Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rungta Projects Limited vs Central Coalfields Limited
2023 Latest Caselaw 221 Jhar

Citation : 2023 Latest Caselaw 221 Jhar
Judgement Date : 13 January, 2023

Jharkhand High Court
Rungta Projects Limited vs Central Coalfields Limited on 13 January, 2023
                  IN THE HIGH COURT OF JHARKHAND AT RANCHI

                             Arbitration Appeal No. 25 of 2011

                      Rungta Projects Limited, a Company duly registered under the
                      provisions of the Companies Act, 1956, having its registered office
                      at 301, Mangalam Building, 24 Hemanka Basu Sarani, P.O. -
                      G.P.O Kolkata, P.S. - Hare Street, District - Kolkata - 700001 and
                      its office at Vikash Bhawan, Bariatu Road, Bariatu P.S. - Lalpur,
                      P.O. - Ranchi University, District - Ranchi - 834008, Jharkhand,
                      through its Director Sri Ram Swaroop Rungta, son of late Ram
                      Kumar Rungta at Vikash Bhawan, Bariatu Road, Bariatu, P.S. -
                      Lalpur, P.O. - Ranchi University, District - Ranchi - 834008
                                       ...    ...      Claimant/Opposite Party/Appellant
                                            Versus
                      Central Coalfields Limited, a subsidiary of Coal India Limited and
                      a Government of India undertaking having head office at
                      Darbhanga House, P.S. - Kotwali, P.O. - G.P.O Ranchi, District -
                      Ranchi, through its Chairman cum Managing Director at
                      Darbhanga House, P.S. - Kotwali, P.O. G.P.O Ranchi, District-
                      Ranchi ...           ...      Respondent/Petitioner/Respondent
                                            ---

CORAM: HON'BLE MRS. JUSTICE ANUBHA RAWAT CHOUDHARY

---

                 For the Appellant     : Mr. Pandey Neeraj Rai, Advocate
                 For the Respondents   : Mr. A.K. Das, Advocate
                                       : Mr. Sahay Gaurav Piyush, Advocate
                                       ---
09/13.01.2023          Heard Mr. Pandey Neeraj Rai, learned counsel appearing on
                 behalf of the appellant.

2. Heard Mr. A.K. Das, learned counsel appearing on behalf of the respondent along with Mr. Sahay Gaurav Piyush, Advocate. Arguments of the Appellant.

3. The learned counsel for the appellant has submitted that the learned court below has travelled beyond the permissible grounds for interference under section 34 of the provisions of the Arbitrations and Conciliation Act, 1996 to set aside the award and has not appreciated the findings of the award which is well reasoned and based on interpretation of the contract as well as conduct of the parties and the attending circumstances.

4. The learned counsel for the appellant has submitted that the key issue involved in the present case is as to whether the award was beyond the terms of the contract and a further issue is as to whether the appellant having accepted certain amount on 14.12.2008 during the pendency of the arbitration proceedings by making an endorsement "no claim of the claimant is outstanding as on date as per provision of agreement" can be said to be a final settlement of claim between the parties and whether the

arbitrator could not have gone ahead and awarded any further amount at all pursuant to the arbitration agreement.

5. The learned counsel has also submitted that the impugned order has to be examined in the light of permissible scope of interference under Section 34 of Arbitration and Conciliation Act, 1996. The specific case of the appellant is that the award has been passed in terms of the contract and the payment made on 14.12.2008 with the aforesaid endorsement has no bearing in the matter. The further case of the appellant is that the learned Arbitrator while passing the award has interpreted the various terms of contract and considering the terms of contract, the learned arbitrator has given the award within the terms of reference and in terms of the clauses of the agreement and has not travelled beyond the contract of the parties.

6. The learned counsel has placed the entire award before this Court and has submitted that the entire process was in three parts namely extraction, loading, transportation & unloading. He submits that the loading part was executed partly by pay loaders. He has submitted that the dispute involved in the present case which remained for the Arbitrator to decide was whether price escalation in diesel was payable on the diesel used in pay loaders. The learned counsel submits that the Arbitrator after going through the materials and the various clauses of contract, has recorded a specific finding in para 30 (c) that in terms of clause 36 of the contract, all diesel consuming machines were eligible for payment to the contractor of compensation for increase or decrease in the price of diesel.

7. The learned counsel has placed clause 36 of the contract and he submits that clause 36 of the contract is not confined to use of diesel in surface miner. The learned counsel further submits that so far as the formula is concerned, clause 36.3 gives the formula and the learned Arbitrator has held that clause 36.3 will be deemed to be applicable for operation 1 and 2 and the value of 'C' in the formula was decided by the learned Arbitrator on the basis of materials.

8. Learned counsel submits that the learned Arbitrator was of the specific view that so far as diesel consumption is concerned, the excavation and loading could not be segregated. The learned counsel submits that the learned Arbitrator having interpreted the contract and having taken a plausible and possible view, there was no scope for interference in the award under Section 34 of the Arbitration and Conciliation Act.

9. Learned counsel has submitted that the principles of interpretation of contract is well settled that the contract is to be interpreted not only on the plain reading of the contract, but also taking into consideration the

attending facts of the case. He submits that the learned Arbitrator has taken the entire facts and the terms of the contract to interpret the contract and has passed the award.

10. He has referred to a judgment reported in (2016) 12 SCC 592 para 13 to submit that construction of the terms of contract is primarily within the domain of the Arbitrator. He has further referred to the judgment reported in (2018) 1 SCC 718 para 10 to submit that if the Arbitrator has taken one of the plausible view, the award is to be sustained. The learned counsel has also referred to judgment passed by Hon'ble Supreme Court reported in (2012) 5 SCC 306 para 43 to submit that even if it is not a plausible view and if it is a possible view, then also the award is required to be sustained. The learned counsel has also relied upon judgment reported in (2018) 1 SCC 718 para 11 to submit that the question of interference in the award would arise only when the interpretation given by the Arbitrator shocks the conscience of the court. He has relied upon another judgment reported in (2015) 3 SCC 49 para 56 to submit that the court's view with regard to interpretation of contract will not prevail as the courts are not sitting in appeal to the arbitral award.

11. The learned counsel has also referred to the judgment passed by Hon'ble Supreme Court reported in (2003) 8 SCC 154 para 9 with regard to payment made during the pendency of the arbitral award. He submits that this judgment has been specifically referred to by the learned Arbitrator and considered while proceeding further with the award and rejecting the contention of the respondents that the claim was finally settled between the parties.

Arguments of the Respondents.

12. The learned counsel for the respondents, on the other hand, while opposing the prayer of the appellant has submitted that the impugned order does not call for any interference. The learned court has considered the award and has found that the same is fit to be set aside. He submits that the award is beyond the terms of the contract. He has also submitted that there was no question of making payment of any diesel escalation for the purposes of diesel use in pay loaders as the formula prescribed for calculation of diesel escalation specifically mentioned the use in surface miners and he submits that the formula takes care of the entire gamut of affairs irrespective of where the diesel is used. The learned counsel submits that once the formula has been prescribed, the formula by itself could not have been interfered and given a different interpretation by the learned Arbitrator.

13. The learned counsel submits that the learned Arbitrator has not only misinterpreted the contract, but has travelled beyond the contract and has re-written the agreement between the parties.

14. The learned counsel has also submitted that the learned Arbitrator could not have taken into consideration the study carried out by the respondents on the basis of the report dated 29.11.2005 as the agreement was concluded as back as on 08.04.2004. He submits that subsequent circumstances cannot be used to interpret an agreement. The learned counsel has heavily relied upon the aforesaid note put by the appellant at the time of receiving the payment on 14.12.2008, though during the pendency of the arbitration proceedings. He submits that there is no bar in law for making payment of the entire dues during the pendency of the arbitration agreement, the same having been received without any protest, there was no scope for the learned Arbitrator to proceed further and pass any award.

15. The learned counsel submits that since the arbitration proceeding was pending, the appellant ought to have received the amount under protest and such amount was admittedly received without any protest therefore the learned arbitrator has wrongly passed the award.

16. The learned counsel has referred to the judgment passed by Hon'ble Supreme Court reported in (1994) Supp. (3) SCC 126 para 5; (2000) 8 SCC 1 para 5 to submit that the claim beyond the agreement cannot be entertained. He has also referred to a judgment passed by this Court reported in (2001) 1 JLJR 48 para 16 and 17 to submit that in the said case, the reference to arbitration was itself rejected on account of no dues certificate given by the claimant. He has referred to judgment reported in (2011) 15 SCC 101 para 11 to submit that the learned Arbitrator cannot rewrite the terms of the contract. He has also referred to judgments reported in (2006) 4 SCC 445 para 13 and 14 and AIR 2003 SC 2629 para 14, 22, 73 and 74 to submit that the award is fit to be set aside when it is against the substantive provision of law and contrary to the contract.

17. Arguments concluded.

18. Post this case on 14.02.2023 for judgment.

(Anubha Rawat Choudhary, J.) Saurav/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter