Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Director vs M/S. Vikram Hospital Pvt. Ltd
2023 Latest Caselaw 2802 Kant

Citation : 2023 Latest Caselaw 2802 Kant
Judgement Date : 2 June, 2023

Karnataka High Court
The Director vs M/S. Vikram Hospital Pvt. Ltd on 2 June, 2023
Bench: H.P.Sandesh
                                                -1-
                                                           MFA No. 5144 of 2017




                        IN THE HIGH COURT OF KARNATAKA AT BENGALURU

                             DATED THIS THE 2ND DAY OF JUNE, 2023

                                             BEFORE

                             THE HON'BLE MR JUSTICE H.P.SANDESH

                   MISCELLANEOUS FIRST APPEAL NO. 5144 OF 2017 (ESI)

                   BETWEEN:

                   1.    THE DIRECTOR
                         ESI CORPORATION,
                         SUB REGIONAL OFFICE,
                         1ST FLOOR, ESI DISPENSARY,
                         BADEMAKAN EXTENSION,
                         BANGALORE-MYSORE ROAD,
                         MYSORE-570 007.
                                                                   ...APPELLANT

                        (BY SRI. GEETHADEVI M.P., ADVOCATE [THROUGH VC])

                   AND:

                   1.    M/s. VIKRAM HOSPITAL PVT. LTD.,
                         PARAMAHAMSA ROAD,
Digitally signed
by SHARANYA T            YADAVAGIRI ROAD,
Location: HIGH           MYSORE-570 020,
COURT OF                 REPRESENTED BY ITS
KARNATAKA
                         DR. S.B.VIKRAM
                                                                 ...RESPONDENT

                           (RESPONDENT IS SERVED AND UNREPRESENTED)

                        THIS MFA IS FILED U/S 82(2) OF EMPLOYEES STATE
                   INSURANCE ACT 1948, AGAINST THE ORDER DATED
                   16.05.2017 PASSED IN ESI. APPLICATION NO.3/2015 ON THE
                   FILE OF THE JUDGE, EMPLOYEES STATE INSURANCE COURT,
                   MYSORE, PARTLY ALLOWING THE APPLICATION FILED UNDER
                   SECTION 75(1)(g)OF THE ESI ACT.
                                -2-
                                          MFA No. 5144 of 2017




     THIS APPEAL COMING ON FOR ADMISSION THIS DAY,
THE COURT DELIVERED THE FOLLOWING:

                          JUDGMENT

This matter is listed for admission. Heard the learned

counsel appearing for the appellant. Though the respondent is

served, he did not choose to engage the counsel or to appear

before the Court.

2. This appeal is filed under Section 82(2) of the

Employees State Insurance Act, 1948, against the order dated

16.05.2017 passed in ESI Application No.3/2015 on the file of

the Employees' State Insurance Court, Mysore, partly allowing

the application filed under Section 75(1)(g) of the ESI Act.

3. The factual matrix of the case of the ESI., is that

the respondent establishment is a Hospital. The respondent is

covered under the provisions of the ESI Act and it was allotted

a code number. By operation of Sections 39 and 40 of ESI Act

read with Regulation 31 of the ESI Regulation 1950, the

respondent was liable to pay ESI contribution. The ESI

contribution for the period covering from November 2012 to

April 2013, was paid by the respondent belatedly. Therefore,

there was a delay in contribution ranging from 253 days to 341

MFA No. 5144 of 2017

days, depending upon the due dates for monthly contribution in

terms of Regulation 31 of ESI Regulation 1950. Accordingly, a

notice dated 03.04.2014 was issued to the respondent under

Section 85(B) of the Act read with regulation 31-C of the ESI

(General) Regulation 1950. After giving opportunities to the

respondent to present its case with regard to the proposed

determination of damages under Section 85-B of the ESI Act.

After considering the respondent's reply an order was passed

by the statutory authority on 22.01.2015, determining and

claiming a damage of Rs.3,95,473/-. The respondent was liable

to pay the said amount as statutory damages, for the delay in

payment of contribution for the period herein before narrated.

It is contended that the respondent herein has approached the

ESI Court in ESI Application No.3/2015 challenging the said

order/Demand Notice dated 22.01.2015. The ESI Court by an

order dated 16.05.2017 has partly allowed the said application,

restricting the quantum of damages due, to 50% of

Rs.3,95,473/- only, by modifying the 85-B order dated

16.05.2017, wherein the claim was Rs.3,95,473/-. Being

aggrieved by the said order, the present appeal is filed before

this Court.

MFA No. 5144 of 2017

4. The main contention of the learned counsel

appearing for the appellant before this Court is that the

damage amount of Rs.3,95,473/- for the delay in payment of

contribution for the period i.e., November 2012 to April 2013.

The said calculation is made based on the regulation. The

respondent was duty bound to pay the contribution regularly, in

terms of Sections 39 and 40 of the ESI Act read with Regulation

31 of ESI (General) Regulation 1950. The liability on the

respondent for payment of contribution is by operation of law.

The respondent need not be issued with any Section 45-A order

for this purpose, in view of the fact that for the above said

period, the contribution due and paid belatedly was in respect

of regular monthly paid employees, covered under the

provisions of the ESI Act as "Insured Persons" as defined under

Section 2(9) of the ESI Act. The respondent on its own duty

bound to pay ESI contribution regularly, under Sections 39 and

40 of the ESI Act.

5. It is contended that when the amount was not paid

towards the contribution and merely because the payment of

contribution amount with interest that will not take away the

proviso to Sub Section (1) of Section 85-B of the ESI Act and

MFA No. 5144 of 2017

they are bound to pay the damages and determination of

damages by the statutory authority dated 22.01.2015 cannot

be faulted. The Trial Court has committed an error in ignoring

the very proviso of the ESI Act and the judgment of this Court

in the case of Workmen of BEL v. ESIC reported in ILR 1995

KAR 2539, is very clear that they are bound to pay the

damages. The very order passed by the Trial Court is

erroneous.

6. The learned counsel appearing for the appellant in

support of her arguments relied upon the judgment of the Apex

Court in the case of Horticulture Experiment Station

Gonikoppal, Coorg v. Regional Provident Fund

Organization reported in (2022) 4 SCC 516, wherein, the

Apex Court held that the failure to deposit contribution -

Imposition of damages for delayed payment - Breach of civil

obligations/liabilities committed by employer. The Apex Court

held that, is sufficient for imposition of penalty or damages -

There is no further requirement on authority concerned to

examine existence of element of actus reus/mens rea or to

examine issue of justification, for imposing damages. The

learned counsel also brought to the notice of this Court the

MFA No. 5144 of 2017

paragraph Nos.14 and 15 of the judgment, wherein, the Apex

Court has taken note of the earlier judgments. In paragraph

No.15, the Apex Court came to the conclusion that after

detailed discussion taking note of the exposition of law on the

subject, it is well-settled that means that mens rea or actus

reus is not an essential element for imposing penalty or

damages for breach of civil obligations and liabilities. Hence,

the learned counsel would vehemently contend that the

principle laid down in the judgment is applicable to the case on

hand.

7. The learned counsel also brought to the notice of

this Court that the reasoning given by the Trial Court, while

considering the issue involved between the parties in paragraph

No.18, the Trial Court came to the conclusion that admittedly

when the amount was due to the ESI Corporation, it is paid

along with its interest and the matter is to be considered

regarding the damages. The notice produced by the respondent

at Ex.R1 discloses that the Corporation has imposed the

damages at the rate of 25% in respect of the delayed payment

by counting the number of days delay. In this regard, there is

due of Rs.1,99,452/- to the Corporation disputing this aspect as

MFA No. 5144 of 2017

the contribution is paid along with interest, the damages are to

be assessed and also an observation is made that no doubt, the

ESI authority has calculated the damages as per Regulation

31(c) of the ESI Regulations. On considering the financial

stringency of the applicant/Company, the amount claimed by

the authority is exorbitant and it has to be reduced. On

considering the defense of the applicant, it discloses that there

is no mens rea on the part of the applicant in making the

delayed payment. Mens rea is one of the aspects to be

considered for levy of the damages. Hence, reduced the

amount.

8. The learned counsel appearing for the appellant

would vehemently contend that the Trial Court has committed

an error while discussing the mens rea in paragraph No.19 of

its judgment and the Apex Court in the judgment referred

supra categorically held that the breach of civil

obligations/liabilities committed by the employer, the same

itself is sufficient for imposition of penalty or damages. There is

no further requirement on authority concerned to examine

existence of element of actus reus/mens rea or to examine

issue of justification, for imposing damages. Having taken note

MFA No. 5144 of 2017

of the principles laid down in the judgment referred supra and

also the reasoning given by the Trial Court, wherein, the Trial

Court came to the conclusion that no mens rea. The question of

considering the mens rea does not arise in view of the

principles laid down in Horticulture Experiment Station

Gonikoppal, Coorg's case (supra), it is a breach of civil

obligations committed by the employer. The Apex Court also

held that it is sufficient for imposition of penalty or damages

and no further requirement on authority concerned to examine

with regard to existence of mens rea. When such being the

case, the very judgment relied upon by the learned counsel for

the appellant is aptly applicable to the case on record. The Trial

Court has proceeded in an erroneous approach that mens rea is

one of the aspect to be considered for levy of the damages. It

is not in dispute that the contribution was not made on time,

there was a delay and the interest and damages to be

calculated at the rate of 25% in respect of the delayed payment

while counting the number of days delay. When the Apex Court

says that, it can be recovered by means of penalty or damages

and the damages is also calculated based on Regulation 31(c)

of the ESI Regulations, the Trial Court has committed an error

MFA No. 5144 of 2017

in reducing the amount by applying mens rea and the same is

not permitted. Hence, the order passed by the Trial Court

requires to be set aside.

9. In view of the discussions made above, I pass the

following:

ORDER

(i) The appeal is allowed.

(ii) The impugned order dated 16.05.2017 passed in ESI Application No.3/2015 on the file of the Judge, Employees State Insurance Court, Mysore, is set aside.

(iii) The respondent is directed to pay the damages as claimed by the appellant.

Sd/-

JUDGE

CP

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter