Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vijay Kumar Jha And Others vs Ranchi Municipal Corporation And ...
2026 Latest Caselaw 1244 Jhar

Citation : 2026 Latest Caselaw 1244 Jhar
Judgement Date : 17 February, 2026

[Cites 0, Cited by 0]

Jharkhand High Court

Vijay Kumar Jha And Others vs Ranchi Municipal Corporation And ... on 17 February, 2026

Author: Rajesh Shankar
Bench: Rajesh Shankar
  IN THE HIGH COURT OF JHARKHAND AT RANCHI
             W.P. (C) No. 6864 of 2025
Vijay Kumar Jha and Others ...          ...     ...    ...     Petitioners
                        Versus
Ranchi Municipal Corporation and Others ...        ...     Respondents
                        ---------
CORAM:              HON'BLE THE CHIEF JUSTICE
             HON'BLE MR. JUSTICE RAJESH SHANKAR
                        ---------
For the Petitioners:    Mr. Sumeet Gadodia, Advocate
                        Mr. Aditya Kumar, Advocate
                        Ms. Sharda Kumari, Advocate
                        Mrs. Shilpi Sandil Gadodia, Advocate
                        Mr. Prakhar Harit, Advocate
                        Mr. Anish Lal, Advocate
For Resp. Nos.1&2:      Mr. L.C.N. Shahdeo, Advocate
                        Mr. Yash Raj Gupta, Advocate
For Resp. Nos.3&4:      Mr. R.N. Sahay, Sr. Advocate
                        Mr. Yashvardhan, Advocate
For Resp.5-11,13,14:    Mr. Indrajit Sinha, Advocate
                        Mr. Kashish Tiwary, Advocate
                        ---------
08/Dated: 17.02.2026

1.    Heard the learned counsel for the parties.

2. Mr. Indrajit Sinha, learned counsel, points out that respondent

nos.12, 15 and 16 have since expired. He also hands in a note giving

details of the legal representatives of these deceased respondents.

3. With the consent of the learned counsel for the parties, leave is

granted to the petitioner to bring on record the legal representatives of

respondent nos.12, 15 and 16.

4. Necessary amendment to be carried out within a week.

5. Mr. Sinha states that he will appear on behalf of the legal

representatives.

6. Accordingly, service upon the legal representatives is waived.

7. This matter relates to the assignment of the learned Single

Judge. However, by order dated 15th of January 2026, the learned

Single Judge noted that there was a conflict between two orders

which would require consideration by the Division Bench. Based upon

this, the matter was placed before the Division Bench.

8. The conflict, according to the order of 15th January 2026, was

between the orders dated 6th of December 2025 and 19th of December

2025. By the first order, the learned Single Judge, having the regular

assignment, ordered notice but directed that, until further orders, there

shall be no construction on the plot in question. By the second order

dated 19th December 2025, another learned Single Judge, before

whom the matter came up because the learned Judge who passed

the order dated 6th of December 2025 was on leave, vacated the

interim order restraining construction on the said plot and held that the

respondent nos.3 and 4 "shall continue to make construction on the

plot in question and the Respondent Nos.3 and 4 are permitted to

start the construction of the work till further order of the Court."

9. Mr R.N. Sahay, the learned Senior Counsel appearing on

behalf of respondent nos. 3 and 4, submitted that the first order dated

6 December 2025 was only an ad-interim order made without notice

to the opposite party. In our opinion, however, both orders were ad

interim. The second order does not touch the prima facie merits. It

only vacated the first order because the first order was made ex parte.

10. The second order, made when the learned Single Judge who

made the first order was on leave on that day, only states that the 3rd

and 4th respondents shall continue the construction until further orders

of the Court.

11. In any event, we do not think that the two orders, which are

purely ad-interim arrangements made until regular Bench would

resume and take up the issue of interim relief, could be said to be

conflicting and, therefore, necessitating consideration by the Division

Bench of this Court.

12. The learned counsel for the parties agree that the matter may

be restored to the learned Single Judge, as the matter pertains to the

assignment of the learned Single Judge. Such a course, in our

opinion, would be appropriate because it would not deprive the parties

of a right to appeal and a forum. The appeal forum would also benefit

from a reasoned order made after considering the rival claims,

pleadings, and documents.

13. The learned counsel for the respondents, however, submitted

that directions may be issued, or at least a request made, for the

expeditious disposal of either the petition itself or the application for

interim relief. They submitted that any restraint on the construction

would severely prejudice the respondents, because the construction

in question, apart from being consistent with validly issued

permissions, was undertaken after obtaining finances from banks and

financial institutions.

14. Mr Sahay submitted that the petition was not maintainable for

various reasons, including, but not limited to, the availability of

alternative remedies to the petitioner.

15. Mr. Gadodia, whilst not objecting to any direction for the

expeditious disposal of the petition or the application for interim relief,

contested the remaining submissions. He submitted that the

petitioners have no other alternative or efficacious remedy other than

instituting the writ petition. He submitted that this was a case of fraud

in the issuance of permissions and that the construction was being

carried out on the designated open space/common area. He

submitted that such construction far exceeds the permissible FAR,

and that the petitioners will be able to demonstrate this before the

learned Single Judge. He also sought to rely on the reports of the

Municipal Engineers/Junior Engineers/Town Planners, etc., to submit

that the constructions were patently illegal and unauthorised.

16. At this stage, since the matter is to be returned to the learned

Single Judge, it is not for this Court to adjudicate on or even comment

on the rival contentions. All contentions, including that of

maintainability, fraud and other contentions, are explicitly left open to

be decided by the learned Single Judge on their own merits and in

accordance with the law.

17. None of the observations in this order or the order made on

29.01.2026 or the two ad-interim orders needs to influence the

learned Single Judge in deciding the petition or the application for

interim relief in accordance with law and on their own merits.

Therefore, once again, we clarify that all contentions of the parties

remain open to decision by the learned Single Judge in accordance

with law, on their own merits.

18. Accordingly, we remit this matter to the learned Single Judge

having the roster to decide such matters, with a request that the

petition itself be disposed of expeditiously or the prayer for interim

relief be heard and decided expeditiously. This is because until the

prayer for interim relief is decided by the learned Single Judge, the

arrangement reflected in our order dated 29.01.2026 shall continue

given the statement now made by the learned counsel for the Ranchi

Municipal Corporation that no construction would be allowed at the

site until the petitioner's prayer for interim relief vide I.A. No. 531 of

2026 is disposed of by the learned Single Judge.

19. Accordingly, we remit the matter to the learned Single Judge

having the roster assignment, again with a request to consider either

disposing of the petition itself or to dispose of the petitioners' prayer

for interim relief, as expeditiously as possible.

20. The learned counsels for the parties have assured this Court

that they would co-operate with the learned Single Judge in the

expeditious disposal. The ad-interim arrangement in terms of the

order dated 29.01.2026 and based upon the statement of the learned

counsel for the Ranchi Municipal Corporation shall continue until the

prayer for interim relief is considered and disposed of on its merits and

in accordance with the law.

21. The parties/learned counsels for the parties may now appear

before the learned Single Judge on the 25th of February 2026 at 10:30

a.m.

22. The Registry is to list this matter on the said date before the

assignment or roster Bench.

(M. S. Sonak, C.J.)

(Rajesh Shankar, J.) February 17, 2026 Manoj/ Sharda/Cp.1

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter