Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

B Raghunath Prasad vs The Executive Engineer (Ele)
2022 Latest Caselaw 7961 Kant

Citation : 2022 Latest Caselaw 7961 Kant
Judgement Date : 2 June, 2022

Karnataka High Court
B Raghunath Prasad vs The Executive Engineer (Ele) on 2 June, 2022
Bench: Ravi V Hosmani
                                                    -1-




                                                               RSA No. 1586 of 2011


                           IN THE HIGH COURT OF KARNATAKA AT BENGALURU
                               DATED THIS THE 02ND DAY OF JUNE, 2022
                                                  BEFORE
                              THE HON'BLE MR JUSTICE RAVI V HOSMANI
                           REGULAR SECOND APPEAL NO. 1586 OF 2011 (MON)

                      BETWEEN:

                            B. RAGHUNATH PRASAD
                            S/O B. BEERAPPA
                            AGED ABOUT 49 YEARS
                            OCC:PWD CLASS-I CONTRACTOR
                            R/AT 1ST CROSS
                            RAVINDRA NAGAR EXTENSION
                            SHIMOGA CITY-577 201.

                                                                          ...APPELLANT
                      [BY SRI UMESH MOOLIMANI, ADVOCATE FOR
                          SRI S.V. PRAKASH., ADVOCATE (VC)]

                      AND:

                      1.    THE EXECUTIVE ENGINEER (ELE.)
                            KARNATAKA ELECTRICITY BOARD
                            KPTCL (NOW MESCOM)
                            MRS DIVISION
                            SHIMOGA CITY-577201.
Digitally signed by
VEENA KUMARI B        2.    THE SECRETARY
Location: High              KARNATAKA ELECTRICITY BOARD
Court of Karnataka
                            BANGALORE / GENERAL MANAGER
                            (ADMN & HRD), KPTCL
                            (NOW BESCOM)
                            BENGALURU-560 001.

                                                                      ...RESPONDENTS
                      [BY SRI H.V.DEVARAJU, ADVOCATE (PH)]

                             THIS RSA FILED UNDER SEC.100 OF CPC., AGAINST THE
                      JUDGMENT     AND   DECREE    DATED     14.12.2010   PASSED   IN
                      R.A.NO.227/2005 ON THE FILE OF THE PRL. DISTRICT JUDGE,
                                   -2-




                                             RSA No. 1586 of 2011


SHIMOGA, ALLOWING THE APPEAL AND SETTING ASIDE THE
JUDGMENT         AND   DECREE    DATED     24.10.2005     PASSED   IN
O.S.NO.263/1997 ON THE FILE OF THE PRL. CIVIL JUDGE (SR.DN) &
C.J.M, SHIMOGA.


      THIS APPEAL COMING ON FOR HEARING, THIS DAY, COURT
DELIVERED THE FOLLOWING:


                          JUDGMENT

Challenging judgment and decree dated 14.12.2010

passed by Principal District Judge, Shimoga, in

R.A.No.227/2005 and judgment and decree dated 24.10.2005,

passed by Principal Civil Judge (Sr.Dn.) and CJM at Shimoga, in

O.S.No.263/1997, this appeal is filed.

2. Appellant herein was plaintiff in original suit and

respondent in first appeal, whereas respondents herein were

defendants no.1 and 2 in suit and appellants no.1 and 2 in first

appeal. They shall hereinafter be referred as per their ranks in

original suit.

3. Plaintiff filed O.S.No.263/1997 seeking for recovery

of Rs.52,000/- with interest at 18% per annum from date of

suit till realisation. In plaint, it was stated that plaintiff was a

private contractor and defendant no.1 was executive engineer

RSA No. 1586 of 2011

working under defendant no.2. It was further stated that

defendant no.1 had issued a tender notification on 22.02.1994

for carrying construction of compound wall to left side of M.R.S.

Shimoga. That plaintiff had submitted his bid quoting rate of

Rs.4,10,272.50. Plaintiff's bid was accepted by defendant no.1

and tender was awarded to him by issuing letter dated

14.12.1995. An agreement incorporating terms and conditions

was also executed. As per terms of agreement, work was

required to be completed 'within six months from date of

its commencement'.

4. It was further stated that though agreement was

executed on 25.12.1995, spot was not identified and issuance

of work order was delayed, constraining plaintiff to commence

work only from 01.05.1996. Delay was alleged to be on account

of acts of defendants. Upon completion of construction, plaintiff

submitted final bills for acceptance. But, defendant no.1 did not

make payment. It was stated that defendant no.1 was due as

follows:

           a) Deposited amount               Rs.12,000.00
           b) 5% deducted in cash bill       Rs.15,000.00
           c) Final work bill payment        Rs.25,000.00
                                      Total Rs.52,000.00





                                                   RSA No. 1586 of 2011


5. Claiming said amount, plaintiff got issued legal

notice dated 10.07.1997 to defendant no.1. Instead of making

payment, a false reply was got issued on 21.07.1997

contending that defendants were not liable to pay any amount.

Constrained by refusal by defendant to make payment, plaintiff

filed suit for recovery of amount due.

6. On service of suit summons, defendant no.1 filed

written statement generally denying plaint averments and

specifically stating that work spot was not identified. It was

asserted that immediately after signing of agreement on

25.12.1995, lineout was given. Thereafter, there was no

obstacle to plaintiff to commence work. It was specifically

pleaded that in final bill submitted, plaintiff clearly admitted

that work was started on 25.12.1995 and completed on

18.10.1996, which was clearly more than stipulated period of

six months. Plaintiff could have approached competent

authority and got delay condoned. Instead of same, plaintiff

had filed suit.

RSA No. 1586 of 2011

7. While denying plaintiff's claim as imaginary

defendant no.1 stated that it was plaintiff who was liable to pay

to defendants following sums:

i) intermediate payment of Rs.2,82,284.90

ii) Deduction towards income tax, sales tax and security deposit of Rs.28,738/-.

iii) Amount of Rs.499/- towards income tax, Rs.998/-

towards sales tax, security deposit of Rs.3,732/- and;

iv) Penalty on Rs.3,41,426.18 @ 7.5% i.e., Rs.25,607/-.

Based on above figures, defendant no.1 alleged that

plaintiff himself was due to defendants.

8. Based on pleadings, trial Court framed following

issues:

1. Whether the plaintiff proves that the commencement of work was delayed for want of written order from the defendant?

2. Whether the plaintiff is entitled to suit claim with interest at 18% p.a. as claimed?

3. What Decree or Order?

RSA No. 1586 of 2011

9. Thereafter plaintiff got himself examined as PW.1.

Exhibits P.1 to P.9 were marked. On behalf of defendants

Assistant Executive Engineer, was examined as DW.1 and

Exhibits D1 to D.9 were marked.

10. On consideration, trial Court answered issue no.1 in

negative; issue no.2 partly in affirmative and issue no.3 by

decreeing suit in part and directed defendants no.1 and 2

jointly and severally to pay Rs.48,262/- with interest at 6% per

annum.

11. Aggrieved by judgment and decree, defendants no.1

and 2 preferred R.A.No.227/2005 on several grounds. It was

contended that trial Court failed to appreciate oral and

documentary evidence in proper perspective. It was contended

that plaintiff had violated terms of tender agreement by failing

to complete construction within time prescribed. Despite same,

trial Court decreed suit. It was also contended that impugned

judgment and decree was erroneous, capricious, arbitrary and

contrary to law and facts of case.

12. Considering grounds urged, first appellate Court

framed following points for its consideration:

RSA No. 1586 of 2011

1. Does appellants/defendants prove that the respondent/contractor did not construct the compound on the left side of M.R.S. Shimoga within the contractual period of 6 months from the date of its commencement as per the contract entered into between themselves and respondent on 25.12.1995 and so, they have levied penalty at the rate of 7.5% per annum on the tender amount and so, they are justified in deducting that penal amount from the final bill of the respondent.

2. Does respondent/plaintiff prove that the delay caused in commencing the contract work was due to the laches and negligence of the appellants/defendants in not delivering the work spot along with measurement and work order and so, he is entitled to recover and suit amount of Rs.52,000/- from the appellants/defendants?

3. Does appellants further prove that impugned judgment and decree passed by the court below is erroneous, capricious, arbitrary, contrary to facts and law and needs to be set aside?

4. What Order or Decree?

13. On consideration, first appellate Court answered

points no.1 and 3 in affirmative; point no.2 in negative and

point no.4 by allowing appeal and setting aside judgment and

decree passed by trial Court. Aggrieved thereby, plaintiff is in

second appeal.

RSA No. 1586 of 2011

14. Sri Umesh Moolimani, Advocate for Sri S.V.

Prakash, learned counsel for plaintiff submitted that admittedly,

tender condition clearly stipulated that work was to be

completed within six months from date of commencement of

work. Ex.P9 - Tender Notification itself provided for deduction

of period of monsoon. Plaintiff commenced work on 1.05.1996

and completed it on 18.10.1996. Even by assuming that

plaintiff had commenced work on 25.12.1995, it is common

knowledge that monsoon in Shimoga extends beyond three

months i.e., from June upto September. Therefore, completion

of work on 18.10.1996 cannot be said to be beyond stipulated

period. Therefore, trial Court was justified in decreeing suit and

first appellate Court erred in setting aside same.

15. It was further contended that defendants paid first

and second bill submitted by plaintiff but withheld payment of

third and final bill. Security deposit and earnest money deposit

(EMD) are also not paid despite plaintiff issuing legal notice on

10.07.1997. First appellate Court failed to appreciate these

factors while passing impugned judgment and decree.

RSA No. 1586 of 2011

16. Learned counsel further submitted that plaintiff had

very clearly pleaded sums due as follows:

            3rd and final bill             -     Rs.25,000/-

            EMD                            -     Rs.12,000/-

            5% deduction in each bill
            towards security deposit       -     Rs.15,000/-

17. Without any challenge to said calculation made by

plaintiff in plaint, first appellate Court erred in reversing decree

passed by trial Court. It was lastly contended that impugned

judgment and decree passed by first appellate Court was

contrary to admissions given by DW-1.

18. On other hand, Sri. H.V. Devaraju, learned counsel

for respondent no.1 supported impugned judgment and decree

opposed appeal. It was contended that tender agreement very

clearly stipulated that period of completion of work was six

months. It was specifically pleaded by defendant no.1 that date

of commencement of work was 25.12.1995 as stated by

plaintiff in final bill. There is no dispute about date of

completion i.e., 18.10.1996. Therefore, plaintiff clearly fail to

complete work within six months. It was further contended

intention of defendants in stipulating period of six months for

- 10 -

RSA No. 1586 of 2011

completion was to ensure completion of work before onset of

monsoon. In any case, even if, period of three months were to

be deducted, plaintiff would have nevertheless fail to complete

work within six months. Therefore, defendant no.1 was fully

justified in imposing penalty @ 7.5% on amount of

Rs.3,41,426.18. In view of same, plaintiff himself was due sum

of Rs.28,738/- to defendants. Therefore, there was no merit in

suit claim.

19. Learned counsel further contended that while

passing impugned judgment and decree had framed two issues

and had answered issue no.1 in negative which was not

challenged by plaintiff. By virtue of same, finding that no delay

occurred on account of defendants attained finality. Such being

case, trial Court erred in relying upon Ex.D.6 to conclude that

plaintiff has not commenced work as on 19.01.1996. Learned

counsel submitted that even finding of trial Court that plaintiff

failed to establish that date of commencement of work was

01.05.1996 also remained unchallenged. Relying upon evidence

led by defendants, without giving clear finding regarding date

of commencement, trial Court concluded that work was

commenced within period of six months. First appellate Court

- 11 -

RSA No. 1586 of 2011

upon reconsideration of evidence had rightly set aside said

finding. It was lastly submitted that finding of first appellate

Court regarding date of commencement of work being a finding

of fact did not call for interference in second appeal.

20. Heard learned counsel, perused impugned

judgment and decree and records.

21. Appeal was admitted on 04.12.2015 to consider

following substantial questions of law:

"1. Whether judgment and decree passed by appellate Court in allowed R.A.No.227/2006 filed by defendants and setting aside judgment and decree passed in O.S.No.263/1997 by trial Court and consequently dismissing suit of plaintiff for recovery of money is sustainable in law?

2. To consider other substantial questions of law which may arise while hearing appeal."

During argument, no other substantial question of law is

proposed for consideration. Therefore, only substantial question

of law framed is examined herein.

- 12 -

RSA No. 1586 of 2011

22. It is not in dispute that in response to tender

notification dated 22.02.1994, plaintiff had submitted his bid on

22.11.1994 and was awarded tender work. Tender agreement

was executed on 25.12.1995 and work order issued on said

day. It is also not in dispute that period stipulated for

completion of work was six months from date of

commencement of work. Date of completion of work on

18.10.1996 is also not in dispute. In Ex.P.9 - there is clear

stipulation that period of six months shall exclude monsoon

period.

23. As per above submissions, main dispute is

regarding date of commencement of work. While it is

contended by plaintiff that date of commencement of work was

01.05.1996 and as it was completed on 18.10.1996, it was

within six months. But according to defendant no.1, date of

commencement of work was 25.12.1995 as stated by plaintiff

in his first running bill submitted on 16.02.1996.

24. In this regard, trial Court observed that tender

agreement was executed between plaintiff and defendant no.1

on 25.12.1995. It referred to plaintiff's admission about receipt

- 13 -

RSA No. 1586 of 2011

of letter - Ex.D.6, from defendant no.1, wherein defendant

no.1 directed plaintiff to commence/complete work as soon as

possible. It noted that first running bill submitted by plaintiff

Ex.D.1 was on 15.02.1996. As running bills can be submitted

only after commencement of work, trial Court held plaintiff's

claim of date of commencement of work as 01.05.1996 was

not correct. It referred to Ex.D.6 - letter issued by defendant

no.1 to plaintiff on 19.01.1996 stating that plaintiff had not

started work and cautioning him that if he fails to take up work

as early as possible, consequent action would follow.

25. As either of parties fail to lead evidence and

establish specific date of commencement of work, trial Court

hypothetically considered date of commencement of work as

19.01.1996 i.e. date of Ex.D.6. It referred to cross-examination

of DW-1 wherein he admitted that period of three months is

excluded from period of completion of work if it covers

monsoon period and also about one week time required for

removal of fence from place of construction. By excluding

monsoon period of three months as well as time taken for

removal of fence from deemed period of construction i.e., from

19.01.1996 to 18.10.1996, apart from one week period

- 14 -

RSA No. 1586 of 2011

required for removal of fence, trial Court held that plaintiff had

completed construction within six months.

26. However, first appellate Court while answering point

no.1 considered date of execution of agreement i.e. 25.12.1995

as date of commencement of construction and date of

completion as 18.10.1996 to hold that completion of

construction was belated by period of three months twenty

three days. It referred to denial of knowledge about period of

monsoon being excluded from time stipulated for completion of

construction as attempt to hide truth. It also referred to

contents of Exs.D.3 to D.6 and D.8 i.e., correspondence by

defendant no.1 with plaintiff, whereunder plaintiff was

prompted to commence and complete work within time as

indicating lapses on part of plaintiff. On such finding, it held

that defendants were justified in imposing penalty @7.5%.

While passing impugned order, first appellate Court also

observed that in final bill plaintiff had mentioned date of

commencement of work as 25.12.1995 and therefore plaintiff

was estopped from contending otherwise.

- 15 -

RSA No. 1586 of 2011

27. However, final bill submitted by plaintiff is not

marked in evidence, neither of exhibits Ex.D.1 to D.8 mention

date of commencement of work. Indeed there is no pleading

with regard to delay occurring on account of failure by

defendant no.1 to ensure removal of fence existing at work

site. Even finding of trial Court that plaintiff's claim to have

commenced work from 01.05.1996 cannot be accepted as

plaintiff had submitted running bills on 15.02.1996 would be

justified. Further as noted above DW-1 admitted during cross-

examination that three months would be period of monsoon.

28. Further definition of month in Section 35(3) would

be calendar month. Hence, six months would be six calendar

months commencing from 19.01.1996. I am supported by

judgment of this Court in case of Loordswamy Vs. Presiding

Officer ESI Court and another reported in ILR 2001 Kar

2276 and decision of Hon'ble Supreme Court in case of Tamal

Lahiri Vs. P.N. Tagore reported in (1979) 1 SCC 75.

29. Therefore, computation of time taken for

completion of construction even from 19.01.1996 till admitted

date of completion i.e., 18.10.1996 would be two days shy of

- 16 -

RSA No. 1586 of 2011

nine months (excluding first day). If monsoon period of three

months is excluded, time taken for construction would be within

six months.

30. In view of above, finding of first appellate Court

regarding date of commencement of work as well as its

conclusion that time taken for completion of construction was

belated by three months and twenty three days would be

contrary to evidence on record and perverse. Hence,

substantial question of law is answered in affirmative.

In result I pass following:

ORDER

Appeal is allowed. Impugned judgment and decree

passed by Principal District Judge, Shimoga, in

R.A.No.227/2005 is set aside and judgment and decree dated

24.10.2005, passed by Principal Civil Judge (Sr.Dn.) and CJM,

Shimoga, in O.S.No.263/1997 is restored. Defendants are

directed to pay Rs.48,262.00 with future simple interest at rate

of 6% p.a., from date of order.

Sd/-

JUDGE *Psg/BVK

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter