Citation : 2022 Latest Caselaw 743 j&K
Judgement Date : 9 May, 2022
HIGH COURT OF JAMMU AND KASHMIR AND LADAKH
AT JAMMU
Reserved on 20.04.2022
Pronounced on 09.05.2022
WP(C) No. 463/2022(O&M)
BGE MFB JV .....Appellant(s)/Petitioner(s)
Through: Mr. Abhinav Sharma, Sr.Advocate with
Mr. Abhimanyu Sharma, Advocate
vs
Union of India and others ..... Respondent(s)
Through: Mr. P. S. Chandel, CGSC
Coram: HON'BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
JUDGMENT
1. Dispute in the present petition is with regard to the project of national as
well as strategic importance regarding prestigious Udhampur-Srinagar-
Baramulla Rail Link project, as such, taking into consideration the
urgency involved, the matter was taken up for final consideration, with the
consent of both the sides.
2. In the present petition, the petitioner has prayed for following reliefs:
"(a) To direct the respondent to permit the petitioner to participate and bid
in the tender for „SLOPE STABILIZATION AT KATRA END OF ANJI
KHAD BRIDGE ON KATRA-DHARAM SECTION OF UDHAMPUR-
SRINGAR-BARAMULLA RAIL LINK PORJECT‟, by extending the
date of submission of e-bid;
(b) To direct the respondents not to proceed ahead with e-tender for
„SLOPE STABILIZATION AT KATRA END OF ANJI KHAD BRIDGE
ON KATARA-DHARAM SECTION OF UDHAMPUR-SRINAGAR-
BARAMULLA RAIL LINK PROJECT‟ till the date for submission of e-
bid is extended and the petitioner is permitted to participate for
submission of the e-bid and not to finalize the tendering process till such
time the date for submission of e-bid be extended;
(d) Direction against respondents directing them not to open the financial
bid of the tender till such time the petitioner makes its bid and the
technical bid of the petitioner is opened;
3. It is stated that the petitioner is a joint venture between M/s MFB Geotech
Pvt. Ltd. and M/s Bumi Geo Engineering LLC with MFB Geotech Pvt.
Ltd being the lead partner of the joint venture. The petitioner claims to
have executed successfully various projects including the projects of the
railway construction works of the respondents.
4. It is stated that the tender was floated by the respondent No. 3 for the
aforesaid project on 08.02.2022. The project cost was estimated to be a
sum of Rs. 58,17,89,503/- and the project required urgent execution of the
works within a period of five months. The tender also required the deposit
of earnest money of Rs. 30,59,000/- by the bidder. The bidding process
was to be conducted on and through the Indian Railways E-Procurement
System or the IREPS portal and the earnest money was to be deposited
only through the IREPS. The bidding process was to close on 04.03.2022
at 3.00 PM. The petitioner accordingly executed the transfer of earnest
money deposit of Rs. 30,59,000/- on 03.02.2022 by transferring the
amount from IDBI Bank to the SBIepay facility. The sum was deducted
from the account of the petitioner from IDBI Bank and transfer was
confirmed to be a „Success‟. Even after the successful transfer, on the
IREPS portal the status of the payment for earnest money deposit did not
go through and as a result thereof, the petitioner was unable to go through
with the process of submitting its bid. The IREPS portal was reflecting the
bank status as „failed‟ and the transaction status as „pending for
authorization‟. The petitioner addressed an email to respondent No. 3 at
3.41 am in night of 03.03.2022 and in the early morning 04.03.2022
pointing out that while its bank indicated the transfer to be a "Success",
the IREPS portal was not reflecting the correct payment status. A request
was also made that in view of this technical error at the end of the
respondents, the time for making the bid ought to be extended. The
petitioner received a response to its email from the respondents at 11.47
am on 04.03.2022 wherein the petitioner was advised to get in touch with
the IREPS Help Desk and the petitioner was also intimated by the
respondents that there is no change in tender conditions. The petitioner
accordingly, telephonically contacted the IREPS Help Desk in the
morning of 04.03.2022 but the IREPS instead of resolving the issue,
directed the petitioner to consult the SBIepay facility to address the
technical glitch. It is further stated that in the meantime, the petitioner
effected a second transfer of the earnest money deposit of Rs. 30,59,000/-
in the morning of 04.03.2022. This amount was also deducted from the
account of the IDBI Bank account of the petitioner and the transfer receipt
indicated the transfer to be successful but this time also, the payment did
not go through and the IREPS portal continued to reflect that the payment
of earnest money deposit is pending. The transaction tracking report
indicated that the transaction is pending authorization at the end of
SBIepay. The petitioner wrote another email to the respondent No. 3 at
1.59 PM on 04.03.2022 reporting that even the second transfer of the
earnest money deposit is not being successfully recorded and reflected in
the IREPS portal. Considering the situation another request was made to
extend the time for making the bid which was now to expire within an
hour. The respondent No. 3 failed to resolve the issue or extend the time
for making the bid. The petitioner also wrote a letter to the respondent No.
3 on 04.03.2022 narrating the circumstances and in view of the
importance of the project, it was again requested that the timeline for
making the bid ought to be extended to enable the petitioner to put in its
bid. However, the respondents failed to consider the request of the
petitioner. Narrating these facts, the petitioner has approached this Court
for extension of the time for making bid on the grounds that the petitioner
has been unable to participate and bid for the project for none of its fault,
lapse or negligence but a glitch and/or lapse at the end of the respondents
and/or its payment facilitator. It is further submitted that the project is
being executed using public funds and resources and it is vital that it be
executed in the most cost effective and efficient manner, which in turn
would require the participation of maximum number of entities in bidding
process and make available their expertise and competence for the project.
It is further averred that the denial to participate in the bid is not only a
loss for the petitioner as it violates the right and legitimate expectation of
the petitioner but also is a loss for the State which is deprived of the true
and fair competition to ensure the best possible execution of the project. It
is further stated that the State is enjoined to not only ensure that there is
parity and fairness in the treatment of all participating bidders, but also
that the right to participate in a bid and particularly a project of public
importance is not unfairly curtailed. The petitioner has placed on record
the tender documents, the receipts regarding the payment made by the
petitioner and the various communications to demonstrate that the
petitioner had been making efforts for participating in the bid well before
the close of bidding process.
5. Response stands filed by the contesting respondent Nos. 2 and 3, in which
it has been stated that as per clause 5.3, the bidder was required to register
himself with IREPS and the detailed IREPS manual and procedure for e-
tendering was available on Indian Railway website. For participating in
the tendering process, the bidder as per clause 11.0 was required to
furnish earnest money deposit of Rs. 30,59,000/- to be submitted through
online payment mode available on IREPS Portal only and the petitioner
failed to deposit the earnest money at the time of submission of the bid as
such the petitioner cannot be considered for participation in the tendering
process by extension of time. It is also stated that the bidding process was
to start from 08.02.2022 and last date for submission of the bid was fixed
as 04.03.2022 up to 15:00 hours and clause 9.0 provides for time for
opening of the bid(Technical bid) on 04.03.2022 at 15:30 hours and clause
11.0 provides that the earnest money to the tune of Rs. 30,59,000/- has to
be submitted through online payment modes on IREPS portal only. It is
also stated that the IREPS (Indian Railways E-Procurement System)
portal belongs to the Indian Railways and as per the Ministry of Railway
guidelines all the tenders for execution of works are to be invited through
IREPS portal only. It is further stated that just like the petitioners, the
answering respondents are also users of the IREPS portal. It is also
averred that the petitioner did not deposit the earnest money from
18.02.2022 till 02.03.2022 and waited till the fag end. The amount so
transferred by the petitioner through its bank has not been credited into
the account of answering respondents till date which is substantiated by
the statement of the accounts maintained by the answering respondents
which is linked with the IREPS portal. It is also stated that the emails
written by the petitioner were duly replied by the answering respondents
and the petitioner was informed that the issue with respect to payment
failure is related to its bank account and same may be dealt with by its
bank and the petitioner was further requested to contact the IREPS help
desk. The respondents have further stated that other successful bidders
also made the payments on 02.02.2022 at 12:12 hours, on 03.03.2022 at
17:07 hours and on 04.03.2022 at 12:58 hours which would substantiate
the fact that the failure in making payment is not on the part of the IREPS
or its bank but on the part of the petitioner‟s bank. The respondents have
also stated that the petitioner right from the very beginning had every
intention to stall the smooth functioning of the tendering process as
number of times requests were made by the petitioner to extend the date
of submission of the bids,so as to enable the petitioner to participate in the
tendering process.
6. Precisely the stand of the respondent Nos.2-3 is that there was no fault on
the IREPS portal and the fault, if any, was with the petitioner and it‟s
bank and further the petitioner right from the very beginning intended to
stall the implementation of the project by making requests for extension of
time for making bid.
7. The petitioner in response to the objections filed by the respondents filed
a supplementary affidavit, in which besides reiterating the submissions
made in the main writ petition, stated that the respondents through one Sh.
Girish from IT department provided „any desk‟ screen sharing facility to
facilitate the transaction and despite the efforts on the part of the
petitioner, the petitioner could not participate in the tendering process.
The petitioner has also mentioned about the emails addressed to the
respondents and the email on 04.03.2022 addressed by the SBI Branch
Gurgaon to Delhi Branch. In a supplementary affidavit, the petitioner has
pleaded about the efforts made by him to participate in the tendering
process and further that the fault was with the respondents, IREPS portal
and SBIepay service provider/associate channel partner.
8. The respondents in response to the supplementary affidavit besides
reiterating their earlier stand, pleaded that the first part of the tender
pocket system namely technical bid was opened on 04.03.2022 at 3.49
hours and now the petitioner cannot be granted any second chance for
participating in the tendering process particularly when the other bidders
successfully placed their bids on 02.03.2022, 03.03.2022 and 04.03.2022
and also that because of the interim direction dated 09.03.2022, the
execution of national project Udhampur-Srinagar-Baramulla Rail Link
Project has been badly affected. It is also stated that the respondents have
been paying annual service fee of Rs. 31,33,080/- per annum for
maintenance of IREPS and using IREPS portal since 2016 and till date
more than 1800 tenders have been floated through IREPS portal but no
complaint has ever been received and rather the earnest money deposit
was credited into the account of IREPS portal by the other bidders on
03.03.2022 and 04.03.2022 speaks the volume that there was no error on
the IREPS portal as alleged by the petitioner.
9. The respondents have also placed on record the various emails as also the
communication dated 18.02.20221 and 22.02.2022 addressed by the
petitioner to the respondents and also the Refund Policy of SBIepay as
annexure-VI.
10. Mr. Abhinav Sharma, learned senior counsel appearing for the petitioner
has vehemently argued that the petitioner had paid the earnest money
deposit of Rs. 30,59,000/- twice but because none of the fault of the
petitioner, the petitioner has been deprived of its right to participate in the
tendering process and rather the fault was lying with the IREPS portal or
with SBIepay that the petitioner could not participate in the bidding
process because of non-payment of EMD. He further argued that the
public interest would be served if there is wide participation of the bidders
in the tendering process.
11. Per contra, Mr. P. S. Chandel, learned Central Government Standing
Counsel has vehemently argued that the respondents 2 and 3 did not
receive any amount from the petitioner as is evident from the account
statement placed on record by the respondents and further once the
petitioner did not deposit the earnest money deposit, it has no right to
participate in the tendering process and further because of the project
being of national importance, the time limit of the tender cannot be
extended, so as to enable the petitioner to participate in the same more
particularly when the technical bid stands already opened on 04.03.2022
at 3.49 PM.
12. Heard and perused the record.
13. The respondent Nos. 1 to 3 had floated the tender No. KR-PD-JK-SST-
ANGI-02-2022 for Slope Stabilization at Katra end of Anji Khad Bride on
Katra-Dharam section of Udhampur-Srinagar-Baramulla Rail Link
Project, Jammu and Kashmir on 08.02.2022. The bidding system was two
pocket system. The date and time of uploading the tender was fixed as
08.02.2022 and tendering closing time was fixed as 04.03.2022 at 1500
hours. The period of the completion of the tender was fixed as 05 months
and further the estimated value of the project was Rs. 58,17,89,503/- and
the bidders were required pay an earnest money deposit of Rs. 30,59,000/-
for participation in the tendering process.
14. As per condition No. 17 of the instructions of the tender, the tenderer was
required to deposit Rs. 30,59,000/- towards earnest money with the tender
and further condition No. 17.03 of the tender provides that the tender
received without earnest money in the prescribed format and value as
specified in the tender document shall be summarily rejected. As per
condition No. 17.7 payment of earnest money deposit in respect of e-
tendering should be submitted through online payment modes available on
IREPS portal only and Fixed Deposit Receipt/Demand Draft etc, were not
to be accepted as earned money deposit for tenders invited on IREPS (e-
tender portal). As per the NIT, the bids were to be submitted online on
IREPS portal. As per condition No. 17.8 proof of the transaction towards
payment of earnest money through online payment mode was required to
be scanned in PDF format and uploaded during the online submission of
the e-bid not later than the prescribed date and time or e-bid submission.
Thus, the payment of earnest money was sine qua non so as to enable the
bidders to participate in the bidding process. The contention of the
petitioner is that the petitioner twice transferred the amount i.e. on
03.03.2022 and 04.03.2022 but these transactions were shown as pending
for authorization on the IREPS portal. So far as the receipt regarding the
transfer of earnest money placed on record by the petitioner are
concerned, the same are the screenshots of „IDBI e-banking: view
approval queue‟, as is evident from page No. 227(Annexure-V). It is also
evident that the respondent Nos. 1 to 3 provided all possible help to the
petitioner,so as to enable the petitioner to participate in the tendering
process as is evident from the admission made by the petitioner that any
desk facility was provided to the petitioner but still the petitioner could
not participate in the tendering process.
15. Further e-mail dated 04.03.2022(Page-241) reveals that the SBIepay has
already confirmed that this is a failed transaction and the funds pertaining
to the said transaction will be credited back to the originator account by
the end of the day i.e. on 07.03.2022. The failed transactions are not
unknown in banking business as is evident from Refund Policy of
SBIepay (annexure-VI).A perusal of the Annexure IV (Page-54) placed
on record by the respondents along with their objections, regarding
earnest money deposit report reveals that three bidders have successfully
made the payment of earnest money deposit on 02.03.2022 at 12:12:59
hours, on 03.03.2022 at 17:07:38 and on 04.03.2022 at 12:58:43 hours.
16. The petitioner too claims to have transferred the amount on 03.03.2022
and 04.03.2022 i.e. the dates on which the other bidders have already
made the payment. Besides the petitioner, there is no complaint by anyone
with regard to the inability in making the payment of earnest money
deposit. Had there been any technical glitch either on the portal of IREPS
or SBIepay, that was the channel partner of the IREPS, then certainly
there would have been other complaints as well and it seems that the
glitch/lapse, if any, was either on the part of the petitioner or on the part of
its bank. The petitioner has not been able to demonstrate that the fault was
on the part of IREPS portal or with SBIepay, that prevented the petitioner
from participating in the tendering process.In MHADA v. Shapoorji
Pallonji & Co. (P) Ltd., reported in (2018) 3 SCC 13,the Apex Court has
observed that the generation of acknowledgments in respect of other
bidders and the absence of any glitch in the technology would strongly
indicate that the bid submitted by the first respondent was not a valid bid.
17. It requires to be noted that the timeline fixed for submission of bids is
very crucial for the timely completion of any project and the project in
question is a project of national as well as strategic importance and
permitting the petitioner to participate in the tender process by extending
the time would mean the retendering of the project by the Court
particularly when the technical bids stand already opened on 04.03.2022
and it would amount to giving second opportunity to the petitioner which
is not permissible. In MHADA v. Shapoorji Pallonji & Co. (P) Ltd.,
reported in (2018) 3 SCC 13,the Apex Court has further observed that the
directions issued by the High Court in favour of the first respondent
virtually confer on the said respondent a second opportunity, which
cannot be countenanced.
18. It is not the case where the petitioner has not been treated equally along
with other bidders and also there are no allegations of mala fide or
arbitrariness on the part of the respondent Nos. 2-3 and rather there is
admission on the part of the petitioner that the officials of the respondent
Nos. 2-3 rendered assistance to the petitioner so as to enable the petitioner
to participate in the tendering process. The petitioner was provided equal
opportunity to participate in the tendering process but the petitioner could
not successfully pay the EMD, that was a pre-requisite for participation in
the tendering process for one reason or another but not attributable to the
respondents. In National High Speed Rail Corpn. Ltd. v. Montecarlo
Ltd., 2022 SCC OnLine SC 111, the Supreme Court has observed as
under:
95. Even while entertaining the writ petition and/or granting the stay which ultimately may delay the execution of the Mega projects, it must be remembered that it may seriously impede the execution of the projects of public importance and disables the State and/or its agencies/instrumentalities from discharging the constitutional and legal obligation towards the citizens. Therefore, the High Courts should be extremely careful and circumspect in exercise of its discretion while entertaining such petitions and/or while granting stay in such matters. Even in a case where the High Court is of the prima facie opinion that the decision is as such perverse and/or arbitrary and/or suffers from mala fides and/or favouritism, while entertaining such writ petition and/or pass any appropriate interim order, High Court may put to the writ petitioner's notice that in case the petitioner loses and there is a delay in execution of the project due to such proceedings initiated by him/it, he/they may be saddled with the damages caused for delay in execution of such projects, which may be due to such frivolous litigations initiated by him/it. With these words of caution and advise, we rest the matter there and leave it to the wisdom of the concerned Court(s), which ultimately may look to the larger public interest and the national interest involved.
19. It requires to be noted that the petitioner on 22.02.2022 wrote to the
respondent Nos. 2 to 3 for extending the date for submission of bids by at
least three weeks i.e. up to 25.03.2022 so as to enable the petitioner to
participate in the tender and in the said e-mail, it has been mentioned by
the petitioner that the petitioner needs some more time (pandemic
situation due to Omicron) for joint venture formalities and compliance
like apostille etc. The petitioner has not denied the said communication
which further gives credence to the contention of the respondent Nos.2 to
3 that the petitioner right from the very beginning wanted the extension of
time for participation in tendering process.
20. As such, this Court does not find any illegality, arbitrariness and mala fide
on the part of respondent Nos. 2 and 3 in continuing with the tendering
process to the exclusion of the petitioner, by not extending the period for
making bid. The petitioner cannot be allowed to participate in tendering
process by extending the time for making bids because any delay in the
completion of project would not be in the public interest particularly in
view of the fact that the project was required to be completed in five
months.
21. In view of all what has been discussed above, the present petition has no
merit, as such, the same is dismissed.
(Rajnesh Oswal) Judge JAMMU 09.05.2022 Rakesh Whether the order is speaking: Yes/No Whether the order is reportable: Yes/No
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!