Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Daya Shankar Rai vs Central Coalfields Ltd. And Anr
2022 Latest Caselaw 348 Jhar

Citation : 2022 Latest Caselaw 348 Jhar
Judgement Date : 9 February, 2022

Jharkhand High Court
M/S Daya Shankar Rai vs Central Coalfields Ltd. And Anr on 9 February, 2022
                                 1




             IN THE HIGH COURT OF JHARKHAND AT RANCHI
                  Arbitration Application No.09of 2020

          M/s Daya Shankar Rai                 ... ... Petitioner

                                     Versus

       Central Coalfields Ltd. and Anr.           ......Respondents
                                   -------

CORAM:HON'BLE MR. JUSTICE SUJIT NARAYAN PRASAD

-------

For the Petitioner :Mr. Indrajit Sinha, Advocate For the Respondents : Mr.Amit Kumar Das, Advocate

----------------------------

07/Dated09th February, 2022

The matter has been taken upthrough video

conferencing.

2. The instant application has been filed under

Section 11 (6) (C) of the Arbitration & Conciliation Act,

1996 (hereinafter referred to as "the Act, 1996") whereby

and whereunder the prayer for appointment of arbitrator

has been made in view of condition stipulated under

Clause 9 of the Agreement dated 20.11.1991.

3. The brief facts of the case, as per the

pleadings made in the application, which is required to be

enumerated for proper adjudication of lis, reads as under:

The applicant, having been found to be successful

bidder for road construction/repair work of strengthening

and widening of Khelari to Kalyanpur Road, entered into

an agreement on 20.11.1991 with respondents-CCL for

total value of Rs. 1,80,45,673.84. It is alleged that though

the completion period of work in question was ten

months, but, due to default on the part of respondents

there was delay in the work completion and it was

completed by 10.02.1995. It has further been stated that

during course of execution of work the applicant was to do

additional work beyond the scope of agreement namely;

(i)supply and stacking of coarse sand, (ii).labour for

mixing of gravel sand, (iii).excavation of the composed

draw (iv)carriage of metals (v)providing 7.5 cm thick

bitumen concrete after mixing with extra quantify for

bitumen at the rate of 9.51 kg per meter square instead of

agreement specification of 2.794 kg per meter square.

According to applicant, the entire work was

completed as per the agreement but the payment for

providing 7.5 cm thick bitumen concrete after mixing with

extra quantify for bitumen at the rate of 9.51 kg per meter

square instead of agreement specification of 2.794 kg per

meter square was not made by the respondents instead of

repeated request made by the applicant during course of

execution of the work.

Since the claim of the applicant was not decided by

the respondents-authorities, the applicant was compelled

to invoke the arbitration clause, whereupon a sole

arbitrator was appointed by this Court in Arbitration

Application No. 46 of 2004. The learned Arbitrator

adjudicated the claim and passed an Award dated

26.12.2008 whereby claim of the applicant was rejected.

However, a lump sum amount of Rs. 10,00,000/- (ten

lakh) was awarded in favour of applicant under Section 74

of the Indian Contract Act, 1872.

The respondent, being aggrieved with the aforesaid

Award filed a petition, being Misc. Arbitration Case No. 06

of 2009 under Section 34 of the Act, 1996,which was

dismissed vide order dated 09.03.2011 by learned Sub-

Judge VI, Ranchi. The applicant also filed a petition, being

Misc. Arbitration Case No. 14 of 2009 under Section 34(2)

of the Act, 1996, for modification of Award dated

26.12.2008, which was dismissed vide order dated

09.03.2011.

The respondent challenged order dated 09.03.2011

passed in Misc. Arbitration Case No. 6 of 2009 before this

Court in Arbitration Appeal No. 4 of 2011 and the

applicant challenged order dated 09.03.2011 passed in

Misc. Arbitration Case No. 14 of 2009 before this Court in

Arbitration Appeal No. 06 of 2011.

This Court, after hearing the parties and materials

available on record, set aside the Award passed by learned

Arbitrator vide order dated 25.07.2019 on the ground of

point of impartiality of the Arbitrator and granted liberty

to the parties to take steps in accordance with law for the

purposes of resolution of their dispute, thereby the instant

application has been filed by the applicant-petitioner

under Section 11 (6) (c) of the Act, 1996 for appointment

of sole Arbitrator.

4. Mr. Indrajit Sinha, learned counsel for the

applicant-petitioner has submitted that in view of

judgment rendered by Hon'ble Apex Court in McDermott

International Inc. Vs. Burn Standard Co. Ltd & Ors

[(2006) 11 SCC 181 and in Project Director, National

Highways No. 45 E and 220 National Highways

Authority of India vs. M. Hameem&Anr. [(2021) 9 SCC

1],law is settled that application filed under Section

11(6)(C) of the Act, 1996 after setting aside award earlier

passed by the sole arbitrator is maintainable.

5. Mr. Amit Kumar Das, learned counsel for the

respondents-CCL has not disputed the aforesaid legal

position.

6. This Court, having heard learned counsel for the

parties and after going through the materials available on

record,has found that the instant application has been

filed under Section 11(6)(C) of the Act, 1996for

appointment of sole arbitrator in terms of Clause as

contained in agreement. Counter affidavit has been filed

on behalf of respondents disputing the prayer made in the

application by taking stand about non-maintainability of

the instant application.

This Court has also gone through the issue

referred/rendered by Hon'ble Apex Court in McDermott

International Inc. Vs. Burn Standard Co. Ltd & Ors

(supra) wherein at paragraph 52, it has been held that

after quashing of award it will be open for the parties to

begin the arbitration again, if is desired.

The relevant passage of said judgment is being

quoted and referred hereunder as:

"52. The 1996 Act makes provision for the supervisory role of courts, for the review of the arbitral award only to ensure fairness. Intervention of the court is envisaged in few circumstances only, like, in case of fraud or bias by the arbitrators, violation of natural justice, etc. The court cannot correct errors of the arbitrators. It can only quash the award leaving the parties free to begin the arbitration again if it is desired. So, the scheme of the provision aims at keeping the supervisory role of the court at minimum level and this can be justified as parties to the agreement make a conscious decision to exclude the court's jurisdiction by opting for arbitration as they prefer the expediency and finality offered by it."

Similar view has been reiterated by Hon'ble Apex

Court in the judgment rendered in Project Director,

National Highways No. 45 E and 220 National

Highways Authority of India (supra) wherein at

paragraph 25 it has been laid down that the application

under Section 11 (6)(C) is maintainable for appointment of

sole arbitrator once award is being quashed by the

competent Court of law.

7. Though the respondents have taken the plea

of non-maintainability of instant application in the

counter affidvit but Mr. Das, learned counsel for the

respondents-CCL Management has fairly submitted that

after the judgment having been pronounced by the

Hon'ble Supreme Court, as above, laying down the

rulethat the application under Section 11 (6)(C) is

maintainable for appointment of sole arbitrator once

award is being quashed by the competent Court of law,

the issue is now no more res integra.

8. This Court, considering the submissions advanced

by learned counsel for the parties and ratio laid down by

Hon'ble Apex Court in the judgments rendered in

McDermott International Inc. Vs. Burn Standard Co.

Ltd & Ors (supra) and Project Director, National

Highways No. 45 E and 220 National Highways

Authority of India (supra), is of the considered view that

the instant application is maintainable.

9. Since this Court arrives at a conclusion about

maintainability of the instant application and applicant

has invoked the jurisdiction under Section 11(6)(c) of the

Act, 1996 praying for appointment of arbitrator under

Clause 9 of the agreement dated 20.11.1991, this Court is

of the considered view that sole arbitrator is required to be

appointed by invoking jurisdiction conferred under

Section 11(6)(c) of the Act, 1996.

10. In view thereof, learned counsel for the parties are

directed to furnish the list/name of Former Judges of this

Court for his/her appointment as sole arbitrator, so as to

scrutinize their names from the list provided by the

Registrar General of this Court before passing order of

appointment of sole arbitrator, subject to his consent and

declaration.

Needless to say that the said appointment will be

subject to Section 12 (5) of the Act, 1996.

11. Post this matter on 17th February, 2022.

(Sujit Narayan Prasad, J.) Alankar/-

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter