Citation : 2026 Latest Caselaw 2186 J&K
Judgement Date : 10 April, 2026
Sr. No. 1
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
CJ Court
Case: Arb P No. 25/2026
Des Raj Nagpal Contractors Pvt. Ltd. ..... Appellant/Petitioner(s)
Through: Ms. Nancy Mahajan, Advocate.
Vs
Union of India and anr. ..... Respondent(s)
Through: Mr. Vishal Sharma, Sr. Advocate (DSGI) with
Mr. Karan Sharma, CGSC.
CORAM: HON'BLE THE CHIEF JUSTICE
ORDER
10.04.2026
01. The present petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short 'the Act') for appointment of an independent Arbitrator.
02. The petitioner, a Company, carrying the business of Military Engineering Services (MES), was allotted a contract bearing No. CA No. CEPZ-25/2019-20 (subsequently amended as CEPZ-12/2021-22) for the project of "Provision of Tech Sehd OtmAccn and Swts at Birupr Ratnuchak" having contract value of ₹1,42,98,600.00 accepted by the Chief Engineer Pathankote zone on 31.03.2022. Work Order No. 1F was issued on 20.06.2022 by the Garrison Engineer Project Jammu establishing the date of commencement as 05.07.2022 and the date of completion as 04.07.2023. The petitioner completed the awarded work besides completing the additional works as directed by the Garrison Engineer and the Completion Certificate in this behalf was issued on 10.07.2023. Initially, on 05.08.2023 intimation with regard to formal Pre final bill, final RAR and comprehensive final bill was given to the concerned Engineer in-charge, thereafter, submitting the formal Final bill on 09.08.2023 for the clearance of the requisite dues. Which was retuned unsanctioned on 11.03.2024. Vide letter dated 21.08.2023, the petitioner requested to treat the pre-final bill and final bills as 'signed under protest', as also vide letter dated 05.09.2023, for providing a copy of the final bill forwarded to HQ CEPZ. On 14.09.2023, the respondents while intimating the petitioner that the final bill had been forwarded to CEPZ, issued a communication dated 06.10.2025 amending the contract agreement agency from GE(P) Jammu to GE Kaluchak unilaterally. The petitioner on 26.12.2023 requested the respondents to appoint the arbitrator for resolution of the dispute arisen between the parties on account of non- payment of the bill amount as also on vide letters dated 22.02.2024 and 03.04.2024, information was furnished about the total outstanding amount of ₹ 3,17,861.72. Respondents on 11.03.2024 returned the final bill unsanctioned with a request to the petitioner to resubmit the final bill separately in duplicate for Part-A denoted as AGREED PART and Part-B as DISPUTED PART, to which protest was raised by the petitioner on 18.03.2024. On account of the said dispute of non-payment of final bill by the respondent, the petitioner invoked Condition 70 of GCC (IAFW-2249-1989) already contained in the Agreement, vide letters dated 19.02.2025 and 28.04.2025 as also seeking appointment of an arbitrator to adjudicate upon the disputes between the parties, though the respondents omitted to act. However, it is submitted that out of the total outstanding dues, vide Payment Order issued through PCDA (NC) Jammu bearing Voucher Number 56/1030/BR-II(P) dated 09.08.2025 ₹ 2,06,372.00, was processed in favour of the petitioner. It is further averred that notwithstanding the consistent efforts to amicably settle the dispute arisen between the parties, the outstanding final dues remained unpaid. Hence, on account of nonfeasance from the respondents, the present petition.
03. Heard. Notice.
04. Served with advance copy of the petition, Mr. Karan Sharma, learned Central Government Standing Counsel, present in Court, accepts notice.
05. Learned counsel for the respondents vehemently disputes/denies the claim that is sought to be made by the petitioner being apparently misconceived and untenable. However, the existence of the arbitration clause, as aforesaid, and its invocation by the petitioner vide notices dated 19.02.2025 and 28.04.2025, is not disputed.Accordingly, itisurgedthatletanarbitratorbeappointedand the respondents be granted liberty to raise all possible pleas/ objections before the arbitrator in this regard.
06. Accordingly, in the wake of the position sketched out above and in terms of the statements made by the learned counsel for the parties, as also the clause contained in the agreement itself, the petition is allowed.
07. With consent of learned counsel for the parties, Sh. Rajinder Paul Singhal, Additional Director General Retd, MES R/o B-380 Chandi Mandir Cantt,-134107, is appointed as the sole arbitrator. Who shall proceed with the matter in accordance with the provisions of the Act. And to make an award within the time provided in the Act itself after charging the prescribed fee along with incidental expenses to be shared by the parties. The respondents are at liberty to raise all the objections as regards the subject matter before the learned Arbitrator.
08. Registry to send a copy of this order to the learned arbitrator.
09. Disposed of.
(ARUN PALLI) CHIEF JUSTICE Jammu 10.04.2026 Sunita
SUNITA KOUL 2026.04.16 14:59
integrity of this document
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!