Citation : 2022 Latest Caselaw 828 j&K
Judgement Date : 23 May, 2022
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
OWP No. 628/2012
IA Nos. 1/2018, 863/2012
Reserved on : 20.04.2022
Pronounced on :23.05.2022
Sanjay Gupta .....Petitioner(s)
Through: Mr. Rahul Pant, Sr. Advocate with
Ms. Shreya Nagpal, Advocate
Vs.
State of J&K and others ..... Respondent(s)
Through: Mr. Rajneesh Raina, Advocate
Coram: HON'BLE MR. JUSTICE TASHI RABSTAN, JUDGE
JUDGMENT
1. The petition in hand has been filed by the petitioner on the grounds that
the petitioner is owner in possession of the land measuring 1144.25
square feet comprised in Khasra No. 330-Min situated at Maheshi Gate,
Gurudwara Sunder Singh Road, Jammu which was purchased by him on
07.03.1989 from one Kesar Singh S/o Sh. Ram through a registered sale
deed executed on 07.03.1989 and registered with the court of learned
Sub-Registrar, Jammu on 08.03.1989. It is averred that as per the sale
deed the land which was purchased by the petitioner from Kesar Singh
measured about 5½ marlas and taking advantage that the petitioner
normally resides outside J&K in connection with his job, an unnecessary
dispute was raised by the neighbours which was ultimately settled in
terms of a compromise deed and the petitioner was left with an open
land measuring 882.75 sq.ft. only. Subsequently, some more land
adjoining to the land, which was earlier part of 5½ marlas and given
away in compromise deed, was purchased back by the petitioner vide
sale deed dated 06.07.2010.
2. It is averred that with a view to raise the construction of his residential
house, the petitioner had earlier applied for grant of building permission
on the aforesaid 882.75 sq.ft. before the Jammu Municipal Corporation
and after completion of all the requisite formalities the building
permission case of the petitioner was placed before the Building
Operations Control Authority for approval and sanction, who after
considering the no objection certificate from all requisite quarters and
after due verification of the title of the petitioner and in the light of no
objection certificates issued by Revenue and Nazool authorities, granted
permission to the petitioner vide order dated 24.04.2000 passed by the
respondent No. 2. However, the petitioner could not raise the
construction of his residential house in pursuance of the permission
granted within the period of its validity, as such, once again he applied
to the respondent No. 2 for revalidation and the request of the petitioner
was acceded to and permission granted was revalidated for three years in
pursuance of the order dated 18.09.2003, however, during this period
also the petitioner could not raise construction because of the third party
dispute raised by neighbor.
3. It is further averred that the petitioner once again approached the
respondent No. 2 to seek further extension of three years and the request
was again accepted and the building permission was further extended for
a further period of three years w.e.f. 17.09.2008 vide order dated
17.12.2008, however, the respondents asked the petitioner to file an
undertaking to the effect that if the learned civil court gave any adverse
judgment against the petitioner, the same could be abided by him, which
was submitted by the petitioner.
4. It is further averred that while the petitioner was making necessary
preparation to commence the building construction and was out of
station in connection with employment, he was informed that the
respondent No. 2 had trespassed on his land and started leveling the
same by using JCB and the fencing erected by the petitioner had been
dismantled, even nallah which existed towards the northern side of the
plot of the petitioner had been damaged. The petitioner rushed to the
respondents and met the then Commissioner, however, after having
failed to find any logical response from the then Commissioner and
threatening posture, the petitioner was constrained to file a suit for
permanent prohibitory injunction against the Jammu Municipal
Corporation and others seeking a decree restraining them from
interfering or causing any interference or damage to the property of the
petitioner and had also sought injunction against the respondents for
revoking, recalling or cancelling the building permission as the
respondent No. 2 had threatened to do so during the course of meeting
with the petitioner. In the suit, the learned trial court vide order dated
25.05.2010, directed the parties to maintain status quo and the moment
the order of status quo was served upon the respondents, i.e., on
26.05.2010, the respondent No. 2 immediately kept the building
permission granted in favour of the petitioner in abeyance on the ground
that there was some dispute between the petitioner and his neighbor
going on in the civil courts. It is averred that the petitioner challenged
the order of keeping the building permission in abeyance dated
25.05.2010 through the medium of OWP No. 1147 of 2010 but later on
the said writ petition has been withdrawn with liberty to file fresh, in
view of the settlement arrived at between the petitioner and his neighbor,
namely, Chaina Ram.
5. It is contended that vide order dated 09.04.2011, the court of learned 1 st
Civil Subordinate Judge (Municipal Magistrate), Jammu restrained the
Jammu Municipal Corporation and its officers from interfering in the
suit land till disposal of the main suit, subject to an undertaking that in
case the defendants succeed in proving their ownership over the disputed
land, the petitioner would immediately surrender the vacant possession
of the suit property, to which an appeal was preferred by the Jammu
Municipal Corporation before the learned 1 st Additional District Judge,
Jammu, which was dismissed by the appellate court vide order dated
30.08.2011. The respondents have also preferred the civil revision
petition against the order of appellate authority which too was dismissed
by the High Court vide order dated 22.12.2011.
6. It is further contended that while the petitioner was pursuing his remedy
before the civil court and had been granted an injunction against the
respondents by the trial court vide order dated 09.04.2011, the
respondent No. 2 informed the petitioner that he could not be allowed to
raise the construction as the building permission had since been kept in
abeyance and the petitioner reasoned with the respondent No. 2 that the
abeyance order has already become infructuous in view of the
compromise deed with the neighbor, however, the respondent No. 2
persisted without any logical reason. Therefore, the petitioner once again
approached the High Court for challenging the infructuous order dated
25.05.2010. The respondents were put to notice through Dasti service,
who on coming to know about filing of the writ petition, instead of filing
their response, immediately placed the matter before the Building
Operation Control Authority on 04.06.2011 and with a view to render
the aforesaid petition infructuous, issued order dated 25.07.2011
withdrawing the building permission granted in favour of the petitioner.
The petitioner challenged the aforesaid order dated 25.07.2011 through
the medium of OWP No. 1143/2011 and the High Court vide order dated
17.11.2011 partially allowed the petition by quashing the order dated
25.07.2011, however, the prayer of the petitioner for extending the
period of validity of sanction granted by the respondent No. 2 for the
period for which it remained in abeyance and incapable of being
operated, was not allowed. The petitioner was given liberty to file afresh
before the respondent authorities to seek permission for raising
construction on the land.
7. It is further contended that the petitioner submitted his fresh application
on 25.11.2011, however this time the petitioner applied for seeking to
raise the commercial construction, as the area where the land is situated
had been fully developed as commercial area and the Chief Town
Planner had also earlier written to the respondent No. 2 on 11.12.1999
that the land use of the area earmarked in the Jammu Master Plan is
commercial, where the petitioner's plot is located and recommended the
same.
8. It is contended that as per the provisions of Jammu Municipal
Corporation Building Bye-Laws, 2011, the petitioner became entitled to
raise the construction as per the plan submitted by him on account of
failure of the respondent No. 2 to take a decision in the matter of either
granting sanction or receiving the same under intimation to the
petitioner. Also, the petitioner with a view to deposit the building
permission fee made an application to the respondent No. 2 on
16.03.2012 requesting to intimate him about the exact building
permission fee so that he could commence his building operation,
however, this letter too has not been responded by the respondent No. 2.
The respondent No. 2 and his officers have told the petitioner that he
would not be allowed to raise any construction on the land on the ground
of deemed permission by operation of law. It is further contended that
the petitioner made further representations to the respondent No. 2
through email on 01.04.2012 and 02.04.2012, but there is no response.
Therefore, the petitioner is left with no other option but to approach this
Court.
9. The respondents have filed objections, whereby they resisted the petition
filed by the petitioner on the ground that the respondents have granted
building permission to the petitioner to raise a residential construction
vide order dated 24.04.2000 and the building permission was revalidated
thrice vide different orders and the latest building permission was
validated from 17.09.2008 for three years. It is further averred in the
objections that some dispute between the petitioner and one Chain Ram
was erupted, leading to filing of a complaint against the petitioner
regarding his ownership over the land before the respondents and after
receiving the complaint the respondents passed the order, which was
subject impugned in OWP No. 762/2011 and kept the permission in
abeyance. During investigation, it was found that the respondents are the
real owner of the land and the petitioner with the help of some forged
documents has succeeded in getting the building permission and after
coming to know that the petitioner is not the real owner of the land, the
building permission granted in favour of the petitioner was withdrawn
vide order dated 25.07.2011.
10. It is further averred in the objections that the petitioner has challenged
the order of withdrawal of permission before the High Court by filing a
writ petition being OWP No. 1143/2011 and vide order dated
17.11.2011 the Court decided the writ petition and quashed the order of
withdrawal of permission and directed the petitioner to apply afresh. The
petitioner had also filed a civil suit and the same is pending before the
learned Municipal Magistrate, Jammu, wherein the petitioner has sought
similar relief which the petitioner is seeking in the present writ petition.
Since the matter in controversy is directly called in question by availing
two different remedies, hence the petition deserved outright dismissal. It
is further averred that the BOCA has approved construction of boundary
wall, subject to the title verification and demarcation by the revenue
authorities, however, the petitioner never got title verification. Even, it
was again intimated to the petitioner through letter dated 12.04.2012 that
his case was placed before the BOCA and the authority has desired to
get the demarcation and title verification of the land and all the other
members of the authorities, i.e., CTP, TPO, PDD, S&D, PHE and Urban
Transport Environment Improve Committee have not issued no
objection certificates in favour of the petitioner and without the accent of
above said members the building permission cannot be acceded.
11. Further averred that after grant of permission it came to the notice of the
respondents that the petitioner is encroaching upon the Municipal land
which was in possession of the respondents and when the respondents
objected, the petitioner lodged a claim against the said land and also
relied upon the permission granted in his favour. In the khasra girdawari,
the respondents are mentioned as the real owner. The sale deed executed
between the petitioner and one Kesar Singh does not disclose the true
location of the property, khasra number is not mentioned and the vendor
Kesar Singh has also not disclosed his source of title over the land in
question and such type of transfer is not valid under Transfer of Property
Act.
12. Heard learned counsel for the parties.
13. Precise and only grievance projected by the petitioner is that he has
submitted the site plan of proposed construction on the land in question
along with application for building permission for raising commercial
construction along with the requisite documents including the title on
25.11.2011, but the authority has neither rejected nor accorded building
permission despite lapse of more than sixty days. It is averred that the
petitioner has acquired an indefeasible right of deemed sanction under
Regulation 7(3) of Control of Building Operations Regulations.
14. It is necessary to have a look at the provisions of Scheme. Regulation 7
of Control of Building Operations Regulations deals with grant of
building permission, the same is reproduced as under:-
"7. Grant of Permission (1) The Chairman of the Authority shall place the application and Building Plan alongwith the Inspector's report before the Authority for its consideration.
(2) The Authority shall either grant the permission subject to such conditions as may be specified or refuse to grant permission on such grounds as may also be specified and recorded.
(3) The Authority shall decide the matter within a maximum period of sixty days from the date of submission of the application and in case no decision can be taken within this stipulated period, the permission shall be deemed to have been accorded.
(4) In case the Authority refuses the grant of permission the grounds of such refusal shall be communicated to the applicant in writing within seven days from the date of the decision.
(5) The permission shall be issued only after the applicant deposits the building permission fees as approved by the competent authority."
15. Regulation 7(3) reproduced herein above, no doubt, envisages that the
authority is required to decide the application within a period of max. 60
days failing which, it creates an indefeasible right of deemed permission.
Regulation 8 provides that no permission shall be granted unless the
applicant has provided sufficient proof in support of his ownership of the
land. Section 5 of Control of Building Operations Act, 1988 provides for
making an application for permission as contemplated under Section 4 to
concerned authority.
16. In the present case, admittedly, the petitioner approached the
authority/respondent herein by submitting the site plan of proposed
commercial construction on 25.11.2011 which has been received by the
respondents' office on 1st December, 2011. In terms of the regulations
referred herein above the ownership over the land is prerequisite to get
building permission from the authority. The respondents vide letter dated
28.01.2012 have approved the case of the petitioner for raising
construction of boundary wall, subject to verification of title. It is the
case of respondents that vide letter dated 28.01.2012 the petitioner was
requested to get title verification, i.e., much before the expiry of max
sixty days in terms of Regulation 7(3) of Control of Building Operations
Regulations, but the petitioner, instead of answering the
queries/submitting the requisites as asked by the authority, has
approached this Court by filing the present writ petition. The petitioner,
therefore, has no indefeasible right of deemed permission merely on the
plea of expiry of sixty days period.
17. My view is fortified by the observation of the Hon'ble Apex Court in
case titled "Commissioner of Municipal Corporation, Shimla vs. Prem
Lata Sood and ors." reported as 2007(11) SCC 40. Relevant paras 36,
39 & 47 of the aforesaid judgment of the Apex Court is reproduced as
under:-
"36. Section 247 no doubt provides for a legal fiction specifying a period of sixty days, within which the application for grant of sanction of a building plan should be granted, but the said period evidently has been considered to be providing for a reasonable period during which such application should be disposed of. However, only because the period of sixty days has elapsed from the date of filing of application, the same by itself would not attract the legal fiction contained in Section 247 of the 1994 Act. When such an application is attended to and the defects in the said building plans are pointed out, there cannot be any doubt whatsoever that the applicant must satisfactorily answer the queries and/or remedy the defects in the building plans pointed out by the competent authority.
37. XXXXX
38. XXXXX
39. It is now well-settled that where a statute provides for a right, but enforcement thereof is in several stages, unless and until the
conditions precedent laid down therein are satisfied, no right can be said to have been vested in the person concerned. The law operating in this behalf, in our opinion is no longer res integra.
40. XXXXX
41. XXXXX
42. XXXXX
43. XXXXX
44. XXXXX
45. XXXXX
46. XXXXX
47. There cannot be any doubt whatsoever that an owner of a property is entitled to enjoy his property and all the rights pertaining thereto. The provisions contained in a statute like the 1994 Act and the building bye-laws framed thereunder, however, provide for regulation in relation to the exercise and use of such right of an owner of a property. Such a regulatory statute must be held to be reasonable as the same is enacted in public interest. Although a deeming provision has been provided in sub-section (1) of Section 247 of the 1994 Act, the same will have restricted operation. In terms of the said provision, the period of sixty days cannot be counted from the date of the original application, when the building plans had been returned to the applicant necessary clarification and/or compliance of the objections raised therein. If no sanction can be granted, when the building plan is not in conformity with the building bye-laws or has been made in contravention of the provisions of the Act or the laws, in our opinion, the restriction would not apply despite the deeming provision."
18. The judgments cited by learned counsel for the petitioner are
distinguishable to the facts of the case in hand.
19. In view of the facts and circumstances of the case discussed herein
above, this writ petition is disposed of with a direction to the petitioner
to approach the respondents' office to do the needful in terms of letter
dated 28.01.2012 (Annexure-B to the objections) within a period of two
weeks. Thereafter, the respondents are directed to consider the
application submitted by the petitioner dated 25.11.2011 seeking
building permission to raise commercial construction on the land in
question, within a further period of four weeks, of course under rules.
JAMMU (Tashi Rabstan)
23.05.2022 Judge
Pawan Angotra
Whether the order is speaking : Yes/No
Whether the order is reportable : Yes/No
PAWAN ANGOTRA
2022.05.23 16:13
I attest to the accuracy and
integrity of this document
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!