Citation : 2024 Latest Caselaw 26576 Kant
Judgement Date : 7 November, 2024
-1-
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 7TH DAY OF NOVEMBER 2024
PRESENT
THE HON'BLE MR. JUSTICE S. G. PANDIT
AND
THE HON'BLE MR. JUSTICE C.M.POONACHA
R.F.A. NO.851 OF 2012 (MON)
C/W
RFA.CROB. NO.3 OF 2013 (MON)
R.F.A. NO.851/2012
BETWEEN:
K SAMBASIVA RAJU
S/O LATE SRI K A NARASIMHA RAJU
AGED ABOUT 60 YEARS
OCC: CONTRACTOR, R/O PLOT NO.118
NCC ENCLAVE, MEDCHAL ROAD
SECUNDERABAD-500055.
... APPELLANT
(BY SRI. PRASAD RAO, ADV. A/W
SRI SAMPATH BAPAT, ADV.)
AND:
1. M/S. ESSAR CONSTRUCTIONS LTD.,
REP. BY ITS EXECUTIVE DIRECTOR
ESSAR HOUSE, 11, KESHAVRAO MARG
MAHALAKSHMI, MUMBAI-400034.
-2-
2. THE SENIOR PROJECT MANAGER WORKS
(PACKAGE IV & V)
M/S. ESSAR CONSTRUCTIONS LTD.,
JUBILEE COMPLEX
25TH KM, PB ROAD, HONNUR
GOLLAHATTI,
DAVANGERE-577556.
...RESPONDENTS
(BY SRI BHARGAVA D BHAT, ADV. FOR R1)
THIS APPEAL IS FILED UNDER SECTION 41 RULE 1 &
2 R/W SECTION 96 OF CPC, AGAINST THE JUDGMENT AND
DECREE DATED 07.03.2012 PASSED IN OS NO.82/2007
ON THE FILE OF I ADDITIONAL SENIOR CIVIL JUDGE,
DAVANAGERE, PARTLY DECREEING THE SUIT FOR
RECOVERY OF AMOUNT.
RFA.CROB.NO.3/2013
BETWEEN:
ESSAR PROJECTS (INDIA) LIMITED
(FORMERLY KNOWN AS M/S. ESSAR
CONSTRUCTION LTD.,)
ESSAR HOUSE, 11,
KESHAVRAO KHADYE MARG
MAHALAKSHMI,
MUMBAI-400034
REPRESENTED BY ITS
DEPUTY GENERAL MANAGER
AND ALSO THE GPA HOLDER OF
THE APPELLANT.
(THE 2ND DEFENDANT SENIOR PROJECT MANAGER
WAS IN EXISTENCE WHEN THE CONSTRUCTION
WORK WAS IN PROGRESS. AFTER COMPLETION
-3-
OF THE WORK THE POST OF SENIOR PROJECT
MANAGER IS NOT IN EXISTENCE. HENCE NOT
MADE AS PARTY TO THIS CROSS OBJECTION).
... CROSS OBJECTOR
(BY SRI BHARGAVA D. BHAT, ADV.)
AND:
SRI K SAMBASIVA RAJU
S/O LATE SRI K A NARASIMHA RAJU
AGED ABOUT 60 YEARS
CONTRACTOR
R/O H.NO.PLOT NO.118
NCC ENCLAVE, MEDCHAL ROAD
SECUNDERABAD-500055
ANDHRA PRADESH.
... RESPONDENT
(BY SRI. PRASAD RAO, ADV. A/W
SRI SAMPATH BAPAT, ADV.)
RFA.CROB IS FILED IN RFA 851/2012 FILED U/O 41,
RULE 1 & 2 OF CPC, AGAINST THE JUDGMENT AND
DECREE DATED 07.03.2012 PASSED IN O.S.82/2007 ON
THE FILE OF I ADDITIONAL SENIOR CIVIL JUDGE,
DAVANAGERE, PARTLY DECREEING THE SUIT FOR
RECOVERY OF AMOUNT.
RFA NO.851/2012 AND RFA.CROB.NO.13/2013
HAVING BEEN HEARD AND RESERVED FOR JUDGMENT ON
03.09.2024 COMING ON THIS DAY, S.G.PANDIT J.,
PRONOUNCED THE FOLLOWING:
CORAM: HON'BLE MR JUSTICE S.G.PANDIT
and
HON'BLE MR JUSTICE C.M. POONACHA
-4-
CAV JUDGMENT
(PER: HON'BLE MR JUSTICE S.G.PANDIT)
Plaintiffs' appeal under Section 96 of the Code of
Civil Procedure, 1908 aggrieved by judgment and
decree dated 07.03.2012 in O.S.No.82/2007 on the
file of I Additional Senior Civil Judge at Davanagere
(for short, 'Trial Court'), by which, suit for recovery of
amount is partly decreed, rejecting major portion of
the claim.
2. The parties to this appeal would be referred
to as they stood before the Trial Court.
3. Plaintiff presented the plaint with a prayer
for a judgment and decree for recovery of a sum of
Rs.2,01,24,111/- with 24% interest per annum in
favour of the plaintiff against the defendants jointly
and severally. It is the case of the plaintiff that the
second defendant entered into a contract with the
plaintiff for execution of work i.e., excavation from
borrow source, transportation, dumping, spreading,
watering, greeding and compaction to most
specifications at Ranebennur bypass inclusive of testing
the whole duration of the work. It is stated that the
work order was issued on 01.09.2003 (Ex.P1) and in
terms of the work order the period of contract was
from 01.09.2003 to 31.12.2003. The work is to be
carried out as per instructions of Engineer In-charge.
The plaintiff was assured of 7,50,000 CUM of earth
work and for which payment shall have to be made
within thirty working days from the date of submission
of the bill. That on discretion of the first defendant and
based on the availability, diesel or any material shall be
issued to the plaintiff for construction and execution of
works in question and value of the same will be
recovered from RA bills. It is also stated that the
defendants have the right to increase/decrease the
scope of work and change the location. The contract
could be terminated by the defendants by giving seven
days notice if they are not satisfied with the
performance of the works executed by the plaintiff and
the plaintiff would not be entitled for any computation
or claim in that regard. Plaintiff further states that
pursuant to the work order and taking into consideration
the nature of work, he made all arrangements by
engaging required men, machinery and material and
deployed them at the site so as to complete the work
within the stipulated time. It is the case of the plaintiff
that though the work entrusted have been executed as
per specifications and as per the instructions of the
Engineer In-charge, payments were not made by the
defendants in terms of the contract, due to which, the
plaintiff suffered heavy financial loss. It is specifically
averred that as per the terms and conditions of the
contract, the defendants were obliged to show borrow
area from where necessary required earth have to be
procured. The contract work could not be completed
before 31.12.2003 on account of non-availability of
sufficient quantity of earth in the borrow area shown
by the defendants. The plaintiff could not achieve
progress of work as he had to move from one borrow
area to other borrow area as shown by the defendants.
Plaintiff further states that taking into consideration the
above and considering the letter of the plaintiff dated
18.12.2003, period of contract was extended up to
31.05.2004 and the same was confirmed by
defendants' letter dated 25.12.2003. It is further
stated that the defendants failed to show designated or
approved borrow area even during the extended
contract period, in spite of several requests made by
the plaintiff. Having waited, the plaintiff is said to have
written a letter dated 30.01.2004 informing about the
mobilization of men and machinery, which have
become completely idle because of non-showing of
borrow area and requested to do the needful at an
early date. Plaintiff states that the defendants having
failed to show the borrow area and having failed to
fulfill their part of contractual obligations and having
not paid the bills in terms of the contract for the works
executed, there is breach of contract by the
defendants. The plaintiff further states that to avoid
further loss, withdrew the machinery deployed at sites
from 10.03.2004 by keeping only skeleton staff. The
plaintiff addressed a letter dated 26.06.2004 informing
all the problems and sufferences encountered and
sought for settlement of payment in terms of the
contract and requested to refund of payments illegally
deducted from out of the bills towards diesel supplied
in excess of the rates fixed together with interest at
18%. It is the further grievance of the plaintiff that the
defendants dodged the plaintiff in making payment of
even admitted amounts and have not paid any final bill
to the extent of works executed and further failed to
entrust the works as agreed and pressurized for giving
no claim certificate in a dotted lines for the reasons
best known to them. The plaintiff got issued a legal
notice dated 18.10.2004 calling upon to make
payments of claim within 15 days and defendants
replied the said notice on 14.03.2005 falsely denying
the claim of the plaintiff.
4. The plaintiff claimed a sum of
Rs.34,86,028/- as the defendants had failed to make
payment for actual work carried out with regard to
earth work; claimed a sum of Rs.23,58,864/- towards
obtaining suitable material from excavation at borrow
area; claimed a sum of Rs.8,05,182/- towards
difference in quantity of lease charges; claimed a sum
of Rs.43,85,010/- towards loss of profit; claimed a
sum of Rs.24,85,000/- towards loss of idle charges;
- 10 -
claimed a sum of Rs.5,67,000/- towards refund of the
excess excise duty recovered with interest at the rate
of 18% p.a., from 15.05.2004 till the date of suit and
24% p.a., from the date of suit till realization.
5. On service of summons, defendant No.1
failed to appear and was placed exparte. Defendant No.2
filed written statement through its Advocate denying the
whole claim, but admitted the entrustment of work under
Ex.P1 work order. It is stated that the contract period
was from 01.09.2003 to 31.12.2003 and the plaintiff
was required to carry on work as per specifications of
Clause (305) which is self explanatory. The second
defendant specifically denied the averment in the plaint
that the plaintiff was assured work of execution of
7,50,000 CUM of earth work for which, payment will
have to be made within thirty days from the date of
submission of the bill as false. Further it is stated that
the plaintiff has to do the work as per the stipulations
- 11 -
made in the work order. Without completing the work
as per the stipulations, the plaintiff has no right to
submit the bill. The second defendant specifically
stated that the defendant company has made the
payments to the plaintiff in time as per the actual
work done by the plaintiff. The claim put forth by the
plaintiff was very high and the same was not
proportionate with the actual work done. The plaintiff
except commencing the work as per schedule has not
carried out the work as per schedule and thereby the
plaintiff has committed the breach of the terms and
conditions of the work order. The second defendant
specifically denied the averment of the plaintiff that
the contract shall be terminated by the defendants by
giving seven days notice if not satisfied with the
performance of the work as distorted version. The
second defendant specifically denied the allegation of
the plaintiff that the plaintiff executed work as per
- 12 -
specifications and as per instructions of the Engineer
In-charge, payments were not made by the defendants
in terms of the contract and consequently the plaintiff
suffered heavy financial loss, as totally false.
6. The defendants specifically denied the
allegation of the plaintiff that as per the terms and
conditions of the contract the defendants obliged to
show borrow area from where necessary required earth
have to be procured, as false. The defendants admit
that contract work to be completed by 31.12.2003, but
denied the allegation that the work could not be
completed on account of non-availability of sufficient
quantity of earth in the borrow area shown to the
plaintiff by defendants. This defendant also denied the
allegation that the contract period was extended up to
31.05.2004, taking note of the problems of the plaintiff
and considering the letter of the plaintiff dated
18.12.2003 saying that the same is distorted version of
- 13 -
the plaintiff. The second defendant also specifically
denied the allegation that the defendants failed to
show any designated or approved borrow area for
importing necessary earth. Further, the defendants
denied the allegation that the defendants have
committed breach of contract by not fulfilling their part
of contractual obligations right from the inception of
entrustment of work as such they are liable for
consequences and losses suffered by the plaintiff as
false. The defendants admit writing letter dated
09.06.2004 and states that the contents of the letter
are self explanatory. Further, it is stated that the
plaintiff has given no claim certificate on 10.06.2004 at
the time of receiving the payment of final bill amount
by giving no claim statement, the plaintiff has
unequivocally and categorically admitted that nothing
is due by the defendants to the plaintiff. The
defendants have specifically contended that the
- 14 -
plaintiff has no right to interpret any of the terms and
conditions of the work order so as to suit his
convenience.
7. Lastly, the defendants contend that the
defendants made payment to the plaintiff on
31.12.2003, 17.01.2004, 17.02.2004, 19.03.2004,
17.05.2004 and 10.06.2004 and all these payments
are duly acknowledged by the plaintiff. As the plaintiff
has received the payments stated above, by issuing
no claim certificate, nothing is payable by the
defendants to the plaintiff. There is no cause of action
for filing the suit and the plaintiff is not entitled for
any relief or reliefs, as such prayed for dismissal of
the suit.
8. Based on the above pleadings, the Trial
Court framed as many as 13 issues which reads as
follows:
- 15 -
"1) Whether the plaintiff proves that as per the work order Dt: 01/09/2003 he had to execute excavation work as detailed in para 1 of the plaint ?
2) Whether the plaintiff further proves that as per the work contract he was required to execute 7,50,000 cum of earth work for which payments were to be made as per Annexure-I appended to the work order?
3) Whether the plaintiff proves that the defendants have not made payments to him as per the terms of contract, due to which he suffered financial loss?
4) Whether the plaintiff further proves that on account of default and wrongful act on the part of the defendants the work could not be completed?
5) Whether the plaintiff proves the alleged breach of terms of contract by the defendants as alleged in para 4 of the plaint ?
6) Whether the plaintiff further proves the default of the defendant in making payment of bills to him in terms of contract?
- 16 -
7) If so, whether the plaintiff is entitled for recovery of the suit claim amounts from the defendants as sought for?
8) Whether the second defendant proves that the plaintiff himself is guilty of breach of the terms of contract as contended in paras-8,11, 13 & 18 of his written statement?
9) Whether the second defendant proves his discharge from liability from paying the suit claim amounts in view of 'No Claim Certificate' issued by the plaintiff on 10/06/2004?
10) Whether the second defendant further proves that the suit of the plaintiff is barred by limitation?
11) Whether the suit of the plaintiff is
hit by the doctrine of estoppel and
acquiescence?
12) Whether the second defendant
further proves the alleged payment of amount to the plaintiff as contended in para-32 of the written statement?
- 17 -
13) What order or decree ?"
9. In support of his case, plaintiff examined
himself as PW1 and no other supporting witness is
examined apart from marking Ex.P1 to Ex.P32.
Defendants examined three witnesses as DW1 to DW3
and marked documents Ex.D1 to Ex.D25 in support of
their case. The Trial Court under impugned judgment,
decreed the suit to an extent of Rs.2,15,868/- holding
defendants are jointly and severally liable to pay the
said amount with interest at the rate of 18% p.a.,
from the date of the suit till realization, rejecting
major portion of the claim of the plaintiff. Plaintiff is in
appeal against portion of the judgment and decree by
which, his major claim is rejected.
10. Heard learned counsel Sri.Prasad Rao for
Sri.Sampat Bapat, learned counsel for
appellant/plaintiff, learned counsel Sri.Bhargav D.
- 18 -
Bhat, for respondents/defendants. Perused the appeal
papers as well as the Trial Court Records.
11. Learned counsel Sri.Prasad Rao for
appellant/plaintiff would submit that the Trial Court
committed grave error in rejecting major claims of the
plaintiff and only in decreeing to an extent of
Rs.2,15,868/- with 18% interest. Learned counsel
would submit that impugned judgment and decree is
the result of non-looking into the materials on record
and failure to appreciate the evidence on record.
Learned counsel would submit that the defendants
have not disputed the entrustment of work in terms of
work order dated 01.09.2003 (Ex.P1). Learned
counsel referring to Ex.P1 submits that, the major
portion of the work is excavation at borrow area and
transportation of earth from borrow area to the work
area. Since the defendants failed to identify the
borrow area and handover the same to the plaintiff,
- 19 -
the plaintiff could not progress with the work, even
though the plaintiff had mobilized men and machinery.
As the mobilized men and machinery were to be kept
idle because of non-identification of borrow area, the
plaintiff would be entitled for idling charges. Further,
learned counsel would submit that even during the
extended period of contract, the defendants failed to
identify and handover borrow area which resulted in
further delay in carrying out the entrusted work.
Learned counsel would further submit that even the
bills submitted for the works carried out were not
paid. Learned counsel would further submit that the
defendants assured 7,50,000 CUM of earth work
quantity as per specification in terms of Ex.P1, but
failed to record proper measurement of the work
carried out by the plaintiff. Learned counsel would also
submit that the defendants alleged certain adhoc
payments not with reference to the actual works,
- 20 -
without furnishing any particulars, obtaining signature
of the plaintiff on the RA bills prepared by the officials
of the defendants. It is specifically contended by the
learned counsel that payments have not been made
on the running bills at Ex.P16 to Ex.P19 which
resulted in breach of contract. Learned counsel for the
appellant/plaintiff would submit that the defendants
have not properly made payments for the work
executed as per the terms of specifications under the
strict supervision of defendants' engineers. Learned
counsel would further submit that the defendants
have failed to place on record the certification said to
have been made in respect of the works carried out by
the plaintiff. Learned counsel would submit that the
defendants have failed to make payments to the
plaintiff in respect of actual works turned out by the
plaintiff. Learned counsel would submit that plaintiff
as a sub-contractor has executed certain works and
- 21 -
those works have to be measured and basing on that
measurement quantities which should be arrived at,
the plaintiff would raise the bills in the name of its
company. Learned counsel would further submit that
NHAI has entrusted certain works to the defendants
and in turn, a portion of the work was entrusted by
defendants to the plaintiff.
12. Learned counsel for the plaintiff inviting
attention of this Court to Ex.P1 - Work order submits
that, joint measurement in the presence of the
plaintiff and defendants' representative is mandatory
and the same shall be taken into consideration for
payment. It is submitted that in respect of Ex.P16 to
Ex.P19 - RA bills, though joint measurements have
not been taken, the defendants have taken signature
of the plaintiff on those RA Bills and adhoc payments
were made. Learned counsel would submit that DW1
in his cross-examination admitted the execution of
- 22 -
excavation work by the plaintiff and in terms of the
work carried out, defendants have failed to make
payment. Thus, learned counsel would submit that the
claims made in the plaint are for the works carried out
by the plaintiff and also towards the period during
which the plaintiff could not carry out the work
resulting in keeping the men and machinery idle,
during which period if he worked could have earned
profit. Thus, learned counsel taking through the
entire evidence and documents on record, submits
that the Trial Court committed grave error in rejecting
the claim of the plaintiff and prays to allow the appeal.
13. On the other hand, learned counsel
Sri.Bhargav Bhat appearing for defendant No.2 and
Cross-Objector supports the judgment and decree
passed by the Trial Court, but opposes the portion of
judgment by which entire cost is awarded to the
plaintiff. Learned counsel would submit that vide order
- 23 -
dated 20.04.2018 of the National Company Law
Tribunal, Mumbai Bench (NCLT) admitted EPC
Constructions India Ltd., into Corporate Insolvency
Resolution Process (CIRP) in terms of the provisions of
the Insolvency and Bankruptcy Code, 2016. It is also
submitted that NCLT appointed Mr.Abhijith
Guhathakurta as the Resolution Professional (RP) of
the Corporate Debtor and subsequently NCLT by order
dated 07.05.2021, directed initiation of liquidation of
the Corporate Debtor. Further, it is stated that
Corporate Debtor is in its last stage of a Court
appointed liquidation process. Since the liquidation
proceedings is in progress, he submits that the
present proceedings cannot continue inasmuch as it
would hamper the liquidation process. Further,
without prejudice to the above contention, learned
counsel would contend that the judgment and decree
under appeal is reasoned one and the Trial Court has
- 24 -
addressed all issues and would corroborate with the
documents on record. Thus, he prays for dismissal of
the appeal.
14. On hearing the learned counsel appearing
for the parties and on perusal of the entire records,
the following points would arise for our consideration:
1. Whether the Trial Court is justified in decreeing the suit only in respect of claim item No.2.04(a) to the tune of Rs.2,15,868/- and in rejecting other claims?
2. Whether as contended by the defendants, the present proceedings cannot be continued?
15. Answer to the point No.1 would be in
affirmative and to point No.2 in the negative for the
following reasons:
16. It is an admitted fact that NHAI had
entrusted certain work to defendants. The defendants
- 25 -
in turn had entrusted a portion of the work entrusted
to them by the NHAI to the plaintiff. There is no
dispute with regard to entrustment of work by
defendant No.2 to the plaintiff in terms of work order
dated 01.09.2023, (Ex.P1). The scope of work
entrusted to the plaintiff was excavation from barrow
source, transportation, dumping, spreading, watering,
grading and compaction to most specifications at
Ranebennur by-pass inclusive of testing the whole
duration of the work. In terms of the work order, the
quantity of work entrusted was 75,000 CUM. The
contract amount was indicated as at Annexure-A1 to
work order Ex.P1. The measurement Clause of
contract i.e. work order at Ex.P1 reads as follows:
"Quantities are indicated in BOQ is tentative. Quantities approved/accepted and certified for payments by Essar/consultant client shall be considered for payment. Joint measurement shall be taken in presence of your and Essar's representatives and the same
- 26 -
shall be considered for payment. Resources are to be provided as per the requirement of site management. The material delivery shall be as per the requirement of our engineers."
17. A reading of the above Clause makes it
abundantly clear that joint measurement shall be
taken in the presence of plaintiff's representative as
well as the representative of defendants and the said
joint measurement shall be the basis for payment.
Further, it also makes it clear that the quantities
approved/accepted and certified for payments by the
defendants or consultant of defendants shall be
considered for payment. The Clause with regard to RA
Bills under Ex.P1 work order reads as follows:
"The R.A. bill shall be prepared on monthly basis and submitted to our accounts department. All the bills shall be raised on Essar constructions Ltd., and the same shall be verified and certified for payment by our Engineer concerned. Cost for all services rendered shall be recovered from your bills."
- 27 -
18. The above Clause would state that the RA
Bills shall be prepared on monthly basis and shall be
raised on the defendants' construction company which
shall be verified and certified for payment by the
defendants' engineer concerned.
19. In the light of the undisputed Ex.P1 - work
order, entrustment of work and quantity of work to be
executed by the plaintiff i.e. 75,000 CUM is proved,
but the grievance of the plaintiff is that borrow area
was not identified and handed over to the plaintiff
which resulted in delay in execution of work and the
defendants failed to make payment for the works
carried out and in terms of RA Bills submitted.
20. Ex.P1, work order dated 01.09.2003 is the
suit document and the case of the plaintiff as well as
defendants rests on the said document. A perusal of
Ex.P1, work order indicates that, period of contract
- 28 -
was from 01.09.2003 to 31.12.2003. But, admittedly
plaintiff could not execute the work during the said
contract period and in terms of Ex.P3 - letter dated
18.12.2003, sought extension of time till 31.05.2004
so as to complete the work entrusted to him. The
reason stated in Ex.P3, letter dated 18.12.2003 is that
on account of non-availability of sufficient quantity of
earth in the borrow areas, he could not procure the
required earth for completion of work. Accordingly, in
terms of Ex.P4 - letter dated 25.12.2003 of the
defendants, the contract period was extended up to
31.05.2004 on the same terms and conditions of the
original work order. A careful reading of Ex.P1-work
order dated 01.09.2003, it would not indicate with
regard to borrow area and it is not a pre-condition for
the defendants to identify and hand over borrow area
to the plaintiff to commence his work or to complete
his work.
- 29 -
21. PW1 i.e. plaintiff in his cross-examination
has admitted that Ex.P1 contains the terms of contract
and he has agreed to work in terms of the said work
order. He has also admitted in his cross-examination
that the work entrusted by the defendants to him is
the work of NHAI. It is also admitted by PW1 that he
was working as sub-contractor under the defendants.
Further PW1 states that in terms of Ex.P1, work
carried out by him is to be jointly measured, but the
work carried out by him is not measured in the
presence of the representative of the defendants. It is
the claim of the plaintiff that Ex.P1 to Ex.P23 indicates
the work carried out by him. But, he also admits that
he has not obtained signature of the representative of
the defendants on the said Exhibits. At paragraph 19
of PW1's cross-examination, PW1 has categorically
admitted that there is no mention in Ex.P1 as to
whether the defendants have to provide or show or
- 30 -
arrange the borrow area. If that is the admission and
if that is the terms and conditions on which plaintiff
has agreed to carry out the work in terms of Ex.P1-
work order, the plaintiff cannot blame the defendants
that the defendants have failed to arrange or show the
borrow area, which resulted in delay in execution of
work.
22. In terms of Ex.P1-work order, the bills
submitted by the plaintiff qualifies for payment only if
it contains the certificate for payment by the
consultant of the defendants and if it is on the joint
measurement of plaintiff and defendants'
representatives, but none of the bills submitted by the
plaintiff is admittedly not based on the joint
measurement of the plaintiff and defendants'
representatives or it is certified by the engineer of the
defendants. At paragraph 16 of the cross-examination
of PW1, PW1 has stated as follows:
- 31 -
".................... £Á£ÀÄ PÉÊUÉÆAqÀ AiÀiÁªÀÅzÉà PÉ®¸ÀzÀ C¼ÀvÉAiÀÄ£ÀÄß ¥ÀæwªÁ¢AiÀÄgÀ ¸ÀªÀÄPÀëªÀÄzÀ°è C¼ÀvÉ ªÀiÁr¹®è. ¥ÀæwªÁ¢AiÀÄjUÉ ºÀt ¥ÁªÀjUÁV ©¯ï UÀ¼À£ÀÄß PÀ¼ÀÄ»¸ÀĪÀ ¸ÀªÀÄAiÀÄzÀ°è CªÀÅUÀ¼À eÉÆvÉ PÀªÀjAUï ¯ÉlgÀ£ÀÄß ºÉÆgÀvÀÄ¥Àr¹ £Á£ÀÄ JµÀÄÖ PÉ®¸À ªÀiÁrzÉÝÃ£É JAzÀÄ vÉÆÃj¸ÀĪÀ zÁR¯ÉUÀ¼À£ÀÄß MzÀV¹®è. ............. £Á£ÀÄ JµÀÄÖ PÉ®¸À ªÀiÁrzÉÝÃ£É J£ÀÄߪÀÅzÀgÀ DzsÁgÀzÀ ªÉÄÃ¯É £À£ÀUÉ ¥ÀæwªÁ¢AiÀÄjAzÀ ºÀt ¥ÁªÀw DUÀ¨ÉÃQvÀÄÛ JAzÀgÉ ¤d. £Á£ÀÄ JµÀÄÖ PÉ®¸À PÉÊUÉÆArzÉÝÃ£É JAzÀÄ vÉÆÃj¸ÀĪÀ zÁR¯ÉAiÀÄ£ÀÄß ºÁdgÀÄ¥Àr¸ÀzÉà ¥sÉÊ£À¯ï ©¯ï vÀAiÀiÁj¸À®Ä DUÀĪÀÅ¢®è.. ................. £Á£ÀÄ JµÀÄÖ PÉ®¸À ªÀiÁrzÉÝÃ£É JAzÀÄ vÉÆÃj¸À®Ä zÁR¯ÉUÀ¼À£ÀÄß £Á£ÀÄ EnÖ®è. .............. ¤¦ 1 jAzÀ ¤¦ 23 zÁR¯ÉUÀ¼ÀÄ £Á£ÀÄ JµÀÄÖ PÉ®¸À ªÀiÁrzÉÝÃ£É JAzÀÄ vÉÆÃj¸ÀĪÀ zÁR¯ÉUÀ¼ÁVgÀÄvÀzÉ . ¥ÀæwªÁ¢AiÀÄgÀ AiÀiÁªÀÅzÉÃ
- 32 -
¥Àæw¤¢AiÀÄÄ ¸À»AiÀÄ£ÀÄß ¤¦ 21 jAzÀ ¤¦ 23gÀ zÁR¯ÉUÀ¼À ªÉÄÃ¯É £Á£ÀÄ ¥ÀqÉzÀÄPÉÆAr®è."
23. Further, PW-1 has stated that he has no
knowledge about the specifications issued by the
Ministry of Road Transport and Highways with regard
to road and bridge work and he has also no knowledge
about the specifications issued by the Ministry of Road
Transport and Highways. He has also admitted that
there is no mention in Ex.P1 as to whether the
defendants have to provide or show or arrange the
borrow area. He has further stated that he has not
prepared the measurement sheet and have no
documents to show that joint measurement is done as
mentioned in the work order.
24. On the contrary, evidence of defendants
i.e. DW1 states that plaintiff is a sub-contractor and
the work entrusted to the plaintiff is the work given by
the NHAI. If the plaintiff had carried out work,
- 33 -
certainly the measurement of the work done by him
would have taken jointly and certified by ICT Ltd. DW1
has also stated that the plaintiff located the borrow
area and requested for soil testing. The borrow areas
located by the plaintiff is approved by the ICT, which
is consultant of NHAI. DW1 specifically states that
plaintiff has to maintain the measurement sheets in
respect of the work entrusted to him, but the plaintiff
has not maintained any measurement sheets. As the
plaintiff has not maintained the measurement sheets,
there is no basis for the claim made by plaintiff. It is
also stated that the plaintiff has not taken signatures
of any of the authorized representatives of the
defendants for any of the documents maintained by
him with regard to the work executed by him. DW1 in
his cross-examination has stated that for each work
undertaken by defendants, there would be Project
Manager and there would be separate contract cell to
- 34 -
monitor the sub-contractor's work. It is the case of
the defendants that they have recorded the joint
measurement in the presence of PW1 in respect of the
work carried out and they are marked as Ex.D2 to
Ex.D12. But, DW1 or his representatives have not
signed on those exhibits. Further, DW1 states that in
terms of Ex.D2 to Ex.D12, interim payments have
been made. It is also stated that Ex.D14 is the
document which shows the payment of RA bills of
DW1 on month-wise. It is stated that payment made
to the plaintiffs are based on Ex.P16 to Ex.P19 and on
actual work done.
25. From a careful analysis of the oral evidence
and documents on record, it could be said that the
plaintiff was entrusted work in terms of Ex.P1 and the
scope of work was mainly excavation from the borrow
source, transportation, dumping, spreading, watering,
grading and compaction to most specifications at
- 35 -
Ranebennur Bypass. The work entrusted was
approximately 7,50,000 CUM. For payment, the
certificate by Essar/consultant shall be the basis
and also joint measurements taken in the
presence of representatives of both the plaintiff
and defendants. All the bills shall be verified and
certified for payment by the defendants' engineer
concerned. PW1 has admitted that there was no
joint measurement and RA bills submitted by him
were without joint measurements. It has also
come on record that the plaintiff has not
maintained measurement sheets. There is no
document to establish the volume of work
carried out by the plaintiff. The plaintiff would be
entitled for payment for the actual work carried out by
him. The defendants' evidence would show that they
have measured the work done by the plaintiff, but
plaintiff or his representative have not signed the
- 36 -
measurement carried out by them. It is also
established that the defendants have made interim
payment to the plaintiff to the extent of work carried
out by him, in terms of the measurement carried out
by the defendants.
26. The Trial Court under the judgment under
appeal has considered each claim of the plaintiff and
has recorded its findings. The Trial Court has found
that the plaintiff is entitled for claim amount only in
respect of item No.2.04(a). Trial Court on examination
of entire material on record has rightly come to the
conclusion that when PW1 himself proved to have
committed breach of terms of Ex.P1, he would not be
entitled to claim any amount under any of the Heads.
From careful examination of material on record as well
as careful scrutiny of the judgment under appeal, we
come to the conclusion that plaintiff has not
maintained any authenticated records to establish the
- 37 -
quantum of work carried out by him, when it is an
admitted fact that plaintiff would be entitled for
payment to the extent of work carried out by him.
Moreover, Ex.P10 is 'No Claim Certificate' issued by the
plaintiff himself, but that itself would not bar the
plaintiff from making any claim. But, it would have
some relevance to the claim made by the plaintiff in
relation to his admissions in the cross-examination.
27. With regard to point No.2, we need not
dwell much since we do not find any merit in the
appeal. Moreover, this is an appeal of the year 2012
instituted much earlier to the initiation of proceedings
under 2016 Code.
28. For the reasons recorded above, we do not
find any merit in any of the contentions of the
appellant/plaintiff to entertain the appeal and also in
- 38 -
the contentions of the respondents/defendants to
entertain the Cross Objections. Hence, the following:
ORDER
i) Regular First Appeal as well as Cross
Objections stand rejected.
ii) The judgment and decree dated
07.03.2012 in O.S.No.82/2007 on the
file of the I Additional Senior Civil
Judge at Davanagere is confirmed.
Sd/-
(S.G.PANDIT) JUDGE
Sd/-
(C.M. POONACHA) JUDGE
NC CT: bms
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!