Avtar Singh and another
Satpal Sharma and ors ... Petitioner(s)
Through: - Mr. Parveen Kapahi Advocate in LPA
No. 236/2019
Mr. Vikas Magotra and Mr. Sachin Sharma
Advocates in LPA No. 284/2019
Vs.
State and ors ...Respondent(s)
Through: - Mr. Rajnish Raina Advocate for
R-2 to 4.
Mr. Pranav Kohli Sr. Advocate with Mr. Arun
Dev Singh Advocate for R-5
CORAM: HON'BLE MR. JUSTICE SANJEEV KUMAR, JUDGE
HON'BLE MR JUSTICE SANJAY DHAR, JUDGE
JUDGMENT
Sanjeev Kumar-J
1 By a common order and judgment dated 19.09.2019, two writ
petitions i.e OWP Nos. 494/2018 and 929/2018, one filed by Avtar
Singh and Vinod Sharma and the other filed by Satpal Sharma and
three others, have been dismissed by a Single Bench of this Court.
Feeling dissatisfied and aggrieved, the writ petitioners have filed two
separate Letters Patent Appeals i.e LPA Nos. 236/2019 and 284/2019
which are being disposed of by this common order and judgment.
2 Before we advert to the grounds of challenge urged by the
appellants (writ-petitioners), we deem it appropriate to give brief
resume of factual antecedents, leading to filing of these appeals.
3 The dispute, which was subject matter of adjudication in the twin
writ petitions, relates to a building being House No. 1, Pacca Danga,
Jammu. The appellants before us are the old tenants in the shops on the
ground floor of the said building which is owned by respondent No.5.
As per the appellants, respondent No.5 for the past some time had been
pressing upon them and other tenants in the building to vacate the
premises under their occupation, so that he could rent out these shops to
the new tenants for higher premium and rentals. Having failed to coerce
the appellants into vacation of the said shops under their tenancy,
respondent No.5 devised a plan to get rid the tenants of the shops. As is
the allegation of the appellants, the respondent No.5 in connivance with
the District Administration and the Jammu Municipal Corporation (for
short 'JMC') Authorities managed to declare the whole building in
which the shops under occupation of the appellants are housed as
unsafe. This was done by the Commissioner, Jammu Municipal
Corporation vide his order No. JM/PS/Com./1640 dated 06.11.2017
whereby the Commissioner granted permission for demolition of the
said building and, as a consequence whereof, the Executive Engineer,
JMC, Division Trikuta Complex, Dogra Hall, Jammu vide a public
notice No. MJ/Tech/T/4636 dated 27.02.2018 notified to all the
occupants of the aforesaid building including the appellants herein to
vacate the premises under their occupation within 15 days so that the
operation of demolishing the existing building is carried out on behalf
of the Commissioner, JMC, Jammu.
4 Faced with the aforesaid public notice, the appellants herein filed
two separate writ petitions seeking, inter alia, a Writ of Certiorari for
quashing the order of the Commissioner, JMC Jammu dated
16.11.2017 (supra) and a public notice dated 27.02.2018 (supra) issued
by respondent No.4. They also sought a Writ of Mandamus declaring
the aforesaid building which houses the shops under their tenancy as
safe or at least safe with respect to the shops under the occupation of
the appellants. The appellants also sought a direction to the respondents
not to demolish the said building.
5 The impugned action of JMC was assailed primarily on the
following grounds:
(i) That the impugned notification issued by respondent No.2 and a public notice issued by respondent No.4 are bad in the eye of law, in that, they have been issued without adopting due process of law;
(ii) That the decision to declare the building as dangerous and unsafe has been taken by the Municipal Authorities at their back, in that, they were never associated with any inspection claimed to have been undertaken by the said Authorities to asses the condition of the building;
(iii) That the building where the source of livelihood of the petitioners i.e shops are situated, has been declared unsafe by the Municipal Authorities without serving upon them any prior notice and, therefore, they were deprived of a fair opportunity of being heard; and
(iv) That the decision to declare the aforesaid building unsafe has been taken by the Municipal Authorities not on the basis of any relevant material, but only to give wrongful benefit to respondent No.5 and to enable him to throw out the appellants from the shops under their tenancy without following the due process of law. The action of the Municipal Authorities is, therefore, vitiated by arbitrariness and mala fides.
6 The writ petitions were resisted not only by the JMC, but
also by respondent No.5. In the objections filed by JMC, it was
contended that the building was declared unsafe after following due
process. The building was got inspected from the experts and it is in
pursuance of the report received from the concerned Executive
Engineer on 27th October 2017, the building was declared unsafe
and the order was conveyed to the owner. Since owner of the
building i.e respondent No.5 had shown reluctance to undertake the
demolition operation, accordingly, an estimate was prepared by the
Municipal Authorities and an intimation was given to respondent
No.5 to deposit the estimated amount. Respondent No.5 complied
with the orders and the amount was deposited by him. Similarly, it
was the stand of respondent No.5 before the Writ Court that the
building, which has been declared unsafe, was constructed more
than 100 years back and was in dilapidated condition for the last
several years. Some portion of the ground floor was repaired in the
year 1974 and that was also more than four decades back. It was
pleaded that since the building had become the potential hazard, not
only for the inmates of the building, but also to the neighbouring
structures and passers-by, as such, an application was moved before
the JMC. The inspection was conducted by the expert Engineer of
the JMC and a decision on the basis of technical advice was taken
by the competent authority to demolish the aforesaid building.
7 The writ Court having considered the rival versions and
perused the record, came to the conclusion that there was no legal
infirmity in the decision of the Jammu Municipal Corporation
declaring the building unsafe and, accordingly, vide order and
judgment impugned, dismissed both the writ petitions. While
dismissing the writ petitions, the Writ Court also expressed hope
that the Jammu Municipal Corporation would carry out some
exercise to find out if there were more such dilapidated buildings in
the city which posed danger to the lives of the people living therein
or in the neighbourhood thereof and take appropriate steps to
prevent any untoward incident. It is this common order and
judgment of the Writ Court which is assailed in these appeals.
8 Having heard learned counsel for the parties and perused
the record produced by Mr. Rajnish Raina, learned counsel
representing the JMC, it is necessary to first set out the provisions of
Section 258 of the Jammu and Kashmir Municipal Corporation Act,
2000 (for short 'the Act').
"258. Restrictions on user of buildings and removal of dangerous buildings:
(1) No person shall, without the written permission of the Commissioner, or otherwise than in conformity with the conditions, if any of such permission;
(a) use or permit to be used for human habitation any part of a building not originally erected or authorized to be used for that purpose or not used for that purpose before any alteration has been made therein by any work executed in accordance with the provisions of this Act and of the bye-laws made thereunder ;
(b) change or allow the change of the use of any land or building;
(c) convert or allow the conversion of one kind of tenement into another kind.
(2) If it appears to the Commissioner at any time that any building is in ruinous conditions, or likely to fall, or in any way dangerous to any person occupying, resorting to or passing by such building or any other building or place in the neighborhood of such building, the Commissioner may, by order in writing, require the owner or occupier of such building to demolish, secure or repair such building or do one or more of such things within such period as may be specified in the order, so as to prevent all cause of danger therefrom.
(3) The Commissioner may also, if he thinks fit, require such owner or occupier by the said order either forthwith or before proceeding to demolish, secure or repair the building so set up a proper and sufficient board or fence for the protection of passers-by and other person, with a convenient platform and hand rail wherever practicable to serve as a footway for passengers outside of such board or fence.
(4) If it appears to the Commissioner that danger from a building which is in a reunions condition or likely to fall is imminent, he may, before making the order aforesaid fence off, demolish, secure or repair the said building or take such steps as may be necessary to prevent the danger.
(5) If the owner or occupier of the building does not comply with the order within the period specified therein, the Commissioner shall take such steps in relation ot the building as to prevent all cause of danger therefrom.
(6) All expenses incurred by the Commissioner in relation to any building under this section shall be
recoverable form the owner or occupier thereof as arrears of tax under this Act".
9 From a reading of Section 258 (2) of the Act, it is evident
that the Commissioner, JMC, if it appears to him at any time that any
building is in a ruinous conditions, or likely to fall, or in any way
dangerous to any person occupying, resorting to or passing by such
building or any other building or place in the neighbourhood of such
building, may, by order, require the owner or occupier of such building
to demolish, secure or repair such building or do one or more of such
things within such period as may be specified in the order so that all
cause of danger emanating therefrom is prevented. It is, thus, not in
dispute that the competent authority to take such decision is the
Commissioner of Municipal Corporation concerned and the decision
must be in writing and after making an objective assessment with
regard to the condition of the building. Order for demolition of the
building shall be made only, if the Commissioner, on the basis of
material before him is of the view that the building is in ruinous and
dangerous condition which, if not demolished, may fall and cause loss
to the life and property of the inmates and those living in the
surrounding thereof. Neither the owner, nor the occupier of such
building can resist such action by the Municipal Corporation, unless the
decision of the Commissioner is perverse or made for oblique purpose.
Since the decision to declare a building unsafe and liable to be
demolished is a decision of technical nature and can be taken by the
authority concerned on the basis of expert opinion, as such, the same
may not be amenable to challenge in the writ jurisdiction, for, this
Court, while exercising its extraordinary jurisdiction under Article 226
of the Constitution does not sit in an appeal over the decision of the
authorities based upon expert opinion. This Court does not have any
wherewithal to find out, as to whether, on the basis of material
considered by the competent authority, a particular building ought or
ought not to have been declared unsafe. Unless the Court finds a
decision arbitrary, perverse or mala fide, the same shall not be
interfered with in the exercise of writ jurisdiction. The contours of
power of this Court under Article 226 of the Constitution are now well
defined and need no elaborate debate.
10 In the aforesaid backdrop, when we examine the case on
hand, we do not find that the decision of the Municipal Authorities to
declare the building unsafe is either arbitrary or perverse. We also do
not find any arbitrariness in the decision making process. On the other
hand, from a perusal of the record, we find that before declaring the
aforesaid building unsafe, a Committee of experts headed by Executive
Engineer of JMC conducted the inspection of the said building and
reported that the building was unsafe and too old to be repaired. It is apt
to reproduce the technical report submitted by the Executive Engineer
concerned after inspection of the building which is reproduced as
under:
"As per the letter of Deputy Commissioner, Jammu received from higher authorities of Municipal Corporation after visiting the site of above said work, it has been seen that the building is totally unsafe as it is too old to repair. The over all condition of building is worsed and it may
collapse at any time and may damage the surrounding structures and also may cause loss of lives because it is very crowded place.
Keeping in view the above mentioned facts the estimate has been framed for accord of administrative approval."
11 It is true that the process for declaration of the building as
unsafe was initiated by the Municipal Corporation on the bidding of
Additional Deputy Commissioner, Jammu, who vide his
communication dated 29th August 2017 called upon the Municipal
Commissioner to look into the matter in the light of report furnished by
the Executive Engineer PWD (R&B) Construction Division-II Jammu
certifying that the building belonging to respondent No.5 i.e House No.
1, Pacca Danga, Jammu was unsafe and that there was every
apprehension of the building crumbling down any time resulting into a
mishap in and around the building premises. However, the
Commissioner, JMC did not pass the order on the basis of aforesaid
communication of the Additional Deputy Commissioner, Jammu, but
instead, asked the Executive Engineer and the Assistant Executive
Engineer concerned to inspect the building and report about its
condition. It is only after receiving the technical report from the
concerned Engineering Division of the Municipal Corporation, the
action was approved by the Commissioner on 06.11.2017. Accordingly
a formal order was issued by the Joint Commissioner (Works),
Municipal Corporation, Jammu on 10.11.2017 directing the owner of
the building to dismantle/demolish the same within a period of one
month. This is followed by a public notice which is impugned in both
the writ petitions.
12 The contention of learned counsel for the appellants that
the decision to declare the building unsafe was taken by the
respondents at their back is without any substance and deserves to be
rejected for the reason that Section 258(2) of the Act does not cast any
such obligation on the Commissioner to provide an opportunity of
being heard to the owner or the occupier of the building, sought to be
declared unsafe, nor given the nature of power given to the
Commissioner under Section 258 of the Act, the compliance with the
principles of nature justice before declaring a building unsafe could be
inferred. Otherwise also, in the instant case, the appellants, who are in
occupation of the shops as tenants, have been given ample opportunity
to put up their case.
13 It is true that the inspection preceding the decision taken
by the Municipal Corporation was without formally associating the
appellants in the process, but, later on, when the Commissioner
appointed by this Court, visited the spot for inspection, all the
imamates of the building including the appellants herein had been
intimated well in advance. The Writ Court has rightly declined to
accept the plea of the appellants that they have been condemned
unheard by the Municipal Authorities. To the similar effect is meritless
the plea of the appellants that the Commissioner passed the order in a
mechanical manner, in that, he did not consider or explore the
possibility of safeguarding the building by effecting necessary repairs.
But, for the material on record which unequivocally suggests that the
building as a whole is unsafe and is too old to be repaired, we could
have accepted this plea of the appellants.
14 As has come on record, the building is 100 years old and
the ground floor of the same was repaired somewhere in the year 1974
i.e more than four decades back and has developed cracks all around.
Not only the Engineering Division of the Municipal Corporation, but
also the Commissioner appointed by this Court twice, that too, of the
rank of Superintending Engineer has reported that the building is
ruinous and dangerous and poses threat to the life and property of the
inmates and those living in surrounding thereof . As we have observed
hereinbefore, we, in the exercise of writ jurisdiction, cannot sit over a
judgment of experts and the view of the experts, unless it is tainted by
mala fides or is based on no material, is required to be respected and
given effect to. This is exactly what has been done by the Municipal
Corporation Authorities.
15 We have perused the report submitted by the Executive
Engineer, PWD (R&B) Construction Division-II, Jammu to the
Additional Deputy Commissioner, Jammu, report submitted by the
Engineering Division of Municipal Corporation and the report by the
expert Dinesh Kumar Rampal, Superintending Engineer, who inspected
the building as a Court Commissioner and all these reports
unequivocally substantiate the fact that the building in question is
indeed unsafe and dangerous and if not pull down in time, may fall
down, causing immense loss to the life and property of the inmates of
the building and also those living in surrounding thereof.
16 Learned counsel for the appellants vehemently urged us to
critically examine the aforesaid reports to find out inherent
contradictions in the findings returned by the different experts. We are
afraid, we cannot do such exercise and deem it better to leave to the
domain experts. We are also not persuaded to accept the argument of
learned counsel for the appellants that the whole exercise culminating
into issuance of impugned public notice is vitiated by mala fide, in
that,the building has been declared unsafe only at the instance of
respondent No.5 to throw out the tenants from the building, otherwise
than in due course of law.
17 We shall be failing in our duty if we do not deal with the
judgment of Delhi High Court in the case of Municipal Corporation
of Delhi vs Hukam Chand Jain, (1970) 6 DLT 165 relied upon by the
learned counsel for the appellants. In the said judgment, the order of
demolition passed by the Commissioner was found fault with by the
High Court on the ground that there was no indication in the order as to
whether the notice should have been for demolition or securing or
repairing the building, the three alternatives provided in the Section for
preventing danger.
18 The aforesaid judgment is not applicable to the facts of the
instant case. This is so, because in the instant case, there is ample
material on record to indicate that the whole building is unsafe and
liable to be demolished. The different reports submitted by the experts
from time to time only indicate towards this fact. It is on the basis of
these reports, the Commissioner has taken a decision to demolish the
building, rather than securing the same by repairs.
19 It would be appropriate to wind up the controversy raised in
these appeals by having reference to a judgment of the Bombay High
Court passed in the case of the Commissioner, Thane Municipal
Corporation and ors vs. Jayantilal Dharmaji Sharma and orders
(Writ Petition No. 8706 of 2018, decided on 01.07.2019). A Single
Bench of Bombay High Court, in the aforesaid case was dealing with
the provisions of Section 264 of the Maharashtra Municipal
Corporations Act, 1949 which is, by and large in pari materia with
Section 258 of the Act. The Bench, relying upon the earlier Division
Bench Judgment of the Court in the case of Diwanchand Gupta v NM
Shah & Ors. AIR 1972 Bom. 316, rejected the argument of the tenants
of the building with respect to which the demolition order has been
passed that the demolition order was wholly unnecessary and the entire
situation had been contrived by the owners to get rid of the tenants. It
was, thus, held that all that the authority had to do was to act bona fide
and not capriciously or with an improper motive. But, if the authority
considered the facts objectively, honestly and bona fide, that authority's
satisfaction would not be open to challenge. Whether or not, a building
should be repaired or pulled down, is a matter of which the authority is
the sole judge. It is not open to the Court to sit in a judgment and to
substitute the opinion of competent authority with its own.
20 The power conferred under Section 258 is a power manifestly
in public interest and is a reasonable restriction on the right to carry on
trade or business within the meaning of Article 19(1)(g) read with
Article 19(6) of the Constitution. Thus, in the absence of a clear
demonstration of abuse of discretion, mala fides, caprice or perversity,
a Court will not interfere to set aside such a notice.
21 Having said that, it cannot be said that the tenants and
occupants vis a vis their tenancy or occupancy are without any remedy
but the remedy lies somewhere else. As is provided in Section 259 (3)
of the Act, the Commissioner, Municipal Corporation is under an
obligation to allow a person or persons who have vacated or have been
removed from any unsafe building in pursuance of any order made by
him to reoccupy the building, provided that the reasons on account of
which the vacation was ordered have been rectified or have ceased to
exist. Similar right is vested in the tenants under the Rent Control
Legislation as well.
22 Viewed in the totality of circumstances obtaining in the case,
we are of the view that no fault can be found with the otherwise well
reasoned judgment of the Writ Court. For the reasons given
hereinabove by us and those contained in impugned judgment, we are
of the considered view that the appeals are without merit and deserve to
be dismissed.
23 We are, however, of the view that the ends of justice would be
met, if, notwithstanding the dismissal of appeals, the interest of the
appellants could be safeguarded. We, therefore, pass the following
directions:
(i) The appellants, who have been ordered to vacate the shops under their tenancy shall be entitled to reoccupy the building once it is constructed by the landlord after demolition of the existing building under the orders of the Municipal Corporation;
(ii) It is made clear that any permission applied for by respondent No.5 for raising fresh construction on the site of the building to be demolished, shall be granted by the Municipal Corporation only if site plan makes a provision for re-erection of the shops demolished;
(iii) The Municipal Corporation shall obtain undertaking from respondent No.5 that he or his successor-in-interest would offer for renting out these shops to the appellants as and when constructed subject to re-fixation of fair rent under the provisions of Rent Control Legislation in force; and
(iv) On the appellants being put in possession of their respective shops, the relationship of the landlord and the tenant between the appellants and respondent No.5 shall revive and continue until determined in accordance with law.
The record is returned to the learned counsel for JMC.
(SANJAY DHAR) (SANJEEV KUMAR)
JUDGE JUDGE
Jammu
19.03.2021
Sanjeev
Whether the order is speaking: Yes
Whether the order is reportable: Yes
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!