Thursday, 21, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Decided On: 16.12.2025 vs Union Of India And Others
2025 Latest Caselaw 10224 HP

Citation : 2025 Latest Caselaw 10224 HP
Judgement Date : 16 December, 2025

[Cites 1, Cited by 0]

Himachal Pradesh High Court

Decided On: 16.12.2025 vs Union Of India And Others on 16 December, 2025

Author: Ajay Mohan Goel
Bench: Ajay Mohan Goel
                                                                                      2025:HHC:43939
           IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA




                                                                                .
                                                          CWP No.           7507 of 2024





                                                          Decided on: 16.12.2025
    M/s The Shivam Enterprises                                            ... Petitioner





                                Versus

    Union of India and others                                                       ... Respondents




                                                     of
    Coram
    Hon'ble Mr. Justice Ajay Mohan Goel, Judge.
    Whether approved for reporting?1
    _____________________________________________________
                          rt
    For the petitioner      :     Ms. Amanpreet Kaur, Advocate
                                  through VC and Ms. Anchal Sharma,
                                  Advocate.

    For the respondents                  :        Mr. Rajinder Thakur,                   CGC        for
                                                  respondents No. 1 and 3.


                                         :        Mr. Rajpal Thakur, Addl. AG for
                                                  respondents No. 2, 4 and 6.
    Ajay Mohan Goel, Judge                        (Oral)

By way of this writ petition, the petitioner has inter alia

prayed for the following reliefs:-

"(i) To issue writ, in the nature of 'Mandamus' directing

respondents No. 1, 3, 5 and 6 to release the pending balance

payment of Rs. 4,18,89,498/- of Engineering, Procurement &

Construction/EPC-25, Chamba agreement dt. 28.01.2022

(Annexure P-3), along with interest @ 12% till realization."

2. When this case was lastly listed before the Court on

11.12.2025, the following order was passed:-

Whether reporters of the local papers may be allowed to see the judgment?

2025:HHC:43939 "As per report of the Registry, the report of the

.

Committee has not been furnished. Learned Counsel appearing

for the petitioner submits that the petitioner has not been

invited by the Committee for any negotiations.

This Court is of the considered view that if that is so,

of then the same amounts to contempt of Court because as far

back as on 31.10.2025, the Court was intimated by learned

Deputy Advocate General that the Committee stood constituted rt and the date was being collected by the Committee and that

petitioner shall be associated by the Committee before any

final decision is arrived at.

The case is ordered to be listed on 16.12.2025, on

which date learned Deputy Advocate General shall apprise the

Court as to what all the Committee has done as from the date

of passing of the above mentioned orders, i.e. order dated

31.10.2025."

3. Today, learned Additional Advocate General has handed

over instructions received from the Executive Engineer, NH Division,

HPPWD, Theog, which are reproduced herein below:-

"In this regard it is submitted that as per the directions

issued vide the matter was pursued with the office of Ld.

District Attorney at the office of the worthy Engineer-in-chief

Shimla and data of the constituted committee is attached for

your kind perusal and also refer to the matter in this regard,

attention is invited to the communication issued from the office

2025:HHC:43939 of the no PW-LC-worthy Engineer-in-Chief. HPPWD vide letter

.

CWPNo.7572/2023/Shivam Enterprises/-2610 dated

08/12/2025, endorsed by the District Attorney (PW), wherein it

has been categorically clarified that, the issue involved in the

matter is not with respect to any admitted liability, but relates to

of a claim raised by the petitioner to which he is not entitled, as

per the respondents. The entire admissible payment in respect

of the executed work already stands released to the petitioner rt and no bill or amount is pending. The Committee for deciding

claims in respect of pending bills of contractors has been

constituted by the Government vide notification dated

07.07.2025, and in the present case, no such pending bill

exists. The information as desired by the Government for

placing the matter before the Committee had already been

submitted vide e-mail dated 16.07.2025. The matter is being

contested by the Department on merits, and instructions have

been sought for apprising the Office of the Learned Advocate

General accordingly.

It is, therefore, respectfully submitted that the factual

position, as clarified above, may kindly be taken on record for

the purpose of compliance of the directions issued by the

Hon'ble High Court please."

4. Reply filed by the respondents-State has also been

perused by the Court and relevant portion thereof reads as under:-

2025:HHC:43939 "3....Accordingly, the work was awarded to the M/s

.

Shivam Enterprises # 110 Bawa Nagar Chandigarh road,

Rajpura 140401, Patiala Punjab on 03-12-2021 2022 (Copy

enclosed as Annexure R-2) with a time limit of 9 months subject

to maintenance for period up to 5 years as per the site handing

of over memorandum the complete site was handed to the

contractor on 05-02-2022 (Copy enclosed as Annexure R-3). The

scope of work mainly comprised of Construction of Retaining - rt wall, Thrie beam Crash barriers, Signage from Katori Bangla to

Chamba Km 39/00 to 106/00 including rectification of

identified black spots (7 Nos) at RD 39/00,RD 42/165 to

42/195,RD 49/880 to 49/960,RD 57/300 to 57/315,

RD59/240, RD59/290 to 59/350& RD 89/620 of NH154A in a

length of KM 30.820 at Project cost of Rs 24.90 Crores. There

are some serious lapses on part of the contractor which are

summarized as under:-

(i) Non completion of critical work:-It is respectfully submitted

that the contractor mainly executed the profitable part of the

work i.e. installation of crash barrier and construction of Plain

cement concrete (PCC) Retaining wall, Reinforced cement

concrete (RCC) Retaining wall in a length of 115 Meter which

was essentially required at site on RD 104/520 to 104/635

(Parel Ghar) photograph attached (Copy enclosed as Annexure

R-18), due to quite narrow portion of the road just along the river

side work was never started by the contractor at site, Despite

2025:HHC:43939 repeated requests and management meetings vide letters on

.

19.03.2022, 19.10.2022, 06.07.2023, 16.08-2023 23.08.2023

20.10.2023 ,28.11.2023 ,01.02.2024 25.05.2024 (Copy

enclosed as Annexure R-4 to R-12) the contractor least bother to

submit the design of RCC Retaining wall which was incumbent

of on his fault, being EPC (Engineering procurement and

construction) mode of contract as such very purpose of sanction

of the road safety DPR (Detailed Project Report) by MORTH rt (Ministry of Road Transport and Highway )was defeated due to

breach of contract on the part of contractor.

(ii) Submission of false bill:-The contractor submitted

wrong/false claim of payment toward his 9th running bill

amounting to Rs.1,74,30,000{ONE CRORE SEVENTY FOUR

LACS THIRTY THOUSAND},on scrutiny of bill in higher office.

The false claim of contractor was noticed and the claim was

rejects as per the Schedule H (Copy enclosed as Annexure R-15)

of the agreement This false claim constitutes a gross breach of

trust and ill intention on part of the contractor to defraud the

Department.

(iii) Arbitration Penalties: Request to Avoid The contractor has

not approached this Hon'ble High Court with clean hands and

he has suppressed the material fact from the Hon'ble court.

However, it is clear that this request is a tactical maneuver to

shift the responsibility of delay and to avoid the penalties that

would otherwise be imposed for none performance, delays and

2025:HHC:43939 fraudulent billing. Even the end treatment of crash barrier was

.

not completed by the contractor which was very crucial for

safety point of view and also pointed out by the Ministry of

Road Transport and Highway (MORT&H) Officer during

inspection vide letter no. 05.07.2024(Copy enclosed Annexure R-

of

13)."

5. This Court is of the considered view that in the peculiar rt facts of this case as there are disputed facts between the parties as to

whether the entire emoluments to which the petitioner is entitled,

stands released in favour of the petitioner or not, these issues cannot

be decided by this Court under Article 226 of the Constitution of

India and the better course for the petitioner shall be to have

recourse to the other legal remedies which are available to it.

6. Accordingly, this writ petition is closed, with liberty to the

petitioner to have recourse to such remedies, as are available to it, in

accordance with law. Pending miscellaneous applications, if any,

also stand disposed of accordingly.

(Ajay Mohan Goel) Judge December 16, 2025 (narender)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter