Citation : 2024 Latest Caselaw 1559 j&K
Judgement Date : 5 August, 2024
HIGH COURT OF JAMMU AND KASHMIR & LADAKH
AT JAMMU
WP(C) No. 1962/2022
Reserved on: 31.07.2024
Pronounced on: 05.08.2024
M/S Cube Construction Engineering ...Petitioner(s)
Through :- Mr. Bhavesh Bhushan, Advocate
v/s
UT of J&K & Ors. .....Respondent (s)
Through :- Mr. Ravinder Gupta, AAG
CORAM: HON'BLE MR. JUSTICE RAJESH SEKHRI, JUDGE
JUDGMENT
1. Petitioner, a partnership firm, pursuant to e-NIT No. CEJ/PMGSY/474 of
2017-18 dated 30.10.2017, participated in the tendering process for the work
namely "Construction and maintenance of road from Malwan Jagir to Abli
Masri, Package No JK04-301, Phase-X, Stage II, Block Doda District Length
6.00 kms" and being the lowest bidder was allotted the aforesaid work vide
Order No. CEJ/PMGSY/27614-23 dated 14.02.2018.
2. The case set up by the petitioner is that on completion of the aforesaid
work, it raised its final bill (CC-8th) to the respondents for pending amount of Rs.
13.90 lacs duly approved by respondents after necessary tests on site. According
to the petitioner, the exceeded work amounting to Rs.13.90 lacs, with respect to
which a comparative statement showing excess over the allotted cost along with
its estimate was prepared and approved by respondent No. 3-Executive Engineer,
PMGSY, Division and was submitted to respondent No. 2-Superintending
Engineer on 23.10.2021. It is contention of the petitioner is that aforesaid work
was completed by it without any complaint or deficiency, owing to which,
Executive Engineer, PMGSY Division, Doda issued a completion certificate on
27.01.2021. According to the petitioner, the balance payment in question is
outstanding against the respondents inspite of regular follow ups on its part.
3. It is further case of the petitioner that it filed a complaint dated 25.01.2022
in the J&K Government Grievance Cell for release of the aforesaid admitted
liability. Respondent No. 3 submitted its reply to the aforesaid complaint of the
petitioner on 01.02.2022 whereby excess work done by the petitioner came to be
admitted but with the reason that payment could not be made due to internal
approvals.
4. Grievance of the petitioner is that despite execution of the allotted work,
within the prescribed period to the satisfaction of the respondents, respondents
have withheld its admitted liability without any reason or justification.
5. Respondents are affront to the claim of the petitioner for the release of
balance payment in question, primarily on the premise that the alleged excess
work might have been done by the petitioner firm on its own free will but
without any express written order from the competent authority. It is contention
of the respondents that petitioner cannot claim the payment, for the excess work
done by it without formal Administrative approval.
6. Heard arguments and perused the file.
7. Learned counsels for the parties have reiterated the grounds urged in their
respective pleadings in the arguments. Learned counsel for the petitioner has
relied upon a judgment dated 07.05.2022 passed by this Court in Abdul Rashid
Malik v. Union Territory of J&K and others; WP(C) No. 873/2021.
8. This Court in Abdul Rashid Malik has held that it is not for the contractor
to consider whether the Administrative approval, technical sanction and other
formalities have been completed or not before undertaking any work, but it for
the respondents to explain how these works were executed in the absence of
necessary approval and sanction. It was also observed that contractor executing
the work on behalf of the respondents undertakes the same on the firm belief that
the work is being undertaken by him on the asking of respondents after its due
approval and completion of all the formalities. The Co-ordinate Bench in the
aforesaid case relying upon M/s Surya Construction v. The State of UP in
Civil Appeal No. 2610/2010 dated 02.05.2010 also clarified that State, while
entering into a contract or agreement with private individuals, has to act in just,
fair and reasonable manner as the contractual obligations of the State coexist
with the constitutional obligations.
9. If the stand of the respondents is carefully glanced over, it is evident that
respondents have neither denied the execution of work done by the petitioner
over and above the allotted work, nor their liability to make the payment. There
is nothing in the stand of the respondents to indicate that petitioner firm has not
executed the allotted work to its satisfaction or within the prescribed time line. It
is also admitted position of fact that completion certification after the execution
of the work also came to be issued by the respondents in favour of the petitioner
firm. The final bill raised by the petitioner firm amounting to Rs.13.90 is also not
in dispute. The only exception of the respondents to the claim of the petitioner is
that it has executed the work over and above the allotted work on its own,
without express Administrative approval. It is contention of the respondents that
application for accord of Administrative approval, for excess work down by the
petitioner creating liability, has been submitted to the higher authorities and as
soon as funds are placed at the disposal of respondent No. 3 by the higher
authorities, payment shall be released in favour of the petitioner.
10. In the circumstances, respondents cannot escape the liability to make the
balance payment for the work, which is admitted to have been executed by the
petitioner firm in the guise of the Administrative approval.
11. It is evident from the very stand taken by the respondents that admitted
liability of the petitioner has been withheld without any lawful justification. The
stand of the respondents, besides being arbitrary, unreasonable and unfair is
unconstitutional. Hence, the present petition is allowed and respondents are
directed to release admitted liability of the petitioner firm amounting to Rs. 13.90
lacs along with interest @ 6% per annum till its realization within a period of six
weeks from the date copy of this order is made available to them.
12. With the aforesaid direction, the present petition stands disposed of.
(RAJESH SEKHRI) JUDGE JAMMU 05.08.2024 (Paramjeet) Whether the order is speaking? Yes Whether the order is reportable? Yes
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!