Wednesday, 20, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Cube Construction Engineering vs Ut Of J&K & Ors
2024 Latest Caselaw 1559 j&K

Citation : 2024 Latest Caselaw 1559 j&K
Judgement Date : 5 August, 2024

Jammu & Kashmir High Court

M/S Cube Construction Engineering vs Ut Of J&K & Ors on 5 August, 2024

             HIGH COURT OF JAMMU AND KASHMIR & LADAKH
                           AT JAMMU



                                                   WP(C) No. 1962/2022

                                                  Reserved on:       31.07.2024
                                                  Pronounced on:     05.08.2024



M/S Cube Construction Engineering                               ...Petitioner(s)

                 Through :- Mr. Bhavesh Bhushan, Advocate
                v/s
UT of J&K & Ors.                                            .....Respondent (s)

                 Through :- Mr. Ravinder Gupta, AAG



CORAM:            HON'BLE MR. JUSTICE RAJESH SEKHRI, JUDGE


                                  JUDGMENT

1. Petitioner, a partnership firm, pursuant to e-NIT No. CEJ/PMGSY/474 of

2017-18 dated 30.10.2017, participated in the tendering process for the work

namely "Construction and maintenance of road from Malwan Jagir to Abli

Masri, Package No JK04-301, Phase-X, Stage II, Block Doda District Length

6.00 kms" and being the lowest bidder was allotted the aforesaid work vide

Order No. CEJ/PMGSY/27614-23 dated 14.02.2018.

2. The case set up by the petitioner is that on completion of the aforesaid

work, it raised its final bill (CC-8th) to the respondents for pending amount of Rs.

13.90 lacs duly approved by respondents after necessary tests on site. According

to the petitioner, the exceeded work amounting to Rs.13.90 lacs, with respect to

which a comparative statement showing excess over the allotted cost along with

its estimate was prepared and approved by respondent No. 3-Executive Engineer,

PMGSY, Division and was submitted to respondent No. 2-Superintending

Engineer on 23.10.2021. It is contention of the petitioner is that aforesaid work

was completed by it without any complaint or deficiency, owing to which,

Executive Engineer, PMGSY Division, Doda issued a completion certificate on

27.01.2021. According to the petitioner, the balance payment in question is

outstanding against the respondents inspite of regular follow ups on its part.

3. It is further case of the petitioner that it filed a complaint dated 25.01.2022

in the J&K Government Grievance Cell for release of the aforesaid admitted

liability. Respondent No. 3 submitted its reply to the aforesaid complaint of the

petitioner on 01.02.2022 whereby excess work done by the petitioner came to be

admitted but with the reason that payment could not be made due to internal

approvals.

4. Grievance of the petitioner is that despite execution of the allotted work,

within the prescribed period to the satisfaction of the respondents, respondents

have withheld its admitted liability without any reason or justification.

5. Respondents are affront to the claim of the petitioner for the release of

balance payment in question, primarily on the premise that the alleged excess

work might have been done by the petitioner firm on its own free will but

without any express written order from the competent authority. It is contention

of the respondents that petitioner cannot claim the payment, for the excess work

done by it without formal Administrative approval.

6. Heard arguments and perused the file.

7. Learned counsels for the parties have reiterated the grounds urged in their

respective pleadings in the arguments. Learned counsel for the petitioner has

relied upon a judgment dated 07.05.2022 passed by this Court in Abdul Rashid

Malik v. Union Territory of J&K and others; WP(C) No. 873/2021.

8. This Court in Abdul Rashid Malik has held that it is not for the contractor

to consider whether the Administrative approval, technical sanction and other

formalities have been completed or not before undertaking any work, but it for

the respondents to explain how these works were executed in the absence of

necessary approval and sanction. It was also observed that contractor executing

the work on behalf of the respondents undertakes the same on the firm belief that

the work is being undertaken by him on the asking of respondents after its due

approval and completion of all the formalities. The Co-ordinate Bench in the

aforesaid case relying upon M/s Surya Construction v. The State of UP in

Civil Appeal No. 2610/2010 dated 02.05.2010 also clarified that State, while

entering into a contract or agreement with private individuals, has to act in just,

fair and reasonable manner as the contractual obligations of the State coexist

with the constitutional obligations.

9. If the stand of the respondents is carefully glanced over, it is evident that

respondents have neither denied the execution of work done by the petitioner

over and above the allotted work, nor their liability to make the payment. There

is nothing in the stand of the respondents to indicate that petitioner firm has not

executed the allotted work to its satisfaction or within the prescribed time line. It

is also admitted position of fact that completion certification after the execution

of the work also came to be issued by the respondents in favour of the petitioner

firm. The final bill raised by the petitioner firm amounting to Rs.13.90 is also not

in dispute. The only exception of the respondents to the claim of the petitioner is

that it has executed the work over and above the allotted work on its own,

without express Administrative approval. It is contention of the respondents that

application for accord of Administrative approval, for excess work down by the

petitioner creating liability, has been submitted to the higher authorities and as

soon as funds are placed at the disposal of respondent No. 3 by the higher

authorities, payment shall be released in favour of the petitioner.

10. In the circumstances, respondents cannot escape the liability to make the

balance payment for the work, which is admitted to have been executed by the

petitioner firm in the guise of the Administrative approval.

11. It is evident from the very stand taken by the respondents that admitted

liability of the petitioner has been withheld without any lawful justification. The

stand of the respondents, besides being arbitrary, unreasonable and unfair is

unconstitutional. Hence, the present petition is allowed and respondents are

directed to release admitted liability of the petitioner firm amounting to Rs. 13.90

lacs along with interest @ 6% per annum till its realization within a period of six

weeks from the date copy of this order is made available to them.

12. With the aforesaid direction, the present petition stands disposed of.

(RAJESH SEKHRI) JUDGE JAMMU 05.08.2024 (Paramjeet) Whether the order is speaking? Yes Whether the order is reportable? Yes

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter