Citation : 2022 Latest Caselaw 9020 Kant
Judgement Date : 17 June, 2022
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 17TH DAY OF JUNE, 2022
BEFORE
THE HON'BLE MR.JUSTICE R. NATARAJ
W.P. NO.3230 OF 2020 (LB - BMP)
BETWEEN:
M/S. SHAKTI DEVELOPERS
PRIVATE LIMITED.,
NO.35/16, 2ND FLOOR,
LANGFORD ROAD CROSS,
BANGALORE - 560 025.
...PETITIONER
(BY SRI.K.N.PHANINDRA, SENIOR ADVOCATE A/W
SRI.K.VIJAYA KUMAR, ADVOCATE)
AND:
1. THE COMMISSIONER
BRUHAT BENGALURU MAHANAGARA PALIKE,
HUDSON CIRCLE, K.R.ROAD,
BENGALURU - 560 001.
2. THE EXECUTIVE ENGINEER (SPL),
SPECIAL DIVISION (RI) TEC SECTION,
ROOM NO.9, ANNEX-3,
N.R.SQUARE,
BENGALURU MAHANAGARA PALIKE,
BENGALURU - 560 002.
3. THE BRANCH MANAGER,
INDIAN OVERSEAS BANK,
EAST END MAIN ROAD,
NO.42/166, EAST END MAIN ROAD,
2
9TH BLOCK, JAYANAGAR,
BANGALORE - 560 069.
...RESPONDENTS
(BY SRI.ARAVIND M NEGLUR, ADVOCATE FOR R1 AND R2;
NOTICE TO R3 IS DISPENSED WITH VIDE ORDER
DATED 15.03.2022)
THIS W.P. IS FILED UNDER ARTICLE 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO SET ASIDE THE
ORDER DATED 23.12.2019 PASSED BY THE COMPETENT
AUTHORITY OF THE R-2 AND ORDER DATED 07.01.2020
ISSUED BY THE R-2 IS PRODUCED AS VIDE ANNEXURE - A AND
B AND ETC.,
THIS W.P. COMING ON FOR PRELIMINARY HEARING IN
'B' GROUP, THIS DAY, THE COURT MADE THE FOLLOWING:
ORDER
The petitioner has sought for a writ in the nature of
certiorari to quash an order dated 23.12.2019 passed by
the respondent No.2 and the order dated 07.01.2020
passed by the respondent No.2, by which, the entrustment
of development of a skywalk was cancelled.
2. The petitioner claims that respondent No.1
invited bids for installation of skywalk at Satellite Bus
Stand, Bengaluru-Mysuru Road from Satellite Bus Stand to
Ramani Timber Mark on Design, Build, Finance, Operate
and Transfer basis for a period of 30 years, in terms of a
tender notification dated 20.12.2016. The petitioner was
the successful bidder whose bid of Rs.1,39,165/- was
accepted on 29.06.2017 by the council of the respondent
No.1. Later, an agreement was executed in favour of the
petitioner authorizing him to operate the facility for a
period of 30 years. The petitioner is stated to have
furnished a bank guarantee for a sum of Rs.25,00,000/-,
which is renewed from time to time which was to be
released after completion of the skywalk as per the design
submitted. The agreement provided that the installation of
the skywalk will be completed within 270 days from the
date of agreement. The respondent No.2 issued a work
order on 24.08.2017 which stipulated a period of 9 months
for completion. The petitioner submitted a detailed plan to
the respondent No.2 for approval on 05.10.2017. The
respondent No.2 approved the plan on 21.07.2018 after a
lapse of 11 months, by which time, the petitioner had
already incurred substantial sums of money towards
structural design and drawing of the skywalk etc. The
petitioner is stated to have availed the services of a Geo-
Technical Team for investigation of soil strength to bear
the weight of the skywalk. The petitioner is stated to have
procured the vertical lifts and other paraphernalia for the
installation of the skywalk. The petitioner has also obtained
an insurance policy which was valid from 12.07.2018 to
11.11.2018. The petitioner claims that the ground
breaking ceremony for the installation of the skywalk was
held on 16.03.2018. When the work was under progress,
the Divisional Control of KSRTC addressed a
communication to the respondent No.1 raising objections
against installing the skywalk and requested the
respondent No.1 to install the skywalk at a different spot.
The respondent No.2 addressed a letter dated 04.09.2018
to the Assistant Commissioner of Police Traffic, Bengaluru
informing him that the work of installation of the skywalk
within the time specified cannot be achieved in view of the
white topping work of Mysuru Road. It also informed the
Police Officer that the KSRTC had permitted the skywalk to
be installed adjacent to a subway of BMTC entrance. This
was followed by a 'No Objection Certificate' issued by the
Commissioner of Police on 11.10.2018 in favour of the
petitioner to start construction. On 25.09.2019,
respondent No.2 issued a fresh work order in favour of the
petitioner to put up the skywalk at the fresh spot identified
and gave 4-5 months to complete the project. After the
petitioner completed all the formalities and ventured to put
up the skywalk, he realized that a major sewage water
channel ran below the TT Room of KSRTC. In view of this,
the officials of the KSRTC agreed to give space inside the
bus terminal and parking area and requested to change
the staircase positions from dog legs to straight legs
towards the landing towards the KSRTC building. After final
marking, the drawings were modified, which was informed
to the Chief Engineer of the respondent No.1 in terms of
the letter dated 28.11.2019. The petitioner claims that it
had undertaken the work on a war footing with a mission
to complete it within 70 days. However, the respondent
No.2 did not approve the plan in respect of the compound
wall to be constructed. When things stood thus, on
22.11.2019 and 21.12.2019, the KSRTC issued a 'No
Objection Certificate' to the petitioner to shift the Police
Chowki and Traffic Controller Room temporarily with a
condition to rebuild the same after completion of skywalk
work. When the installation of the work was under
progress, the respondent No.2 issued an order dated
23.12.2019 that the Competent Authority had directed to
cancel the agreement executed in favour of the petitioner
and forfeited the bank guarantee furnished by the
petitioner for not executing the work in time. Following
this, an order dated 07.01.2020 was passed canceling the
agreement and forfeiting the bank guarantee.
3. Being aggrieved by the aforesaid, the
petitioner is before this Court.
4. Learned Senior Counsel appearing for the
petitioner contended that once the agreement was entered
into, a concluded contract resulted and the respondents
could not have unilaterally terminated the contract.
Learned Senior Counsel further submitted that the
documents placed on record indicated that it was the
respondent No.1 and other state agencies which placed
obstacles in the way of executing the contract and
therefore, the petitioner cannot be held responsible for the
delay. He submitted that since the delay is attributable to
the respondents, the contract entrusted to the petitioner
cannot be terminated.
5. On the other hand, learned counsel for the
respondents submitted that the petitioner was required to
execute the work within 4-5 months from 25.09.2019 but
the petitioner did not take any effective steps in that
regard and therefore, the respondents were within their
right to rescind the contract as per the agreement. The
learned counsel relied upon the judgment of the Hon'ble
Apex Court in the case of TATA CELLULAR VS. UNION
OF INDIA reported in (1994) 6 SCC 651 to contend that
the Courts cannot judicially review commercial decisions
taken by the respondents.
6. Learned Senior Counsel for the petitioner on
the other hand relied upon the judgment of the Hon'ble
Apex Court in the case of ABL INTERNATIONAL LTD.
AND ANOTHER VS. EXPORT CREDIT GUARANTEE
CORPORATION OF INDIA LTD. AND OTHERS. reported
in (2004) 3 SCC 553 and contended that the Courts
under Articles 226 of the Constitution of India are not
handicapped to deal with the situation where a State acts
beyond the scope of the contract.
7. I have considered the contentions raised by
the learned counsel for the parties.
8. A perusal of the letter dated 25.09.2019
addressed by the respondent No.2 clearly indicates that
the respondent No.2 had shifted the location of the
skywalk from what was agreed under the agreement dated
24.08.2017. The respondents had substituted the period of
completion of the skywalk by 4-5 months from
25.09.2019. It is evident that even after 25.09.2019, the
petitioner was confronted with issues that were raised by
the KSRTC, which is evident from the letter dated
21.12.2019. Therefore, it is clear that the delay in
establishment of the skywalk was not attributable to the
petitioner but was solely attributable to the respondents
and other state agencies. The respondents ought to have
foreseen these issues before concluding to invite tender.
The petitioner after having taken steps by furnishing a
bank guarantee for a sum of Rs.25,00,000/- and investing
money for procuring the vertical lifts etc. cannot be put to
a disadvantage at the mere whim of the respondents. A
perusal of Annexure-A dated 23.12.2019 indicates that
there was no conscious decision taken by the respondents
before terming that the petitioner was responsible for the
delay in implementation of skywalk.
9. The respondent No.2 has claimed that the time
fixed for the completion of skywalk was 16.12.2019, which
is belied by the letter dated 25.09.2019. Even otherwise, it
is imperceivable for any person to put up a skywalk with so
many State agencies revolting against the establishment of
skywalk. It is relevant to note that the petitioner was
responsible to put up the skywalk based on design, build,
finance, operate and transfer basis for a period of 30
years. Therefore, the respondents were not affected
commercially in any way and the delay in establishment of
the skywalk would only eat into the profits of the
petitioner. A perusal of Annexure-D which is an order
passed by the respondent No.2 indicates that there was no
commercial call taken by the respondents to terminate the
contract. Hence, the reliance placed by the learned counsel
for the respondent on the judgment in TATA CELLULAR
(Supra). On the contrary, it was based on a direction
issued by the Commissioner of the respondent No.1 to
cancel the contract for non-implementation of the project
within time. The respondents have blissfully ignored the
problems faced by the petitioner in establishing the
skywalk and have cancelled the contract at their mere
whims and fancies. The State and its agencies are bound
to conduct its activities in a non-arbitrary manner and
taking into account the difficulties faced by the petitioner
in implementation of the project. It is evident from the
record that the petitioner was not at fault in not executing
the contract within time and it was State agencies who
were entirely responsible for delaying the project.
10. In that view of the matter, the respondents are
bound to permit the petitioner to execute the project
within a time framed that may be fixed. Therefore, this
writ petition is allowed. The impugned orders passed by
the respondent No.2 dated 23.12.2019 and 07.01.2020
are hereby quashed. The respondent No.3 is directed to
permit the petitioner to install the skywalk as per the letter
dated 25.09.2019 (Annexure-T) within a period of four
months from the date of receipt of the certified copy of this
order. If the petitioner fails to implement the project within
the stipulated time, the respondents are at liberty to take
steps to terminate the contract without any further notice
to the petitioner. The bank guarantee furnished by the
petitioner shall stand restored and shall be released after
the petitioner completes the installation of the skywalk in
all respects. In order to expedite the installation, the
following directions are issued:
(i) That the petitioner shall install the skywalk at
the location shown in the letter dated 04.09.2018 issued
by the respondent.
(ii) That the work of installation shall not be
hampered/obstructed/objected by any agency of the State.
(iii) That the jurisdictional Police shall take proper,
effective and immediate steps to stop any
nuisance/obstruction by any person whomsoever against
the installation of the skywalk.
(iv) The skywalk shall be installed as per the
design furnished and approved by the respondent No.2.
The petitioner shall ensure that the vertical lifts shall
always be functional 24 X 7 X 365 days.
(v) The respondent No.2 shall conduct periodical
checks to assess the safety of the skywalk and the side
bars and whether the vertical lifts are service regularly.
Sd/-
JUDGE NR/-
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!