Wednesday, 17, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The General Manager vs Pawan Kumar And Another
2025 Latest Caselaw 1638 HP

Citation : 2025 Latest Caselaw 1638 HP
Judgement Date : 8 July, 2025

Himachal Pradesh High Court

The General Manager vs Pawan Kumar And Another on 8 July, 2025

                                       1


                                                               ( 2025:HHC:21814 )

    IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA

                                   RFA No.67 of 2014 a/w connected




                                                                 .
                                   matters





                                   Date of Decision : 08.07.2025

    1.    RFA No.67 of 2014





    The General Manager, NTPC Kol Dam Project
                                                         ...... Appellant
                        Versus

    Pawan Kumar and another
                                                         ......Respondents





    2.    RFA No.68 of 2014

    The General Manager, NTPC Kol Dam Project
                                                         ...... Appellant
                        Versus


    Desh Raj and another
                                                         ......Respondents
    3.    RFA No.69 of 2014

    The General Manager, NTPC Kol Dam Project
                                                         ...... Appellant



                        Versus

    Seema and another
                                                         ......Respondents




    4.    RFA No.70 of 2014





    The General Manager, NTPC Kol Dam Project
                                                         ...... Appellant
                        Versus





    Padam Raj and another
                                                         ......Respondents
    5.    RFA No.71 of 2014

    The General Manager, NTPC Kol Dam Project
                                                         ...... Appellant
                        Versus

    Hari Om and another
                                                         ......Respondents
    6.    RFA No.72 of 2014

    The General Manager, NTPC Kol Dam Project
                                                         ...... Appellant
                        Versus




                                                ::: Downloaded on - 09/07/2025 21:18:00 :::CIS
                                               2


                                                                      ( 2025:HHC:21814 )


    Anupma and another
                                                                ......Respondents
    7.     RFA No.73 of 2014




                                                                        .
    The General Manager, NTPC Kol Dam Project





                                                                ...... Appellant
                           Versus

    Basantpur Khadi Gram Udyog Gen Kalian Samiti and another





                                                                ......Respondents





    Coram:


    The Hon'ble Mr. Justice Bipin Chander Negi, Judge

    Whether approved for reporting?1


    For the appellant(s)    :    Mr. Neeraj Gupta, Senior Advocate, through Video
                                 Conferencing with Mr. Pranjal Munjal and Mr. Harshit
                                 Sharma, Advocates.


    For the respondents     :    Mr.   Rajiv   Rai,    Advocate,   through  Video
                                 Conferencing and Mr. Mukesh Sharma and Ms. Rajni
                                 Gandhi, Advocates, for respondent No.1, in all the
                                 appeals, except RFA No.73 of 2014.




                                 Mr. Sushil Chauhan, Advocate,             for respondent
                                 No.2, in RFA No.73 of 2014.





                                 Mr. Diwakar Dev Sharma, Additional Advocate
                                 General, for respondent No.2/State, in all the
                                 appeals.





    Bipin Chander Negi, Judge (oral)

RFA No.67 of 2014 a/w RFA Nos.68 to 73 of 2014

All these Regular First Appeals arise out of a common reference

Award dated 13.12.2013, hence, they are being taken up together for

adjudication. Vide order dated 03.01.2011, the Reference Court has

consolidated all these matter with Reference Petition No.28 of 2010.

Whether reporters of Local Papers may be allowed to see the judgment? Yes

( 2025:HHC:21814 )

2. The present appellants are the beneficiaries for whom the land was

acquired by the State of Himachal Pradesh for construction of Kol Dam

.

Hydro Power Project. In the case at hand, land measuring 2-0-11 Bighas

were acquired in Village Tatapani, Tehsil Karsog, District Mandi, Himachal

Pradesh. The requisite necessary notification under Section 4 of the Land

Acquisition Act was issued by the State of Himachal Pradesh on 09.05.2005.

As a squeal to the aforesaid notification, Award No.80 of 2008 was

announced by the Acquisition Collector, Kol Dam, on 08.03.2008.

3. Perusal of the Award reflects that insofar as land acquired was

concerned, acquisition charges were paid on the basis of classification of

land. Land in the Award passed by the Land Acquisition Collector was

classified into eight categories. The highest award was made for Dhani Abal

and least was paid for Gair Mumkin/Khadyatar.

4. Insofar as structures over the acquired land were concerned,

measurements and assessments of the same were got done by the Civil

Engineers of the Office of the Land Acquisition Collector, Kol Dam, Bilaspur,

Himachal Pradesh. Subsequent to the measurement and assessment,

notice under Section 9 of the Act was given to the owners of the land qua the

structures to file their objections, if any with respect to the measurement and

claims thereupon. No one has filed objections with respect to the

measurement. Hence, based on the measurement and assessment made

compensation was awarded qua the structure.

5. Feeling aggrieved of the Award bearing No.80 of 2008 announced on

08.03.2008, the land owners and structures owners preferred appropriate

Reference Petitions under Section 18 of the Act before the concerned Court.

( 2025:HHC:21814 )

The Reference Petitions, in the case at hand were decided on 13.12.2013.

Insofar as acquisition for land was concerned, uniform rate was awarded by

.

the Reference Court. The uniform rate awarded was the highest

compensation awarded by the Land Acquisition Collector for the eight

classes of land acquired. The Land Acquisition Collector had awarded

Rs.6.41 lacs approximately for "Dhani Abal, therefore, this highest rate was

made applicable for the entire land.

6. Insofar as structures acquired were concerned, the Reference Court

noticed that in the measurement and assessment made, no amount had

been paid to the structure owners on account of labour charges, foundation

building charges, carriage charges and electricity charges. In assessing the

structures, reliance was placed on the "Guidelines for Preparation of

Estimates" laid by the Public Works Department and placed on record as

Ex.PW1/H. The assessments of structures by the Land Acquisition Collector

were placed on record as Ex.PW1/A to Ex.PW1/D.

7. In the aforesaid backdrop, there are two contentions, primarily raised

by learned counsel for the appellants/beneficiary of the acquisition:

a. The first submission is with respect to the uniform rate

awarded;

b. The second submission is with respect to additions made by the Reference Court, while awarding, with respect to structures acquired.

8. Insofar as the first contention is concerned, the law with respect to

award of compensation at uniform rates, when the purpose of acquisition is

common and no developmental activity is required to be carried out is no

longer res integra and stands settled by Hon'ble the Supreme Court in

( 2025:HHC:21814 )

Himmat Singh and others vs. State of Madhya Pradesh and another,

(2013) 16 SCC 392 (para 34); Peerappa Hanmantha Harijan (Dead) By

.

Legal Representatives and others vs. State of Karnataka and another,

(2015) 10 SCC 469 (paras 80 and 81); as also this Court in RFA No. 953 of

2012, titled as Land Acquisition Collector & another vs. Jatinder Singh,

decided on 01.06.2016 and other connected matters.

9. Insofar as the second contention is concerned, the measurement and

structures, in the case at hand, are concerned, the same were got done by

the staff of the office of the Land Acquisition Collector concerned. The same

is evident from the contents of Award No.80 of 2008, passed by the Land

Acquisition Collector on 08.03.2008. Item No.4 in the Award, deals with the

compensation of houses/built up structures. The measurement and

assessment so done has been placed on record as Ex.PW1/A to Ex.PW1/D.

From the perusal of the measurement/assessment done, it is evident that no

amount has been awarded insofar as carriage is concerned. Other than the

aforesaid, insofar as raising of foundation of houses, in the case at hand, is

concerned, no amount for the same has been given in the measurement and

assessment so done. Conspicuous by absence is also the non-payment of

amount on account of labour charges incurred for the construction of the

houses, in the case at hand. A meager amount has been awarded on

account of electricity supply and electrical fittings/installations.

10. From a perusal of Ex.PW1/H i.e. "Guidelines for preparation of

assessments" prepared by the Public Works Department, it is evident from

Item No.14 thereof that normally insofar as water supply, sanitary installation,

electricity supply, fittings thereof are concerned for both 12.5% of the cost of

( 2025:HHC:21814 )

the building, needs to be allotted. In the case at hand, allotment of electrical

installation has been done on the basis of measurement/assessment. No

.

allocation in the assessment has been made with respect to water supply

and sanitary installation, for which also structure owners are entitled.

11. Keeping in view the aforesaid non-grant, I see no reason to interfere

with the amount so awarded for electrical charges, therefore, the present

appeal(s) are dismissed, being devoid of merit. Pending miscellaneous

application(s), if any, shall also stand disposed of.

CMP No.14985 of 2025 in RFA No.73 of 2014

12. No reply is intended to be filed on behalf of the non-applicants.

Non-applicants have no objection, if in case, the amount is ordered to be

released in favour of the applicant.

13. In this case only land was acquired and there was no structure

involved.

14 For the reasons stated in the application, the same is allowed. In

the case at hand, 50% of the awarded amount stands already released in

favour of the applicant. The balance 50% of the amount lying deposited

in the Registry of this Court along-with proportionate interest accrued

thereupon is ordered to be released in favour of the applicant. The

amount be remitted to the bank accounts, details whereof, have been

given in Paragraph-7 of the application, subject to proper verification of its

identity. The application stands disposed of.



                                                     ( Bipin Chander Negi)
    July 08, 2025 (KS)                                       Judge





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter