Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Karnataka Housing Board vs National India Contractor And ...
2024 Latest Caselaw 26541 Kant

Citation : 2024 Latest Caselaw 26541 Kant
Judgement Date : 7 November, 2024

Karnataka High Court

Karnataka Housing Board vs National India Contractor And ... on 7 November, 2024

Author: S.G.Pandit

Bench: S.G.Pandit

                             -1-


      IN THE HIGH COURT OF KARNATAKA AT BENGALURU

       DATED THIS THE 07TH DAY OF NOVEMBER, 2024

                          PRESENT

           THE HON'BLE MR. JUSTICE S.G.PANDIT

                            AND

          THE HON'BLE MR. JUSTICE C.M. POONACHA

             R.F.A. No.1325 OF 2008 (MON)

BETWEEN

KARNATAKA HOUSING BOARD
A STATUTORY BODY CONSTITUTED
UNDER THE KARNATAKA
HOUSING BOARD ACT HAVING
ITS OFFICE AT CAUVERY BHAVAN,
K.G.ROAD, BANGALORE-560 009
                                            ...APPELLANT
(BY SRI RAJESH MAHALE, SENIOR ADVOCATE A/W
    SMT SUMANGALA GACHCHINAMATH, ADVOCATE FOR
    SRI GURUDEV I GACHCHINAMATH, ADVOCATE)

AND

NATIONAL INDIA CONTRACTOR
AND ENGINEERS
A REGD. PARTNERSHIP FIRM HAVING
ITS HEAD OFFICE AT KATRI HOUSE,
628, 13TH ROAD, KHAR (WEST)
MUMBAI-400 052,
REPTD. BY ITS EXECUTIVE PARTNER
MOHAMED AHMED USMAN GANI KHATRI
                                            ...RESPONDENT
(BY SRI. ARIF BHATI, ADVOCATE)
                                                    -2-


      THIS RFA IS FILED U/S 96 OF THE CPC AGAINST THE
JUDGEMENT     AND    DECREE    DT.30.6.2008   PASSED     IN
OS.NO.11343/1996 ON THE FILE OF THE XXVI ADDL. CITY CIVIL &
SESSIONS JUDGE, MAYOHALL UNIT, BANGALORE, DECREEING THE
SUIT FOR RECOVERY OF MONEY AND ETC.

      THIS APPEAL HAVING BEEN RESERVED FOR JUDGMENT ON
14.08.2024, COMING ON FOR PRONOUNCEMENT THIS DAY,
POONACHA J, DELIVERED THE FOLLOWING:

CORAM:             HON'BLE MR JUSTICE S.G.PANDIT
                   and
                   HON'BLE MR JUSTICE C.M. POONACHA

                                       CAV JUDGMENT

(PER: HON'BLE MR JUSTICE C.M. POONACHA)

The present appeal is filed by the defendant under

Section 96 of the Code of Civil Procedure, 19081 challenging

the judgment and decree dated 30.6.2008 passed in OS

No.11343/1996 by the XXVI Additional City Civil and Sessions

Judge, Mayo Hall Unit, Bangalore2, whereunder the suit for

recovery of money filed by the respondent/plaintiff has been

decreed by the Trial Court directing the appellant/defendant to

pay a sum of `81,46,758.20 together with interest at 4% pa.,

from the date of the suit till realization with costs.

2. Parties will be referred to as per their rank before

the Trial Court for the sake of convenience.

Hereinafter referred to as 'CPC'

Hereinafter referred to as the 'Trial Court'

3. It is the case of the plaintiff that pursuant to a

paper publication made by the defendant inviting tenders for

construction of 909 tenements in Bengaluru city for slum

dwellers, the plaintiff participated in the said tender. That the

plaintiff was invited by the defendant for negotiations and the

agreement arrived at between the parties in the negotiations

was confirmed by letter of the plaintiff dated 28.10.1991,

whereunder the following terms were agreed:

a. To accept/execute and complete the works of construction of 909 tenements at 15% above S.R (Schedule of Rates) 1990-91. Cement and steel was to be supplied at the agreed issue rate;

b. Sanction of 15% mobilisation advance of the total work value against bank guarantee without interest;

c. To release 50% of the mobilisation advance along with the work order;

d. To recover mobilisation advance in 10 installments commencing from 3rd running bill;

e. To issue individual work order as and when the clear site is handed over to the plaintiff;

f. To award the works before the SR of 1991-92 is released;

g. Offer for entire project of 909 houses.

3.01. It is the further case of the plaintiff that the

defendant informed the plaintiff that construction of the

tenements behind Gajanana Talkies could not be taken up since

the site was under dispute and indicated that construction of

tenements at Appa Reddy Palya numbering 356 and

construction of 462 tenements at Jeevanahalli (Doddagunte)

was to be taken up immediately. Accordingly, the plaintiff

commenced construction work of 462 out of promised 707

tenements at Jeevanahalli on 20.12.1991 even without the

work order. It is the further case of the plaintiff that between

18.12.1991 and 2.11.1992 the bills were prepared and moneys

were paid. That the construction of 770 units at Jeevanahalli

over a total sital area of 3.876 acres was segregated as

follows:

      a. In Sy.No.150/1                   -         308 units

      b. In Sy.Nos.151 and 152            -      274 units

      c. In Sy.No.158                     -      188 units


     3.02.   That    only   construction       of     462   tenements    at

Jeevanahalli was entrusted and the sital area for construction of

378 units was released. It is the further case of the plaintiff

that the sital area was not made available at one time and that

they were made available as follows:

a. in Sy.No.158, site area for 180 units was handed over on 14.1.1992 and markings were made on the same day;

b. in Sy.No.158, site area for 4 units was handed over on 14.1.1992 and markings were commenced on 12.3.1992;

c. in Sy.No.152, site area for 58 units was handed over on 14.1.1992 and markings were made on the same day;

d. in Sy.No.151, site area for 106 units was handed over on 14.1.1992 and markings were made on the same day;

e. in Sy.No.151, site area for 24 units was handed over on 25.5.1995 and markings were made on the same day;

f. in Sy.No.151, site area for 6 units was handed over on 15.12.1995 and markings were made on the same day.

3.03. It is the further case of the plaintiff that 75% of the

site area was handed over to it only in the year 1995. That in

terms of clause (3), date of commencement is when 75% of

the site is given to the contractor. Hence, the period for

completion of 18 months is to be construed from 15.12.1995

and that the plaintiff had time till June 1997 to complete the

work. That the plaintiff entered upon the work for ultimate

construction and completion of 770 units at Jeevanahalli

without any formalities being completed and without work

order issued by the defendant. That the work was commenced

and being carried out only on adhoc instructions issued by the

officials of the defendant present on the site from time to time.

3.04. That the plaintiff had furnished on 26.12.1991 to

the defendant a bank guarantee in a sum of `17.50 lakhs

taking the contract value at `2,13,00,000/-. It is the further

case of the plaintiff that it had faced variety of problems

commencing from marking of sital area, digging of trenches,

procurement of water etc., which although was brought to the

notice of the defendant, and was reacted with lethargy and

delay. That the work progressed in a haphazard manner for

some time solely on account of the fact that the defendant was

not in a position to furnish detailed drawings and instructions

and provide materials in adequate quantities on time, from

time to time. That the officers of the defendant on the site

frequently changed instructions, thus hindering the progress of

the work and requiring the plaintiff to do additional work.

3.05. That the parties entered into an agreement on

12.3.1992 and the defendant issued work order on the same

day. The construction as agreed to be carried out are:

a. Work of construction of 770 units at Doddagunte - Jeevanahalli in Sy.Nos.150/1, 151, 152 and 158 was entrusted at 15% over the estimated rates on SR 1990-91;

b. The total value of the contract was `1,88,59,825/-;

c. The period of completion was fixed at 18 months from the date of handing over to the plaintiff at not less than 75% of the work site area comprising in a block after the issue of the work order;

d. The plaintiff had paid a mobilization advance at 15% of the value of the work order without interest;

e. Mobilization advance was to be recovered in 10 equal instalments starting from 3rd RA bill with intent that the entire mobilization advance is recovered in 10 instalments or before 75% of the work is completed, whichever is earlier;

f. The defendant would withhold a sum of `12,04,500/- as further security deposit from the bills;

g. Steel was to be supplied free of cost and cement at the rate of `86/- per bag with supply of the steel and cement at the spot of construction.

h. In the work order the defendant undertook to sent to the plaintiff Schedule -B being the details of the quantities of works, the rates per unit etc.

3.06. It is the further case of the plaintiff that effective

from 1.1.1992 the government directed that SR under 1990-

91 be increased by 10% as per the government circular

dated 12.3.1992.

3.07. It is the further case of the plaintiff that pursuant to

issuing the work order on 12.03.1992 and fixing the

valuation of the contract at `1,88,59,825/-, the defendant

called upon the plaintiff to modify the existing bank

guarantee given by it from `17.5/- lakhs to `16.00 lakhs for

the purpose of release of mobilization advance. That the

project requirement of cement and steel was never

provided.

3.08. It is the specific case of the plaintiff that right from

the first day the defendant has defaulted in performing its

obligations, which included, not giving drawings, schedule

of progress not being furnished and specifications being

changed from time to time. That despite the tender for

construction of 909 units being accepted, the plaintiff was

permitted to work only in respect of 348 units and that too

in an area not covered by the original tender. That despite

the failure of the defendant, the plaintiff fulfilled a

substantial portion of its obligation under the contract by

February 1993.

3.09. With regard to the payment of bills, it is the case

of the plaintiff that there was a continued default by the

defendant with regard to same, inasmuch as, as per

PWG/65, clause 7(a), the plaintiff was to submit bills by 15th

of each month for all items of work executed in the previous

month. That the defendant was unable to furnish the bill of

quantities with the unit rates. That the parties had orally

agreed which was confirmed by the conduct of the parties

that the plaintiff would raise bills every month. Accordingly,

between 20.12.1991 and May 1996, 14 bills were prepared

by the Assistant Executive Engineer and passed by the

Executive Engineer, which shows the progress of work even

as assessed by the defendant. That the defendant was not

accurate in making measurements and even this has been

objected to. That in the bills, the defendant has been not

making payments for items of work completed leaving a lot

of payment to be made. That after 31.08.1995, bills were

prepared by the Assistant Engineer, but for some reason

they were never taken on record and consequently, the

plaintiff itself prepared bill Nos.15 and 16 in the prescribed

form and sent the same to the defendant by registered post.

However, the said bills have not been scrutinised by the

defendant and no notice has been issued as contemplated

under clause 7(b) of PWG/65 before taking measurements.

Hence, it is deemed that the said bill Nos.15 and 16 are

correct.

3.10. It is the further case of the plaintiff that the

value of the project being more than `1.00 lakh, the

progress of work ought to have been reviewed by the

Executive Engineer along with the plaintiff every fortnight

and such review should have indicated the delay in progress

was due to non supply of materials, drawings, etc. However,

no such reviews were ever done. That the delay in work was

not due to any lapse on the part of the plaintiff.

3.11. It is the case of the plaintiff that as on

31.8.1995, even according to the defendant, the plaintiff

had completed the tendered items as well as the extra items

and they were reflected in the bills. Thereafter, the work

was done by the plaintiff till April 1996. That the plaintiff

had submitted bills of an aggregate value of `1,15,67,934/-

and it received a payment of `91,25,635/- leaving a balance

of `24,42,300/-. That the bank guarantee of a value of

`9.00 lakhs was invoked by the defendant in May 1996.

That the plaintiff had worked up to April 1996. That the

plaintiff received a letter dated 5/11.6.1996, whereunder the

defendant rescinded the work contract. It is further stated

that the defendant called upon the plaintiff to come for joint

measurements on 26.7.1996. However, the plaintiff sought

for fixing of a date after 26.7.1996. Hence, no joint

measurement as required was taken.

3.12. Various notices were exchanged between the

parties, consequent to which the plaintiff filed the suit for

recovery of `81,46,758.20 together with interest at 18%

p.a. The claim of the plaintiff made in the suit was under

the following heads:

a. On account of loss of profits and loss of overheads `12,25,888/-

b. On account of excess EMSD collected and interest thereon ` 1,74,420/-


     c. On account of transportation
       costs for cement and steel.          `   56,035/-

     d. Service charges on (c) at 12%       `    6,724.20

     e. On account of mobilization and
       Special reliefs.                     ` 2,21,215/-

     f. Damages on account of loss
        during the period between
        21.12.91 to 11.7.96 of `94,67,578/-
        restricted to                      `14,00,000/-

     g. On account of 10% adhoc
       increase in SR 90-91
       effective 1.1.92                    `26,20,177/-

     h. Value of R.A. Bill No.15            `21,16,285/-

     i. Value of RA bill No.16            __` 3,26,014/-__

                  Total                   ` 81,46,758.20/-


4. The defendant entered appearance and filed written

statement denying the case of the plaintiff. However, it is

admitted by the defendant that the plaintiff was the successful

tenderer for construction of 909 tenements for rehabilitation of

slum dwellers in 7 places of Bangalore. However, since there

were difficulties in handing over the scattered sites in vacant

possession, it is the case of the defendant that it negotiated

with the plaintiff for construction of houses under the scheme

at alternate places and Doddagunta (Jeevanahalli) land bearing

Sy.No.150/1P, 151, 152 and 158 was identified wherein 770

houses/units were to be constructed, which was accepted by

the plaintiff. Accordingly, agreement dated 12.3.1992 was

entered into. However, during the course of execution of the

contract, the work on land bearing Sy.No.150/1P where 308

houses were proposed could not be taken up because of Court

stay and the work was restricted to 462 houses at Jeevanhalli,

to which the plaintiff agreed and commenced the work.

4.01. It is the further case of the defendant that the

plaintiff did not show required progress of the work within the

stipulated time and due to serious lapses on the part of the

plaintiff in execution of the work as well as the quality of the

progress of work, no further work was entrusted to the plaintiff

and the defendant was compelled to restrict the tenements

awarded. It is further contended that the plaintiff failed to

complete construction in all respects even with regard to 462

houses which was entrusted to the plaintiff and the plaintiff

resorted to unhealthy correspondences. It is further contended

that due to the inaction and delay caused by the plaintiff, the

defendant Board suffered heavy losses on account of the

project not being completed within the specified time and the

slum dwellers who were the beneficiaries were put to hardship

and inconvenience on account of the lapses of the plaintiff.

4.02. It is the further case of the defendant that the

contract was awarded to the plaintiff on the basis of the

contract rates prevailing during the year 1990-91 plus 15% of

tender premium. That the work order was issued on 12.3.1992

on execution of the tender agreement by the plaintiff. The

period of completion of the contract was 18 months from the

date of handing over of the sites and approximate amount of

contract of the sanctioned estimate rate based on SR of year

1990-91 plus 15% of the tender premium was specified. That

on the request of the plaintiff, mobilization advance amount of

`16.00 lakhs at 15% on pro-rata basis of the total value of the

work was paid when the work order was issued to enable the

plaintiff to go ahead with the construction. That the

mobilization advance amount was an interest free advance

which was recoverable in 10 equal instalments out of the

running bills starting from the 3 rd bill onwards. It was also

agreed that the entire mobilization advance amount was to be

cleared and adjusted in 10 equal instalments in the running

bills or before 75% of the work completion, whichever is

earlier.

4.03. The defendant has denied the case of the plaintiff

that the construction of 462 units at Jeevanahalli was a new

item for which no new rates, terms and conditions were

quoted, accepted or agreed upon. That the contract agreement

dated 12.3.1992 clearly indicated that the plaintiff agreed to

execute the work at Jeevanahalli in lieu of the construction of

909 houses at different places in the same terms and

conditions already agreed.

4.04. It is denied by the defendant that it got the plaintiff

to commence the work of 462 units out of 707 promised at

Jeevanahalli on 20.12.1991 even without the work order. That

the required land area for construction of houses in

Sy.Nos.151, 152 and 158 were handed over on 14.1.1992 itself

in vacant possession even before the agreement was executed

and work order was issued so as to enable the plaintiff to make

preliminary arrangement for starting with the construction

work. However, the plaintiff failed to give the required

progress as per the terms of the contract. The defendant

denied that 75% of site area was handed over to the plaintiff

only in the year 1995. It is the contention of the defendant

that the required sites have been handed over long back during

January 1992 and as per the condition of the contract, the

plaintiff was bound to complete the work of construction by

September 1993. It is contended that the plaintiff voluntarily

agreed to execute the work of construction of houses at

Jeevanahalli and on the request made by the plaintiff an

amount of `16.00 lakhs interest free mobilization amount was

released.

4.05. It is the contention of the defendant that the

primary responsibility to arrange for marking and infrastructure

facilities was that of the contractor. That there were three

open wells and in addition two borewells were handed over to

the plaintiff with sufficient yield of water. Hence, it is denied

that the plaintiff has suffered any hardship in execution of the

work. It is further contended that the drawings and details

along with materials were made available and the work could

have been carried out to 376 units without any hindrance. That

the defendant had also paid running bills in respect of the work

executed by the plaintiff without any delay. That the plaintiff

had accepted the measurements and received payments.

4.06. It is the further case of the defendant that houses

were to be constructed to the extent of land available. That

despite the efforts and endeavours made by the defendant and

the vacant land being made available to the plaintiff, the

targeted progress was not given by the plaintiff. That at the

time of rescinding the contract on 11.6.1996, the plaintiff had a

balance of 6177 bags of cement which were misused for

construction of hollow blocks and 5 metric tonnes of steel

unused which were the excess material which were released by

the plaintiff towards execution of the work. It is further

contended that the plaintiff had secured advance and the

materials to the tune of `13.00 lakhs and the defendant

released the said amount to enable the plaintiff to execute the

work within the stipulated time. It is further contended that the

plaintiff has misused the department material for his own gain

and that if the material and advances were properly utilized for

the work, 378 tenements could have been completed. That the

lapses on the part of the plaintiff resulted not only in abnormal

delay in completion of the project, but also resulted in heavy

losses to the defendant.

4.07. It is further contended that the balance work was

taken up by the defendant at the risk and cost of the plaintiff.

That the plaintiff is due to the defendant in a total sum of

`26,74,054/- in the following manner:

     i.     Towards secured advance
            Outstanding amount                       `13,01,165/-

    ii.     Cost of still unused and not
            returned                                 ` 3,77,780/-

   iii.     Cost of cement                           ` 9,95,109/-
                                                     __________
                          Total                      `26,74,054/-


4.08. It is further contended that the plaintiff never used

to submit running bills as required under clause 7(a) of the

contract. However, the officials of the defendant prepared

running bills to the extent of work done and the payments were

accepted by the plaintiff. That the plaintiff deliberately stopped

work which has caused hardship to the defendant. It is further

contended that the bills submitted by the plaintiff were fictitious

and not in accordance with the actual work done at the spot.

4.09. It is further contended that the plaintiff was asked

to be present on 20.6.1996 for taking final measurements.

However, since the plaintiff was not present, the

measurements were taken in his absence and mahazar has

been drawn to that effect. That on the basis of the final

measurements taken, the final bill was prepared, according to

which the amounts payable was `44,000/- which was adjusted

towards the dues payable by the plaintiff. It is further

contended that the plaintiff had no intention to complete the

work in view of the fact that further execution of work would

get him meagre bills and recovery would be effected against

heavy outstanding dues and payable by the plaintiff. That

since the plaintiff stopped the work and there was no response

to the notices issued, the defendant was constrained to invoke

the bank guarantee. It is denied that the plaintiff continued to

work up to April 1996. It is contended that the plaintiff has

stopped the work long back and has failed to perform its

obligations under the contract. That the plaintiff had

abandoned the work and left the work site for more than six

months as on taking of the measurements.

4.10. The defendant also denied the claim made by the

plaintiff towards loss of profits and other claims made in the

plaint. Hence, the defendant sought for dismissal of the suit.

5. Based on the pleading of the parties, the Trial Court

framed the following issues:

"1. Whether defendant proves that the required land area for construction of houses in Sy.

Nos.151, 152 and 158 were handed over to the plaintiff on 14.01.1992 itself?

2. Whether defendant proves that the plaintiff voluntarily agreed to execute the construction of houses at Jeevanahalli and at his request an amount of Rs.16.00 lakhs interest free mobilisation advance was released?

3.Whether plaintiff proves that the defendant took decision to bifurcate the construction of '770' houses at Jeevanahalli?

4.Whether plaintiff proves that the defendant has failed to fulfil its obligations as per the terms of agreement dated 12.03.1992?

5.Whether plaintiff proves that the delay in progress of construction of houses was due to non- supply of materials and drawings by the defendant?

6. Whether plaintiff proves that as on 31.08.1995 it had completed tendered and extra items work?

7. Whether defendant proves that the suit of the plaintiff is bad for want of notice under Section 72 of Karnataka Housing Board Act, 1962?

8. Whether defendant proves that by virtue of Court Stay Order the work on Sy No.150/IP could not be taken up?

9. Whether defendant proves that the work entrusted to the plaintiff was not completed within stipulated '18' months and time was the essence of contract it was forced to rescind the contract on 11.06.1996?

10. Whether defendant proves that as on 11.06.1996 the plaintiff had balance of 6177 bags of cement and 14.5 metric ton of steel?

11. Whether plaintiff proves that it is entitled to claim 10% increase in the rates over and above S.R. 90-91?

12. Whether plaintiff is entitled to recover from the defendant Rs.81,46,758-20 as detailed in para 34 of its plaint?

13. Whether plaintiff is entitled to claim interest; if so, at what rate?

14. What decree or order? "

6. The Executive Engineer of the plaintiff was

examined as PW.1. Exs.P1 to P90 have been marked in

evidence. The Manager of the defendant - Board was

examined as DW.1 and the Assistant Executive Engineer as

DW.2. Exs.D1 to D58 have been marked in evidence. The Trial

Court by its judgment and decree dated 30.6.2008 decreed the

suit and directed the defendant to pay a sum of `81,46,758.20

to the plaintiff with interest at 4% pa., from the date of suit till

date of realization with cost. Being aggrieved, the present

appeal is filed.

7. Heard the submissions of learned Senior Counsel

Sri Rajesh Mahale along with learned counsel Sri Gurudev I

Gachchinamath for the appellant/defendant and learned

counsel Sri Arif Bhati for the respondent/plaintiff.

8. Learned Senior Counsel for the appellant contends

that admittedly as per the averments made at para Nos.10 and

11 of the plaint the property was handed over to the plaintiff to

commence construction work on 14.01.1992. That the terms

and conditions under which the defendant was required to carry

out the work was stipulated in the agreement dated

12.03.1992 (Ex.P.49) and that the plaintiff did not carry out the

work within the stipulated time in terms of the agreement. It is

further contended that 14 bills of the plaintiff have been cleared

in respect of the work carried out by it and there is no question

of the defendant paying any further amounts to the plaintiff. It

is further contended that in terms of the said agreement

(Ex.P49), the defendant was required to supply cement and

steel to the plaintiff for carrying out construction work. That the

said cement and steel have been supplied which has not been

utilized by the plaintiff for the work that it was required to carry

out under the agreement. It is further contended that the

defendant is not entitled to pay any further amounts and that

the running bill Nos.15 and 16 have been unilaterally prepared

by the plaintiff. It is further contended that when the plaintiff

was notified regarding joint measurements that was required to

be taken, no representative of the plaintiff was present. That

since the plaintiff did not carry out the work in terms of the

agreement, the said agreement was rescinded vide notice /

order dated 05/11.06.1996 (Ex.D.6). It is further contended

that due to the plaintiff not carrying out the work in terms of

the agreement, the defendant was justified in rescinding the

contract and the plaintiff is not entitled for any damages. That

the plaintiff did not furnish any material to demonstrate and

justify the quantum of damages sought for in the plaint and in

the absence of the same, the Trial Court was not justified in

awarding damages and decreeing the suit. It is further

contended that the judgment of the Trial Court being erroneous

and contrary to the material on record, is liable to be set aside

and the suit is liable to be dismissed. Hence, he seeks for

allowing of the above appeal and granting of the reliefs sought

for.

9. Per contra, learned counsel for the respondent -

plaintiff submits that although the tender was called for

construction of 909 tenements in 4 slums, only 1 slum was

handed over to the plaintiff for carrying out construction. It is

further contended that the plaintiff was called upon to

commence the construction, even prior to execution of the

agreement by the plaintiff and in terms of the instructions of

the defendant, the plaintiff commenced the construction work

as required. It is further contended that the plaintiff has

repeatedly corresponded with the defendant in bringing to its

notice the various shortcomings on the part of the defendant

and the plaintiff repeatedly sought for resolution of various

issues due to which the plaintiff was facing impediments in

carrying out the construction. However, it is contended that the

defendant did not respond to the said issues raised by the

plaintiff. It is further contended that the defendant did not hand

over the site as required, due to various reasons and the

plaintiff was required to commence construction only after

these sites were handed over without any encumbrances which

the defendant failed to do within stipulated time. It is further

contended that the defendant did not supply the requisite

quantities of cement and steel. That PW.1 has not been cross-

examined by the defendant regarding the said aspect of the

matter. It is further contended that the panchanama drawn

does not speak of any cement and steal that is available with

the plaintiff. Hence, it is contended that the plaintiff is entitled

to the damages sought for in the suit. That the Trial Court has

adequately appreciated the oral and documentary evidence and

decreed the suit which ought not to be interfered with by this

Court. Hence, he seeks for dismissal of the above appeal.

10. Both the learned counsel have referred to various

correspondences between the parties and the relevant

correspondences which will be considered during the course of

this judgment.

11. The submissions of both the learned counsel have

been considered and the material on record including the

records of the Trial Court have been perused.

12. The questions that arises for consideration are:

i. Whether the finding of the Trial Court on issue Nos.1 to 6 is erroneous and liable to be set aside?

ii. Whether the Trial Court was justified in recording a finding that the defendant is due and payable the sum of `81,46,758/- claimed by the plaintiff in the plaint?

iii. Whether the judgment and decree passed by the Trial Court is erroneous and liable to be interfered with?

Re.question Nos.(i) to (iii):

13. It is forthcoming from the factual matrix that it is

undisputed that the defendant invited tenders for construction

of tenements in Bengaluru city for slum development in which

the plaintiff participated. It is further undisputed that the

plaintiff was invited for negotiation by the defendant. It is

forthcoming from the letter dated 28.10.1991 (Ex.P.2) that the

plaintiff wrote to the defendant placing on record the agreed

terms pursuant to the negotiation held between the parties and

the said terms are as under:

a. "To accept/execute and complete the works of 909 tenements at 15% above the SR of 1990-

91. Cement and steel to be supplied at site at agreed issue rate. We also confirm your having agreed to

b. Sanction us 15% mobilisation advance on the total contract value against Bank guarantee BUT WITHOUT INTEREST.

c. Release atleast 50% of the agreed mobilisation advance along with the work order.

d. Recover the released mobilisation advance in ten equal instalments from ten running bills. First instalment to start from 3rd bill onwards.

e. Issue individual work order as and when the clear site is handed over to us.

f. Award us the works before the SR of 1991-92 is released.

g. Our offer as above is for the entire project of 909 houses."

14. Vide letter dated 06.12.1991 (Ex.P.3), the

defendant responding to the letter (Ex.P.1) confirmed that the

tenders negotiated at 15% above the estimated rates based on

S.R.No.90-91. Further, it is stated that the sites at Appareddy

Palya and the slum behind Gajanana Talkies are clear and the

plaintiff was requested to contact the defendant for entering

into a contract for issuance of a work order. It was further

informed that action regarding request for payment of

mobilization advance will be taken.

15. It is necessary to consider the correspondences

between the parties to adjudicate upon the questions that arise

for consideration. Accordingly, the correspondences are

considered as under:

i. The defendant, vide letter dated

11.12.1991 (Ex.P.4), directed the plaintiff to start the

work at Appareddy Palya immediately and directed the

plaintiff to contact the Assistant Executive Engineer of

the defendant for further information.

ii. The plaintiff, vide letter dated 11.12.1991

(Ex.P.5), informed that in the site of Appareddy Palya

only about 20 houses can be constructed and

requested the defendant to look into the matter and

arrange to handover clear site where at least 25 to

30% of the tenements (out of total 909 can be

constructed).

   iii.        The       defendant,    vide        letter      dated

18.12.1991       (Ex.P.6),     informed   the      plaintiff    that

construction of tenements behind Gajanana Talkies

cannot be taken up since the site is under dispute.

Hence, construction of tenements at Appareddy playa

numbering 36 may be taken up. It is further informed

that construction of 462 units at Doodagunte

(Jeevanahalli) be taken up immediately. That the work

may be started either on 19.12.1991 or 20.12.1991

since the Hon'ble Minister for Housing and Urban

Development is pressing for starting of the work. It is

further informed that construction of 36 units at

Jayaraj slum may also be taken up. Hence, it is

informed that the total number of units entrusted was

530 and the balance of about 379 units will be

entrusted immediately.

iv. Vide letter dated 28.12.1991 (Ex.P.7) the

plaintiff informed the defendant that they have started

cleaning the site, marking and excavation of marked

houses at Jeevanahalli. The plaintiff sought for release

of the proportionate mobilisation advance.

v. Vide letter dated 06.01.1992 (Ex.P.8), the

plaintiff informed the defendant that although work

commenced for construction of 462 tenements at

Jeevanahalli, more that two weeks ago, progress could

not be achieved due to various reasons. The reasons

are set out in the said letter including foundation

details not being made available, water struck while

putting the foundation, that markings made during the

second half of the day get wiped out by next morning

since the site is being used as a play ground by the

children.

vi. The defendant vide letter dated

24/25.01.1992 (Ex.P.9) placed on record that the

Housing Commissioner along with the Executive

Engineer inspected the site and the plaintiff was

requested to excavate the work and start bed concrete

work under intimation to the defendant.

vii. Vide letter dated 11.02.1992

(Ex.P.10/D.2), the plaintiff informed the defendant

that the excavation foundation concrete and stone

masonry work is in full progress at Jeevanahalli. The

plaintiff sought for issuance of the work order and

payment of the mobilisation advance.

viii. It is forthcoming that vide copy of letter

dated 07.02.1992, which is annexed along with

Ex.P10, the Indian Bank informed the plaintiff

regarding the amendments made in the bank

guarantee. It is relevant to note here that the

amendment was also to substitute the words 462

units at Doddagunte (Jeevanahalli) in place of '909

slums'. Further, a sum of `1,09,00,000/- was to be

substituted in place of `2,13,00,000/- and

`16,00,000/- was to be substituted in place of

`17,50,000/-.

ix. Vide letter dated 18.02.1992 (Ex.P.11),

the plaintiff wrote to the defendant that even though

the site made available at Doddagunte for

construction of 462 tenements was not the one

mentioned in the tender, as a special consideration

since the same falls under the constituency of the

HUD Minister, the work has been started. Further, the

plaintiff mentioned that despite commencement of

work, no work order has been issued and mobilisation

advance for 909 slums has not been paid. Further, the

plaintiff set out various hardships that were being

faced by them in the matter of carrying out of the

work including purchase of quarry materials, fetching

of water, non-availability of labour etc. It is further

mentioned that the work which was shaping up well

has been stopped by the concerned Assistant

Executive Engineer. Hence, the plaintiff sought for

issuance of work order, release of the agreed

mobilisation advance at the earliest and to provide a

Borewell at the site.

x. Vide letter dated 27.02.1992 (Ex.P.12) the

plaintiff highlighted the hardship caused due to non-

availability of water and sought for providing a

Borewell at the site.

xi. The proceedings of the meeting held on

10/11.03.1992 between the parties (Ex.D.4) discloses

that the technical approval is accorded to the estimate

amounting to `2,23,27,000/- for the construction of

770 houses at Doddagunte (Jeevanahalli) in

Sy.No.150/1, 151, 152 and 158. It is further noted

that the tenements of the plaintiff for construction of

909 units at 15% above the existing rates at SR.90-91

has been approved in the meeting of the board held

on 04.02.1992 that the over all project cost should not

exceed `2,23,27,000/-.

xii. Vide letter dated 06.04.1992 (Ex.P.13),

the plaintiff authorized their General Manager Mr.

Shrikant R. Karnataki, to sign the bills, letters etc.,

and also accept cheques on their behalf.

xiii. Vide letter dated 08.04.1992 (Ex.P.14) the

defendant referring to the work order bearing

No.1/92-93 dated 12.03.1992 and its other

correspondences informed the plaintiff that in terms of

the tender notification and work order, the period of

completion of work is 18 months including the rainy

season from 15th June to 15th September. Further

reference has been made to construction of 770 units

at Doddagunte (jeevanahalli), the work order and the

meeting held on 26.3.1992, wherein it was agreed to

complete the work within 12 months. It was further

placed on record that the condition for completing the

work within 12 months was releasing the mobilisation

advance and for the said purpose the plaintiff was

requested to present a bar chart for financial and

physical completion of work within 10 months before

the release of mobilisation advance.

xiv. Vide letter dated 20.04.1992 (Ex.P.15) the

defendant informed the plaintiff that the Chairman of

the defendant had inspected the work at Dr.

Ambedkar slum on Murphy Town, Lingarajapuram

tank bed and Doddagunte (Jeevanahalli) site on

22.03.1992 and issued various instructions. It is

relevant to note that with regard to the work at the

Doddagunte (Jeevanahalli) site unhappiness was

expressed for the slow progress of work and the

plaintiff was instructed to improve the tempo of the

progress of work.

xv. Vide letter dated 15.05.1992 (Ex.D.29)

the defendant informed the plaintiff that various

points regarding the construction being carried out at

Doddagunte (Jeevanahalli) including that the masons

were not doing the size stones masonry with proper

size stones; that the stones are not being dressed

before laying; that the line, length and level are taken

carelessly; that some new masons were engaged for

the work who do not know the masonry work and that

they don't differentiate between size stones and

rubble; that the laying of stones are done haphazardly

effecting the quality of the work; that the supervision

staff of the plaintiff do not take notice of the same to

correct the mason, though the department staff

repeatedly instructed them regarding the same.

Further various short comings were pointed and it is

stated by the defendant that the desired progress is

not possible from the plaintiff with the type of

organisation and set up, even though they brought

sufficient construction material at the site. The

defendant further called upon the plaintiff to submit

the bar chart early and reinforce men and material at

the site to gear up the tempo of progress and that any

lapse may invite serious action.

xvi. Vide letter dated 18.05.1992 (Ex.P.16),

referring to the construction of 462 units at

Doddagunte (Jeevanahalli) and the letter dated

13.05.1992, the plaintiff informed the defendant of

various requirements including supply of working

drawings, plinth beam details, required steel and

sufficient place for casting yard.

xvii. Vide letter dated 27.05.1992 (Ex.P.17)

referring to its earlier letter dated 10.04.1992, the

defendant requested the plaintiff for submission of bar

chart to closely monitor the progress of work within

the time schedule.

xviii. Vide letter dated 05.06.1992 (Ex.P.18),

the plaintiff wrote to the defendant with regard to the

observations regarding progress of work. The plaintiff

informed the defendant regarding progress of work

and further requested for providing schedule - B as

also working drawings. It was further informed that

cement and steel were required to be supplied at work

site, that the plaintiff was made to collect cement

from Jayanagar and steel from A.D. Halli. It was

further requested that the construction of 464 houses

being allotted (out of which only 80% has been

allotted), is only part of the successful tender for

construction of 909 houses. It is further informed that

men and machineries earmarked and geared up for

909 houses is idle. The plaintiff requested the

defendant to award balance portion of work.

xix. Vide letter dated 08.06.1992 (Ex.P.19),

the plaintiff requested the defendant for consideration

of awarding of further work of construction of 909

tenements.

xx. Vide letter dated 10.07.1992 (Ex.P.20)

the plaintiff informed the defendant that they have

geared up and planned to hand over the houses by

the end of October, 1992, much before the stipulated

dated of 12th of March 1993 and that the plaintiff

themselves are not happy with the progress due to

strike of the transporters and non receipt of cement

which is beyond their control. Hence, the plaintiff

requested the defendant to look into the matter

regarding supply of cement early.

xxi. Vide letter dated 18.07.1992 (Ex.P.21) the

plaintiff informed the Chairman of the defendant that

despite passage of six months, the plaintiff being the

successful tenderer for the construction of 909

tenements, they have been awarded only 40% of the

work i.e., 464 units out of which site for 94 units is

yet to be made available. That men, material and

machineries kept ready for 909 units has remained

idle and are thus incurring losses. Hence, the plaintiff

requested the defendant to award the proposed

project at Doddagunte (Jeevanahalli) on 5½ acres of

acquired land.

xxii. Vide letter dated 20.07.1992 (Ex.P.22)

addressed by the plaintiff to the defendant, the

plaintiff admitted that they could not give the desired

progress due to non supply of cement and steel by the

defendant and that they purchased cement in the

open market and enclosed the bills for the same.

Hence, the plaintiff sought for release of material

advance and also sought for reimbursement of the

extra cost of cement incurred by the plaintiff. The bills

of purchase of the cement was also enclosed along

with the said letter.

xxiii. The defendant vide letter dated

22.07.1992 (Ex.P.23) highlighted the fact that no

cement has been supplied and made a request for

immediate supply of cement.

xxiv. Vide letter dated 03.08.1992 (Ex.P.24) the

plaintiff informed the defendant, while referring to the

work order dated 12.03.1992 for 770 units at

Doddagunte, placed on record that only 366 units

have been entrusted and for want of availability of site

for the remaining units have not been entrusted.

Hence, the plaintiff requested for immediate

arrangements to handover the site along with the

markings.

xxv. The plaintiff vide letter dated 28.08.1992

(Ex.P.25), while referring to the letter of the

defendant dated 17.08.1992 has informed the

defendant, inter alia, that the work awarded by the

defendant was outside the purview of the tender for

909 tenements, that the supplies of cement and steel

have been irrational and that although two borewells

have been dug, no pump sets and no electricity

connection have been provided at the site. That there

was complete demobilisation of men and machinery

for over 1½ month and due to non supply of cement

the hollow concrete blocks could not be manufactured

during the said period.

xxvi. Vide letter dated 02.09.1992 (Ex.P.26),

the defendant while responding to the letter of the

plaintiff - Ex.P.25 has stated regarding the land have

been available for construction of 464 units. Further

the defendant admitted that due to various factors

there was delay in the supply of the cement. Further

the defendant admitted that there was a delay in the

changes recommended by the architect. However,

water and electricity supply are responsibility of the

tenderer. Further, the defendant informed the plaintiff

that the reasons mentioned by the plaintiff in its letter

Ex.P.25 cannot be the reason for the delay and

informed that the defendant expects early completion

of tenements. That depending on the progress of the

work, defendant will take appropriate action in

awarding the work concerning the tender for 9090

tenements.

xxvii. Defendant vide letter dated 14.09.1992

(Ex.D.30) informed the plaintiff that during the

inspection of the site, it has been noticed that hollow

blocks cast at the site are being used on the works

without required curing which was objectionable.

Further, it informed that the arrangements for curing

was very poor and that the hollow blocks had not

acquired required strength. Hence, it is informed that

the blocks manufactured should be tested by the

quality control sub-division before being used. Hence,

the defendant informed the plaintiff that necessary

instructions be issued to the site Engineer and that

there should be no deviation on the said instructions.

xxviii. Vide letter dated 23/25.09.1992 (Ex.P.27)

the defendant, in furtherance of its letter - Ex.P.26

informed the plaintiff to take up fabrication of steel for

lintels and proceed with the work of casting of the

same without further delay and also ensure that the

roof slab is laid by the end of dated October 1992.

xxix. Vide letter dated 05.10.1992 (Ex.D.31),

the defendant referring to the undertaking dated

08.04.1992 executed by a representative of the

plaintiff, as also its letters dated 08.07.1992,

13.05.1992, 09.04.1992 and 27.07.1992, informed

the plaintiff that the bar chart of the work in terms of

the undertaking dated 08.04.1992 of the

representative of the plaintiff has not been furnished.

It is further informed that, as seen from the last paid

bill, there is short progress. Hence, the defendant

informed the plaintiff to raise the work progress to the

agreed monthly progress by the next bill, failing which

the penal clauses of the contract would be enforced.

xxx. Vide letter dated 23.10.1992 (Ex.P.28) the

defendant referring to the meeting dated 21.10.1992

reminded the plaintiff to submit the necessary bar

chart, failing which action will be taken to cancel the

contract.

xxxi. The plaintiff vide its letter dated

29.10.1992 (Ex.P.29) referring to the letter - Ex.P.28

intimated the defendant that copy of the sanctioned

estimate of schedule - B to enable preparation of the

required bar chart was not provided despite repeated

requests. It also informed that construction at

Doddagunte is outside the purview of the tender.

Further it is informed that some of the houses have

already reached roof level and the roof related

drawings has not been furnished by the defendant. It

is further placed on record that the oral changes are

proposed in the stair case and hence, sought for

revised drawings. The plaintiff also sought for

clarification regarding work of the internal walls which

has been stooped by concerned architect. Hence, the

plaintiff informed the defendant that maintaining

progress in the absence of related drawings and

clarifications was left to the imagination of the

defendant.

xxxii. Vide letter dated 31.10.1992 / 02.11.1992

(Ex.P.30) the defendant referring to the letter -

Ex.P.29 enclosed a copy of the schedule - B to enable

submission of the bar chart.

xxxiii. Vide letter dated 24.12.1992 (Ex.D.32),

the defendant referring to the letter dated 08.12.1992

of the plaintiff informed that the bar chart submitted

by the plaintiff shows the period of completion at

September 1993 which extends to 19 months instead

of 18 months as per the agreement. Further 464 units

were to be completed within 18 months from March

1992, but the plaintiff has given a program for

completion of 348 units which should be completed by

April 1993, where as the plaintiff has given

programme up to September 1993 which is not

correct. It is further informed that the progress of the

site is behind schedule which is to be expedited. The

defendant has further informed that inspite of

repeated reminders and instruction that there is no

improvement in the style of working at the site. That

the curing is poor and centering and laying of concrete

is for from satisfactory. That the field staff of the

plaintiff did not understand the instructions given by

the department staff and that if the same is not

corrected, action will be taken in terms of the

agreement. The defendant also sought for bar chart

showing physical and financial progress.

xxxiv. Vide letter dated 01.01.1993 (Ex.D.34),

the defendant referring to the plaintiff's letter dated

28.12.1992 informed the plaintiff that with regard to

the issue of cement bags for the Jeevanahalli project,

that sofar 11,600 bags of cement have been issued to

the plaintiff and the plaintiff was permitted to bring

1,605 bags and use the same during the month of

August 1992. That the overall quantity issued on the

work is 13,250 bags, but when the actual physical

progress of the work is assessed, the up to date

consumption is only 7,000 bags and that the plaintiff

was left with 6250 bags for which no work is done.

Hence, the stoppage of work on account of non issue

of cement is not justified. It is further informed that

curing is not satisfactory and that laying of concrete to

roof slab, lintel, chejja and staircase is very carelessly

done and lot of honeycombs are seen after centering.

That in spite of mobilisation advance and regular bills

in respect of the work done, the progress work is

poor. Hence, the defendant informed the plaintiff that

unless the defects are rectified in toto and the bank

guarantee submitted for the mobilisation advance is

received no recommendation for issue of any material

will be made.

xxxv. The plaintiff vide letter dated 12.01.1993

(Ex.P.31) informed that 25% of the project units

would be handed over by March 1993 at Jeevanahalli

and subject to supply of cement and steel, clearance

of drawings and bills periodically and instructions and

directions in the right tempo.

xxxvi. Vide letters dated 01.02.1993 and

10.02.1993 (Ex.P.32 and 33) the plaintiff informed the

defendant that they are facing tremendous shortage

of supply of cement and sought for action at the

earliest.

xxxvii. Vide letter dated 06.02.1993 (Ex.D.36)

the defendant informed the plaintiff that they have

laid the roof concrete on 3rd block of Sy.No.158 on

12th and 13th January 1993 leaving three stair case

and two units in the middle without concreting. That

no arrangements have been made to lay the concrete

for the remaining portion. It is further placed on

record that the staff of the plaintiff has informed that

they have not procured the jelly for the work. It is

further placed on record that plaintiff has lifted 150

bags on 03.02.1993 informing that they will be lent

for purchasing blocks and that though the defendant

was not obliged to supply of cement for manufacture

of blocks, sufficient quantity was issued to ensure

good progress of work. The defendant has placed on

record that the plaintiff is misusing the cement and

steel and has not making arrangements for proper

progress of work. It is further placed on record that

the staff of the plaintiff have informed the defendant

that two pumps which are used for curing are under

repair. It is informed that bar chart as promised to be

supplied by the plaintiff was not done. Hence, the

defendant informed the plaintiff that it was

recommending to the higher authorities for applying

the penal clauses of contract and for imposing fines on

the inordinate delay.

xxxviii. Vide letter dated 10.02.1993 (Ex.D.35)

the defendant has informed the plaintiff that it has

issued 14,348 bags of cement and 70 Metric Tons

(M.T) of steel and the consumption is only 8000 bags

of cement and 46 M.T of steel. Hence, denied the

statement of the plaintiff that cement and steel is not

issued. The defendant further requested the plaintiff

for bar chart to keep track of the progress of work and

substantiation of utilisation of material on the work.

The defendant further informed that the penalty of

`100/- per day will be starting from 20.02.1993, if

work is not resumed and continuous work is done not

till the end of the tender which expires on 30.09.1993.

xxxix. The plaintiff vide letter dated 18.02.1993

(Ex.P.34) informed that the works of casting roof

slabs, hollow block masonry, fixing of doors, windows,

plasting etc., are in progress and sought for

preparation of four RA bills.

xl. The plaintiff vide letter dated 18.02.1993

(Ex.P.35) listed progress of the work and also listed

out various issues faced by the plaintiff. It is further

placed on record that it received 15,800 bags of

cement and consumed 15,710 bags. The basis of

consumption has also been furnished. Hence, the

plaintiff has placed on record that as only 90 bags

(wrongly calculated as 80 bags in Ex.P35) of cement

are in stock. It is further stated that the imposition of

penalty is not justified. It is further informed that by

February 1993 the plaintiff has planned to handover

25 units to slum dwellers and requested for handover

of balance 561 units and the balance work in terms of

work order.

xli. The plaintiff vide letter dated 23.02.1993

(Ex.P.36) has sought for sanitation, water supply and

electrical drawings of the earliest as also the sanction

schedule - B at the earliest. The plaintiff sought for

the handover of balance 561 houses.

xlii. Vide letter dated 05.03.1993 (Ex.P.38) the

plaintiff referring to the letter of the defendant dated

03.03.1993 informed that the sanction schedule - B is

not handed over. Further it has informed that water

supply, electricity and sanitation has been handed

over on 01.03.1993. Further the plaintiff requested

the defendant to consider with holding supply of

cement against recovery of cement as they are in

need of financial assistance. Further the plaintiff

stated that the scope of the work allotted as per

estimates, schedules, EMD which may be handed over

to avoid entitling the plaintiff to claim losses towards

machinery, labourers, staff establishment overheads,

etc. It is further informed that the bank guarantee is

valid up to August 1993 and the same will be

extended. It further informed that the plaintiff has

been paid only 75% of the windows and 25% is with

held and release of same was sought. It is further

informed that the question of non preparation of bill

No.4 did not arise and imposition of penalty was

unjustified.

xliii. The defendant vide letter dated

06.03.1993 (Ex.D.38) referring to letter - Ex.P.34 of

the plaintiff enclosed para wise replies to the same

and also regretted slow progress of work. It is further

informed that action will be taken in terms of penal

clauses of the agreement.

xliv. Vide letter dated 31.03.1993 (Ex.P.37) the

plaintiff informed the defendant that they have no

stock of cement and that they have not received

cement from the defendant due to which the progress

of work is suffering. Further the plaintiff is suffering

from financial crisis due to non-release of bills by the

defendant. Hence, supply of sufficient quantity of

cement and release of bills were requested at the

earliest.

xlv. Vide letter dated 07.05.1993 (Ex.P.39) the

plaintiff stated regarding non supply of cement at

regular intervals and non payment of bills and sought

for making necessary arrangements to avoid losses.

xlvi. Vide letter dated 22.06.1993 (Ex.P.40),

the plaintiff referring to the meeting dated 07.06.1993

with the Housing Commissioner denied that the

plaintiff is due to the defendant in a sum of

`9,40,000/-. Further the plaintiff informed the

defendant to recover the cement, if any against a sum

of `7,17,500/-. It further informed that the bank

guarantee is valid up to August 1993 and the same

would be renewed. It is further informed that

payment of 4th RA bill of `9,40,000/- is pending. That

revised bar chart for extension period in terms of the

discussions with the Housing Commissioner will be

submitted on payment of the 4th RA bill. It further

sought for supply of cement as there was no cement

with the plaintiff. It further informed that around 38%

of the work has been handed over and 75% of the

tendered work ought to have been handed over. That

the work was entrusted on 12.03.1992 with the period

of 18 months for completion. However, only 348 units

against the allotted 909 units as per tender were

handed over. That due to non supply of cement by the

defendant that the work could not be completed as

per the time schedule. Further it was informed that a

fresh bar chart with extension period to be submitted

on the defendant with release of `5,00,000/- against

the 4th RA bill. That the defendant was liable to pay a

sum of `9,40,000/- towards the 4 th RA bill and that

the plaintiff will start working immediately on release

of `5,00,000/- on issue of bulk quantity of cement by

the defendant.

xlvii. Vide letter dated 29.6.1993 (Ex.P41), the

plaintiff submitted a revised bar chart to the

defendant with extension period of 348 units at

Sy.Nos.151, 152 and 158 at Jeevanahalli -

Doddagunte. However, it is stated that the said

revised bar chart was subject to various conditions (11

nos.).

xlviii. Vide letter dated 7.5.1993 (Ex.P42) the

plaintiff referring to the various letters written by the

defendant sought to visit the office of the Chief

Engineer of the defendant to personally cover the

issues raised in the said correspondences.

xlix. Vide letter dated 1.7.1993 (Ex.P43), the

plaintiff referring to the meeting with the Housing

Commissioner on 7.6.1993 and other correspondences

confirmed that upon receipt of the cement shifting

letter on 30.6.1993 the work has started.

l. Vide letter dated 6.7.1993 (Ex.P44) the

plaintiff sought for extension of time for completing

348 units at Sy.Nos.151, 152 and 158 at Jeevanahalli

- Doddagunte up to March, 1994. It is stated that

extension was due to unavoidable circumstances from

the defendant.

li. Vide letter dated 16.7.1993 (Ex.D40), the

defendant responding to the letter - Ex.P41 informed

that the period under the contract expires on

12.9.1993 and the work was required to be completed

before the said date. It is further informed that there

was regular supply of cement from time to time and

14666 bags have been issued against the utilised

cement of 8596 bags towards the work and 6843 bags

towards manufacture of hollow blocks. Further, it is

placed on record that the plaintiff stopped the work

since December 1992, which is not correct. It is

further informed that handing over of balance

site/houses as demanded by the plaintiff will arise

only after completion of the work on hand. The

plaintiff was called upon to step-up with the work

progress.

lii. Vide letter dated 27/29.7.1993 (Ex.P45),

the plaintiff informed the defendant that the shifted

quantity of cement from Valmikinagar site is almost

over and further arrange for bulk quantity of cement

to avoid stoppage of work.

liii. Vide letter dated 28.07.1993 (Ex.P.46),

the plaintiff referring to the letter of the defendant -

Ex.D.40 intimated the plaintiff that the cement supply

is almost exhausted and if further bulk quantity is not

released the work in progress will be effected. It

further intimated that the cement supply by the

plaintiff of 1650 bags will be removed if payment at

`117 is not released for the same. It is further

informed that the 4th part bill has not been paid. It is

further demanded that the balance contract work

should be handed over at the earliest to avoid further

claims and losses.

liv. Vide letter dated 03.08.1993 (Ex.P.47),

the plaintiff, referring to the meeting in the chamber

of the Housing Commissioner on 07.06.1993 and

earlier correspondence, intimated that the work is in

progress inspite of non-cooperation by the defendant.

It further placed on record that bulk quantity of

cement should be released without further delay as to

avoid stoppage of work. It is further stated that the

instructions of the Housing Commissioner has been

maintained and the progress of the work has been

kept up in spite of non cooperation. It is further stated

that the quantity of cement consumed is accepted by

the defendant in the previous letter and there is no

further balance from the quantity supplied from the

department.

lv. Vide letter dated 06.08.1993 (Ex.P.48),

the plaintiff sent a reminder to the defendant

regarding various aspects including payment of 4th

part bill, release of balance payment for cleaning

works, etc.

lvi. Vide letter dated 06.09.1993 (Ex.D.41),

the defendant referring to the letter of the plaintiff

dated 03.09.1993 and earlier correspondence

intimated the plaintiff regarding cement consumption

and that the block / mixture machine after service /

repair is kept at the site.

lvii. Vide letter dated 09/10.09.1993

(Ex.D.42), the defendant issued a show cause notice,

to show cause within 10 days as to why action should

not be taken in terms of the contract. The said show

cause notice has placed on record, various alleged

lapses on behalf of the plaintiff.


  lviii.        Vide letter dated 14.09.1993 (Ex.D.43),

the         defendant   has      intimated     the   Housing

Commissioner that the contractor has lost interest in

completing the work. It is further placed on record the

various lapses of the plaintiff and it is also been

informed that works entrusted are in three survey

Nos.151, 152 and 158 and that balance portion of

work in two survey numbers i.e., 151 and 152 would

be withdrawn.

lix. Vide letter dated 13.10.1993 (Ex.D.44),

the plaintiff with regard to the letter of the defendant

regarding encashment of bank guarantee and

undertook to continue with the work in full progress,

which can be seen from the next three months.

lx. Vide letter dated 18.11.1993 (Ex.D.45),

the defendant referring to its earlier letter dated

20.10.1993 and the letter of the plaintiff dated

24.10.1993 informed the plaintiff to expedite the work

including completion of internal services, so as to

handover to the completed units without delay. It

further sought for flooring works, plastering of walls

and curing to be done simultaneously. It sought for

submission of bar charts for granting extension of

time.

lxi. Vide letter dated 26/27.11.1993 (Ex.D. 25

& 46), the defendant referring to the letter of the

plaintiff dated 04.11.1993 has placed on record that

the defendant has supplied 15038 bags of cement and

70.52 metric tons of steel, but the plaintiff has lifted

850 bags of cement and 14.365 metric tons of steel

unauthorizedly. Hence, it has disputed the assertion of

the plaintiff that despite non supply of materials by

the defendant the work progress will be continued.

Further it is stated that the centring work at

Sy.No.152 has not started except Sy.No.151. It is

further stated that the manufacturing of cement

concrete hollow blocks are not being done

continuously. It is further stated that the revised bar

chart has promised has not been furnished. It is

further stated that the men and labour engaged in

work are meagre, compared to left over portion for

complexion and the work progress is slow. The

defendant has further stated that as per its

assessment, the plaintiff will not be able to complete

the work in time as promised. The defendant further

informed the plaintiff that they fail to give satisfactory

progress engaging sufficient men, labour and

materials, the defendant will be constrained to

rescined the balance work and complete the same

through another agency. It is relevant to note that

said notice (Ex.D.25) which was sent by registered

post has been returned as not claimed.

lxii. Vide letter dated 06.11/12.1993

(Ex.D.33), the defendant informed the plaintiff that

there is delay and unsatisfactory progress in the work

and that despite repeated reminders, no action has

been taken. The defendant has called upon the

plaintiff to look into the matter and to take necessary

action to make up back log and shortfall in the

progress and also maintain good quality of work and

that if the short fall is not made good within the

stipulated time, the plaintiff will be liable for penal

action.

lxiii. Vide letter dated 18/20.12.1993 (Ex.D.10)

the defendant referring to its earlier letters dated

25.09.1993 (Ex.D43) and 18.11.1993 (Ex.D.45) as

well as the undertaking dated 16.10.1993, informed

the plaintiff that the work has been stopped since two

weeks and the registered letters sent by the

defendant are returned as not claimed. That as per

the contract, the work should have been completed

and units handed over by 12.09.1993 that the

progress achieved is not encouraging. Hence, the

plaintiff was intimated that the centering and laying of

roof in Sy.No.151 and 152 was required to be done on

or before 31.12.1993 failing which the said letter itself

will be a final notice and action will be initiated as per

agreement.

lxiv. Vide letter dated 24.12.1993 (Ex.D.11),

the defendant referring to its earlier letters including

letter - Ex.D.10 has informed the plaintiff that no

action has been taken despite lapse of three months

of the period stipulated in the agreement and that the

plaintiff has failed to keep up to the undertaking dated

13.10.1993 that work has been stopped since fifteen

days without valid reasons even thought penalty of

`100/- per day have been imposed for short progress.

That 858 bags of cement and 14.385 metric tons of

steel and mobilization advance of `14.40 lakhs is

outstanding and that there is no satisfactory work

progress. Hence, it was informed that if the centering

and laying of roof in Sy.No.151 and 152 are not done

within 31.12.1993 and the construction work is not

commenced, the deposits of the plaintiff will be

forfeited and penal clauses in the agreement would be

enforced and the plaintiff will be recommended for

black listing.

lxv. Vide letter dated 21.02.1994 (Ex.D.12 /

Ex.D.47), the plaintiff informed the defendant that the

balance quantity of steel is with them and will be used

for the work as and when required.

lxvi. Vide letter dated 19/22.04.1994

(Ex.D.13), the defendant issued a "pre-final notice" to

the plaintiff, referred to its earlier correspondence and

intimated that the progress achieved is to an extent of

` 45,82,366/- as against estimated cost of

`2,23,27,000/- which is unsatisfactory. It is further

reported that as per the report of the Assistant

Executive Engineer of the defendant the plaintiff has

not resumed the work as on 05.04.1994. Hence, the

plaintiff was called upon to immediately commence

the work failing which the contract would be

rescinded.

lxvii. Vide letter dated 10/11.05.1994

(Ex.D.14), the defendant referring to the earlier

correspondence and referring to the joint meting held

on 22.02.1994 intimated the plaintiff that the revised

bar chart has not been produced. Further it has

intimated that in the event that the work has not

completed on a "war footing basis", the defendant will

withdraw a portion of the work and carry out the

same, at the risk of the plaintiff.

lxviii. Vide letter dated 31.08.1995 (Ex.D.48),

the defendant informed the plaintiff that tempo of

progress of the work is not satisfactory and that the

beneficiaries are expressing their apprehension for the

delay caused in the completion of houses. Hence, the

plaintiff was informed to step-up the progress failing

which penal clauses will be imposed.

lxix. Vide letter dated 11.09.1995 (Ex.P.52),

the plaintiff referring to the letter of the defendant

dated 31.08.1995, informed that the centering for

casting, lintels, chejjas, roofs, plastering, etc are in

progress. That the work is kept as per the supply of

departmental materials and to increase the required

tempo of progress, maximum quantity of

departmental materials are required. It is further

informed that as per mutual discussion in the chamber

of the defendant the sanitation works will be started

shortly.

lxx. Vide letter dated 13.10.1995 (Ex.D.49),

the defendant informed the plaintiff that they have

issued 1200 bags of cement during the months of July

to September 1995 and the work carried out during

July and August has been measured and paid. That

651 bags of cement were used on work and the same

was recovered in the 14th RA bill. Hence, there were

549 bags of cement at the site. It is further informed

that 175 bags of cement were also issued on

27.09.1995. Hence, there is total 724 bags at the site.

That as per the existing work it was estimated that

200 bags of cement was consumed and there should

be a balance of 500 bags of cement as on the date of

letter. Hence, it is informed that until all the 500 bags

of cement should be used for work, no fresh cement

will be given. It is further informed that curing work is

not being carried out properly for the plastering and

that centering work is also not done properly. The

plaintiff was informed to rectify the said issues. It is

further informed that 10.5 metric tons of steel was

issued on 28.07.1995 and only 29 units have been

casted. Hence, there is balance steel and cement

available to carry out the work. It is further informed

that the defendant has paid for steel windows and

doors fixing. Hence, the plaintiff was requested to

bring the quantity to the site and fix the same without

further delay. It is further placed on record that

despite repeated instructions, sanitary works are not

being done properly and the plastering to inside walls

is being done without fixing doors and windows.

lxxi. Vide letter dated 20.11.1995 (Ex.D.50),

the defendant has informed the plaintiff that curing

and centering work is not done properly. It is further

informed that the material advance given for nearly

`40,000/- hollow bricks was give and the same is not

available on the site. Further 21.00 metric tons of

steel issued was not available at the site. That the

plaintiff has promised to bring back the balance

quantity of steel to the work site. It is also noticed

that steel doors and windows are fixed at site is not

according to specification and measurements. Hence,

needful action by the plaintiff was requested.

lxxii. Vide letter dated 27.11.1995 (Ex.D.51),

the defendant referring to its earlier correspondence

has issued notice No.5 listing out the various

deficiencies and further informed the plaintiff that the

Minister of State Housing and the local MLA have

expressed unhappiness with the execution of the

work. It is further instructed that proper action be

taken to accelerate the work and complete the same

as per the schedule failing which fine will be imposed.

lxxiii. Vide letter 07/12.12.1995 (Ex.D.53), the

defendant once again informed the plaintiff regarding

various details and deficiencies in the work carried out

by the plaintiff.

lxxiv. Vide letter dated 28.12.1995 (Ex.D.54),

the defendant has once again pointed out various

deficiencies in the work of the plaintiff and required

the plaintiff to carry out the work and treat the said

letter as final notice.

lxxv. Vide letter dated 05/08.01.1996

(Ex.D.55), the defendant once again listed out the

various deficiencies and pointed out that the total

outstanding secured advance was `13,00,945/- and

called upon the plaintiff to take necessary action and

read the said letter as a final notice.

lxxvi. Vide letter dated 28/29.02.1996

(Ex.D.57/D26/P53), the defendant pointed out the

various deficiencies in the work of the plaintiff and

informed that necessary action would be taken as per

the agreement including resending of the contract if

the needful is not done within time;

lxxvii. Vide letter dated 5.3.1996 (Ex.P54) the

plaintiff referring to the various earlier

correspondences, listed out action for sorting out

various issues;

lxxviii. The plaintiff, vide legal notice dated

7/8.3.1996 (Ex.P55) has called upon the defendant to

sort out the differences to ensure completion by April,

1996;

lxxix. The plaintiff, vide letter dated 12.3.1996

(Ex.P56) has sought for issue of departmental

materials to facilitate completion of the work in terms

of the work order;

lxxx. Vide letter dated 13.3.1996 (Ex.P57), the

plaintiff requested the defendant to withdraw the

letter issued by it to the bank not permitting the

plaintiff to encash the bank guarantee;

lxxxi. The plaintiff vide letter dated 18.3.1996

(Ex.P58) referring to the meeting held between the

parties on 15.3.1996 conveyed to the defendant that

pending settlement of its claims, the plaintiff will be

increasing the strength of the work force and give

progress of 3.5 lakhs by April, 1996, on specific

assurance that payments would be released. It

further requested for 407 bags of cement to be issued

immediately for carrying out the work up to 5.4.1996;

lxxxii. The plaintiff vide letter dated 21.3.1996

(Ex.P59) requested for issue of material for

completing the works in all respects with respect to

378 units;

lxxxiii. Vide letter dated 21.3.1996 (Ex.P60), the

plaintiff sought for copies of the bill Nos.1 to 144;

lxxxiv. Vide letter dated 21.3.1996 (Ex.P61) the

plaintiff sought for payment of intermediate bill

amounting to `21,61,285.16. It also requested for

copies of bill Nos.1 to 14 contending that there was

some omission in the measurements recorded by the

defendant;

lxxxv. The defendant got issued a registered

letter dated 26.3.1996 (Ex.P63), whereunder it

referred to its earlier correspondences as well as letter

dated 21.3.1996 of the plaintiff (Exs.P59 and P60) and

in detail set out its responses, inter alia, placing on

record that there is recovery outstanding towards

consumed cement of 9980 bags up to 14 RA bill and

until the cost of the cement is recovered, there is no

funds available to purchase the quantity of the

cement. It has further placed on record that the

balance quantity of 17.8 MTs., steel with the plaintiff

and until the said quantity is consumed, the balance

quantity cannot be issued. It has further placed on

record that if the plaintiff does not give the required

progress by 6.4.1996 to complete the balance work,

action will be initiated;

lxxxvi. Vide registered letter dated 30.3.1996

(Ex.P64) in response to the legal notice dated

7.3.1996 (Ex.P55), the defendant has in detail

responded to the assertions made by the plaintiff vide

the said legal notice;

lxxxvii. The plaintiff vide its letter dated 3.4.1996

(Ex.P65) in response to the letter of the defendant

dated 30.3.1996 (Ex.P64) as disputed the assertions

made by the defendant regarding supply of cement

and steel. Further, the plaintiff sought for settlement

of existing claims as also the payment of pending bills

and handing over of the balance site;

lxxxviii. Vide letter dated 11.4.1996 (Ex.P66) the

plaintiff referring to its earlier correspondences sought

for supply of cement/steel and also settlement of its

existing claims;

lxxxix. Vide letter dated 25.4.1996 (Ex.P67) the

plaintiff once again sought for payment of existing bills

and supply of material;

     xc.     Vide     communication          dated      5.6.1996

 (Ex.P69),   the    defendant       issued   to   the   plaintiff,

contract rescinding order whereunder the defendant

intimated the plaintiff that the tender agreement has

been rescinded and requested that the representative

of the plaintiff be present at the site on 20.6.1996 at

11.00 am., for taking final measurements;

xci. Vide letter dated 19.6.1996 (Ex.P70) the

plaintiff noticing the letter of the defendant dated

5.6.1996 has intimated that the plaintiff is unable to

be present for the joint measurements and sought for

deferment of the joint measurements;

xcii. Vide legal notice dated 17.10.1996

(Ex.P87) the plaintiff got issued a legal notice under

Section 72 of the Karnataka Housing Board Act, 1962

and made a claim for payment of a total sum of

`1,75,10,964/- from the defendant.

16. It is forthcoming from the aforementioned that

pursuant to the tender dated 14.10.1991 issued by the

defendant for construction of the said 909 tenements,

negotiations took place between the plaintiff and the defendant

regarding the same and in October, 1991 itself, the defendant

had intimated the plaintiff that various sites were unable to be

handed over to the plaintiff for construction of the said

tenements due to various issues/disputes. It is further

forthcoming from the communication dated 18.12.1991 (Ex.P6)

that the defendant had requested the plaintiff to take up

construction of 36 tenements in Appareddy Palya and further

construction of 462 tenements at Jeevanahalli/Doddagunte

immediately and sought for the work to be commenced on

either 19.12.1991 or 20.12.1991 since the Hon'ble Minister for

Housing and Urban Development was pressing for starting of

the work. Further, it is forthcoming from the letter dated

28.12.1991 (Ex.P7) that the plaintiff has acknowledged to the

defendant that it has started cleaning of the site and

excavation of marked houses.

17. Thereafter, various communications have been

exchanged between the parties including the plaintiff having

issued a bank guarantee as is forthcoming from the letter dated

11.2.1992 (Ex.P10). The plaintiff vide letter dated 18.02.1992

(Ex.P11) has sought for issuance of work order while placing on

record that the construction of 462 tenements was not part of

the original tender. It is forthcoming that the plaintiff

commenced construction much prior to issuance of the work

order and that the work order was issued on 12.3.1992

(Ex.P83), whereunder construction of 770 units in Sy.No.150/1,

151, 152 and 158 of Doddagunte/Jeevahanalli was entrusted

and the total contract including the tender premium of 15%

was a sum of `1,88,59,825/-. The period of completion was 18

months from the date of entrustment of not less than 75% of

the work site area. Various other conditions including security

deposit was stipulated in the work order (Ex.P83). The

defendant vide letter dated 08.04.1992 (Ex.P14) while referring

to the work order dated 12.03.1992 has placed on record that

although in the work order, the period for completion of the

work was 18 months including the rainy season from 15th June

to 15th September, as per the discussion held on 26.03.1992,

the period of completion of the work was restricted to 12

months.

18. It is forthcoming that the defendant has supplied

various quantities of cement and steel as agreed, apart from

giving mobilization advance. However, the plaintiff has

consistently sought for further supply of cement and steel from

the defendant.

19. As is forthcoming from the letters dated 1.1.1993

(Ex.D34), 4/10.2.1993 (Ex.D35) and 6.2.1993 (Ex.D36) the

defendant has specifically alleged that the plaintiff has

misutilized the cement and steel supplied by the defendant for

the project in question and has in fact, diverted the said

material supplied by not utilizing the same for project in

question. Although the plaintiff has denied the same, there is

sufficient material on record which indicate that the defendant

has clearly pointed out the misappropriation of the material

supplied by it.

20. The defendant vide letter dated 20.04.1992

(Ex.P15) has placed on record the observations/instructions

pursuant to the inspection made by the Chairman of the

defendant on 22.03.1992 whereunder, it, inter-alia, suggested

various measures with regard to the construction carried out at

Doddagunte-Jeevanahalli site. The plaintiff vide letter dated

05.06.1992 (Ex.P18) has placed on record various aspects

regarding construction of 464 units at Doddagunte. In the said

letter, the plaintiff has admitted that out of 464 houses, more

than 20% of the site is yet to be made available. The defendant

vide letter dated 02.09.1992 (Ex.P26), while responding to the

letter of the plaintiff dated 28.08.1992 (Ex.P25), has responded

to the various aspects raised by the plaintiff in the said letter.

Further, the defendant in Ex.P26 has raised various aspects

indicating the slow progress of work and has specifically

stipulated that depending on the progress of the work by the

plaintiff, the defendant will take appropriate action in awarding

the work concerning the tender for 909 tenements.

21. Hence, as is clearly forthcoming from the material

on record, particularly Ex.P26, that the defendant specifically

entrusted construction of 462 units (wrongly mentioned as 464

units) to the plaintiff and also specified that after completion of

the said 462 units in a satisfactory manner the question of

entrustment of further construction to the plaintiff would arise.

However, it is forthcoming that the plaintiff has in all its

correspondences specifically demanded from the defendant for

entrustment of the balance work of construction of 909

tenements. The demand of the plaintiff for entrustment of

balance work of 909 tenements is ex facie untenable having

regard to the fact that the area in which the construction was

required to be taken was not available with the defendant.

Although the plaintiff participated in the tender issued by the

defendant for construction of 909 tenements, there was no

binding obligation on the defendant to entrust the said work to

the plaintiff. It is relevant to note that the work order (Ex.P83)

was for construction of 707 tenements. However, the defendant

has entrusted construction of 462 units to the plaintiff and had

specifically stipulated vide Ex.P26 that appropriate action for

awarding the work with regard to the 909 tenements will

depend on the progress of the work by the plaintiff in respect of

the construction of 462 units already entrusted.

22. The defendant vide letter dated 23.10.1992

(Ex.P28) had called upon the plaintiff to do the needful

regarding the submission of the bar-chart, failing which action

will be initiated to cancel the contract. The plaintiff, vide letter

dated 29.10.1992 (Ex.P29) had sought for copy of the sanction

estimate or Schedule-B, on receipt of which the required bar-

chart would be prepared. The defendant vide letter dated

31.10.1992 / 02.11.1992 (Ex.P30) forwarded a copy of the

Schedule-B which contained the details/specifications of the

construction that was required to be carried out by the plaintiff.

23. Further, despite the defendant repeatedly pointing

out various deficiencies in the construction activity that was

carried on by the plaintiff, the plaintiff has repeatedly claimed

for the balance construction work to be handed over and also

claimed that it had mobilized requisite men and material for

construction of the entire work as demanded. However, it is

relevant to note that there is no material placed on record by

the plaintiff to demonstrate that it has mobilized the entire men

and material. On the contrary, the claim of the plaintiff that it

had mobilized all the men and material is ex facie untenable

having regard to the fact that the defendant has from time to

time pointed out the slow progress of the work carried on by

the plaintiff and has repeatedly asked for the plaintiff to

expedite the work. If the plaintiff had, infact mobilized the

men and material to carry out construction of 909 tenements,

the question of slow progress of work by it would not have

arisen.

24. It is relevant to note that vide letter dated

06.02.1993 (Ex.D36) the plaintiff has specifically alleged

regarding the plaintiff misusing the steel and also that two

water pumps used for curing were under repair for more than a

month. Hence, the defendant called upon the plaintiff to comply

with the work progress failing which the penal clause under the

contract would be applied. Further, vide letter dated dated

02.05.1992 (Ex.D28), which has been issued by the defendant

in reply to the plaintiff's letter dated 18.02.1993 (Ex.P34), the

defendant enclosed parawise replies to the letter of the plaintiff

and further intimated that action will be taken by imposing

penal clauses and withdrawal of work.

25. It is forthcoming from a perusal of the

correspondences as noticed above that despite the demand

made by the defendant to expedite the progress of the

construction work, the plaintiff has made a counter demand for

supply of material and payment of bills. In fact, it is

forthcoming from letter dated 01.01.1993 (Exs.D34), letter

dated 7/12.12.1995 (D53) and letter dated 28/29.02.1996

(D57) that the plaintiff has also stopped the work on the

ground that the defendant has not supplied material to the

plaintiff.

26. It is clear that the plaintiff has admitted vide letter

dated 05.06.1992 (Ex.P18) that it had received more than 80%

of the area to put up construction of 462 units at Jeevanahalli-

Doddagunte. In terms of the tender (Ex.P83) and as recorded

in Ex.P14, the time for completion of the construction was 12

months. Hence, the plaintiff was required to complete the

construction within 12 months from 05.06.1992.

27. Since there was delay in the completion of

construction, various correspondences have been exchanged

between the parties and the parties have also held various joint

meetings to address the issues arising from the said delay. The

minutes of the meeting held on 21.02.1994 (Ex.P51) discloses

that the parties agreed to the manner of resolution of various

aspects including the demand of the plaintiff for further cement

as well as payment of pending dues. However, since according

to the defendant, the work had not progressed in terms of what

was agreed between the parties, various notices have been

issued i.e., Ex.P53/Ex.D57, Ex.P63, etc. Thereafter, the

defendant vide letter dated 05.06.1996 (Ex.P69) has issued the

"Contract Rescinding Order" whereunder it has rescinded the

contract entrusting the work to the plaintiff and directed the

representative of the plaintiff to be present at the site on

20.06.1996 for taking final measurements. However, the

plaintiff vide letter dated 19.06.1996 (Ex.P70) has sought for

rescheduling of the date fixed for taking joint measurements. It

is also relevant to note here that the plaintiff also issued legal

notice dated 07.03.1996 (Ex.P55) to the defendant.

28. The defendant has also issued various notices to

the plaintiff i.e., notice dated 19/22.04.1994 (Ex.D13), notice

dated 10/11.05.1994 (Ex.D14), final notice dated 15.6.1994

(Ex.D15), final notice dated 19.7.1994 (Ex.D16), notice dated

20.02.1996 (Ex.D18/Ex.D57), notice dated 20.03.1996

(Ex.D19), notice dated 26/27.11.1993 (Ex.D25/Ex.D46), notice

dated 28/29.02.1996 (Ex.D26), notice dated 05/08.01.1996

(Ex.D27), notice dated 15.05.1992 (Ex.D29), notice dated

01.01.1993 (Ex.D34), notice dated 10.02.1993 (Ex.D35),

notice dated 09/10.09.1993 (Ex.D42), notice dated 31.08.1995

(Ex.D48), notice dated 13.10.1995 (Ex.D49), notice dated

20.11.1995 (Ex.D50), notice dated 27.11.1995 (Ex.D51),

notice dated 01.12.1995 (Ex.D52) and notice dated 05.01.1996

(Ex.D55) with regard to the alleged delay in the progress of the

work by the plaintiff.

29. The Trial Court has, while considering issue No.1

recorded a finding that the version of the plaintiff is supported

by relevant documents and defendant has failed to prove the

issue. Further, while considering the claim of the plaintiff, the

Trial Court has held that the plaintiff has stated in the plaint

that the land in Sy. No.151 for 24 units were handed over on

25.05.1995 and the Survey number site area for 6 units was

handed over on 15.12.1995. The Trial Court has further held

that the version of the plaintiff is supported by relevant

documents without specifically recording a finding as to which

of the documents demonstrates the same. Hence, the finding

of the Trial Court on issue No.1 is ex-facie untenable and liable

to be set aside.

30. The Trial Court while considering issue No.2 has

noticed that although the plaintiff was the successful tenderer

for construction of 909 tenements in seven places in Bengaluru,

due to difficulties in handing over the possession of the area to

the plaintiff for construction, negotiations were made for

construction of 770 houses in Jeevanahalli-Doddagunte in Sy.

Nos.150, 151, 152 and 158 which was accepted by the

plaintiff. The Trial Court has further, noticing Exs.P6 and P7

held that the defendant has asked the plaintiff to take up the

construction work immediately even without executing proper

agreement. Hence, the Trial Court has held issue No.2 in the

Negative.

31. The Trial Court while considering issue Nos.4 to 6

merely noticed that the plaintiff has filed an affidavit

containing 125 pages and marked Exs. P1 to P9. Further,

noticing that the defendant examined its Manager as DW.1 and

Assistant Executive Engineer DW.2 and marked Exs.D1 to D58,

without noticing any specific correspondence between the

parties, merely recorded a finding that the correspondence

clearly goes to show that the defendant is at fault. The said

finding recorded by the Trial Court is ex-facie untenable and

liable to be set-aside.

32. The Trial Court has noticed that the defendant

entrusted the work of construction of 462 units at Jeevanahalli

and the defendant gave sital area for construction of 376 units,

the site area for 348 units was handed over on 14.01.1992

and remaining units was handedover on 15.12.1995. Further,

the Trial Court noticing the testimony of DWs.1 and 2 held that

DW.1 has admitted that 75% of the area was given to the

plaintiff only on 15.12.1995 and that DW.2 admitted that in the

year January 1992 area given to the plaintiff was only for 348

units in Jeevanahalli. The said finding of the Trial Court is

contrary to Ex.P18 as has been noticed at para 26 herein

above.

33. The Trial Court while considering the claims made

by the plaintiff and while discussing regarding issue Nos.12 and

13 has, after noticing the 9 claims made for a total sum of

`81,46,758.20 has recorded the following findings:

"31. The plaintiff estimated the loss during the period between 1991 to 1996 to the extent of `94,67,578/-; but restricted the claim only for `14,00,000/-. While discussing above issues and particularly while discussing issue Nos.3 to 6, the Court has come to the conclusion; it is the defendant who has failed to supply materials like cement, steel and structural drawings to defendant in time. Further, the Court has also come to the conclusion that the defendant has not handed over the complete 75% of the site (area) to the plaintiff before December 1995 and as per the terms and conditions the plaintiff was liable to finish the work in June 1997; but in June 1996 itself the defendant without any valid reasons rescinded the contract of the plaintiff.

Further, the defendant officials stopped the work of construction temporarily. The defendant officials have also asked the plaintiff to change and alter the structures in the middle and all these facts caused delay in finishing the work by plaintiff. For that, the plaintiff is not responsible.

The defendant itself is responsible for the delay caused in finishing the work. The claim of the plaintiff is supported by various documents and bills submitted by the plaintiff. There is no reason to discard the claim of the plaintiff for a decree for `81,46,758.20 paise. Hence, the suit of the plaintiff is to be decreed."

34. With regard to the construction carried out by the

plaintiff it is relevant to note that the defendant from time to

time pointed out various deficiencies in the work carried out by

the plaintiff including the improper curing, unsatisfactory

progress of the work, not carrying out the work as per the

instructions given by the officials of the defendant, etc., as is

forthcoming from letters dated 28.08.1992 (Ex.P25),

10.03.1994 (Ex.D14), 28/29.02.1996 (Ex.D18), 14.09.1992

(Ex.D30),06.02.1993 (Ex.D36) and letter dated 13.10.95

(Ex.D49). Although the plaintiff has repeatedly sought for

various drawings and particulars to enable it to carry out the

construction, there is overwhelming evidence on record to

demonstrate that the plaintiff was not carrying out the work as

specified by the defendants. Having regard to the same, the

defendant had imposed a penalty of `100/- per day as is

forthcoming from the letter dated 10.02.1993 (Ex.D35), letter

dated 18.2.1993 (Ex.P35), letter dated 7/12.12.1995.

However, despite imposition of the penalty, the plaintiff has

continued to carry on the work, although in its correspondences

with the defendant, the plaintiff has protested the imposition of

the penalty.

35. It is relevant to note that the defendant has issued

various notices to the plaintiff by specifically stipulating that

there is delay in the progress of the work and notifying the

plaintiff to expedite the completion of the work, failing which

the penal clauses in the Agreement would be imposed and also

the contract terminated. This aspect has already been noticed

at para 24 hereinabove. Further, it is also pertinent to note that

some of the notices issued by the defendant to the plaintiff

were also returned as unserved.

36. It is also relevant to note that on the date when the

defendant called upon the plaintiff to be present for joint

measurement, the Plaintiff was not present. It is further

forthcoming that the defendant has specifically notified the

plaintiff that the work at the site has stopped and there were

no men of the plaintiff who was present at the site.

37. The Trial Court has not appreciated the material on

record with respect to the claims made by the plaintiff while

awarding the amounts sought for in the suit. Merely on a

cursory mention of some of the documents, the Trial Court has

decreed the suit of the plaintiff by granting the entire sum of

`81,46,758.20. The said judgment of the trial Court is ex-facie

erroneous and liable to be interfered with.

38. Learned counsel for the respondent/plaintiff

vehemently contended that PW.1 has not been cross examined

regarding the testimony adduced by the plaintiff claiming

damages. However, it is relevant to note that the plaintiff was

required to plead and prove the basis of its claim of damages.

The plaintiff is not entitled to succeed in the suit by merely

demonstrating that there was delay by the defendant in

handing over certain requirements for completion of the work

entrusted to the plaintiff by the defendant. The plaintiff is

specifically required to plead and prove its entitlement in

respect of each claim of damages made by it. In that regard, it

is relevant to note that apart from adducing the testimony of

PW.1 who was the partner of the plaintiff, no other witness, like

the Supervisor who was supervising the work at the site on

behalf of the plaintiff, etc., has been examined to testify

regarding the extent of manpower and material maintained at

the site. The plaintiff has also not produced any material on

record to demonstrate that it has made payments in respect of

the manpower it had allegedly maintained at the worksite of

the defendant. Although the plaintiff has filed a voluminous

affidavit by way of examination in chief giving details of various

calculations on the basis of which it has made its claim for

damages, the plaintiff has failed in producing the necessary

documentary material in support of the oral evidence adduced

by it to justify its claim for damages.

39. The plaintiff has made a claim towards bill Nos. 15

and 16. However the plaintiff has failed to demonstrate that it

has carried out the works, the cost of which was claimed vide

the said bill Nos.15 and 16.

40. The plaintiff has also made a claim for further

amount in respect of bill Nos.1 to 14. It is relevant to note

here that the Bill Nos.1 to 14 which were submitted to the

defendant in respect of the work carried on by the plaintiff have

been paid by the defendant. Although the plaintiff has sought

copies of the said bill Nos.1 to 14 as is forthcoming from letter

dated 1.03.1996 (Ex. P60) the plaintiff has failed to take any

steps in the suit requiring the defendant to produce the said

bills, so as to mark the same in evidence in order to prove its

entitlement for any further amounts that the defendant is liable

to pay under the said bills Nos.1 to 14. In the absence of the

plaintiff calling upon the defendant in the proceedings before

the trial Court to produce Bill Nos.1 to 14, the claim of the

plaintiff in respect of any further amounts claimed in the Bill

Nos.1 to 14 is not liable to be granted.

41. It is relevant to note here that the defendant has

examined its Manager as DW.1 and Assistant Executive

Engineer in its project office as DW.2. DW.1 has, in detail set

out as to how the plaintiff has, despite having been supplied

the requisite quantities of cement and steel, has not shown

requisite progress of work resulting in the defendant

terminating the contract vide contract agreement rescinding

order dated 5.6.1996 (Ex.P69) and 5/11.6.1996 (Ex.D6).

Further, it has been stated by DW.1 that, consequent to

rescinding the contract with the plaintiff, the defendant itself

has completed the 384 units departmentally. He has

specifically deposed that the defendant, in its Board Meeting

held on 13.8.1996 has, approved the revised cost of `75.60

laksh proposed for completion of the said 384 units

departmentally. It is further relevant to note that the

defendant produced the sketch of the project (Ex.D20) and

measurement books as Exs.D21, D22 and D23. Five books

containing vouchers, indents and invoices for supply of cement

and steel have been marked together as Ex.D24.

42. DW.2 who is the Assistant Executive Engineer has

also deposed regarding the stoppage of work on 15.2.1996 and

that the plaintiff not being present for joint measurements.

DW.2 has also stated in his affidavit by way of examination-in-

chief that the cost incurred by the defendant towards the

balance work was `75,50,000/-. The cost towards the material

supplied to the plaintiff has also been stated in the affidavit.

Although the plaintiff and the Trial Court have placed reliance

on the cross-examination of DW.1 to contend that 75% of the

sital area was not handed over, having regard to the plaintiff

itself admitting vide letter dated 5.6.1992 (Ex.P18) that it had

received more than 80% of the payment to put up construction

of 462 units, it is now not open to the plaintiff to contend that

requisite area has not been handed over.

43. It is relevant to note here that in the present case,

the plaintiff has not completed construction of the work

entrusted to it. In fact it has abandoned the project as is

forthcoming from letters dated 28/29.2.1996 (Ex.P53 and

Ex.D57) resulting in the defendant rescinding the contract vide

said letters. It is further clear and forthcoming that the

defendant has undertaken completion of the balance work by

itself having regard to the failure of the plaintiff to complete the

construction of the work entrusted to it. The Trial Court has

miserably failed in considering this aspect of the matter and

hence, the judgment of the Trial Court is contrary to the

material on record.

44. It is also relevant to note that the defendant has

produced the relevant measurement books as well as the

vouchers, indents and invoices vide Exs.P21 to P24 indicating

the extent of construction that has been carried out periodically

as well as the material supplied. The Trial Court has not

appreciated the said documents while considering the claim of

the plaintiff.

45. In view of the discussion above, the judgment of

the Trial Court decreeing the suit of the plaintiff for a sum of

`81,46,758.20 is unsustainable and not based on the material

available on record. The plaintiff has miserably failed in

proving that the defendant was liable to pay the amounts

claimed by the plaintiff. Hence, the question Nos.(i) to (iii)

framed for consideration are answered in the negative.

46. This Court by order dated 06.04.2009 granted

interim stay of the impugned judgment and decree subject to

the appellant depositing 50% of the decreetal amount before

this Court. Accordingly, the appellant has deposited a sum of

`40,73,379/- vide cheque bearing No.276786 dated

15.05.2009. Hence, the said amount is required to be

refunded to the appellant.

47. In view of the aforementioned, the following:

ORDER

i. The above appeal is allowed with costs;

ii. The judgment and decree dated 30.6.2008 passed

in OS No.11343/1996 by the XXVI Additional City

Civil and Sessions Judge, Mayo Hall Unit,

Bangalore, is set aside;

iii. OS No.11343/1996 on the file of XXVI Additional

City Civil and Sessions Judge, Mayo Hall Unit,

Bangalore, is dismissed with costs;

iv. The amount of `40,73,379 deposited by the

appellant before this Court pursuant to the order

dated 06.04.2009 shall be refunded to the

appellant.

v. Modified decree to be drawn accordingly.

Sd/ (S.G.PANDIT) JUDGE

Sd/-

(C.M. POONACHA) JUDGE

Bs/nd/pnv/sh/yan

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter