Citation : 2022 Latest Caselaw 3030 Kant
Judgement Date : 22 February, 2022
:1:
IN THE HIGH COURT OF KARNATAKA
DHARWAD BENCH
DATED THIS THE 22ND DAY OF FEBRUARY, 2022
BEFORE
THE HON'BLE MR. JUSTICE R. NATARAJ
M.F.A. NO.22130/2010 (ESI)
BETWEEN:
ESI CORPORATION,
REP. BY ITS JOINT DIRECTOR,
ESI CORPORATION, SUB-REGIONAL OFFICE,
NO.H-42 GROUND FLOOR, NIKETAN,
DOLLARS COLONY, ADJ. NEW CENTRAL
BUS-STAND, HUBBALLI-580030.
... APPELLANT
(BY SRI VINAY S.KOUJALAGI & SRI V.M.SHEELAVANT, ADVOCATES)
AND:
M/S ANJANEYA COTTON MILLS PVT.LTD.,
JAYALAKSHMI, P.B.ROAD,
DAVANGERE,
REP.BY ITS MANAGING DIRECTOR.
... RESPONDENT
(BY SRI. SURESH S.GUNDI, ADVOCATE)
THIS MISC.FIRST APPEAL IS FILED UNDER SECTION 82(2) OF
THE E.S.I. ACT, 1948 AGAINST THE JUDGMENT AND ORDER DATED
02.11.2009, PASSED IN ESI APPLICATION NO.45/2005, ON THE FILE
OF THE EMPLOYEE'S STATE INSURANCE COURT, HUBLI, AT HUBLI,
ALLOWING THE PETITION FILED UNDER SECTION 75 OF THE
EMPLOYEES STATE INSURANCE ACT, 1948.
THIS APPEAL COMING ON FOR FINAL HEARING, THIS DAY, THE
COURT DELIVERED THE FOLLOWING:
:2:
JUDGMENT
This appeal under Section 82(2) of the Employees State
Insurance Act, 1948 (henceforth referred to as 'Act of 1948') is
filed by the ESI Corporation challenging the order dated
02.11.2009 passed by the Employees State Insurance Court,
Hubballi (henceforth referred to as 'ESI Court') in ESI Application
No.45/2005 by which it set aside the contribution demanded
from the respondent.
2. The respondent is an establishment covered under
the provisions of the Act of 1948. The ESI Corporation had
passed an order under Section 45(A) of the Act of 1948
demanding contribution of Rs.1,23,833/-. Later it reduced the
same to a sum of Rs.93,905/- which was challenged by the
respondent in ESI application No.15/1999. The ESI Court allowed
the same in part, in terms of the order dated 14.03.2001 and
struck off the interest demanded and ordered to pay the balance
contribution of Rs.18,803/- since the respondent had already
deposited part of the amount demanded. This order was again
challenged in MFA No.3030/2001. This Court in terms of the
order dated 31.10.2003 remitted the case back to the ESI Court
to reconsider the case relating to the grant of interest. After
remand, the ESI Court passed an order on 01.07.2004 and
directed the payment of Rs.42,433/- towards interest. The
respondent deposited the amount on 16.07.2004. Thereafter the
ESI Corporation claimed damages of Rs.79,768/-. The
respondent challenged the order imposing damages by filing ESI
Application 45/2005. The appellant opposed the application. The
respondent examined one of its employees as AW1 and marked
documents as Ex.A1 to A6 while the appellant marked Exs.R1 to
R9.
3. Based on the oral and documentary evidence, the
ESI Court held that the time to make the contribution began
from 01.07.2004 when the ESI Court passed an order directing
the respondent to pay Rs.42,433/-. The ESI Court held that the
respondent had paid the interest of Rs.42,433/- on 16.07.2004
within 15 days from the date of the order and that the
respondent is not liable to pay damages. The ESI Court found
that the damages was claimed for the period 08.02.1996 to
25.08.1996 based on an order under Section 45(A) of the Act of
1948 which was challenged before the Courts which reached
finality on 01.07.2004. Hence the ESI Court held that there was
no justification for claiming damages. Hence it allowed the
application filed by the respondent.
4. Being aggrieved by the order passed by the ESI
Court dated 02.11.2009, the present appeal is filed.
5. Learned counsel for the appellant submitted that the
liability to pay damages arose immediately on default of payment
of the contribution and therefore the demand for damages was
justified.
6. Per contra, the learned counsel for the respondent
submitted that the question of paying contribution was finally
decided on 01.07.2004 and that the respondent had deposited all
the amounts demanded as contribution and interest and
therefore there is no justification to claim the damages.
7. I have considered the submissions made by the
learned counsel for the parties.
8. The facts as narrated above undeniably demonstrate
that the respondent had challenged the order demanding
contribution and the same attained finality on 01.07.2004 when
the respondent called upon to pay interest on the contribution.
There is no deliberate delay on the part of the respondent.
However the respondent has paid all the amounts demanded
including the interest within the specified time and therefore the
question of demanding damages from the respondent does not
arise. The ESI Court has carefully considered the contentions
urged as well as the judgment of the Madras High Court in
Madras Hotel Ashoka Private Limited V/s ESIC and Regional
Director ESIC Chennai V/s N.Dhasarathy and sons and another
and the judgment of the Hon'ble Supreme Court in Regional
Director ESIC Kerala V/s Metropolitan Engineering Company
Limited and held that the demand for damages was unjustified.
9. The respondent having paid the contribution as
demanded as well as the interest, cannot be penalized to pay
damages. In that view of the matter, this appeal lacks merit and
the same is dismissed.
SD/-
JUDGE
CLK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!