Citation : 2023 Latest Caselaw 10483 HP
Judgement Date : 28 July, 2023
IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
RSA No.506 of 2018
.
Decided on: 28.07.2023
State of H.P. & others ...Appellants
Versus
Molak Ram Kashyap ...Respondent
Coram
The Hon'ble Mr. Justice M.S. Ramachandra Rao, Chief Justice
Whether approved for reporting?
For the appellants: Mr. Arsh Rattan, Deputy Advocate
General.
For the respondent: Mr. Romesh Verma, Senior Advocate
with Mr. Sanket Sankhyan, Advocate.
M.S. Ramachandra Rao, Chief Justice (Oral)
This Second Appeal is preferred by the State of Himachal
Pradesh challenging the judgment and decree dt. 29 th March, 2018 in
Civil Appeal No.25-S/13 of 2017 of Additional District Judge (II),
Shimla, confirming the judgment and decree dt. 20th March, 2017 in
Civil Suit No.185.01 of 2013/11 of the Civil Judge(Senior Division)
Court No.1, Shimla, Himachal Pradesh.
2) The respondent is owner of land under Khata no.51, Khatauni
no.158, Khasras no.1103, 1107 and 1108 of Mauja Dharogra
.
Pargna Saraj, Tehsil Sunni, District Shimla.
3) He executed a gift deed on 19.06.2004 of a portion of the land
owned by him for a construction of a road from Malgipul to
Dharogra.
4) He alleged that the rest of the land is fertile and valuable, but the
contractor engaged by the appellants, negligently constructed the
road causing damage to the land and fruit bearing trees on the
remaining land, including an orchard.
5) It is alleged that the contractor dumped huge quantity of debris and
stones on the land of the respondent, ignoring repeated requests of
the respondent to stop doing so resulting in damage to the land.
6) The respondent issued a letter dt. 4th September, 2007 to the
Secretary PWD Himachal Pradesh Government and also a demand
notice dt. 8th January, 2008 specifically claiming damages for the
land of the respondent; and since the issue was not resolved, the
suit was filed seeking recovery of Rs.3,25,880/- alongwith future
interest from the date of filing of the suit till realization and also
permanent prohibitory injunction for restraining the appellants
from interfering with the suit land directly or indirectly in any
manner or throwing any debris from road site towards their land.
.
7) Written statement was filed by the appellants admitting the gift of
the land by the respondent, but they denied that the rest of the land
was valuable and also denied that there are apple plants grown over
it.
8) It was also denied that there was no damage done to the land
retained by the respondent and it was contended that the contractor
had taken all precautions, but despite the same due to hilly and
sloppy terrain, some debris and boulders were bound to fall down.
It is contended that thereafter quick action was taken by the
appellants and the contractor was directed to remove the debris. It
is contended that only the contractor is liable for the damages
caused by his negligence and not the appellants.
9) On the basis of these pleadings, the trial Court framed the
following issues:
"1. Whether the plaintiff is entitled for damages to the tune of Rs.3,25,880/- alongwith future interest @ 12% per annum, as prayed for? ...OPP
2. Whether plaintiff is entitled for relief of permanent prohibitory injunction, as prayed for? ...OPP
3. Whether the suit is not maintainable? ...OPD
4. Whether the plaintiff is estopped to file the present suit, as alleged? ...OPD
5. Whether the suit is bad for non joinder of
.
necessary parties, as alleged? ...OPD
6. Whether the suit is not properly valued for the purposes of court fee and jurisdiction, as
alleged? ...OPD
7. Whether the present suit do not disclose any cause of action, as alleged? ...OPD
8. Whether the plaintiff has not approached this court with clean hands, as alleged? ...OPD
9. Relief."
10) Before the trial Court, the respondent examined PW-1 to PW-10
and marked Ext. PW4/A to Ext. PW10/H. The appellants examined
DW-1 and DW-2 and marked Ext. DW2/B and DM1 to M4.
11) After considering the oral and documentary evidence, the trial
Court came to the conclusion that while constructing the road, no
proper care was taken to protect the remaining land of the
respondent, which he had not gifted to the State, and there was
rashness and negligence in executing their own contract by the
contractor.
12) The trial Court held that perusal of the jamabandi Ext. PW8/A
proved that there were fruit bearing trees on the remaining portion
of the land retained by the respondent, that the report Ext PW4/A
proved that damage was caused to the land on which fruit bearing
.
trees were existing, and this demarcation was carried out by the
revenue officials who admitted during cross-examination that when
the road was being constructed, damage was caused to the fruit
bearing trees as well as remaining land of the respondent.
13) He also relied on Ext. PW7/C which fixed the loss of fruit bearing
trees as Rs.25,880/-.
r He further relied on Ext. PW4/A and
PW10/C reports to hold that damage is not only caused to the fruit
bearing trees, but also to the vacant land and beside this
compensation further compensation was also required to be paid to
the respondent.
14) The trial Court also relied on the evidence of PW-9, a Civil
Engineer, who assessed the damage in his report Ext. PW8/A
showing that loss to the tune of Rs.2,93,253/- was caused. It held
that non-impleadment of the contractor was not fatal because even
the copy of the agreement entered into by the appellants with the
contractor was not placed on record.
15) The trial Court also granted relief of injunction restraining the
appellants from interfering over the suit land directly or indirectly
in any manner, and also restrained the appellants from throwing
any debris or stones from the road site towards the suit land. It also
.
directed them to remove the debris and stones which they have
thrown towards the suit land and restore the suit land to its original
position.
16) This was challenged by the appellants before the Additional
District Judge (II), Shimla, but the said appeal was also rejected,
confirming the findings of the trial Court.
17) The appellate Court held that there was admission in the pleadings
and evidence of the appellants' witnesses proving the damage to
the land and orchard of the respondent during the construction of a
link road by throwing debris and boulders thereon.
18) It also observed that the appellants had not led any cogent and
convincing evidence to show that the link road was constructed
strictly as per the technical specifications, and that the witnesses of
the appellants had admitted in their cross-examinations that there
were apple trees on the land of the respondent which were
damaged during the construction of the link road, and that the
assurance was given to the respondent that damage done to his land
will be made good.
19) It relied on the judgment in Rylands vs. Fletcher (1868) LR 3 HL
330 and held that it was the duty of the appellants to take
.
precautionary measures to prevent the sliding of debris into the
land of the respondent situated on the lower side of the road and
after completion of the construction they should have taken action
to compensate the respondent to the damage caused to his land and
orchard.
20) Challenging the decision, this RSA is filed.
r This RSA was
admitted on 26.11.2018 to consider the following substantial
question of law:
" Whether the judgments and decrees passed by
the learned Courts below are perverse inasmuch as they are based upon mis-reading of the
pleadings as also the oral and documentary evidence?"
21) Learned counsel for the appellants sought to contend that the
judgments of the trial Court as well as appellate Court are both
perverse.
22) After carefully considering the pleadings and entire evidence on
record and the reasons recorded by the trial Court as well as the
appellate Court, I do not find any perversity in the said findings
recorded by them.
.
23) The said findings had been recorded on the basis of certain
admissions made by the witnesses examined by the appellants
themselves and therefore cannot be said to be perverse.
24) I therefore do not find any merit in the RSA, which is accordingly
dismissed.
25) Pending application(s), if any shall also stand disposed of.
( M.S. Ramachandra Rao ) Chief Justice
July 28, 2023
(vt)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!