Thursday, 21, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

____________________________________________________ vs H.P.State Electricity Board Ltd
2023 Latest Caselaw 18373 HP

Citation : 2023 Latest Caselaw 18373 HP
Judgement Date : 24 November, 2023

Himachal Pradesh High Court

____________________________________________________ vs H.P.State Electricity Board Ltd on 24 November, 2023

Author: M.S. Ramachandra Rao

Bench: M.S. Ramachandra Rao

    IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA




                                                                           .
                               Arb. Case No. 595 of 2023





                               Date of decision: 24.11.2023
    ____________________________________________________
    A2Z Infra Engineering Ltd.                 ...Petitioner





                               Versus

    H.P.State Electricity Board Ltd.    ...Respondent




                                                 of
    ____________________________________________________
    Coram:
    The Hon'ble Mr. Justice M.S. Ramachandra Rao, Chief Justice
    Whether approved for reporting?1
                       rt
    ____________________________________________________
    For the petitioner :    Mr. Sumeet Raj Sharma, Advocate.

    For the respondents:                Ms. Sunita Sharma, Senior Advocate
                                        with Mr. Dhananjay Sharma, Advocate.


    M.S. Ramachandra Rao, Chief Justice (Oral)

This is an Application filed under Section 11 (6) of

the Arbitration and Conciliation Act, 1996 (for short 'the Act') to

appoint an Arbitrator to adjudicate a dispute between the parties

arising out of an Agreement dt. 24.02.2012, under which a

Contract was awarded to the applicant by the respondent with the

following description:

"Design, engineering, manufacture, testing of equipment and supply F.O.R. destination site basis of sub-station equipment and spares for 132/33 KV 16

Whether the reporters of Local Papers may be allowed to see the judgment?

MVA (3x5.33 MVA 1-phase) substation at Gaura, Distt. Solan (HP) on turnkey basis against tender

.

specification No. SSD-301/11:"

2. The dispute in the instant case, according to the

applicant, is a deduction made by the respondent from the bills

of payable to the applicant of a sum of Rs.87,96,524/- allegedly

towards liquidated damages from various RA bills raised by the

applicant.

rt

3. The applicant contends that though the sub-station

was successfully charged by them on 30.08.2014 and was even

inaugurated by the Chief Minister of Himachal Pradesh on

01.11.2014, but on account of certain delays in completion of the

work under the Contract which were solely and entirely

attributable to the respondent, the applicant cannot be denied the

said amount by the respondent.

4. In the reply filed by the respondent, the allegation of

the applicant is disputed and a plea of bar of limitation is also

raised. But the applicant contends that the payment under the

Contract was to be made to the applicant by the respondent w.e.f.

30.10.2020 and in fact the applicant had also issued a legal notice

to the respondent to appoint an Empowered Officer to adjudicate

.

the dispute on 01.12.2020 and had also sought time for extension.

There is a response by the respondents dt. 25.03.2021 according to

which Chief Engineer (Generation) HPSEBL, Sundernagar was

appointed as an Empowered Officer for settlement of the dispute

of and therefore, the claim of the applicant cannot be said to be time

barred.

5. rt In the instant case, the dispute between the parties

regarding the deduction of liquidated damages is a dispute which

requires adjudication and the applicant had invoked Arbitration

Clause 4.41.1 of the Agreement dt. 24.02.2012, and even issued a

notice dt. 04.04.2023 seeking appointment of an Arbitrator.

6. The issue of limitation raised by the respondent in the

factual circumstances of the case may require evidence and

appears to be a mixed question of law and fact. Therefore, in view

of the bar contained in Section 11(6-A) of the Act, which requires

this Court to confine itself to the examination of the existence of

the Arbitration Agreement, Shri D.K. Sharma, District &

Sessions Judge (Retd.), is appointed as an Arbitrator to resolve the

dispute between the parties, after his disclosure in writing is

obtained in terms of Section 11(8) of the Act, and only after

.

receipt thereof, shall his appointment, as an Arbitrator, come into

force.

7. On his giving consent to arbitrate the dispute between

the parties as an Arbitrator, Shri D.K. Sharma, District & Sessions

of Judge (Retd.), R/o Village Nalvi, P.O. Khantal, Pargana Chautta,

Tehsil Sunni, District Shimla, H.P. shall enter into reference, and rt shall pass an award in accordance with law.

8. Copy of this order be forwarded to the learned

Counsel for the parties as also to the learned Arbitrator. The

learned Arbitrator so appointed shall be entitled to fee as per

stipulation contained in 4th Schedule appended to the Arbitration

and Conciliation Act, 1996.

9. The application is disposed of accordingly alongwith

pending application(s), if any.

(M.S. Ramachandra Rao) Chief Justice

November 24, 2023 (hemlata)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter