Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Bharat Coking Coal Limited vs M/S Annapurna Construction
2025 Latest Caselaw 4741 Jhar

Citation : 2025 Latest Caselaw 4741 Jhar
Judgement Date : 15 April, 2025

Jharkhand High Court

M/S Bharat Coking Coal Limited vs M/S Annapurna Construction on 15 April, 2025

Author: Sanjay Kumar Dwivedi
Bench: Sanjay Kumar Dwivedi
                                                                                2025:JHHC:11342

                     IN THE HIGH COURT OF JHARKHAND, RANCHI
                                          ----

C.M.P. No. 879 of 2022

----

M/s Bharat Coking Coal Limited, through its HOD (Legal) namely, Ved Prakash, aged about 56 years, son of late Radhe Krishna Prasad, having its office at Koyla Bhawan, P.O. Koylanagar, P.S.Koylanagar, District Dhanbad, Jharkhand ...... .... ... Petitioner(s)/Judgment Debtor

-- Versus --

M/s Annapurna Construction, through its Partner, having its office J.C. Mallik Road, Hirapur, P.O. and P.S. Dhanbad, Town and District Dhanbad, Jharkhand ...... ..... ......Opposite Party

----

CORAM: HON'BLE MR. JUSTICE SANJAY KUMAR DWIVEDI

---

For the Petitioner(s) : Mr. Indrajit Sinha, Advocate Ms. Prerna Jhunjhunwala, Advocate For the Opposite Party(s) : Mr. P.K. Bhattacharya, Advocate Mr. Aditya Kumar Jha, Advocate

----

20/15.04.2025 Heard the learned counsel appearing on behalf of the petitioner as well

as the learned counsel appearing on behalf of the sole respondent/Opposite

party.

2. This petition has been filed under Article 227 of the Constitution of India

for setting aside the order dated 20.09.2022 passed by learned Civil Judge

(Senior Division) -II, Dhanbad in Execution Case No.29 of 2014.

3. The learned counsel appearing on behalf of the petitioner submits that

the petitioner and the sole opposite party have entered into a contract for

construction of 140 numbers of temporary hutments and the estimated cost of

which was to the tune of Rs.49,45,447.81 and thereafter a formal work order

was issued to the opposite party and in terms of the agreement, the entire

work was to be completed within four months. The formal contract was entered

into for the aforesaid work between the parties which was also containing the

arbitration clause. The said contract was not completed within time and request

was made for extension of time and that was also granted by the petitioner and

the dispute has further arose between the parties and for that the arbitration

2025:JHHC:11342

clause has been invoked and the opposite party has raised the claim of

Rs.55,01,640.66 and the petitioner herein has also raised counter claim of

Rs.28,47,860.57. The learned Arbitrator has passed the Award on 13.07.1994 to

the tune of Rs.18,97,729.37 with interest @ 18 % per annum in favour of the

opposite party, however, the counter claim of the petitioner herein has been

rejected by learned Arbitrator which was challenged before the Subordinate

Judge, Dhanbad in Title (Arbitration) Suit No.109 of 1994 for being made a rule

of the Court in terms of section 14 of Arbitration Act, 1940. In the said

proceeding, the petitioner has filed objection under section 15, 16, 30 and 33 of

the Arbitration Act, 1940 which was rejected by the order dated 03.06.1995

passed by the learned Subordinate Judge)-IV, Dhanbad in Title (Arbitration) Suit

No.109 of 1994. The opposite party has filed Execution Case No.6 of 1995 in

the court of learned Civil Judge, Senior Division-IV, Dhanbad which is still

pending. She further submits that against the order dated 03.06.1995 passed in

Title (Arbitration) Suit No.109 of 1994 the petitioner has preferred M.A. No.169

of 1995(R) and in the said case, Civil Revision has also been preferred before

the Hon'ble Patna High Court, Ranchi Bench, Ranchi which was registered as

Civil Revision No.12 of 1996(R) and the M.A. No.169 of 1995(R) and Civil

Revision No.12 of 1996(R) were heard together and the said civil revision was

allowed by the judgment dated 29.04.1997 whereas the aforesaid appeal was

disposed of. The civil revision was filed for interest against the first Award which

was allowed.

4. Aggrieved with the aforesaid judgment passed by the High Court the

petitioner herein has moved before the Hon'ble Supreme Court in Civil Appeal

Nos.5647-48 of 1997. The Hon'ble Supreme Court by the judgment dated

29.08.2003 disposed of observing therein as under:

"We are, therefore, of the opinion that the matter requires reconsideration. Having regard to the facts and circumstances of the case and particularly keeping in view the fact that the matter relates to pure

2025:JHHC:11342

interpretation of document, which gives rise to question of law and instead and in place of remitting the matter to the named arbitrator, we would direct that the disputes in relation to claim item nos.3,7 and 11 be referred to Hon'ble Mr. Justice D.N. Prasad, a retired Judge of the Jharkhand High Court on such terms and conditions as may be mutually agreed upon by the parties. The learned arbitrator is requested to consider the desirability of making his award as expeditiously as possible keeping in view the fact that the mater has been pending for a long time.

These appeals are allowed to the aforementioned extent. No costs."

5. She submits that after remand by the Hon'ble Supreme Court the

dispute with regard to claim nos. 3, 7 and 11 was reconsidered by Mr. Justice

D.N. Prasad, retired and by the Award dated 02.09.2005 has allowed interest at

the rate of 12 % per annum over the awarded amount in claim nos.7 and 11

only till the date of payment to the claimant/respondent-Opposite party. She

submits that the said Award was challenged before the learned Subordinate

Judge-I, Dhanbad in Title (Arbitration) Suit No.109 of 1994 which was dismissed

by the judgment dated 13.05.2010 and the objection filed by the petitioner

against the Award dated 02.09.2005 passed by the learned sole Arbitrator has

been rejected and the said Award was made rule of the Court directing the

Office to prepare decree accordingly and the decree was signed on 22.5.2010.

She submits that the said judgment dated 13.05.2010 was challenged in

Arbitration Appeal No.9 of 2010 which was dismissed by the order dated

09.12.2019. The petitioner has again moved before the Hon'ble Supreme Court

of India challenging the Award dated 09.12.2019 passed in Arbitration Appeal

No.9 of 2010 which was dismissed by order dated 12.2.2022 and thereafter

there is Execution Case No.29 of 2014. She submits that the dispute is there

with regard to interest and there is Execution Case No.29 of 2014. She submits

that the dispute is with regard to interest in view of second Award with regard

to item nos.7 and 11. She submits that in the second Award only two items

have been allowed being item nos.7 and 11 with interest @ 12 % per annum

over the awarded amount till the date of payment. She submits that from which

date the interest will be payable that is not there in the award and in view of

2025:JHHC:11342

that the sole opposite party is only entitled for interest from the date of said

Award, i.e., 02.09.2005. She submits that however the learned executing court

has interpreted the same and directed to pay the interest with effect from the

year 1988 when the first Award was drawn. She submits that the learned

executing court has wrongly interpreted the second Award and directed to pay

the interest with effect from 1988 on item nos.7 and 11 also. She submits that

in view of that the order of executing court is not correct.

6. Per contra, Mr. Bhattacharya, the learned counsel appearing on

behalf of the sole Opposite party submits that the learned Arbitrator after

remand by the Hon'ble Supreme Court has already granted the interest at the

rate of 12 % per annum which was challenged before the High Court and the

High Court has dismissed the same and against that the SLP has been preferred

which has further been dismissed. He submits that in light of the dismissal by

the Hon'ble Supreme Court the grounds taken by the petitioner herein deemed

to be there and the Hon'ble Supreme Court has not entertained the same and in

view of that the learned executing court has rightly passed the said order.

7. It is an admitted position that the dispute arose and pursuant to

that arbitration clause has been invoked. The learned first Arbitrator has passed

the Award which has been made a rule of the Court in light of section 14 by the

learned court and the interest part has been challenged by the sole respondent

in Civil Revision and the M.A was preferred against the said Award by the

petitioner herein and the M.A and the Civil Revision have been disposed by the

Court and the Civil Revision was allowed by the High Court with regard to the

interest and the M.A has been disposed of. Against that, the petitioner herein

has moved before the Hon'ble Supreme Court and the Hon'ble Supreme Court

after hearing remanded the matter to decide the issue nos.3,7 and 11 and

pursuant to that, the learned Arbitrator has decided the same and claim no.3

was not allowed, however, the item nos.7 and 11 was allowed and the interest

2025:JHHC:11342

@ 12 % per annum over the awarded amount. However, in the Award it is

specifically not disclosed as to from what date the interest will be payable.

Interest is already granted by the first Award which was the subject matter in

M.A and Civil Revision before the Hon'ble Supreme Court. The second Award

has further been challenged in Arbitration appeal No.9 of 2010 which has been

dismissed by the High Court by the judgment dated 09.12.2019 and the High

Court has taken note of the fact that the loss and profit aspect has been taken

care of in the Award and dismissed the said Arbitration Appeal and the Hon'ble

Supreme Court has further dismissed the same challenge in S.L.P. being Special

Leave to Appeal (Civil) No. 2361 of 2021. Thus, the grounds taken by the

petitioner herein are deemed to be there which has been affirmed up to the

Hon'ble Supreme Court. A person deprived of the use of money to which he is

legitimately entitled has a right to be compensated for the deprivation, call it by

any name. It may be called interest, compensation or damages. This basic

consideration is as valid for the period the dispute is pending before the

arbitrator as it is for the period prior to the arbitrator entering upon the

reference. Further, the contract did not prohibit the Award of interest with

respect to delayed payment.

8. In view of above, considering that the matter has been finally

settled up to the Hon'ble Supreme Court, no interference is required in the

impugned order dated 20.09.2022. The learned executing court has only

interpreted the Award and this can be done by the learned executing court and

there is no illegality in the same.

9. As such, C.M.P. No.879 of 2022 is dismissed.

10. Pending petition, if any, also stands disposed of accordingly.

( Sanjay Kumar Dwivedi, J.)

SI/,A.F.R.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter