಮತು "ೊಪ.ಳ 4ಾಲೂ+ಕುಗಳ VVಧ
3ಾ ಮಗಳ*+ 1STS ವಗ ದ&ಯ*+ ಹಂ9"ೆ         ೕಡುವಂ4ೆ "ೋHರುವ 300.3         .Tಾ    ಾಮಥ ದ ಪವನ
Vದು W Xೕಜ ೆಯ ಸಳವF ಾಸ[ ಜfೕ ಾ[ರುತ ೆ ಸದHಯವರು 3.3 ಮ.Tಾ . ಾಮಥ ದ 91
Vಂc     ಟDೈ P ಗಳನುO ಅಳವ&ಸುBದುl, ಅಳವ&ಸುವ Wind Turbine ಗ?3ೆ ಅvಾಂಶ ಮತು
Mೇ ಾಂಶಗಳನುO     ೕ&ರು4ಾMೆ. ಅದುದHಂದ ಸದH ಅwವೃRx ಾರರು ಅಳವ&ಸುವ ಪ B ಟDೈ P ನ
footprint _ಾಗ"ೆ) 4 ಎಕMೆಗಳಂ4ೆ ಒಟು6 364 ಎಕMೆ (91 x 4 =364) ಜfೕನನುO bಾತ ಪವನ Vದು W
Xೕಜ ೆಯನುO        ಅನುzಾ{ನ3ೊ?ಸಲು     Toposheet   57     A/2    ಮತು         57   A/3    ಗಳ*+
ಉಪXೕ[,"ೊಳ@ಬಹು ಾ[ ೆ Aಾಗೂ ಸದHಯವರು ಅಳವ&ಸುವ ಪವನ Vದು W ಘಟಕಗಳ
ಅಂತರವನುO        MNRE       ಸು4ೋ ೆ/bಾಗ ಸೂ9ಯಂ4ೆ          (Micrositing          Guidelines)
ಆಳವ&ಸDೇ"ಾ[ರುತ ೆ. ಆದ "ಾರಣ Xೕಜ ೆ3ೆ Dೇ"ಾಗುವ ಜfೕನನುO ಪ|ೆಯುವFದು ಮತು.
PGCIL ಂದ Evacuation Mಾvೇಪkಾ ಪತ Aಾಗೂ LTA approval ಪ|ೆಯುವFದು ಅwವೃRx ಾರರ
ಜ ಾDಾlHEಾ[ರುತ ೆ ಎಂದು B?ಸು4ಾ ಈ "ೆಳಕಂಡ ಷರತುಗ?3ೊಳಪಟು6 M/s Torrent Solar
Power Private Limited ರವH3ೆ "ೊಪ.ಳ 0 ೆಯ ಯಲಬು3ಾ ಮತು "ೊಪ.ಳ 4ಾಲೂ+ಕುಗಳ VVಧ
3ಾ ಮಗಳ*+ ISTS ವಗ ದ&ಯ*+ 300.3         .Tಾ   ಾಮಥ ದ ಪವನ Xೕಜ ೆಯನುO ಹಂ9ಕ ೕಡಲು
ಸfBಯು ಸTಾ ನುಮB\ಂದ J~ಾರಸು• bಾ&ರುತ ೆ.

       1)        ಸದH Xೕಜ ೆ\ಂದ ಉ4ಾ.ದ ೆEಾಗುವ Vದು W ನುO "ೇಂದ ಸ"ಾ ರದ
                 Power Grid Corporation of India Limited (PGCIL) ನ Vದು W
                 ಪ ಸರಣ _ಾಲ"ೆ),
                       _ಾಲ"ೆ) _ೋ&,,
                               _ೋ&, Aೊರ Mಾಜ ಗ?3ೆ SECI N&`ಂa / ಮೂರ ೇ ವ >3ೆ
                 Inter State Transmission System (ISTS)S ಮು ಾಂತರ Vದು W
                 ಸರಬMಾಜು bಾಡಲು
                                   15




            2)    ಈ3ಾಗ ೇ ಇತMೆ ಅwವೃRx ಾರರುಗಳ€ ಹಂ9"ೆ/4ಾB
                                              ಹಂ9"ೆ 4ಾB ಕ ಅನುSೕದ ೆಯನುO
                  ಪ|ೆRರುವ ಪ ೇಶದ*+ ಪ ಾIತ Xೕಜ ೆಯು Overlap ಆ[ದl*,+ ಸದHಯವರು
                  "ೋHರುವ ಪ ಾವ ೆಯ ಹಂ9"ೆ/4ಾB
                                   ಹಂ9"ೆ 4ಾB ಕ ಅನುSೕದ ೆಯು ರದುl3ೊಳ€@ತ ೆ."
                                                                      ೆ

                                                      (Emphasis added)

The latitude and longitude of WTG locations were also indicated in

the order of approval. The petitioner enters into an agreement with

KREDL on 07-03-2022.          The location for the agreement with

latitude and longitude is as follows:


                               "....     ....   ....

      WHEREAS the State of Karnataka has decided to permit private
      sector to generate Electricity from Wind Energy projects in the
      State.

      M/s Torrent Solar Power Private Limited, have requested
      KREDL to grant permission to allot a wind power project of
      300.3 MW capacity at Kukanur, Masba Hanchinal, Kalkera,
      Budshettinhal, Nittali, Kakkihalli, Gavarahala, Tipparasanala,
      Chendoor, Benakal, Yadiyapura, Balageri, Bedavatti, Arkeri,
      Mangalura,    Muthal,    Hirebidanal,    Kadhrahali,   Kinnala,
      Chikkabıdanal, Talakanpura, Honhunsi, Yelamgeri, Hanmanhatti
      and Kudrimoti villages of Yelaburga and Koppal taluks,
      Koppal district, Karnataka and the same having being
      recommended      by     KREDL       vide   its   letter    No:
      KREDL/08/TSPPL-300.3               MW/Yelaburga/Koppal/F-
      10(2022)/204, Dated: 31-01-2022, the Government had
      accorded approval for the project vide Government Order No:
      ENERGY 59 NCE 2022, BENGALURU, Dated: 23-02-2022.

      Tentative Latitude and Longitude of WTG Locations for
      300.3 MW (91 Nos of WTG X 3300 kW) capacity Wind
      Power Project of M/s Torrent Solar Power Private
      Limited."
                                        16




Conversion     orders     are    accordingly     passed    by    the    Deputy

Commissioner on 3 dates viz., 27-04-2023, 31-10-2023 and

29-11-2023. On 13-12-2023, the Ministry of Power, Government

of India grants approval to the respondent - Power Grid under

Section   68(1)   of    the      Act    for   establishment     of   Overhead

Transmission lines of 400 kV in Koppal and Gadag districts. On 26-

12-2023, the petitioner alleges that the respondent entered into

Transmission Service Agreement with the Central Transmission

Utility. The respondent defends the said allegation contending that

the respondent has complied with all the statutory requirements of

publicity regarding the alignment of the transmission lines, by

publishing the notices in leading newspapers of Koppal and Gadag

districts. When things stood thus, on 06-07-2024 a public notice is

issued by the respondent under Section 15(2) of the Act of the

respondent's    project    for    drawing      up   of   transmission    lines.

Objections were invited from general public mentioning the name of

Koppal and Gadag district, which are the places in which the

transmission lines would pass. On 26-12-2024 the Ministry of

Power, Government of India, under Section 164 of the Act, confers
                                  17



upon the respondent the powers conferred upon the Telegraph

Authority.



      9. On the other hand, in compliance with the timeline

stipulated, the petitioner initiated the requisite activities for timely

implementation of the project and while conducting the foundation

and drilling work for WTG at the proposed project site, the officers

of the respondent approach the petitioner and directs the petitioner

to stop erecting the WTG, as some of the survey numbers acquired

by the petitioner were falling near the line corridor of the

respondent which was within 100 mtrs distance in Sy.No.202/2.

Therefore, now the lines are to clash with the windmill. Therefore,

the petitioner then taking up to the respondent of the issue receives

the impugned letter on 06-02-2025 to stop work.         The impugned

letter reads as follows:


      "From:        Chandran G (जी. चं न) <[email protected]>
      Sent:         Thursday, February 6, 2025 15:28
      To:           Abhilash Murali/Wind-Project/Kamrej
      Subject:      Fw: Final Route Transmission scheme for
                    integration of Renewable Energy Zone (REZ)
                    Phase-ll in Koppal (Phase-A) and Gadag-II
                    (Phase-A) in Karnataka System Strengthening at
                                 18



             Koppal-II and Gadag-II for integration of RE
             generation projects
Attachments: 400KV     DC     KG   Line    Final  Alignment
             20250129.kmz, Koppal Kudgi.kml;
             Koppal_Raichur_Total_File.kmz, Gadag Koppal
             Line-2 After DS kml; Tentative Survey Numbers
             2nd 400KV DC Gadag-Koppal Line.pdf

You don't offers get email from [email protected]. Learn why this is
important
[External: Treat content with extra caution.]

Dear Sir,
Please see the trailling mail

Thanks and Regard,

चं न जी./CHANDRAN G
महा बंधक /General Manager
पावर    ड को पल गदग ांस मशन ल मटे ड
(पावर    ड कॉप रे शन ऑफ इं$डया ल मटे ड क& पण(
                                           ू *वा म+व वाल, सहयक कंप-न)

POWERGRID KOPPAL GADAG TRANSMISSION LIMITED
(A  WHOLLY     OWNED        SUBSIDIARY OF POWERGRID
CORPORATION OF INDIA LTD)
KOPPAL CAO/को पल -नमा(ण .े/
400 के वी म-नराबाद
           ु       उप क34/400KV MUNIRABAD SUBSTATION,
गल
 ु दाह5ल, पो*ट/Guldahalli Post को पल िजला/KOPPAL DISTRICT,
कना(टक/KARNATAKA - 583228.
Cell +91 9434740004
___________________________________________________

From: Chandran G(जी चं न] <[email protected]>
Sent: Thursday, February 6, 2025 3:21 PM
To:[email protected] <abhilash.murali@torren
tpower.com>
Cc:     Pawan      Kumar      Gupta     {पवन    कमार
                                                 ु        ग7ा
                                                           ु }
<[email protected]>; Venkatarao Chejarla {चेजारला व3 कट
                           19



राव} <[email protected]>; Pavan Kumar Kaja {काजा पवन
कमार
 ु  }       <[email protected]>;Chandrakant.       {चं कांत}
<[email protected]>; Balineni Bhaskar {बा लने-न भा*कर}
<[email protected]>; Harish Kumar Nair {एस.एच. के.
नायर} <[email protected]>; MS Hejib {एम. एस. हे िजब}
<[email protected]>;     sr2rpit   <[email protected]>;
Srinivas P {पी. <ी-नवास} <[email protected]>; Santosh
Narinoi {संतोष नर,नोई} <[email protected]>; Rahul Raj
{राहल
    ु  राज} <[email protected]>; Sivakumar       Sivadanam
{ शवदानम शवकमार
            ु  } <[email protected]>
Subject: Final Route Transmission scheme for integration of
Renewable Energy Zone (REZ) Phase-II in Koppal (Phase-A) and
Gadag-II (Phase-A) in Karnataka System Strengthening at
Koppal-II and Gadag-II for integration of RE generation projects

Dear sir,

We    POWERGRID      KOPPAL    GADAG     TRANSMISSION
LIMITED (A Wholly Owned Subsidiary of Power Grid
Corporation of India Limited) under MoP, Govt. of India,
executing the transmission line and substations for
integration of renewable energy in and around Gadag and
Koppal in Karnataka.

In this regard it is to inform that all the transmission line
routes are already finalised and constructions works are
under progress. (Please refer the attached kml files)

It is noticed that in Ryavanki village (Kuknoor Taluk)
near our 400KV D/C Gadag-Koppal Line-I tower location
3/10 soil investigation works are being carried out for a
wind mill project by your representative which is faling
under our line corridor within 100Mtr distance in Survey
No. 202/2 which is not permissible as per prevalling
norms.

Kindly verify your proposed installations coordinates and
keep the required distance from our transmission line
route/corridor.
                                 20



The tentative list of survey numbers through which our
2nd 400KV D/C Gadag-Koppal Line-2 pesses under system
strengthening is also attached for your ready reference.
Kindly verify and keep the required distance for your
installation for smooth completion of our Transmission
Lines.

In this regard as requested over phone earlier, you are
once again requested to visit our office for a joint
verification without any further delay to avoid any clash
of installation under our line corridor.

Thanks and Regard,

चं न जी./CHANDRAN G
महा बंधक /General Manager
पावर    ड को पल गदग ांस मशन ल मटे ड
(पावर    ड कॉप रे शन ऑफ इं$डया ल मटे ड क& पण(
                                           ू *वा म+व वाल, सहयक कंप-न)

POWERGRID KOPPAL GADAG TRANSMISSION LIMITED
(A  WHOLLY     OWNED        SUBSIDIARY OF POWERGRID
CORPORATION OF INDIA LTD)
KOPPAL CAO/को पल -नमा(ण .े/
400 के वी म-नराबाद
           ु       उप क34/400KV MUNIRABAD SUBSTATION,
गल
 ु दाह5ल, पो*ट/Guldahalli Post को पल िजला/KOPPAL DISTRICT,
कना(टक/KARNATAKA - 583228.
Cell +91 9434740004

दावा+याग: यह ईमेल पावर    ड के दावा+याग -नयम व शत? 4ववारा शा सत है िजसे
http://apps.powergrid.in/Disclaimer.htm पर         दे खा   जा   सकता    है ।
Disclaimer:     This      e-mail      is             governed           by
http://apps.powergrid.in/Disxlaimer.htm."

                                                       (Emphasis added)
                                 21



The letter is indicative of the fact that the WTG coordinates were all

varied by the petitioner and the respondent had shared only the

tentative list of survey numbers. The petitioner was also asked to

keep the required distance from respondent's installation for

smooth     completion    of    respondent's     transmission    lines.

Communications galore between the two, reiterating their stand.


      10. The extent of the deviations of the petitioners WTG

locations and coordinates from those approved by KREDL, which are

conflicting with the respondents transmission line corridor, as

demonstrated by the respondent is as follows:

           "CHART OF THE LATITUTE AND LONGITUDE OF WTG
                 LOCATIONS AND TOWER LOCATIONS
                                  22



      11. The entire case of the petitioner is that the petitioner has

received an approval from KREDL in terms of a Government Order

for establishment of WTG coordinates, therefore, there cannot be

shifting of the coordinates.   It is the other way round.     The WTG

coordinates and the Government Order states that they were

tentative in nature. Being tentative, the petitioner must have been

completely aware of the fact that, if the latitude or longitude would

be shifted, it would create a problem to the petitioner themselves.

The petitioner did not have that power under any agreement or in

law to unilaterally shift without approval and without notice of such

shifting to any Authorities. Therefore, the problem now generated

is not because of the respondent, but because of the petitioner

shifting the WTG coordinates and not otherwise.



      12. It is trite that laying down of electricity transmission lines

by Power Grid serves a larger public interest, as they are essential

requirements for growth and development of the country's economy

and the well being of the citizens. This is what is recognized by the
                                      23



Apex Court in the case of CENTURY RAYON LIMITED v. IVP

LIMITED1 wherein the Apex Court holds as follows:


                                  "....     ....    ....


               8. On the aspect of use of the land belonging to a third
        party for setting up of the electricity transmission line, we would
        refer to the judgment of this Court in Power Grid Corpn. of India
        Ltd. v. Century Textiles & Industries Ltd. [Power Grid Corpn. of
        India Ltd. v. Century Textiles & Industries Ltd., (2017) 5 SCC
        143] wherein a Division Bench of this Court while examining
        Section 164 of the Electricity Act had observed that the
        appropriate Government may by order in writing for the purpose
        of placing of electric lines or electrical plant for the transmission
        of electricity necessary for the proper coordination of works,
        confer on any public officer, licensee or any other person
        engaged in the business of supplying electricity under the
        Electricity Act any of the powers that the telegraph authority
        possesses under the Telegraph Act with respect to the placing of
        the posts and lines for the purposes of a telegraph. This
        conferment of powers would be subject to such conditions and
        restrictions, if any, that the appropriate Government may
        impose and the provisions of the Telegraph Act.

               9. Reference was made in Power Grid Corpn. of India Ltd.
        case [Power Grid Corpn. of India Ltd. v. Century Textiles &
        Industries Ltd., (2017) 5 SCC 143] to Sections 10 [ "10. Power
        for telegraph authority to place and maintain telegraph
        lines and posts.--The telegraph authority may, from time to
        time, place and maintain a telegraph line under, over, along or
        across, and posts in or upon, any immovable property:Provided
        that--(a) the telegraph authority shall not exercise the powers
        conferred by this section except for the purposes of a telegraph
        established or maintained by the Central Government, or to be
        so established or maintained;(b) the Central Government shall
        not acquire any right other than that of user only in the property
        under, over, along, across, in or upon which the telegraph

1
    (2021)20 SCC 758
                             24



authority places any telegraph line or post; and(c) except as
hereinafter provided, the telegraph authority shall not exercise
those powers in respect of any property vested in or under the
control or management of any local authority, without the
permission of that authority; and(d) in the exercise of the
powers conferred by this section, the telegraph authority shall
do as little damage as possible, and, when it has exercised
those powers in respect of any property other than that referred
to in clause (c), shall pay full compensation to all persons
interested for any damage sustained by them by reason of the
exercise of those powers."] and 16 [ "16. Exercise of powers
conferred        by    Section    10,    and    disputes    as   to
compensation, in case of property other than that of a
local authority.--(1) If the exercise of the powers mentioned
in Section 10 in respect of property referred to in clause (d) of
that section is resisted or obstructed, the District Magistrate
may, in his discretion, order that the telegraph authority shall
be permitted to exercise them.(2) If, after the making of an
order under sub-section (1), any person resists the exercise of
those powers, or, having control over the property, does not
give all facilities for this being exercised, he shall be deemed to
have committed an offence under Section 188 of the Indian
Penal Code, 1860 (45 of 1860).(3) If any dispute arises
concerning the sufficiency of the compensation to be paid under
Section 10 clause (d), it shall, on application for that purpose by
either of the disputing parties to the District Judge within whose
jurisdiction the property is situate, be determined by him.(4) If
any dispute arises as to the persons entitled to receive
compensation, or as to the proportions in which the persons
interested are entitled to share in it, the telegraph authority
may pay into the court of the District Judge such amount as he
deems sufficient or, where all the disputing parties have in
writing admitted the amount tendered to be sufficient or the
amount has been determined under sub-section (3), that
amount; and the District Judge, after giving notice to the parties
and hearing such of them as desire to be heard, shall determine
the persons entitled to receive the compensation or, as the case
may be, the proportions in which the persons interested are
entitled to share in it.(5) Every determination of a dispute by a
District Judge under sub-section (3) or sub-section (4) shall be
final: Provided that nothing in this sub-section shall affect the
right of any person to recover by suit the whole or any part of
any compensation paid by the telegraph authority, from the
                             25



person who has received the same."] of the Telegraph Act which
postulates the power of the telegraph authority to maintain
telegraph lines and posts and the provisions relating to
compensation in exercise of those powers. Clause (d) to Section
10 requires that the telegraph authority shall do as limited
damage as possible in exercise of powers to place and maintain
telegraph lines and posts, and full compensation shall be paid to
all persons interested for any damage sustained by them. Sub-
section (1) to Section 16 states that in the case of resistance or
obstruction in respect of powers exercised by the telegraph
authority under clause (d) to Section 10, the District Magistrate
may in his discretion make an order that the telegraph authority
shall be permitted to exercise the powers. Sub-section (3) to
Section 16 states that if any dispute arises with regard to the
sufficiency of the compensation to be paid under clause (d) to
Section 10, the District Judge within whose jurisdiction the
property is situated shall determine the compensation.

     10. On the legal effect of these provisions, this
Court had observed : (Power Grid Corpn. of India case
[Power Grid Corpn. of India Ltd. v. Century Textiles &
Industries Ltd., (2017) 5 SCC 143] , SCC pp. 152-55,
paras 21, 23 & 26)

             "21. It is not in dispute that in exercise of
      powers under the aforesaid provision, the
      appropriate Government has conferred the powers
      of telegraph authority vide Notification dated 24-
      12-2003 exercisable under the Telegraph Act,
      1885 upon the Power Grid. It may also be
      mentioned that a Central transmission utility
      (CTU) is a deemed licensee under the second
      proviso to Section 14 of the Electricity Act, 2003.
      Power Grid is a Central transmission utility and is,
      therefore, a deemed licensee under the Electricity
      Act, 2003. This coupled with the fact that Power
      Grid is treated as authority under the Telegraph
      Act, 1885, it acquires all such powers which are
      vested in a telegraph authority under the
      provisions of the Telegraph Act, 1885 including
      power to eliminate any obstruction in the laying
      down of power transmission lines. As per the
      provisions    of    the   Telegraph    Act,   1885,
      unobstructed access to lay down telegraph and/or
                        26



electricity transmission lines is an imperative in
the larger public interest. Electrification of villages
all over the country and availability of telegraph
lines are the most essential requirements for
growth and development of any country, economy
and the well-being/progress of the citizens. The
legislature has not permitted any kind of
impediment/obstruction        in     achieving      this
objective and through the scheme of the Telegraph
Act, 1885 empowering the licensee to lay
telegraph lines, applied the same, as it is, for
laying down the electricity transmission lines.

                             ***

23. Section 10 of the Telegraph Act, 1885 empowers the telegraph authority to place and maintain a telegraph line under, over, along or across and posts in or upon any immovable property. The provision of Section 10(b) of the Telegraph Act, 1885 makes it abundantly clear that while acquiring the power to lay down telegraph lines, the Central Government does not acquire any right other than that of user in the property. Further, Section 10(d) of the Telegraph Act, 1885 obliges the telegraph authority to ensure that it causes as little damage as possible and that the telegraph authority shall also be obliged to pay full compensation to all persons interested for any damage sustained by them by reason of the exercise of those powers.

***

26. We also do not find that the action of the Power Grid, in the given circumstances, by not shifting the transmission lines was arbitrary. From the facts noted above, it becomes apparent that not only it was unfeasible to change the alignment as almost entire work had already been completed by the time the writ petitioner started protesting against this move, even otherwise, the Power Grid has given sufficient explanation to point out that all relevant factors/aspects were kept in mind while laying down the impugned transmission lines. Such transmission lines had to be in straight

line to the extent possible for eliminating loss of transmission. It is also explained that electricity transmission is usually laid or crossed over agricultural land where minimum extent of land gets utilised for erecting towers and where agricultural activities are not prejudiced / obstructed in any manner. The purpose is to avoid buildings, religious places, ponds, etc. while laying down these transmission lines. It is only when it becomes inevitable that towers are placed on the private lands to the minimum and least extent possible. That is what was tried to achieve in the instant case. Another important factor, which needs repetition at this stage is that no blasting is permissible within 300 m from the 400 kV line (already existing) or the tower structure. Mining of limestone can be taken up by adopting the methods other than use of explosive/blasting -- without damage to the tower foundation/tower structure or the line, which can be accomplished by using jack hammer/pneumatic hammer with compressor so as to avoid any damage to the line or tower. This aspect has also been taken note of by the learned Single Judge of the High Court in the judgment dated 11-3-2008 [Century Textiles & Industries Ltd. v. Power Grid Corpn. of India Ltd., WP (C) No. 1909 of 2007, order dated 11-3-2008 (Chh)] . The Division Bench [Century Textiles & Industries Ltd. v. Power Grid Corpn. of India Ltd., WA No. 42 of 2008, order dated 2-8-2010 (Chh)] did not differ with any of these findings."

11. The decision in Power Grid Corpn. of India Ltd. case [Power Grid Corpn. of India Ltd. v. Century Textiles & Industries Ltd., (2017) 5 SCC 143] highlights the imperative and the need for unobstructed access for laying down the electricity transmission lines in the larger public interest as these are essential requirements for growth and development of the country, economy and well-being of the citizens."

(Emphasis supplied)

The Apex Court holds that Power Grid is a deemed licensee under

the Electricity Act, 2003, and has the power to eliminate any

obstruction in the laying down of power transmission lines.

13. In the light of the judgment of the Apex Court and the

admitted folly of the petitioner in shifting the WTG locations,

without notice or without the concurrence of the Authorities, which

has only led to the present dispute and since the transmission lines

laid down by Power Grid are of a public interest of a higher

pedestal, the WTG lines of the petitioner must yield to the larger

public interest.

In that light, finding no merit in this petition, petition stands

rejected.

Pending applications if any, also stand disposed.

sd/-

(M.NAGAPRASANNA) JUDGE Bkp CT:MJ

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter