Citation : 2021 Latest Caselaw 1464 j&K
Judgement Date : 15 November, 2021
Sr. No. 18
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
CJ Court
Case: OWP no. 1863 of 2017
Building Operation Controlling Authority .....Appellant/Petitioner(s)
Through :- Sh. Harshwardhan Gupta, Advocate.
v/s
Koushalya Devi and others .....Respondent(s)
Through :- Sh. Rahul Bharti, Senior Advocate with
Ms. Mrinal Jain, Advocate.
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE MOHAN LAL, JUDGE
ORDER
1. Heard Sh. Harshwardhan Gupta, learned counsel for the petitioner and
Sh. Rahul Bharti, senior counsel assisted by Ms. Mrinal Jain, learned counsel
for the respondents.
2. The respondents were served with a show-cause notice dated 31.12.2012
by the Building Operation Controlling Authority under Section 7(1) of the
Jammu and Kashmir Control of Building Operation Act, 1988 (for short 'the
Act') to show-cause as to why the violations as detailed above should not be
demolished. The violations detailed above are to the effect that the respondents
have "laid the slab of one room over the existing walls during odd hours".
3. The said show-cause was followed by an order dated 07.01.2013 passed
by the Joint Commissioner (A), Municipal Corporation Jammu under Section
7(3) of the Act stating that as the respondents have laid slab of one room over
the existing walls without the permission of the Jammu Municipal Corporation,
therefore, the said construction/the slab of one room is directed to be
demolished within five days failing which it will be demolished by the Jammu
Municipal Corporation at the risk of the respondents.
4. The above order passed under Section 7(3) of the Act was assailed by
the respondents by filing appeal before the Jammu and Kashmir Special
Tribunal, Jammu. The Tribunal has allowed the appeal by the impugned
judgment and order dated 06.04.2016 and has compounded the construction @
Rs.50/- per sq.ft.
5. Aggrieved by the aforesaid judgment and order, the Building Operation
Controlling Authority, Jammu Municipal Corporation has preferred this
petition after more than one and a half years of the order contending that the
appeal of the respondents was not within time and that the Tribunal could not
have compounded the constructions as they were major in nature.
6. Notwithstanding the fact that the petition was preferred belatedly, as the
same was entertained and the response was called, we do not consider it
appropriate at this stage to dismiss it on the ground of delay or laches.
7. The order under Section 7(3) of the Act was passed on 07.01.2013 and it
is said to have been served by pasting it on the conspicuous place of the
building on 11.01.2013. The appeal was preferred on 31.01.2013. The time
limit for filing appeal as provided under the Act is within seven days from the
date of order. Thus, apparently the appeal was not preferred within seven days
of the order.
8. The question of preferring the appeal within seven days of the order
would not arise if the order is not brought to the notice of the concerned party,
therefore, in all fairness, the limitation for filing the appeal would
commence/run from the date of the service of the order or the knowledge of the
order.
9. The service of the order is alleged to be on 11.01.2013 on which date the
order was pasted on the wall. The endorsement of pasting of the notice on the
wall as per the report of the process server does not contain any independent
witness, in the absence of which the said pasting does not stand to be proved,
more particularly, when it is disputed.
10. On the other hand, senior counsel for the respondents alleges that the
copy of the said order was served upon him on 29.01.2013.
11. The appeal was filed on 31.01.2013 i.e. within two days of the
service/knowledge of the aforesaid order.
12. In view of the facts and circumstances, we are not inclined to accept the
argument that the appeal was not filed within time or that there was any willful
or deliberate delay on part of the respondents in filing the appeal.
13. Now coming to the second aspect of the matter that the constructions of
the respondents were major in nature and could not have been compounded, we
find that the show-cause notice, the order dated 07.01.2013 or even from the
report of the Khilafwarzi Officer does not reveal that the petitioners ever stated
that the constructions are of such a nature that they would fall within the
definition of the major constructions and as such would not be compounded.
14. It is also nowhere alleged that the respondents have raised constructions
without leaving the requisite set-backs or by violating the height of the building
as permitted under the bye-laws.
15. In the absence of such an averment and in the light of Regulation 11(2)
of the Jammu and Kashmir Control of Building Operation Regulations, 1998,
we are of the view that there is no basis to allege that the constructions are of a
major nature and are not liable to be compounded.
16. The writ petition is bereft of merits and is dismissed.
(MOHAN LAL) (PANKAJ MITHAL)
JUDGE CHIEF JUSTICE
JAMMU
15.11.2021
Raj Kumar
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!