Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Arb.P./37/2021
2022 Latest Caselaw 2815 Gua

Citation : 2022 Latest Caselaw 2815 Gua
Judgement Date : 8 August, 2022

Gauhati High Court
Arb.P./37/2021 on 8 August, 2022
                                                                          Page No.# 1/6

GAHC010210522021




                          THE GAUHATI HIGH COURT
  (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)

                                Case No. : Arb.P./37/2021

            M/S NONDOCHAND NAIDING ,
            A FIRM REP. BY SRI NANDOCHAND NAIDING,
            SON OF LATE HARILAL NAIDING,
            RESIDENT OF DEHENGI BAZAR, P.O. AND P.S. DEHENGI BAZAR,
            DIST.- DIMA HASAO, ASSAM,
            REP. BY ITS CONSTITUTED ATTORNEY SRI REEJEET NUNISA,
            AGED ABOUT 35 YEARS,
            SON OF SRI BIMOL CHANDRA NUNISA,
            R/O- VILL.- DIHUR PHONGLO,
            P.O. AND P.S. MAIBANG, DIST.- DIMA HASAO,
            ASSAM, PIN- 788831.
                                                           ......Petitioner.

            -VERSUS -

         1. THE ADDITIONAL CHIEF ENGINEER AND ANR
            PWD (R AND B) HILLS, HAFLONG, ASSAM, PIN- 788819.

         2: THE EXECUTIVE ENGINEER
            PWD HAFLONG BUILDING DIVISION
            HAFLONG, ASSAM, PIN- 788819.

         3. THE NORTH CACHAR HILLS AUTONOMOUS COUNCIL,
            REP. BY ITS PRINCIPLA SECRETARY, HAFLONG.
                                                      ......Respondents.
          For the Petitioner:                  Mr. B. Pathak, Advocate.
                                              Mr. R. Thadani, Advocate.
                                              Mr. V. Kumar, Advocate.
          For the Respondents :               Mr. R.M. Das,
                                              Standing Counsel, NCHAC.
                                                                                   Page No.# 2/6




                                           BEFORE
                      HON'BLE MR. JUSTICE N. KOTISWAR SINGH


                    Date of Hearing & Judgment :       08.08.2022


                             JUDGMENT AND ORDER (ORAL)



Heard Mr. B. Pathak, learned counsel for the petitioner. Also heard Mr. R.M. Das,

learned Standing Counsel, North Cachar Hills Autonomous Council (NCHAC) appearing for the

respondents.

2. The present petition has been filed under Section 11(6) of the Arbitration and

Conciliation Act, 1996 for appointment of an Arbitrator on the ground that after the dispute

has arisen between the petitioner and the NCHAC authorities, in terms of the Arbitration

Clause 20.1 of the Special Conditions of Contract (SCC), the matter is to be referred to the

Arbitrator in accordance with the Arbitration and Conciliation Act, 1996.

3. Mr. R.M. Das, learned Standing Counsel, NCHAC, however, submits that the dispute

arose out of termination of the contract by the Executive Engineer and there is a specific

provision under Clause 24.1 of the General Conditions of Contract (G.C.C.) of the Agreement

to the effect that if the contractor is of the view that the decision taken by the Engineer was

wrong, the said decision could be referred to the Dispute Review Board, and as such, there is

an Alternative Dispute Resolution Mechanism already in place under the said Agreement and

as such, before the said Arbitration Clause is evoked, the petitioner ought to have evoked the Page No.# 3/6

Dispute Resolution Clause as provided under Clause 24.1 of the General Conditions of

Contract and as such, the present petition is not maintainable.

4. In support of his submission that if there is an existence of an Alternative Resolution

Mechanism or forum available, as provided in the Agreement, the same must be first resorted

to, Mr. Das, learned Standing Counsel, NCHAC has relied upon the decision of this Court

rendered in Bharat Hydro Power Corporation Ltd. and Anr. Vs. A.S.E.B. and Anr .,

reported in 1999 (2) GLT 86 wherein it was held that if there is an alternative forum for

settlement of dispute, the same should be first resorted too.

5. Mr. Das, learned Standing Counsel, NCHAC has also referred to the decision rendered

by the Hon'ble Supreme Court in M.K. Shah Engineers and Constructions Vs. the State

of M.P., (1999) 2 SCC 594 to the same effect.

6. It has been, accordingly, submitted by learned Standing Counsel, NCHAC that the

petitioner should first invoke the said Dispute Resolution Mechanism as provided under Clause

24.1 of the General Conditions of Contract before invoking the Arbitration Clause.

7. Mr. B. Pathak, learned counsel for the petitioner, on the other hand, submits that the

said Clause 24.1 of the General Conditions of Contract is applicable when the decision is

taken by the Executive Engineer. He further submits that though in the present case, the

termination of the contract was by an order issued by the Executive Engineer, the Executive

Engineer had no such authority to terminate the contract inasmuch as only the "Employer"

can terminate the contract as provided under Clause 59.1 of the General Conditions of the

Contract, and who is the "Employer" has been also defined under the aforesaid Agreement as

the "Additional Chief Engineer, PWD (R&B) Hills, Assam, Haflong.

Page No.# 4/6

8. Under the circumstances, learned the Executive Engineer did not have any jurisdiction

or authority to terminate the contract. Only the Additional Chief Engineer, being the employer,

could terminate the contract as provided under Clause 59.1 of the General Conditions of

Contract.

9. Under the circumstances, this itself is also an issue which is required to be considered

by the Arbitrator.

10. Having heard the learned counsel for the parties, this Court would now concur with the

submission advanced by the learned counsel for the petitioner for the following reasons.

11. Though there is a Dispute Resolution Mechanism provided under Clause 24.1 of the

General Conditions of Contract, the said Clause will be applicable only when the decision

taken by the Executive Engineer which is considered to be wrong by the contractor.

12. In the present case, the contract was terminated by the Executive Engineer, and

normally, it would have been required to be referred for the Dispute Resolution under Clause

24.1 of General Conditions of Contract. However, it is also seen that the Executive Engineer

did not have any authority to terminate the contract. For this purpose, only the "Employer"

had the right to do so and the "Employer" has been defined under the Agreement as

Additional Chief Engineer, PWD (R&B) Hills, Assam, Haflong.

13. This Court is of the view that even if the contract was terminated by the Executive

Engineer, but since he did not have any authority, and it could have been terminated only by

the Additional Chief Engineer, PWD (R& B) Hills, Assam, Haflong, the dispute could not be

resolved by resorting to Clause 24.1.

Since the competency of the Executive Engineer to terminate the contract has been also Page No.# 5/6

challenged and there is a specific Clause in the Arbitration Agreement that the "Employer" is

the "Additional Chief Engineer, PWD (R &B) Hills, Assam, Haflong", who could terminate the

contract as provided under the General Conditions of Contract, this Court is of the prima facie

view that the said Clause 24.1 as urged upon by the learned Standing Counsel, NCHAC

appearing for the respondent will not be applicable.

14. Accordingly, this Court would hold that the present dispute can be resolved through

Clause 20.1 of the Special Conditions of Contract.

15. Though this Court had made the observation about the lack of competency of the

Executive Engineer to terminate the contract, in view of the definition of "Employer" as

"Additional Chief Engineer, PWD (R& B) Hills, Assam, Haflong, this issue is also open to be

decided by the Arbitrator.

16. Accordingly, for the reasons discussed above, the matter is referred to the Arbitrator.

17. Accordingly, as also agreed by the parties, this Court appoints Mr. P.C. Phukan, a

retired Judge of this Court as the sole Arbitrator, subject to the declarations to be made under

Section 12 of the Arbitration and Conciliation Act, 1996 (as amended) subject to his consent

and absence of any disabling condition.

18. Parties will accordingly, appear before the learned Arbitrator and thereafter, the

learned Arbitrator will proceed with the matter in accordance with law.

19. The Registry is directed to furnish a copy of this order to Mr. P.C. Phukan, Retired

Judge of this Court, the learned Arbitrator for doing the needful.

Page No.# 6/6

20. With the above observations and directions, the present petition stands disposed of.

JUDGE

Comparing Assistant

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter