Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Karnataka Housing Board Cauvery ... vs The State Bank Of Hyderabad
2023 Latest Caselaw 10623 Kant

Citation : 2023 Latest Caselaw 10623 Kant
Judgement Date : 15 December, 2023

Karnataka High Court

The Karnataka Housing Board Cauvery ... vs The State Bank Of Hyderabad on 15 December, 2023

                           -1-
                                         RFA No.1238/2008
                                     C/w RFA No.1251/2008
                                         RFA No.1252/2008
                                       RFA Crob.No.5/2012

IN THE HIGH COURT OF KARNATAKA AT BENGALURU

    DATED THIS THE 15TH DAY OF DECEMBER 2023
                       PRESENT
       THE HON'BLE MRS JUSTICE K.S.MUDAGAL
                          AND
         THE HON'BLE MR JUSTICE C M JOSHI
    REGULAR FIRST APPEAL No.1238/2008 (MON)
                      C/w
       REGULAR FIRST APPEAL No.1251/2008
       REGULAR FIRST APPEAL No.1252/2008
      REGULAR FIRST APPEAL Crob.No.5/2012

RFA No.1238/2008:

BETWEEN:

1 . THE KARNATAKA HOUSING BOARD
    CAUVERY BHAVAN
    BANGALORE - 560 009
    BY ITS CHAIRMAN

2 . THE HOUSING COMMISSIONER
    THE KARNATAKA HOUSING BOARD
    CAUVERY BHAVAN, BANGALORE-560 009.

3 . THE EXECUTIVE ENGINEER
    THE KARNATAKA HOUSING BOARD
    BELGAUM DIVISION, BELGAUM-01

4 . THE EXECUTIVE ENGINEER
    KARNATAKA HOUSING BOARD
    HUBLI DIVISION, CHANAKYAPURI
    HUBLI-02, DHARWAD DISTRICT

   ALL ARE REPTD. BY ITS SECRETARY          ...APPELLANTS

(BY SRI RAGHAVENDRA A KULKARNI, ADVOCATE)

AND:

NAV VIKAS BUILDERS (P) LTD.,
2ND FLOOR, C BLOCK, AKSHAYA COMMERCIAL
COMPLEX, NO 26, VICTORIA ROAD
                              -2-
                                           RFA No.1238/2008
                                       C/w RFA No.1251/2008
                                           RFA No.1252/2008
                                         RFA Crob.No.5/2012

BANGALORE - 560 047
BY ITS MANAGING DIRECTOR                    ...RESPONDENT

(BY SRI.VIKAS MAHENDRA, ADVOCATE)
     THIS REGULAR FIRST APPEAL IS FILED UNDER SECTION 96
R/W ORDER XLI RULE 1 OF THE CPC AGAINST JUDGEMENT AND
DECREE DT.16.06.2008 PASSED IN OS NO.11145/1997 ON THE
FILE OF THE XXVII ADDL. CITY CIVIL JUDGE, BANGALORE,
DECREEING THE SUIT FOR RECOVERY OF MONEY.

RFA No.1251/2008,
RFA No.1252/2008

BETWEEN:

1 . THE KARNATAKA HOUSING BOARD
    CAUVERY BHAVAN
    BANGALORE - 560 009
    BY ITS HOUSING COMMISSIONER

2 . THE HOUSING COMMISSIONER
    THE KARNATAKA HOUSING BOARD
    CAUVERY BHAVAN, BANGALORE-560 009

3 . THE CHIEF ENGINEER
    THE KARNATAKA HOUSING BOARD
    CAUVERY BHAVAN, BANGALORE-560 009

4 . THE EXECUTIVE ENGINEER
    THE KARNATAKA HOUSING BOARD
    HUBLI DIVISION, CHANAKYAPURI,
    HUBLI, DHARWAD DISTRICT-02
     ALL ARE REPTD. BY ITS SECRETARY
     KHB, BANGALORE - 560 009                   ...APPELLANTS
                                                  (COMMON)

(BY SRI.RAGHAVENDRA A KULKARNI, ADVOCATE)

AND:

1.     THE STATE BANK OF HYDERABAD
       AUSTIN TOWN BRANCH, NO.18
       VICTORIA ROAD, BANGALORE - 47
       BY ITS BRANCH MANAGER
2.     NAV VIKAS BUILDERS (P) LTD.,
       2ND FLOOR, C BLOCK, AKSHAYA COMMERCIAL
                              -3-
                                           RFA No.1238/2008
                                       C/w RFA No.1251/2008
                                           RFA No.1252/2008
                                         RFA Crob.No.5/2012

       COMPLEX, NO 26, VICTORIA ROAD
       BANGALORE - 560 047
       BY ITS MANAGING DIRECTOR              ...RESPONDENTS
                                                (COMMON)
(BY SRI BRIJESH CHANDER GUREE, ADVOCATE FOR R1;
    SRI VIKAS MAHENDRA, ADVOCATE FOR R2)

     RFA NO.1251/2008 AND RFA NO.1252/2008 ARE FILED
UNDER SECTION 96 R/W ORDER XLI RULE 1 OF CPC PRAYING TO
SET ASIDE THE JUDGEMENT AND DECREE DATED 16.06.2008
PASSED BY THE XXVII ADDL. CITY CIVIL JUDGE, BANGALORE, IN
O.S.No.7462/1995  AND    O.S.No.8665/1995    RESPECTIVELY
DECREEING THE SUIT FOR RECOVERY OF MONEY.

RFA CROB.No.5/2012:
BETWEEN:

NAV VIKAS BUILDERS (P) LTD.,
2ND FLOOR, C BLOCK, AKSHAYA COMMERCIAL
COMPLEX, NO 26, VICTORIA ROAD
BANGALORE - 560 047
BY ITS MANAGING DIRECTOR                 ...CROSS OBJECTOR

(BY SRI VIKAS MAHENDRA, ADVOCATE)
AND:

1. THE KARNATAKA HOUSING BOARD
   CAUVERY BHAVAN
   BANGALORE - 560009
   REPTD. BY ITS HOUSING COMMISSIONER

2. THE HOUSING COMMISSIONER
   THE KARNATAKA HOUSING BOARD
   CAUVERY BHAVAN, BANGALORE-560009

3. THE EXECUTIVE ENGINEER
   THE KARNATAKA HOUSING BOARD
   BELGAUM DIVISION, BELGAUM-01
4. THE EXECUTIVE ENGINEER
   KARNATAKA HOUSING BOARD
   HUBLI DIVISION, CHANAKYAPURI,
   HUBLI-2, DHARWAD DISTRICT                ...RESPONDENTS

(BY SRI.RAGHAVENDRA A KULKARNI, ADVOCATE)
                                      -4-
                                                        RFA No.1238/2008
                                                    C/w RFA No.1251/2008
                                                        RFA No.1252/2008
                                                      RFA Crob.No.5/2012

      THIS RFA.CROSS OBJECTION IS FILED UNDER ORDER XLI,
RULE-22 READ WITH SECTION 96 AND SECTION 151 OF CPC
PRAYING TO SET ASIDE THE JUDGMENT AND DECREE DATED
16.06.2008 PASSED BY THE XXVII ADDITONAL CITY CIVIL JUDGE,
BANGALORE IN O.S.11145/1997 DECREEING THE SUIT FOR
RECOVERY OF MONEY.

      THESE REGULAR FIRST APPEALS AND R.F.A.CROSS
OBJECTION HAVING BEEN HEARD AND RESERVED ON 26.09.2023,
COMING ON FOR PRONOUNCEMENT OF JUDGMENT THIS DAY,
K.S.MUDAGAL J., DELIVERED THE FOLLOWING:


                              JUDGMENT

These appeals and cross objection arise out of common

judgment in O.S.No.7462/1995, O.S.No.8665/1995 and

O.S.No.11145/1997 passed by the XXVII Additional City Civil

Judge, Bengaluru.

2. By the impugned judgment and decree, the trial

Court dismissed O.S.No.7462/1995 and O.S.No.8665/1995

and partly decreed O.S.No.11145/1997. The particulars of

the appeals, cross objection, suit and the ranks of the parties

who preferred the appeals and cross objection are as follows:

Sl. Appeal/Cross Suit in O.S. Ranks of parties No. objection No. before the trial Court 1 RFA No.1238/2008 11145/1997 Defendants (KHB) 2 RFA Crob.No.5/2012 11145/1997 Plaintiffs (Contractor) 3 RFA No.1251/2008 7462/1995 Plaintiffs (KHB) 4 RFA No.1252/2008 8665/1995 Plaintiffs (KHB)

3. State Bank of Hyderabad was not made party in

O.S.No.11145/1997. The rest of the parties were common in

all three suits. Except, State Bank of Hyderabad, the other

parties in the said suits are referred to according to their

ranks in O.S.No.11145/1997 since it has larger scope and

State Bank of Hyderabad will be referred to by its name.

4. The brief facts of the case are as follows:

Defendant No.1 Karnataka Housing Board ('KHB' for

short) is a statutory body constituted under the Karnataka

Housing Board Act, 1962. Defendant Nos.2 to 4 are the

Officers of defendant No.1 in various cadres. To

commemorate centenary birth anniversary of

Dr.B.R.Ambedkar, the Government of Karnataka floated a

scheme named as 'Ashraya Scheme' to provide houses and

sites to the people belonging to the weaker sections of the

society. In that regard, the Government of Karnataka issued

the Government orders bearing G.O.No.HUD 407 KHB 91

dated 24.06.1991 and G.O.No.HUD 535 KHB 91 dated

04.11.1991 proposing to build 1,75,000 houses in rural

areas, 30,000 houses in Bangalore urban areas and 30,000

houses in other urban areas. The Government entrusted the

matter to defendant No.1 KHB. The cost of the house in rural

areas was fixed at Rs.15,000/- and in urban areas fixed at

Rs.16,000/-.

5. In that regard, defendant No.1 KHB floated the

tenders by advertising in Deccan Herald, English daily

newspaper on 14.11.1991 from the contractors for execution

of the project in respect of seven assembly constituencies in

Dharwad District namely, Byadagi, Ranebennur, Hirekerur,

Hangal, Shiggaon, Shirahatti and Haveri. Similarly, the

tenders were called for nine assembly constituencies in

Belgaum District namely Ramdurga, Parasgad, Bailhongala,

Kittur, Khanapur, Belgaum Corporation, Uchgaon, Bagewadi

and Gokak.

6. On 27.11.1991, the plaintiff/building contractor

submitted its tender to the Chief Engineer, K.H.B. The

defendants issued letter of intent (Ex.P5 regarding Dharwad)

dated 23.01.1992 accepting the tender of the

plaintiff/contractor to execute the work.

7. Subsequently, defendant No.1/KHB and the

plaintiff entered into two separate contracts for construction

of 8079 houses in the aforesaid seven constituencies of

Dharwad District and for construction of 10251 houses in

nine constituencies referred to above in Belgaum District. The

contracts in respect of nine assembly constituencies in

Belgaum District and seven assembly constituencies in

Dharwad District were executed on 23.03.1992. The work

orders in respect of both the assembly constituencies were

issued.

8. As per the contract, the work was to be

completed within six months from the date of handing over

of the sites to the plaintiff excluding three months of

monsoon session. As per the contract, 5% of the project

costs was to be paid by way of mobilization of amount and

that was paid to the plaintiff on 28.01.1992. Regarding that

the plaintiff had to provide Bank guarantees. The bank

guarantees were issued by State Bank of Hyderabad, Austin

Town Branch, Bangalore. The said bank is defendant No.1 in

O.S.No.7462/1995 and O.S.No.8665/1995.

9. The work orders were issued on 30.03.1992. On

14.05.1992 the plaintiff/contractor requested defendant

No.1/KHB to release mobilization amount. On furnishing

bank guarantees defendant No.1 released Rs.34,84,500/- out

of mobilization amount of Rs.61,29,750/-. Therefore, State

Bank of Hyderabad, Austin Town Branch, Bangalore was

made as party in O.S.No.7462/1995 and O.S.No.8665/1995.

10. On 20.10.1992, defendant No.1/KHB issued letter

through defendant No.4/Executive Engineer of Hubli Division

(Ex.P79) and on 11.08.1992 defendant No.3/Executive

Engineer of Belgaum terminated the contract on the ground

that the plaintiff committed breach of terms of the agreement

and he failed to complete the work as per the agreement.

The bank guarantees were invoked under letter dated

09.11.1992 (Ex.P13 in O.S.No.7462/1995). On 14.03.1995

the Bank repealed the Bank guarantee on the ground that

the invocation was not in terms of Bank guarantee.

11. Plaintiff/contractor filed O.S.No.11145/1997

against the defendants seeking recovery of Rs.5,36,38,077/-

with interest at 18% p.a. contending that the

defendants/KHB without performing their part of contract

illegally terminated the contract.

12. The plaintiff/contractor contended that it had

invested huge manpower and other infrastructure at a larger

cost. But the defendants/KHB did not hand over the sites for

commencement of the construction. The plaintiff further

contended that the contracts were terminated even without

the expiry of stipulated time, thereby it had suffered financial

losses. The plaintiff further contended that by such illegal

cancellation of the contract, its reputation is also affected.

Therefore plaintiff claimed damages on different heads to the

tune of Rs.5,36,38,077/- as aforesaid.

13. The defendants contended that despite handing

over the sites, the plaintiff did not commence the work and

wherever it was commenced, the plaintiff had showed

marginal progress in the work, therefore the defendants were

forced to terminate the contract. According to the

defendants, the termination of the contract was in

accordance with law, therefore they sought dismissal of

O.S.No.11145/1997.

14. The defendants/KHB filed O.S.No.7462/1995

seeking recovery of Rs.53,66,130/- and O.S.No.8665/1995

seeking recovery of Rs.40,73,685/- from the

plaintiff/contractor and State Bank of Hyderabad who had

issued the bank guarantees. Thereafter the

plaintiff/contractor filed O.S.No.11145/1997 against the

defendants claiming damages as aforesaid in respect of

Dharwad and Belgaum Constituencies. The defendants/KHB

in those suits claimed that the contractor did not execute the

work as per the time schedule despite the authorities

releasing the mobilization of funds to the tune of

- 10 -

Rs.61,29,750/- despite handing over the sites, therefore the

authorities were forced to terminate that contract. The

defendants in those suits further contended that the

contractor is liable to refund the mobilization amount. It was

contended that the bank without valid reason illegally

declined to invoke the bank guarantees and pay the funds,

therefore the Bank is also liable to pay the said funds.

15. On the basis of the pleadings of the parties, in all

the three suits, the following issues were framed.

1. Whether the 1st plaintiff-Board has performed its part of the contract referred to in the plaint?

2. Whether the plaintiffs prove the breach of the terms of the contract by the 2nd defendant as pleaded?

3. Whether the termination of the contract referred to in the plaint by the 1st plaintiff-Board is valid?

4. Whether the 1st plaintiff-Board is entitled to force the bank guarantees of the 2nd defendant given by the 1st defendant?

5. Whether the suit is barred by law of limitation?

6. Whether the suit is not maintainable?

7. Whether the plaintiffs are estopped in law from the above delay and default on the part of the 2nd defendant as contended by the 2nd defendant?

8. Whether the 1st plaintiff-Board is entitled to recover the interest as claimed?

- 11 -

9. Whether the plaintiffs are entitled to recover the suit claim from the defendants?

1. Do the plaintiffs prove that the 2nd defendant has committed breach of contract dated 23.03.1992 and as such they incurred loss of Rs.26,45,250/- as averred?

2. Do the plaintiffs further prove valid invocation of bank guarantee as per the terms stipulated?

3. Does the 1st defendant proves that it has utilized the mobilization advance paid by the plaintiffs?

4. Are the plaintiffs entitled to the interest as claimed?

5. Are the plaintiffs entitled to the suit claim?

6. If so, against which of the defendants?

7. What relief?

1. Whether the plaintiff proves that defendants have handed over only 1155 sites in Dharwad District and thus committed breach of contract?

2. Whether the plaintiff proves that the 3rd defendant has handed over only 206 sites in Belgaum District as against 10251 sites and thus committed breach of contract?

3. Whether the plaintiff proves that the defendants have committed breach by not handing over the sites by arbitrarily terminating the contract prematurely?

4. Whether the suit is bad for want of notice under Section 72 of the KHB Act, 1962?

5. Whether the suit is barred in view of Arbitration Clause 26 of the Contract?

- 12 -

6. Whether the suit is bad for mis-joinder of parties and cause of action?

7. Whether the plaintiff proves that it has suffered damages of Rs.5,36,380-77 in respect of Belgaum and Dharwad Districts?

8. Whether the defendants prove that they have handed over all the 10,251 sites in Belgaum District as pleaded?

9. Whether the defendants prove that they have handed over 8079 sites in Dharwad District as pleaded?

10. Whether the defendants prove that this Court has no jurisdiction to entertain and try this suit?

11. Whether the plaintiff is entitled to the reliefs sought for?

12. What decree or order?

16. In O.S.No.7462/1995, the official of the

authorities was examined as PW.1 and Ex.P1 to P15 were

marked. In O.S.No.8665/1995 the very same witness was

examined as PW.1 and Ex.P1 to P15 were marked. After

recording of the evidence of the plaintiff in

O.S.No.7462/1995 and O.S.No.8665/1995, it appears that

those suits were consolidated with O.S.No.11145/1997. In

that suit, on behalf of the plaintiff therein, PWs.1 to 4 were

examined and Exs.P1 to P126 were marked. On behalf of the

defendants therein, DWs.1 to 3 were examined and Exs.D1

to D8 were marked.

- 13 -

17. By the impugned common judgment and order,

the trial Court dismissed O.S.No.7462/1995 and

O.S.No.8665/1995 and decreed O.S.No.11145/1997 holding

that the defendants themselves were guilty of breach of

terms of contract and the termination of the contract was

illegal. The trial Court decreed O.S.No.11145/1997 for

recovery of Rs.4,61,38,077/- with interest at 18% per annum

on Rs.33,14,383/- and at 6% per annum on

Rs.4,17,56,250/-. Plaintiff filed O.S.No.11145/1997 as

indigent person with the permission of the Court, therefore

the Court fee was ordered to be recovered as the first charge

on the decreetal amount.

Submissions of Sri Vikas Mahendra, learned counsel for the plaintiff/Cross Objector:

18. The defendants' own document and the

admissions of their own witnesses show that there was clear

breach of terms of the contract by the defendants. The

evidence adduced by the plaintiff clearly shows that it

suffered damages due to such illegal termination of the

contracts. Therefore, the finding of the trial Court that the

defendants are liable to pay damages to the plaintiff is sound

and reasonable. However, the trial Court committed error in

- 14 -

rejecting the claim of Rs.75,00,000/- on the head of general

damages and awarding interest only at 6% p.a. on

Rs.4,17,56,250/- since the transaction was commercial

transaction, the trial Court should have awarded interest at

18% p.a. on the same also. The contention of the

defendants that the trial Court had no territorial jurisdiction is

wholly unsustainable. As the defendants themselves filed

two other suits regarding the same cause of action before the

very same Court, all other contentions of the defendants in

the appeal and cross objection are unsustainable. The

appeals of the defendants are liable to be dismissed and the

cross objection shall be allowed.

19. In support of his contentions, he relies on the

following judgments:

1. Pathumma v. Kuntalan Kutty1

2. Kiran Singh v. Chaman Paswan2

3. The Associated Cement Company Ltd. v. State of Karnataka3

4. RSDV Finance Co. Pvt. Ltd. v. Shree Vallabh Glass Works Ltd.4

5. K.P.Kanga Rao v. K.V.Venkatesham5

(1981) 3 SCC 589

AIR 1954 SC 340

RFA No.151/2003 D.D.30.11.2009

(1993) 2 SCC 130

(2015) 13 SCC 514

- 15 -

6. Bhagwandas Goverdhanas Kedia v. Girdharilal Parshottamadas and Co.6

7. A.B.C.Laminart Pvt. Ltd. v. A.P.Agencies, Salem7

8. M/s Malaprabha Co-Operative Spring Mills Ltd., Belgaum Dist. V. M/s Buildment Pvt. Ltd.8

9. A.T.Brij Paul Singh v. State of Gujarat9

10. Mohd. Salamatullah v. Govt. of Andhra

Pradesh

11. Dwarkadas v. State of Madhya Pradesh11

12. ITC Zeneca Ltd v. Shri Balaji Agro Traders12

13. The Managing Director, J and K Handicrafts v.

M/s Good Luck Carpets13

14. Karnataka State Financial Corporation v. Sri Nithyananda Bhavan14

15. Syndicate Bank v. West Bengal Cements Limited15

16. The Managing Director Bhoruka Textiles Limited v. M/s Kashmiri Rice Industries16

17. Maharashtra state Electricity Distribution Co.

Ltd. v. Datar Switchgear17

18. Hindustan Construction Co. Ltd. v. State of Bihar18

19. Madhya Pradesh Power Generation Company Limited v. Ansaldo Energia Spa19

20. BT Patil and sons v. The Chief Engineer20

AIR (1966) SC 543

AIR 1989 SC 1239

ILR 2013 KAR 94

AIR 1984 SC 1703

AIR 1977 SC 1481

AIR 1999 SC 1031

RFA No.917/2002 DD 13.10.2009

AIR 1990 SC 864

AIR 1982 Kant 179

AIR 1989 Del 107

RFA No.982/2007 DD 29.01.2008

(2018) 3 SCC 133

(1999) 8 SCC 436

(2018) 16 SCC 661

WA No.672/2007 DD 04.07.2011

- 16 -

21. P.Dasaratharama Reddy Complex v. Government of Karnataka21

22. Hind Construction Contractors v. State of Maharashtra22

23. Mahabir Auto Stores v. Indian Oil Corporation23

24. Gopal Krishnaji Ketkar v. Mahomed Haji Latif24

Submissions of Sri Raghavendra Kulkarni, learned Counsel for the defendants/appellants:

20. The Government of Karnataka had entrusted the

construction work to defendant No.1 and therefore the suit

without impleading the Government is bad for non-joinder of

necessary parties. The work in question had to be executed

in Belgaum District and Dharwad District. Therefore, the

Court at Bangalore had no territorial jurisdiction to adjudicate

the suit in O.S.No.11145/1997. The plaintiff failed to execute

the work within the time stipulated, thereby there was

breach of contract. Hence, the defendants/authorities were

justified in terminating the contract. There was arbitration

clause in the agreement. In the light of the said agreement,

the suit was barred by said arbitration clause. The trial Court

was not justified in awarding damages of Rs.4,61,38,077/-

on the basis of Exs.P106 to P110 which are un-audited

AIR 2014 SC 168

AIR 1979 SC 720

AIR 1990 SC 1031

AIR 1968 SC 1413

- 17 -

accounts. The trial Court should have noticed that the suit for

damages without seeking declaration regarding termination

of the contracts were not maintainable. The findings of the

trial Court that the sites were not handed over to the plaintiff

was contrary to the evidence on record. Dismissal of the suit

of the authorities for recovery of mobilization of funds was

illegal. The bank have not encashed the bank guarantees

illegally and declined to encash the same. Therefore the trial

Court should have passed the decree against them for

recovery of bank guarantees. The trial Court decreed the suit

of the contractor and dismissed the suit of the defendants on

erroneous appreciation of the evidence on record. Therefore

the appeals of the authorities deserve to be allowed and the

cross objection of the contractor is liable to be dismissed.

21. In support of his contentions, he relies on the

following judgments:

1. Athmanathaswami Devasthanam v.

K.Gopalaswami25

2. Angile Insulations v. Davy Ashmore India Ltd.26

3. M/s.Malaprabha Co-operative Spinning Mills Ltd. v. M/s Buildmet Pvt. Ltd.27

4. A.V.M. Sales Corporation v. Anuradha Chemicals Private Limited28

AIR 1965 SC 338

(1995) 4 SCC 153

2012 (3) KCCR 2304 (DB)

(2012) 2 SCC 315

- 18 -

5. ONGC Ltd. v. M/s. Modern Construction and Co.29

6. National Thermal Power Corporation Ltd. v.

Flowmore Pvt. Ltd.30

7. Hindustan Steel Workers Construction Ltd. vs. G.S.Atwal & Co. (Engineers) Pvt. Ltd.31

8. State of Maharashtra v. M/s.National Construction Company32

9. Daewoo Motors India Ltd. v. Union of India.33

10. Laliteshwar Prasad Singh v. S.P.Srivastava34

11. M/s. MSK Projects (I) (JV) Ltd. v. State of Rajasthan35

12. Ravinder Kumar Sharma v. State of Assam.36

Submissions of Sri Brijesh Chander Guree, learned Counsel for the Bank:

22. The invocation of the bank guarantees were not

in accordance with terms of the bank guarantees. Therefore,

the Bank was not liable to encash the bank guarantees in

favour of KHB. Nothing was elicited to show that the bank

had arbitrarily rejected the claim for invocation of the bank

guarantees. Therefore the suits were rightly dismissed by the

trial Court. The said judgments as against the Bank do not

warrant any interference.

AIR 2014 SC 83

(1995) 4 SCC 515

AIR 1996 SC 131

AIR 1996 SC 2367

(2003) 4 SCC 690

(2017) 2 SCC 415

AIR 2011 SC 2979

AIR 1999 SC 3571

- 19 -

23. On consideration of the submissions of both side

and on examination of the records, the points that arise for

consideration are:

(i) Whether the finding of the trial Court that the defendants in O.S.No.11145/1997 are guilty of breach of the terms of the contract is sustainable?

(ii) Whether the finding of the trial Court that the time was not the essence of the contract is sustainable?

(iii) Whether the trial Court was justified in holding that it had the jurisdiction to try O.S.No.11145/1997?

(iv) Whether the impugned common judgment and decree in O.S.No.7462/1995, O.S.No.8665/1995 and O.S.No.11145/1997 is sustainable?

Analysis

Reg. Point No.1 Breach of contract:

24. In all these three suits, common questions of law

and facts are involved. The admitted facts of the case are as

follows:

That defendant No.1/KHB floated a scheme called

'Ashraya Scheme' to provide houses and sites to the people

belonging to the weaker section of the society, by issuing the

Government Orders No.HUD 407 KHB 91 dated 24.06.1991

- 20 -

and No.HUD 535 KHB 91 dated 04.11.1991 proposing to

build 1,75,000 houses in rural areas, 30,000 houses in

Bangalore urban areas and 30,000 houses in other urban

areas. On 14.11.1991, the Government entrusted the project

to defendant No.1/KHB. Cost of the houses in rural areas and

in urban areas was fixed at Rs.15,000/- and Rs.16,000/-

each respectively. Accordingly, defendant No.1 on

14.11.1991 invited the tenders from the contractors. The

tenders of the plaintiff were accepted and agreements were

entered into between the defendants and the plaintiffs for

construction of 8079 houses in 7 assembly constituencies

namely Byadagi, Ranibennur, Hirekerur, Hanagal, Shiggaon,

Shirahatti and Haveri in Dharwad district and 10,251 houses

in 9 assembly constituencies namely Ramdurga, Parasgad,

Bailhongala, Kittur, Khanapur, Belgaum Corporation,

Uchgaon, Bagewadi and Gokak in Belgaum district. The letter

of intent and work orders were issued for release of the

mobilization fund. The defendants took the bank guarantees

from the plaintiff issued by State Bank of Hyderabad. The

documents were separately marked in three suits, therefore

there is duplication of exhibits and witnesses. The trial Court

at least after consolidation of the suits should have

- 21 -

consolidated the exhibits' numbers and the witnesses'

numbers for easy reference. Since O.S.No.11145/1997 is the

comprehensive suit and related to both Belgaum and

Dharwad constituencies, the documents in that case can be

referred for the purpose of these appeals.

25. The description of the documents/exhibits and

the particulars are set out in the table below:

Ex. Description Related constituencies No. P15 Separate Agreements Byadagi, Ranebennur, to P21 for each Hirekerur, Hanagal, constituencies in Shiggaon, Shirahatti and Dharwad District Haveri P22 General conditions of contract P6 to Separate agreement Ramadurg, Parasgad, P14 for each Bailahongal, Kittur, constituencies in Khanapura, Belgaum Belgaum District. Corporation, Uchgoan, Bagevadi and Gokak

26. On the request of the plaintiff, the defendants

released a sum of Rs.34,84,500/- as mobilization fund for the

work in Byadagi, Ranebennur, Hirekerur and Hanagal

constituencies and Rs.26,45,250/- with regard to Shirahatti,

Haveri and Shiggaon constituencies respectively. Regarding

Belgaum District constituency, no mobilization fund was

released. Thus the total mobilization fund released to the

plaintiff was Rs.61,29,750/-. The defendants terminated the

- 22 -

contracts regarding Dharwad District by letters dated

20.10.1992 and 22.12.1992 and Belgaum District by letter

dated 11.08.1992 on the ground that the plaintiff failed to

construct the houses as per the time schedule. Whereas the

plaintiff contends that the defendants themselves failed to

handover the sites as per the agreement, therefore they

were guilty of breach of contract and liable to pay the

damages.

27. The defendants' Counsel contended that the work

should have been completed within six months from the date

of agreement. Whereas the plaintiff contends that the work

had to be completed within six months from the date of the

delivery of the possession of the sites and in those six

months, three months' monsoon period has to be excluded.

Therefore this Court has to find out what was the time

schedule agreed.

28. As rightly pointed by the trial Court, all the

agreements were similar and contain the same clauses.

Clause 2(b) in all the agreements so far it relates to the time

schedule reads as follows:

"Program of work

(b) The Time allowed for carrying out the work as entered in the tender shall be strictly observed by the

- 23 -

contractor, it shall be reckoned from the day of handing over to the contractor, the work site area either full or in parts."

29. In Clause 6 of the agreement, the clause

regarding period of construction is as follows:

"6. Period of construction- six months excluding monsoon......................."

30. As per condition No.11, it was agreed that the

time allowed for the work from the date of the work order to

the contractor is six months period excluding the rainy

season from 15th June to 15th September. The defendants'

witnesses have unequivocally admitted that the time

stipulated starts to run after handing over the possession of

the sites. J.K.Sridharamurthy, the Manager of KHB who is

examined as PW.1 in the defendants' suit unequivocally

admitted that the time stipulated for construction of the

houses was nine months including the monsoon period and

that nine months had to be reckoned from the date of

delivery of the possession of the sites. The conditions of

agreement further show that the concerned Executive

Engineer had to conduct monthly review of the progress of

work and Chief Engineer had to conduct bimonthly review of

the progress of the work. The agreement further provides for

- 24 -

extension of time by the defendants to the plaintiff for

completion of the work in case the work is not completed on

time, on being satisfied about the reason for extension.

31. Therefore the question is whether the defendants

handed over the possession of the sites soon after the

agreements and the date of termination was after six months

of such delivery of possession of the sites to the plaintiff. The

defendants terminated the contracts relating to the

constituencies of Dharwad and invoked the bank guarantees

on the ground that the work was not completed within the

scheduled time. To show that the sites were not handed over

within the scheduled time, the plaintiff relied on Exs.P1 and

P2 the charts prepared by it about delivery of possession of

the sites. Ex.P1 is the chart relating to the constituencies in

Belgaum District and Ex.P2 relates to the constituencies in

Dharwad District. For the purpose of easy grasp, the

relevant particulars in Exs.P1 and P2 are extracted as below:

Description                                                Constituency

                 Bagewadi     Bailhongala   Kittur    Ramadur   Parasgad    Khanapur    Belgaum   Uchgaon   Gokak
                                                      ga                                Corpn.
Total No. of     1097         1147          1097      1147      1147        1147        1150      1097      1222
sites
supposed    to
be     handed
over by KHB
at
Commenceme
nt of contract
                                                                        - 25 -





Total No. of      101                80                25            Nil             Nil         Nil          Nil            Nil           Nil
sites handed
over till date
of cancellation
of contract
Dates        of   20 sites on        20 sites on       25                Not         Not         Not          Not            Not           Not
handover     of   15.7.92            20.7.92           sites on       applicable     applicabl   applicabl    applicabl      applicabl     applic
sites             15 sites on        60 sites on       15.7.92                       e           e            e              e             able
                  20. 7.92           22.7.92
                  66 sites on
                  11.8.92
Completion        20    houses       20 houses         25            Not             Not         Not          Not            Not           Not
date as per       on 15.3.93         on 15.3.93        houses        applicable      applicabl   applicabl    applicabl      applicabl     applic
contract          15    houses                         on                            e           e            e              e             able
                  on 15.3.93         60 houses         15.3.93
                  66    houses       on 15.3.93
                  on 15.3.93
Date         of   11/8/92            11/8/92           11/8/9        11/8/92         11/8/92     11/8/92      11/8/92        11/8/92       11/8/9

contract
Balance time      20 houses -        20 houses         25            Not             Not         Not          Not            Not           Not
for completion    7 months           - 7 months        houses        applicable      applicabl   applicabl    applicabl      applicabl     applic
still available                                        -7                            e           e            e              e             able
on date of        15 houses -
                                     60 houses         months
cancellation of   7 months
                                     - 7 months
contract
                  66 houses -
                  7 months
No. of joint
progress                                  Nil               Nil            Nil             Nil         Nil          Nil            Nil          Nil
review                  Nil
meetings held
by Executive
Engineer     as
required    by
clause 2 (c) of
agreement
No.          of
progress                Nil               Nil               Nil            Nil             Nil         Nil          Nil            Nil          Nil
reviews     by
Chief Engineer
in terms of
Clause 2 (c)
of agreement




 Description                                                                     Constituency

                         Haveri           Shirhatti               Shiggaon         Byadagi       Ranebennu      Hirekarur            Hangal

                                                                                                 r

 Total No. of sites
 supposed to     be           1147              1147                 1197             1147             1197           1097               1147
 handed over by
 KHB             at
                                                            - 26 -





Commencement of
contract
Total No. of sites
handed over till            249            684            182            32            Nil          Nil         Nil
date of cancellation
of contract
Dates of handover       50 sites on    283    sites   28 sites on    32    sites   Not          Not          8 sites on
of sites                24.4.92        on             20.7.92        on            applicable   applicable   13.10.92
                                       07.08.92                      26.9.92
                        76 sites on                   25 sites on
                        10.9.92        179    sites   23.9.92
                                       on 24.9.92
                        123    sites                  94 sites on
                        on             222    sites   5.11.92
                        15.10.92       on
                                       03.11.92       35 sites on
                                                      12.11.92
Completion date as      50 houses      283            28    houses   32            Not          Not          8 houses
per contract            on 23.1.93     houses on      on 15.3.93     houses on     applicable   applicable   on
                                       15.3.93                       25.03.93                                14.4.93
                        76 houses                     25    houses
                        on 15.3.93     179            on 22.3.93
                                       houses on
                        123            23.3.93        94    houses
                        houses on                     on 4.5.93
                        14.4.93        222
                                       houses on      35    houses
                                       2.5.93         on 11.5.93
Date of cancellation    22/12/1992     22/12/1992     22/12/1992     20/10/199     20/10/1992   20/10/1992   20/10/19

Balance time for        50 houses-     283 houses     28 houses- 3   32 houses     Not          Not          8 houses
completion      still   1 month        - 3 months     months         -       5     applicable   applicable   -      6
available on date of                                                 months                                  months
cancellation      of    76 houses      179 houses     35 houses -
contract                - 3 months     - 3 months     3 months

                        123 houses     222 houses     94 houses -
                        - 4 months     -      4.5     4.5 months
                                       months
                                                      35 houses -
                                                      4.5 months
No.     of    joint
progress    review
meetings held by
Executive Engineer          Nil            Nil            Nil            Nil           Nil          Nil         Nil
as   required   by
clause 2 (c) of
agreement
No. of progress
reviews by Chief
Engineer in terms           Nil            Nil            Nil            Nil           Nil          Nil         Nil
of Clause 2 (c) of
agreement
                                - 27 -





     32.   Exs.P1   and   P2    were    not    disputed   by   the

defendants in any manner either in the cross-examination of

the plaintiff's witnesses or in the evidence of defendants'

witnesses. Nothing was produced to show that the sites

referred to in Exs.P1 and P2 were handed over to the

contractor in variance with the entries in Exs.P1 and P2.

J.K.Sridharamurthy official of defendants/KHB in his cross-

examination admitted that his statement in affidavit by way

of examination in chief that the construction should have

been completed within six months was incorrect. He has

admitted that the time stipulated including the monsoon

period was nine months and that had to be calculated from

the date of delivery of possession of sites to the contractor.

Though he claimed that the sites were handed over to the

contractor according to the schedule, he further states that

he cannot give such dates of delivery of possession of sites.

At another breath, he states that despite writing several

letters, the plaintiff did not come forward to take possession

of the sites in respect of four assembly constituencies. But

the said letters were not produced before the Court and he

admitted non-production of the same. He further admitted

that the contracts were terminated even before expiry of

- 28 -

stipulated period. Under the circumstances, the trial Court

was justified in relying on Ex.P1 and P2 and the oral evidence

of the plaintiffs' witnesses.

33. Ex.P1 shows that the defendants did not hand

over a single site in Ramdurga, Parasgad, Khanapura,

Ucchgaon, Gokak, Belgaum corporation etc. It further shows

that the defendants handed over only 101 out of 1097 in

Bagewadi constituency, 80 out of 1147 in Bailhongal, 25 out

of 1097 in Kittur Constituencies. Ex.P1 further shows that

the period for completion of the construction of the houses in

those constituencies was expiring on 15.03.1993. Whereas,

the contract was terminated on 11.08.1992 i.e., seven

months before the expiry of the stipulated period. So far as

Ramadurg, Parasgad, Khanapur, Belgaum Corporation,

Ucchgaon and Gokak, the time for commencement of the

work itself had not started.

34. Ex.P2 shows that the defendants had not handed

over single site in Ranebennur, Hanagal and Hirekerur

Constituencies. In Byadagi constituency as against 1147

sites, only 32 sites were handed over. So far as Haveri and

Shirahatti only 249 and 684 out of 1147 in each taluk were

- 29 -

handed over and in Shiggoan out of 1197 sites only 182 sites

were handed over. Ex.P2 and other evidence on record goes

to show that, the time for completion of the contract in those

constituencies was about to expire on 23.01.1993,

15.03.1993, 14.04.1993, 23.03.1993, 02.05.1993,

22.03.1993, 04.05.1993 and 11.05.1993 (based on data

available regarding delivery of the possession of the sites).

Whereas the contract was terminated on 20.10.1992 and

22.12.1992. That was much before the agreed time.

35. The plaintiff contended that the defendants had

to mark out the sites and deliver the same to it to execute

the work. The plaintiff further contended that in some places

the defendants directed the plaintiff to construct the houses

without such demarcation and the local people laying claim

over the same obstructed for taking possession. Another

Official by name B.R.Hosur, the Executive Engineer, who was

examined as PW.2 states that he has given his evidence

based on the records and he has no personal knowledge

about the facts in question. He further admits that he had no

knowledge about the affairs of defendant No.1 relating to

Belgaum District. He admits that marking out the sites

means marking the exact location of the places where the

- 30 -

houses had to be constructed. Though he claims that

separate work orders were issued in respect of different

villages, he says that he is unaware of it. According to him,

the xerox copies of the work orders are available in the office

records. He unequivocally admits that the defendants had to

handover possession of sites to the plaintiff for taking out the

construction work. One Mohammed Fayazuddin, the

Executive Engineer of defendant No.1 deposed about the

works in Dharwad district. According to him, there are

records in the office of the first defendant to show the dates

on which the sites were handed over to the plaintiff in

respect of different constituencies in Dharwad District.

According to him, the said documents were in

correspondence file. As rightly pointed out by the trial Court,

no such records were produced to prove that the sites were

handed over to the plaintiff as alleged.

36. One T.Mallanna, the Executive Engineer of first

defendant was examined as PW.4. He states in his cross-

examination that he has no personal knowledge about the

contract in question and he is giving evidence based on the

available records and the information gathered by him. He

admitted that no sites were handed over to the plaintiff in

- 31 -

respect of six assembly constituencies in Belgaum District. He

himself admits that he is not able to state about exact

number of sites which were handed over to the plaintiff in

respect of Bagewadi, Bailhongal and Kittur constituencies.

Relying on Exs.P51 and 52 an attempt was made to say that

despite the correspondence by defendant No.4 the plaintiff

itself did not receive the sites. But the above discussed

evidence shows that the defendants failed to prove that the

sites were handed over to the plaintiff on marking. Thus

there was breach of contract on the part of the defendants in

not delivering the sites as agreed.

37. The defendants contended that wherever the

sites were delivered, the work was not executed as per the

time schedule or the progress of the work was very slow.

Therefore the agreements were terminated. The defendants

could ascertain the progress of the work only if they

conducted a review of the work as per the clauses of the

agreements in that regard stated supra.

38. To prove that the work was in progress and the

defendants without any work review falsely alleged slow

progress in the work, the plaintiffs' relied on the evidence of

- 32 -

S.K.Mathur, the Managing Director of the plaintiff who is

examined as PW.1/DW.1 and Exs.P42, P76, P77, P83, P115

to P122. Ex.P42 is a letter dated 07.05.1992 addressed by

defendant No.4 the Executive Engineer, Hubli Division to

defendant No.1. The said document is not disputed. In that

document defendant No.4 himself had admitted that the

excavation work in respect of 50 houses at Karajagi railway

station site was in progress. That letter further shows that

within 2 months of entering into contract, such progress was

made. The witness J.K.Sridhar Murthy admitted that there

was progress in the work entrusted to the plaintiff with

reference to the sites handed over to it. Ex.P76 was marked

through S.K.Mathur. The said admitted document shows that

the plaintiff had made arrangements for exclusive supply of

blocks from three manufacturers. The said document further

shows that the plaintiff was entering into contracts with some

other vendors for supply of power, water, labour and

procuring the machines from Shirke machines and made

arrangements for procuring cements, jalli stones and

deployed the technical staff etc. Ex.P77 is another such work

progress report. Ex.P115 is the letter dated 24.11.1992

addressed by defendant No.4 to the Manager of State Bank

- 33 -

of Hyderabad. In that letter, defendant No.4 himself had

admitted that the work is going on. Exs.P116 to P122 show

that the plaintiff was working on the project. Those

documents also show that they were facing problems in

taking possession of the sites due to some litigation. In

Ex.D1 the letter dated 06.08.1992 (marked in

O.S.No.8665/1995) addressed by defendant No.4 to the

plaintiff, he himself admits that the work is in progress and

the construction of the houses were to be completed by the

end of March 1993.

39. In the light of the aforesaid documents and the

evidence, the burden was on the defendants to prove that

there was slow progress in the work. The defendants did not

produce any material to show that the Executive Engineer

and Chief Engineer conducted the work review as stipulated

in the agreement. The defendants' witnesses unequivocally

admitted that they have not produced any document to show

that such work review was conducted. Therefore the

contention that there was slow progress or no progress in the

work was rightly rejected by the trial Court. Contrary to their

own lapses, the defendants under Exs.P79 and P80 dated

20.10.1992, 22.12.1992 terminated the contracts relating to

- 34 -

7 constituencies in Dharwad district and under Ex.P78 dated

11.08.1992 terminated the contract relating to 9

constituencies of Belgaum District arbitrarily.

40. The trial Court on sound appreciation of the

evidence has returned the finding that the defendants were

guilty of breach of contract and the termination of contracts

were illegal. The said finding does not warrant any

interference.

Reg. Time being the essence of contract:

41. As noted above, the works were to be completed

within nine months including monsoon season. The said 9

months had to be computed from the date of delivery of

possession of sites. Further the contracts provide for

extension of time by the Executive Engineer on review of the

work on the basis of the progress achieved. The contention

that there was no progress in the work is already rejected.

The terms of the contract show that there was provision for

extension of time for completion of the work. Admittedly,

under Ex.D1 (O.S.No.8556/1995) defendant No.4 had

extended time for execution of the work in respect of

Dharwad District till March 1993.

- 35 -

42. Clause 2(d) of the condition of the contract under

Ex.P22 states that, if there is delay on the part of the

contractor to perform the work, according to Clause 2(b) &

(c) they shall be liable to pay penalty at certain percent of

the estimated costs of the balance work which could extend

upto 7½ %. Thus it is clear that the contract contained the

clause for extension of time and imposition of penalty in

cases of default.

43. The Hon'ble Supreme Court in para 8 of the

judgment in Hind Constructions Contractor's case referred to

supra held as follows:

"8. It will be clear from the aforesaid statement of law that even where the parties have expressly provided that time is of the essence of the contract such a stipulation will have to be read along with other provisions of the contract and such other provisions may, on construction of the contract, exclude the inference that the completion of the work by a particular date was intended to be fundamental, for instance, if the contract were to include causes providing for extension of time in certain contingencies or for payment of fine or penalty for every day or week the work undertaken remains unfinished on the expiry of the time provided in the contract such clauses would be construed as rendering ineffective the express provision relating to the time being of the essence of contract. The emphasised

portion of the aforesaid statement of law is based on

- 36 -

Lamprell v. Billericay Union, Webb v. Hughes and Charles Rickards Ltd. v. Oppenheim. ........................."

(Emphasis supplied)

44. Thus it becomes clear that even if one clause of

the contract says that time was the essence of the contract

and if there were clauses for extension of time and imposition

of penalty, then the clause with regard to time being the

essence of the contract renders ineffective. The trial Court

considering the aforesaid facts and circumstances and the

aforesaid judgment of the Hon'ble Supreme Court rightly

rejected the contention that time was the essence of the

contract.

Reg. Jurisdiction:

45. Learned Counsel for the defendants vehemently

argued that the works in question were to be executed in

Dharwad and Belgaum, defendant Nos.3 and 4 were the

residents of Belgaum and Dharwad respectively, therefore,

City Civil Court had no territorial jurisdiction to try the suit.

Section 20(b)(c) of CPC states that the suit can be filed

before the Court within whose jurisdiction any one of the

defendants resides or works or carries its business or cause

of action to suit wholly or in part arises.

- 37 -

46. As rightly pointed out by the trial Court, the suit

agreements were executed in Bangalore, defendant Nos.1

and 2 reside within the jurisdiction of the trial Court namely

XXVII Additional City Civil and Sessions Judge, Bangalore.

Therefore the suit was well within the territorial jurisdiction of

the trial Court. Further the defendants themselves filed the

suits before the very same Court in O.S.No.7462/1995 and

O.S.No.8665/1995 in relation to the contracts of 7

constituencies of Dharwad district claiming that the said

Court has jurisdiction. Therefore the contention that the trial

Court lacked territorial jurisdiction to entertain

O.S.No.11145/1997 is ridiculous and absurd. Suffice it to say

that innumerable judgments relied on by learned Counsel for

the defendants are not applicable to the facts of the present

case. The finding of the trial Court on that point is in

accordance with law and evidence on record.

Reg. Common impugned judgment in O.S.No.7462/1995, O.S.No.8665/1995 and O.S.No.11145/1997:

47. Defendants of O.S.No.11145/1997 filed

O.S.No.7462/1995 for recovery of Rs.53,66,130/- and

O.S.No.8665/1995 for recovery of Rs.40,73,685/- with

interest at 18% per annum against the contractor and the

- 38 -

Bank on the ground that the contracts were terminated. The

said suits were filed claiming that the contractor failed to

perform his part of the contract and on termination of the

contract they are liable to refund mobilization funds released

by KHB with interest and the Bank was liable to encash the

bank guarantees on the request of KHB. It was contended

that the Bank wrongfully declined to encash the bank

guarantees, therefore the bank and the contractor were

jointly and severally liable to pay the said amount with

interest 18% p.a. Whereas the contractor claims that the

termination of the contract itself was illegal and by such

illegal termination he suffered damages to the tune of

Rs.5,36,38,077/-. Both contractor and the bank contended

that invocation of the bank guarantees was not in accordance

with the terms of the bank. Therefore they are not liable to

pay any amount. The contractor claims that as against that

the defendants themselves were liable to pay compensation

of Rs.5,36,38,077/ - with interest at 18% per annum under

different heads as per the table below:

   Sl.               Details                In Rupees    In Rupees
   No
    .
   1     15% profit on the contract value               1,83,89,250/-
         for construction 8079 houses in
         Dharwad District-Contract value
         is Rs.12,25,85,000/-
                                     - 39 -





   2    Expenditure incurred by the
        plaintiff on executing the works
        for Dharwad contract                 70,75,981/-

        Less Mobilisation advance
        received from Karnataka              61,29,750/-      9,46,231/-
        Housing Board.

   3    Expenditure incurred by the
        plaintiff in executing the works
        for Belgaum contract                                23,68,152/-
   4    Interest on items 2 and 3 above
        from the date of incurring to                       10,67,444/-
        date:
   5    General damages on account of
        loss of 5 business and loss of
        reputation:                                          75,00,000/-
        Total                                              3,02,71,077/-
   6    15% profit on the contract value                   2,33,67,000/-
        for construction of 10,251
        houses in Belgaum District
        already included in plaint:
        Contract value
        Rs.15,57,80,000/-
        Total Claim:                                       5,36,38,077/-


48. While answering the aforesaid point it is already

held that the termination of the contracts by the defendants

are arbitrary and illegal. In the similar circumstances, the

Hon'ble Supreme Court in para 12 of the judgment in

Mahabir Auto Stores's case referred to supra held that the

defendants terminated the contract even without giving any

opportunity to the plaintiff to justify itself. Therefore it was

held that when the State or the statutory bodies enter into

contract with the citizens, it should be reasonably fair.

Referring to its several earlier judgments in that paragraph it

was held that even though the rights of the citizens are in the

- 40 -

nature of contractual right, the manner, the method and the

motive of decision of entering or not entering into contract

are subject to judicial review on the touchstone of relevance

or reasonableness, fair play, natural justice, equality and non

discrimination in the type of the transactions and the nature

of the dealing.

49. The plaintiff contended that the defendants

wanted to give the contract to one Swarnamukhi Building

Components Ltd. and Akshaya Constructions for extraneous

consideration. Therefore, they terminated their contract with

the plaintiff without any reasons under the colour that the

progress of the work was slow. According to the contractor,

such termination is colourable exercise of the power.

50. The plaintiff's witnesses viz., B.R.Hosur,

Mohammed Fayazuddin and Mallanna in their cross-

examination unequivocally admitted that immediately after

termination of the contract, the defendants without re-

tendering entrusted the same to one Swarnamukhi Building

Components in Dharwad District and to one Akshaya

Constructions in Belgaum District. Their evidence further

shows that even before termination of the contracts

pertaining to Belgaum District, they have entrusted the

- 41 -

contracts to Akshaya Constructions relating to that district

without re-tendering. Therefore there is lot of force in the

contention of the plaintiff that termination of the contracts

against it were malafide and for extraneous consideration of

favouring the aforesaid two contractors.

51. The witnesses S.K.Mathur and H.Sreenivasan are

the plaintiff's Managing Director and Chartered Accountant

respectively. S.K.Mathur reiterated how they arrived at the

damages claimed by them. They have deposed about the

arrangements which were made to execute the work,

whether the sites were handed over to the contractor.

Rs.94,44,133/- was claimed as expenditure incurred by the

contractor, as per their account books consisting of ledger

books Exs.P85 to P93. They rely on Exs.P94 to

P105/vouchers to support the expenditure incurred by the

contractor.

52. The witnesses have spoken about Exs.P106 to

P110 the auditors reports with balance sheets for four years

from 1991-1992 to 1995-1996. Both witnesses state that

accounts were maintained regularly in usual course and the

same were submitted to the Income Tax Authorities and the

- 42 -

Registrar of Companies. According to their evidence Ex.P111

was the Chartered Accountant's certificate for the total

expenditure on the project with bifurcation between Dharwad

and Belgaum District.

53. The plaintiff claimed that since they had taken

out work in those districts during that time, the contractor

had not accepted any other work. Exs.P85 to P93 were

account books relating to the suit contracts only. According

to their evidence, the plaintiff has incurred expenditure of

Rs.70,75,981/- for Dharwad District on deducting

mobilization advance of Rs.61,29,750/- received from the

Board, the loss suffered by the contractor regarding Dharwad

District is Rs.9,46,231/-.

54. According to the plaintiff's evidence, the plaintiff

incurred expenditure of Rs.23,68,152/-. Admittedly regarding

Belgaum District, no mobilization funds were released. The

plaintiff's witnesses have spoken about arrangements made

to execute the work in question like establishment of six

concrete block making factories in Dharwad and Belgaum

Districts, obtaining the lands in question from Town Municipal

Council, Haveri and conducting of reconnaissance survey etc.

Their deposition was supported by Exs.P26 to P32 and

- 43 -

Ex.P46, the letter dated 31.07.1992 issued by the Chief

Administrative Officer regarding lease of land for block

making factories and the plaintiff's letter dated 19.12.1992 to

the Board. Admittedly part of the work was executed. Due to

abrupt termination of the contracts, except mobilization of

the funds received, no other amount was received by the

contractor. The plaintiff assessed damages at 15% of the

contract value for the construction of 8079 houses in

Dharwad District. The defendants did not dispute that the

contract value of Dharwad District was 12,25,85,000/- and

Belgaum District was 15,57,80,000/- respectively.

55. The Hon'ble Supreme Court in the judgment in

A.T.Brij Paul Singh. V. State Of Gujarat37 held that the

contractor is entitled to 15% of balance of price of the works

as damages in cases of breach of contract. The trial Court

applied the same and accepted that the claim of the plaintiff

for Rs.1,83,89,250/- in respect of Dharwad District and

Rs.2,33,67,000/- in respect of Belgaum District by way of

15% of the profits of the contract value.

56. Since the matters arise out of the commercial

contract, the plaintiff claimed Rs.10,67,444/- by way of

AIR 1984 SC 1703

- 44 -

interest at the rate of 18% per annum. The expenditure

incurred by it was Rs.33,14,383/- (Rs.9,46,231/- +

Rs.23,68,152/-). Since the transaction in question is

commercial in nature, the trial Court rightly allowed the

interest at 18% per annum claimed by the plaintiff.

57. The plaintiff claimed Rs.75,00,000/- by way of

general damages due to arbitrary termination of the contract

due to which his reputation was foiled and he suffered

business loss also. Except the self serving evidence of

S.K.Mathur/DW.1 there was no other independent evidence

to show that due to termination of the contract, reputation of

the plaintiff was lowered in the society and such loss and

reputation had a dent on his business prospects.

58. So far as loss of business suffered by him, he

claimed 15% of the project costs as damages on the head of

loss of profit. He had not commenced the work in Belgaum

District and he had not executed substantial portion of the

work in Dharwad District due to not handing over of the sites.

On that count also, the trial Court has awarded damages of

Rs.2,33,67,000/-. After awarding such compensation, again

awarding compensation on the head of business loss

amounts to duplication. According to the plaintiff's evidence

- 45 -

itself, he did not take up any other work for the purpose of

execution of the work in dispute. When he says that he has

put all his men and material for the purpose of his work, as

rightly pointed out by the trial Court, he accepting other

works during the same period does not arise and more so

that is not acceptable. Therefore the trial Court was fully

justified in rejecting such claim of Rs.75,00,000/-.

Reg. Interest:

59. The plaintiff claimed interest at 18% per annum

on all the items of damages claimed by it. The actual

expenditure or the investment made by the plaintiff was

Rs.9,46,231/- and Rs.23,68,152/-. The rest of the damages

was by way of loss of profit for the contract period. The

damages of Rs.1,83,89,250-/- and Rs.2,33,67,000/- was in

all amounting to Rs.4,17,56,250/- was granted by way of

profit without execution of the work. Therefore the trial Court

justifiably awarded interest at 18% per annum on the

expenditure incurred by the plaintiff and awarded interest at

6% per annum on the award by way of profits. Under such

circumstances, it cannot be said that the trial Court exercised

discretion arbitrarily in awarding interest. Moreover the

defendants are public authorities. The damages have to be

- 46 -

paid from public funds. On that count also, awarding interest

at 18% per annum on the damages is not appropriate. Under

such circumstances, the judgments relied on by learned

Counsel for the plaintiff cannot be justifiably applied to the

facts of the present case regarding interest.

Reg. Bar by Arbitration clause:

60. So far as the contention regarding suit being

barred by arbitration clause, as rightly pointed out by the

trial Court, such plea should have been taken soon before

filing of the written statement. Firstly, that was not seriously

urged before this Court. Secondly, the defendants should

have raised such contention before filing of the written

statement, as per Section 8 of the Arbitration Act, 1996.

Further the defendants themselves filed other two suits

waiving arbitration clause. Therefore, the trial Court rightly

rejected the contention of maintainability of the suit in view

of arbitration clause in the agreement.

Reg. Invocation of Bank guarantees:

61. Much was argued on behalf of the defendants

that the Bank committed default in declining to encash the

bank guarantees and that amounts to violation of the terms

of the bank guarantee, therefore, the Bank is liable to make

- 47 -

good the sums of the bank guarantees with interest. Whereas

the bank claimed that the bank guarantees were not invoked

in accordance with the terms of the bank guarantee,

therefore, it was justified in declining to encash the bank

guarantees.

62. In view of the finding of this Court that the

defendants themselves were guilty of breach of contract,

they are not entitled to invoke the bank guarantees. If the

bank guarantees were permitted to be encashed, that would

have led to miscarriage of justice and multiplicity of the

proceedings, as the plaintiff had to again take recourse for

recovery of the said amount. Therefore, the defendants were

not entitled to invoke bank guarantees.

63. As per Clause 2 of the Bank guarantee bonds, the

defendants were required to make demand invoking Bank

guarantees in following the terms that amount is claimed as

damages by way of loss or damage caused to or would be

caused to or suffered by KHB by reason of any breach by

the said contractor of any of the terms or conditions

contained in the said agreement or by reasons of the

contractor's failure to perform the said agreement.

- 48 -

64. Ex.P10 (O.S.No.8665/1995) is the letter which is

similar to the other letters invoking bank guarantees. In the

said letter, there was no whisper that the bank guarantee is

being invoked and the amount is being claimed by way of

loss or damage caused to or would be caused to or suffered

by KHB as contemplated under Clause 2 of the Bank

guarantee bond. The Bank claims that since the bank

guarantees invocation letters did not include that clause, it

was not liable to encash the bank guarantees. Since the said

material clause was not incorporated in invocation letters, it

cannot be said that the bank's rejection to encash them was

arbitrary.

65. Having regard to the aforesaid facts and

circumstances of the case the judgments in National Thermal

Power Corporation Ltd.'s, Hindusthan Steel Workers

Constructions Ltd., State of Maharastra's and Daewoo

Motors India ltd.'s cases referred to supra relied on by

learned Counsel for the defendants on this point cannot be

justifiably applied to the facts of this case.

Reg. Non-joinder of parties:

66. So far as the contention that the suit was barred

for non-joinder of the parties, the records show that the

- 49 -

defendants in O.S.No.11145/1997 had not raised such

contention before the trial Court and no issues were framed

on the said contention. As against that, they contended that

the suit was bad for mis-joinder of the parties. Therefore it is

not open to them to raise such contention for the first time

before this Court.

67. The above discussions show that the trial Court

on sound appreciation of all the evidence, the applicable law

and supplying sound reasons has partly decreed the suit in

O.S.No.11145/1997 and dismissed O.S.No.7462/1995 and

O.S.No.8665/1995. It can be said that the impugned

judgment and order is well written judgment. Therefore there

are no grounds to interfere with the same. Hence the

following:

ORDER

RFA No.1238/2008, RFA No.1251/2008, RFA

No.1252/2008 and RFA Cross objection No.5/2012 are

hereby dismissed.

The judgment in O.S.No.7462/1995, O.S.No.8665/1995

and O.S.No.11145/1997 are hereby confirmed.

No order as to costs.

- 50 -

The original title deeds furnished, if any, as security by

respondent No.1 in R.F.A.No.1238/2008 shall be returned to

him.

Sd/-

JUDGE

Sd/-

JUDGE

KSR

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter