     C/CA/1927/2021                                 ORDER DATED: 04/01/2022




           IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
                 R/CIVIL APPLICATION NO. 1927 of 2021
                  In F/FIRST APPEAL NO. 26640 of 2021
==========================================================
        PATEL RUGNATH PITAMBAR DIED THROUGH LH PATEL
                  VIRCHANDBHAI RUGNATHBHAI
                            Versus
               SPECIAL LAND ACQUISITION OFFICER
==========================================================
Appearance:
MR AV PRAJAPATI(672) for the Applicant(s) No. 1
for the Respondent(s) No. 2
MS URMILA DESAI, AGP for the Respondent(s) No. 1
==========================================================
 CORAM:HONOURABLE MR. JUSTICE A.G.URAIZEE
                  Date : 04/01/2022
                   ORAL ORDER

1. Rule returnable forthwith. Ms.Urmila Desai, learned AGP waives service of notice of Rule for the respondent - State.

2. Heard Mr.A.V.Prajapati, learned advocate for the applicant and Ms. Urmila Desai, learned AGP for the respondents.

3. The present application under Section 5 of the Limitation Act has preferred to condone the delay of 2090 days which has occurred in preferring First Appeal to assail the impugned judgment and award of the Trial Court.

4. Mr.A.V.Prajapati, learned advocate for the applicant submits that the applicant is a farmer having no knowledge about the legal remedy and hence, he could not prefer the appeal within prescribed period. It is his further submission

C/CA/1927/2021 ORDER DATED: 04/01/2022

that the applicant had not abandoned his right to prefer an appeal and no malafide is apparent so as to dismiss the present application.

5. He relied on the decision of the Supreme Court in case of K. Subbarayudu vs. Special Deputy Collector (Land Acquisition) reported in 2017 (12) SCC 840. He submits that the term "sufficient cause" should receive liberal construction so as to advance substantial justice. He further submits that the applicant is ready and willing to forgo the interest and consequential statutory benefits ensuing from the impugned judgment and order for the period of delay, if the period of delay is condoned. He, therefore, urges that the delay may be condoned.

6. Ms.Urmila Desai, learned AGP has opposed this application and submits that the delay is inordinate and is not sufficiently and satisfactorily explained, except stating that the applicant is a farmer having no knowledge of legal nicety. He, therefore, submits that the delay may not be condoned.

7. I have given my thoughtful consideration to the submissions made at bar. It is undisputed fact that the delay which has occurred in preferring first appeal is huge delay i.e. delay

C/CA/1927/2021 ORDER DATED: 04/01/2022

of 2090 days.

8. At this stage, it is relevant to take into account the observations made by Supreme Court in paragraph Nos. 10 to 12 in case of K. Subbarayudu (supra), which read as under:-

"10. Before the High Court, the appellants relied upon Yellasiri Sarojanamma's case, in L.A.S.S. No.46 of 2015, in which the High Court condoned the delay of 3386 days in filing the land acquisition appeal suit subject to the condition that in the event, the appellant/claimant thereon succeed in appeal, she is not entitled to any interest in respect of the period of delay. The appellants contended that the same approach ought to have been adopted in the case of appellants also. Insofar as, the reliance placed upon by the claimants in L.A.S.S. No.46/2015, the High Court seems to have brushed aside the contention of the appellants on the puerile ground that the relevant fact situation in the said case is not forthcoming in the said order. In our view, the High Court was not right in adopting a different yardstick in the case of the appellants in not condoning the delay.

C/CA/1927/2021 ORDER DATED: 04/01/2022

11. The term "sufficient cause" is to receive liberal construction so as to advance substantial justice, when no negligence, inaction or want of bona fide is attributable to the appellants, the Court should adopt a justice-oriented approach in condoning the delay. In State of Nagaland v. Lipok AO and Others (2005) 3 SCC 752: 2005 (4) JT 10, it was held as under:-

"Section 5 is to be construed liberally so as to do substantial justice to the parties. The provision contemplates that the court has to go into the position of the person concerned and to find out if the delay can be said to have been resulted from the cause which he had adduced and whether the cause recorded in the peculiar circumstances of the case is sufficient".

12. With the acquisition of lands, the lifeline of the agriculturist is lost. There may be omission on the part of the claimants to adopt extra vigilance; but same need not be used as a ground to depict them with negligence or want of bona fide. In case of acquisition of lands

C/CA/1927/2021 ORDER DATED: 04/01/2022

of agriculturists, the courts ought to adopt a pragmatic approach to award just and reasonable compensation and not pedantic in their approach. In Dhiraj Singh (D) Thr. Lrs. Etc. Etc. v. Haryana State and Ors. Etc. Etc. 2014 (9) SCALE 441, it was held as under:-

"15. Equities can be balanced by denying the appellants' interest for the period for which they did not approach the Court. The substantive rights of the appellants should not be allowed to be defeated on technical grounds by taking hyper technical view of self-imposed limitations. In the matter of compensation for land acquisition, we are of the view that approach of the Court has to be pragmatic and not pedantic."

9. In view of the above observations of the Supreme Court coupled with the fact that the applicant is willing and ready to forgo the interest on enhanced compensation and the statutory benefits flowing on the enhanced compensation for the period of delay, if the appeal is allowed, I am of the opinion that the delay needs to be condoned.

C/CA/1927/2021 ORDER DATED: 04/01/2022

10. For the foregoing reasons, the application is allowed and delay of 2090 days caused in preferring first appeal is hereby condoned on condition that the applicant shall not entitle to interest on enhanced compensation and consequential benefits on enhanced compensation for the period of delay, if the appeal is allowed.

11. The application stands disposed of accordingly. Rule is made absolute.

(A.G.URAIZEE, J) MOHMMEDSHAHID

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter