Citation : 2022 Latest Caselaw 101 Kant
Judgement Date : 4 January, 2022
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 4TH DAY OF JANUARY, 2022
BEFORE
THE HON'BLE MR.JUSTICE N.S.SANJAY GOWDA
R.S.A.No.2549 OF 2006 (INJ)
BETWEEN:
M.V.RAJU SINCE DEAD BY LRs.,
1. JAYASHEELA,
W/O M.V.RAJU,
AGED 39 YEARS,
R/AT 2ND CROSS,
BHARATH COLONY,
(GANGA RICE MILL BACK SIDE)
DAVANAGERE - 57701.
2. KAVITHA
D/O M.V.RAJU,
AGED 20 YEARS,
R/AT 2ND CROSS,
BHARATH COLONGY,
(GANGA RICE MILL BACK SIDE)
DAVANAGERE - 57701.
3. MANJUNATHA,
S/O M.V.RAJU,
AGED 19 YEARS,
R/AT 2ND CROSS,
BHARATH COLONGY,
(GANGA RICE MILL BACK SIDE)
DAVANAGERE - 57701.
2
4. MADHU KUMAR,
S/O M.V.RAJU,
AGED 18 YEARS,
R/AT 2ND CROSS,
BHARATH COLONGY,
(GANGA RICE MILL BACK SIDE)
DAVANAGERE - 57701.
... APPELLANTS
(BY SRI. SANATH KUMAR SHETTY AND
SMT. JAYALAKSHMI, ADVS.)
AND:
1 N.G.KOTRABASAPPA,
SINCE DEAD BY LRs
1(a) SATHISH.N.G.,
AGED ABOUT 50 YEARS,
1(b) SURESH N.K.,
AGED ABOUT 44 YEARS,
1(c) PRAKASH.N.K,
AGED ABOUT 42 YEARS,
R-1(a) TO R-1(c) ARE THE
CHILDREN OF LATE N.G.KOTRABASAPPA,
R/AT HANAGODU HOBLI,
NERLIGE GRAMA,
DAVANAGERE TALUK - 577 566.
... RESPONDENTS
(RESPONDENTS SERVED AND UNREPRESENTED)
THIS APPEAL IS FILED UNDER SECTION 100 CPC
AGAINST THE JUDGMENT AND DECREE DATED 12.07.2006
PASSED IN RA.No.68/2003 ON THE FILE OF THE I ADDL.
CIVIL JUDGE (SR.DN), DAVANAGERE, ALLOWING THE
APPEAL AND SETTING ASIDE THE JUDGMENT AND DECREE
DATED 28.02.2003 PASSED IN O.S.No.186/1998 ON THE
FILE OF THE ADDL. CIVIL JUDGE (JR.DN), DAVANAGERE.
3
THIS APPEAL COMING ON FOR FINAL HEARING THIS
DAY, THE COURT DELIVERED THE FOLLOWING:
JUDGMENT
1. This is a second appeal filed by the LR's of the
deceased defendant Sri.M.V.Raju.
2. The respondent - plaintiff ie., N.G.Kotrabasappa
instituted a suit seeking for a decree of injunction to
restrain the appellant - defendant Sri.M.V.Raju from
putting up any sort of construction over the suit property.
The said suit was filed on 06.04.1998. Subsequently, an
amendment application was filed and the said application
was allowed on 03.09.1998. By virtue of the said
amendment, the plaintiff sought for a decree of mandatory
injunction to direct the defendant to demolish the
construction put up in the suit schedule property, failing
which the plaintiff should be permitted to get the building
constructed by the defendant demolished through a
Commissioner.
3. By way of the abovementioned amendment, it was
also pleaded that despite an order of temporary injunction
granted by the trial Court, which was to the knowledge of
the defendant, the defendant had proceeded with the
construction and therefore, the said construction was
illegal.
4. It was the case of the plaintiff that he owned site
No.3 measuring 30 ft x 30 ft which was the suit property.
It may be pertinent to state here that according to the suit
schedule, to the North of site No.3, lay the defendant's
property ie., site No.4. Thus, the plaintiff did not dispute
that to the North of his property, the defendant's property
ie., site No.4 was situated.
5. It was the plaintiff's case that the defendant was
attempting to put up construction on his site No.3. This
suit was contested by the defendant principally on the
ground that the defendant was putting up construction on
his site and not on the plaintiff's site. In fact, it was
admitted by the defendant that his site was situated
towards the South of the plaintiff's site ie., site No.3.
6. It was also contended that he had commenced the
construction after obtaining permission from the
authorities, he had also got fixed the boundaries of his site
before obtaining the licence. The defendant pleaded that
he had not at all encroached upon the plaintiff's site and
was putting up the construction on his site ie., site No.4.
7. The trial Court after considering the evidence
adduced before it, came to the conclusion that the
defendant had already dispossessed the plaintiff before
filing of the suit and therefore, the suit could not be
maintained and it proceeded to dismiss the suit.
8. The plaintiff, being aggrieved, preferred an appeal.
9. The Appellate Court on re-appreciation of the
evidence, came to the conclusion that the endorsement
dated 01.07.1998 at Ex.P19 indicated that even as on
01.07.1998, no permission had been granted by the Town
Municipal Council for construction of the building and
therefore, the contention that the building was put up even
before the suit had been filed could not be accepted. The
Appellate Court took note of the fact that the defendant
had disobeyed the order of temporary injunction and had
proceeded with the construction and in that view of the
matter, the defendant could not avail of any protection for
his illegal actions. The Appellate Court accordingly allowed
the appeal and decreed the suit.
10. It is against this decree that the present appeal has
been filed.
11. This Court while admitting the second appeal
formulated the following substantial question of law.
"(a) Whether the lower Appellate Court is justified in granting relief of permanent injunction in favour of respondent- plaintiff without recording a finding that the appellant-defendant has constructed building on the suit schedule property viz., Site No.3 and not in Site No.4 which
is admittedly owned by the appellant- defendant?"
12. The Appellate Court while recording the finding
regarding construction has noticed that the plaintiff had
approached the police on 06.05.1998 with a complaint and
the police had issued an endorsement at Ex.P18 calling
upon the Commissioner, C.M.D., Davanagere to state as
to which site number, the licence had been given. The
Appellate Court also noticed that as per Ex.P19, the
endorsement dated 01.07.1998, the Commissioner of
Municipal Council, Davanagere had stated that the licence
had not yet been granted to the defendant for construction
of a building and it was therefore clear that no licence had
been issued to the defendant for construction of a house
on site No.4.
13. The Appellate Court also noticed that even in the
licence given subsequently, the boundaries of site No.4
was not mentioned. The Appellate Court, ultimately stated
as follows:
"No documents to show that regarding the boundaries of the properties in which he has constructed the building. He has completed the construction of the property before issuing the Ex.D.12 and D.13. DW 2 and 3 have stated in their evidence that the defendant has put up construction in his site. But it is not possible to believe that the defendant has constructed the building in his Site No.4 in the absence of documentary evidence to show that he has constructed the building within which boundaries. The defendant has failed to prove that he has constructed the building in his Site No.4. On the other hand, the facts and circumstances shows that he has constructed the building in Site No.3. The trial court while discussing issue No.1, 2 and 3 come to the conclusion that the defendant has put up construction in the suit schedule property. But while discussing issue No.8 come to the conclusion on the basis of Ex.P.12 and P.13 that the defendant has constructed the building in Site No.4, Door No.1224, but not in suit schedule property. It is relevant to sate that the trial court has not discussed Ex.D.12 and D.13 in detail and not observed
that when this document came into existence. The trial court has also not discussed anything on Ex.D.9 endorsement dt.29.11.1998 issued by the C.M.D., Davanagere. As I have already stated at one stretch, the trial court comes to the conclusion that the defendant has put up construction in the suit schedule property i.e., Site No.3. At another stretch come to the conclusion that he has put up construction in Site No.4. Considering all these facts, I do not agree with the view of the trial court that the defendant has put up construction in his Site No.4 only, and not put up construction in the Site No.3 i.e., suit schedule property. The plaintiff has put up the construction in the suit schedule property and not in Site No.4."
14. As could be noticed from the above, no specific
finding is given as to whether the construction has been
put up on site No.3 or on site No.4. It is also not clear as
to whether the building constructed existed on site No.3 or
on site No.4. If as a matter of fact, the construction has
been put up on site No.3, obviously, site No.4 should be
available.
15. It may also be possible that due to the
encroachment by the other site owners ie., site Nos.1 and
2, either site No.3 or site No.4 would have been diminished
in size or it may not even be in existence.
16. In the light of the above, it would be therefore
necessary to remand the matter to the trial Court to record
a clear and categorical finding as to whether site Nos.3 and
4 exists, and if so, on which site the construction has been
put up.
17. If it is found that a building has been constructed on
site No.3, obviously, the suit would have to be decreed.
18. If on the other hand, it is proved that the building
was put up on site No.4, the suit of the plaintiff would have
to be dismissed.
19. The trial Court shall also record a finding as to
whether site Nos.3 and 4 actually exists on the spot and
whether any of these sites have been encroached by the
other site owners situated in the same line.
20. The matter shall stand remanded to the trial Court to
record a finding as narrated above.
21. Consequently, the question of law framed by this
Court is answered in favour of the appellant and the
second appeal is allowed in the above terms.
Sd/-
JUDGE
GH
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!