Wednesday, 20, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Email Id vs Email Id: [email protected]
2022 Latest Caselaw 3370 HP

Citation : 2022 Latest Caselaw 3370 HP
Judgement Date : 13 May, 2022

Himachal Pradesh High Court
Email Id vs Email Id: [email protected] on 13 May, 2022
Bench: Mohammad Rafiq
    IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA

                ON THE 13th DAY OF MAY, 2022




                                                      .
                          BEFORE





          HON'BLE MR. JUSTICE MOHAMMAD RAFIQ,
                       CHIEF JUSTICE





               ARBITRATION CASE No. 21 of 2022





         Between:
         M/S. UBITECH (P) LTD.
         HAVING ITS REGISTERED
         OFFICE AT 1D/10, BP,

         NIT FARIDABAD,

         HARYANA (121 001)

         EMAIL ID :
         [email protected]



                                               ...PETITIONER

         (BY MR. ATUL KUMAR




         & MR. DIVYA RAJ
         SINGH, ADVOCATES)





         AND





         HIMACHAL PRADESH STATE
         ELECTRICITY BOARD LTD.
         THROUGH ITS CHAIRMAN
         CUM MANAGING DIRECTOR
         HAVING ITS OFFICE AT:
         VIDYUT BHAWAN, HPSEB
         SHIMLA - 171 004 (HP).

         EMAIL ID: [email protected]

                                                ...RESPONDENT




                                     ::: Downloaded on - 17/05/2022 20:05:52 :::CIS
                                   2



         (BY MR. VIKRANT THAKUR,
         ADVOCATE)

             This case coming on for orders this day, Hon'ble Mr.




                                                            .
    Justice Mohammad Rafiq, delivered the following:





                            JUDGMENT

The petitioner, which is an electrical engineering and

contracting concern, established in the year 1983, dealing in

the field of electrical engineering and contracting of EHV

Substation and Transmission Lines across India, is before this

Court by way of the instant petition under Section 11 of the

Arbitration and Conciliation Act, 1996 (for short 'the Act')

seeking for appointment of an Arbitrator to resolve the dispute

that has arisen between the parties.

2. The case of the petitioner is that the execution work

of "Restructured Accelerated Power Development and Reforms

Programme (R-APDRP) Part-B" ("Paonta Sahib Project"),

which was to be executed in two stages, was awarded to it vide

Letter of Award, dated 9th May, 2012 (Annexure P-1). For each

stage of work, two separate contracts were entered into

between the parties. The total cost of Paonta Sahib Project

was approximately ₹ 4.67 crores, out of which, the cost of

supply part was approximately ₹ 3.84 crores and the cost of

erection part was approximately ₹ 82.95 lacs. Upon receiving

the Letter of Award, the petitioner took active steps to

commence the work by procuring materials and mobilizing

.

resources. The petitioner also submitted drawings and GTPs

for the respondent's approval on 28 th August, 2012. Instead of

facilitating due execution of the Paonta Sahib Project, the

respondent deliberately delayed its execution since its

commencement as approvals for drawing and GTPs remained

pending for more than 5-6 months despite repeated reminders,

which resulted in delay in commencement of the Paonta Sahib

Project. Despite various difficulties being faced by the

petitioner in execution of the work, the sub-station work was

completed in September, 2015, however, the same could not be

commissioned as the respondent did not shut down the power

from the main grid, though, requested by the petitioner vide

various letters. The continuous shut down was provided by

the respondent only on 16th January, 2019 whereafter the line

work and sub-station was commissioned. Though, there were

various lacunae, delay, non-cooperation and casual approach

on the part of the respondent, due to which the execution of

the project was getting delayed, the respondent failed to

release the outstanding payments in consonance with the

terms of the contract and also, illegally deducted liquidated

damages and retained amounts even for those works which

were completed by the petitioner and where no defects were

.

pointed out. Despite the fact that the project is complete and

the respondent is deriving benefit out of the said project since

22nd February, 2017, the respondent has made the payment

partially and still illegally withholding the payments of the

petitioner. Though, the petitioner served legal notice, dated

13th December, 2021, which was received by the respondent on

16th December, 2021, the respondent has neither complied with

the notice nor has replied. Hence, the present petition has

been filed by the petitioner.

3. Notice of the petition was served upon the

respondent, however, no reply, as of now, has been filed by the

respondent.

4. Having regard to the rival submissions taken note of,

it is found: (i) that it is not disputed that there exists an

arbitration clause in the agreement between the parties; (ii)

that certain disputes arose between the parties and, therefore,

the existence of dispute is not doubted; (iii) that the petitioner

invoked the arbitration clause calling upon the respondents to

refer the dispute to the arbitrator; and (iv) that the

respondents have failed to act in accordance with the agreed

procedure in the arbitration agreement to refer the dispute to

the Arbitrator.

.

5. Under these circumstances, it is a fit case for making

a reference to an independent Arbitrator and this application

deserves to be allowed and the dispute referred to arbitration.

6. Accordingly, Hon'ble Mr. Justice Rajiv Sharma,

Judge (Retd.), r/o House No. 505, Sector 36-B, Chandigarh, is

appointed as an Arbitrator, after his disclosure in writing is

obtained in terms of Section 11(8) of the Act and only after

receipt thereof, shall his appointment, as an Arbitrator, come

into force.

7. On his giving consent to arbitrate the dispute

between the parties, as an Arbitrator, Hon'ble Mr. Justice

Rajiv Sharma, Judge (Retd.) shall enter into reference and

shall pass an award in accordance with law. Copy of this order

be forwarded to the learned counsel for the parties, as also to

the learned Arbitrator. The learned Arbitrator so appointed

shall be entitled to fee as per stipulation contained in 4 th

Schedule appended to the Arbitration and Conciliation Act,

1996.

8. The arbitration petition is disposed of accordingly,so

also the pending miscellaneous applications, if any.

.

                                                 ( Mohammad Rafiq )
                                                    Chief Justice
    May 13, 2022





         ( rajni )




                          r           to










 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter