Citation : 2022 Latest Caselaw 670 Del
Judgement Date : 7 March, 2022
IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 07.03.2022
+ O.M.P. (COMM.) No.51/2018
NATIONAL HIGHWAY AUTHORITY
OF INDIA .... Petitioner
versus
SHREE JAGANNATH EXPRESSWAYS
PVT. LTD. .... Respondent
Advocates who appeared in this case:
For the Petitioner : Ms Pinky Anand, Senior Advocate with Mr
Alok Kumar Jain, Mr Sumit Teterwal, Ms
Saudamini Sharma and Ms Kirti Dua,
Advocates.
For the Respondent : Mr Jaideep Gupta, Senior Advocate with
Ms Priya Kumar, Ms Aanchal Mullick and
Mr. Anirudh Bhatia, Advocates.
CORAM
HON'BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J
1. National Highway Authority of India (hereinafter the 'NHAI') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the 'A&C Act') impugning an arbitral award dated 29.09.2017 (hereinafter the 'impugned award') delivered by the Arbitral Tribunal consisting of Justice (Retired) V.K. Gupta, Justice (Retired) G.T. Nanavati and Justice (Retired) Deepak
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 Verma as the Presiding Arbitrator (hereafter the 'Arbitral Tribunal'). The impugned award was delivered by majority, with Justice (Retired) G.T. Nanavati entering a separate dissenting opinion with regard to the claims awarded.
2. The impugned award was rendered in the context of disputes that have arisen between the parties in connection with the Concession Agreement dated 06.08.2010 (hereafter the 'Concession Agreement').
Factual Background
3. In March 2008, NHAI through publication invited Request for Qualification (RFQ) for the work of "Six laning of Chadikhole- Jagatpur-Bhubaneswar section of NH-5 from Km 413.00 to 418.00 and from Km 0.00 to Km 62.00 in the State of Odisha" (hereinafter the 'Project') on design, build, finance, operate and transfer (DBFOT) basis. The concerned section of the National Highway is hereafter, referred to as the 'Project Highway'. After short listing the eligible bidders, NHAI issued a Request for Proposal (RFP).
4. Pursuant to the said RFP, the respondent (hereinafter 'SJE') submitted its bid and after evaluation of the bids, a Letter of Award (hereinafter the 'LoA') was issued in favour of SJE by NHAI on 29.04.2010.
5. Thereafter, on 06.08.2010, the Concession Agreement was signed between the parties.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
6. In terms of the Concession Agreement, SJE was granted the exclusive right, license and authority to construct, operate and maintain the Project Highway for a period of 26 years (including a construction period of 910 days) commencing from the appointed date. Further, SJE was also given the right to collect toll at the rate prescribed under the Fee Notification (hereinafter the 'Fee Notification').
7. In terms of Clause 4.1.2(b) of the Concession Agreement, one of the conditions precedent to be fulfilled by NHAI was the issuance of the Fee Notification, which enabled SJE to collect toll at the prescribed rate.
8. On 02.11.2010, NHAI forwarded a draft of the Fee Notification and sought SJE's consent regarding the same. SJE, responded by a letter dated 15.11.2010, pointing out certain inconsistencies with the draft of the Fee Notification. Thereafter, on 19.01.2011, SJE sent a letter referring to Schedule R of the Concession Agreement and requested NHAI to modify the Fee Notification in conformity with the said schedule.
9. It is material to note that the Project Highway existed and in terms of the Concession Agreement, SJE was entitled to collect toll from the Appointed Date - the date on which the Project entered commercial service in terms of Clause 15.1.1 of the Concession Agreement. Clause 15.1.1 of the Concession Agreement specified that SJE would be entitled to demand and collect user fee, in accordance with Clause 27 of the Concession Agreement, with effect from the Commercial
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 Operation Date ('COD'). It also stipulated that the COD would be the date on which the Conditions Precedent as specified in Clause 4 of the Concession Agreement were complied with or waived. Thus, SJE could commence tolling in respect of the Project Highway of a length of 67 kms from the Appointed Date, that is, even prior to completion of six- laning of the Project Highway. The Project Highway also included a bridge over river Mahanadi (hereinafter the 'Mahanadi Bridge') of a length of 2.25 kms. Additionally, three lanes were required to be added to the Mahanadi Bridge. The disputes between the parties centered around the question whether SJE could collect additional toll in respect of the Mahanadi Bridge prior to completing six-laning of the Project Highway.
10. On 29.04.2011, NHAI, once again, forwarded the Draft Fee Notification, without incorporating the suggestions of SJE, and called upon SJE to give its consent to the same. The Draft Fee Notification provided for tolling of the Mahanadi Bridge, on completion of the six- laning. In response to this, by a letter dated 04.05.2011, SJE conveyed its consent to the Draft Fee Notification subject to its right to seek "suitable contractual remedies".
11. On 10.06.2011, NHAI sent another letter seeking unconditional consent from SJE that it would not raise any litigation with respect to the Draft Fee Notification. SJE responded by a letter dated 16.06.2011 complying with the said request.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
12. The Fee Notification was finally published in the Official Gazette by the Ministry of Road, Transport and Highways (MORTH) on 19.10.2011.
13. On 28.02.2014, SJE informed NHAI that the construction of Mahanadi Bridge (additional three lanes) had been completed and thus, it was entitled to collect additional toll under the provisions of the Concession Agreement.
14. Thereafter, on 08.04.2014, after completion of all tests, the Mahanadi Bridge was opened to traffic.
15. On 30.04.2014, SJE through its letter, proposed to NHAI to revise the User Fee Rates, which were to be effective from 01.04.2014. However, NHAI, by a letter dated 28.05.2014, denied SJE's request to permit collection of additional toll for the Mahanadi Bridge. According to NHAI, SJE could collect additional toll in respect of the Mahanadi Bridge only after competition of the six-laning of the Project Highway.
16. The Completion Certificate for the Mahanadi Bridge was issued on 02.05.2014 after completing all the requisite formalities as stipulated in the Concession Agreement.
17. On 08.07.2014, SJE lodged a claim for loss of toll for the period of 08.04.2014 to 31.05.2014 amounting to ₹6,54,72,105/-. SJE continued to update its claim periodically. However, NHAI did not accept SJE's demand for revising the User Fee Rates to include additional toll for the Mahanadi Bridge.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
18. SJE being aggrieved by NHAI declining to revise the User Fee Rates to include additional toll in respect of the Mahanadi Bridge, issued a notice dated 04.11.2015 initiating the dispute resolution mechanism. A committee of 3 CGMs was constituted to assist the parties in resolution of the disputes. However, the Conciliation attempts failed.
19. On 29.12.2015, SJE invoked Clause 44.3 of the Concession Agreement (the Arbitration Clause) and sought reference of the disputes to arbitration.
20. The following claims were made by SJE in the Statement of Claims:
Claim Particulars Claim no.1 Loss of Revenue due to non-
collection of enhanced toll after the completion of construction of Mahanadi Bridge from 08.04.2014 till the date tolling is allowed to be started thereupon (claim raised till June 2016 was ₹104,05,69,939/-
which included a principal amount of ₹90,33,30,660/- and interest of ₹13,72,39, 279/-) Claim no.2 claim for interest @ 5% over the bank rate on claim 1 from the due date of payment i.e. 08.04.2014 till the actual date of payment Claim no.3 Costs as accrued
21. NHAI filed its Statement of Defence, however, it did not raise any counter-claims.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
22. In the meantime, during the course of the arbitral proceedings, the Provisional Completion Certificate for the Project Highway was granted on 06.01.2017 and SJE was permitted to collect the revised User Fee from 25.02.2017.
23. The impugned award was rendered by the Arbitral Tribunal on 29.09.2017.
24. The impugned award was delivered by majority. Justice (Retired) G.T. Nanavati penned a dissenting opinion rejecting the claims made by SJE. The Arbitral Tribunal (by majority) awarded a sum of ₹104,05,69,939/-, in favour of SJE. In addition, it also awarded pre- award interest at the rate of 5% above the bank rate; future interest at a rate of 2% above the bank rate; and costs amounting to ₹45 lacs.
25. Aggrieved by the impugned award, NHAI has filed the present petition.
Submissions
26. Ms Pinky Anand, learned senior counsel appearing for NHAI, contended that the arbitral award was vitiated by patent illegality as it was beyond the terms of the Concession Agreement and was, ex facie, contrary to the plain language of the Fee Notification. She contended that the Arbitral Tribunal (majority) had in fact re-written the terms of the Fee Notification, which is impermissible. She submitted that the Fee Notification expressly provided that the words and expressions, which were not defined in the Fee Notification but were defined in the Concession Agreement, would have the same meaning as assigned to
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 them in the Concession Agreement. She stated that the expression 'Six- Laning' and 'Construction Period' were defined under the Concession Agreement and the conclusion of the Arbitral Tribunal that SJE was entitled to collect additional toll in respect of the Mahanadi Bridge prior to completion of the Project (Six-Laning of the Project Highway) and during the Construction Period, was contrary to the plain language of the Fee Notification.
27. She submitted that the Arbitral Tribunal had embarked on an exercise to interpret the Fee Notification contrary to its plain language on the premise that it was not in conformity with Schedule R of the Concession Agreement and therefore, was required to be interpreted on a conjoint reading with Schedule R. She submitted that neither the Fee Notification, read on its plain terms, nor the draft of the Fee Notification, as set out in Schedule R, permitted additional tolling in respect of the Mahanadi Bridge from the date of its completion. She contended that the findings of the Arbitral Tribunal were thus, patently erroneous.
28. She also pointed out that one of the prayers sought by SJE before the Arbitral Tribunal was that NHAI be directed to publish a gazetted notification for increase in toll. She submitted that the said prayer clearly indicated that the Fee Notification did not contemplate levy of additional toll in respect of the Mahanadi Bridge. However, the impugned award proceeds on the basis that collection of additional toll in respect of the Mahanadi Bridge was permissible and therefore, runs contrary to SJE's understanding.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
29. Ms Anand also contended that the Fee Notification was issued by the Central Government in exercise of delegated legislative powers. Thus, the Arbitral Tribunal had no jurisdiction to read down the Fee Notification or interpret it in a manner contrary to its plain language.
30. Next, she submitted that the award of compensation to SJE in respect of loss allegedly suffered by it was prohibited under Clause 35 of the Concession Agreement and therefore, the impugned award was liable to be set aside.
31. Lastly, she submitted that the impugned award was vitiated by patent illegality as the Arbitral Tribunal had awarded a sum of ₹104,05,69,939/- on account of loss in revenue from collection of Fees, without any evidence as to the quantification of the said amount. She contended that SJE had not established the amount of loss allegedly suffered by it and the award of the said amount in its favour, was patently illegal.
32. Mr Jaideep Gupta, learned senior counsel appearing for SJE, countered the aforesaid submissions. He submitted that the contentions advanced on behalf of NHAI were in the nature of challenging the impugned award on merits, which is impermissible. He submitted that the grounds urged by NHAI for assailing the impugned award were beyond the scope of Section 34 of the A&C Act and therefore, the petition was liable to be dismissed at the threshold. He referred to the decisions of the Supreme Court in Associate Builders v. Delhi Development Authority: (2015) 3 SCC 49; National Highways
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 Authority of India v. JSC Centrodorstroy: (2016) 12 SCC 592; and Maharashtra State Electricity Distribution Company Limited v. Datar Switchgear Limited and Ors.: (2018) 3 SCC 133, in support of his contention.
33. He submitted that the approach of the Arbitral Tribunal to interpret the Fee Notification by a conjoint reading with the Concession Agreement cannot be faulted. He referred to the decisions of this Court in National Highways Authority of India v. IRB Ahmedabad Vadodara Super Express Tollways Private Limited: (2017) SCC OnLine Del 6891 and IRB Ahmedabad Vadodara Super Express Toll Ways Pvt. Ltd. v. National Highways Authority of India: (2018) SCC OnLine Del 8946 and contended that in the said cases, the arbitral award was set aside on the ground that the arbitral tribunal had ignored the provisions of the concession agreement. He contended that this clearly implies that the terms of the Concession Agreement are required to be considered, while construing the Fee Notification regarding levy of toll.
34. He submitted that the Arbitral Tribunal is the final adjudicator as to the interpretation of the contract as well as the evidentiary value of the material placed before it. In this case, the Arbitral Tribunal had interpreted Clause 35.2 of the Concession Agreement and concluded that it did not bar a claim for User Fees as SJE was prevented by NHAI from collecting the same. The Arbitral Tribunal also found that NHAI had not disputed the quantification of the claims and the contemporaneous correspondence between the parties established the
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 same. Thus, the impugned award is not amenable to challenge on the ground of patent illegality or as being in conflict with the public policy of India.
Reasons and Conclusion
35. At the outset, it is necessary to note that it is SJE's stated case that it is bound by the Fee Notification and is not challenging the same. NHAI had raised certain preliminary objections regarding maintainability of the claims filed by SJE before the Arbitral Tribunal. These included objections to the effect that (i) the challenge to the Fee Notification was barred by limitation; (ii) SJE was estopped from challenging the Fee Notification; and (iii) the Arbitral Tribunal had no jurisdiction to entertain a challenge to the validity of the Fee Notification.
36. All the three members of the Arbitral Tribunal had unanimously accepted that a challenge to the Fee Notification was barred on the aforesaid grounds. The Fee Notification was issued on 19.10.2011 and the arbitral proceedings commenced on receipt of the notice dated 29.12.2015. Therefore, a challenge to the Fee Notification was barred by limitation being beyond the period of three years from the date of its publication. SJE was also estopped from challenging the Fee Notification as it had given its unconditional consent to the Draft Fee Notification prior to its publication on 19.10.2011. It is also not disputed that the Arbitral Tribunal being a private tribunal did not have the
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 jurisdiction to consider any challenge to the Fee Notification as it was issued by the Central Government in exercise of its statutory powers.
37. SJE had successfully defended the preliminary objections raised by NHAI by stating, in unambiguous terms, that it was not challenging the Fee Notification but disputing the manner in which it was construed by NHAI.
38. In view of the above, the dispute is, essentially, centered around the question whether the Fee Notification contemplated levy of additional toll in respect of the Mahanadi Bridge on completion of its construction.
39. The Project Highway was already in existence and so was a bridge over the river Mahanadi. The Concession Agreement between the parties required SJE to widen the said Project Highway including the Mahanadi Bridge. Admittedly, SJE was entitled to collect toll in respect of the Project Highway of a length of 67 kms., even during the 'Construction Period' [the six-laning of the Project Highway]. The length of 67 kms of the Project Highway included the length of the extant bridge over the river Mahanadi.
40. Whilst, SJE claims that it is entitled to collect toll at a higher rate on completion of the works relating to the Mahanadi Bridge (after construction of three lanes over a length of 2.25 KM in addition to the extant four lanes of the Mahanadi Bridge) even prior to completion of the six-laning of the Project Highway, NHAI contends to the contrary. According to NHAI, SJE is entitled to collect a higher toll including on
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 account of construction of the Mahanadi Bridge after completion of the works of the Project Highway and not prior to it.
41. The Provisional Completion Certificate in respect of the Project Highway was issued on 06.01.2017 and therefore, there is no dispute that SJE could collect additional toll in respect of the Mahanadi Bridge thereafter - toll for 64.75 KM of Project Highway plus toll calculated for a structure (Mahanadi Bridge) costing ₹102.3 crores.
42. The principal question before the Arbitral Tribunal was whether SJE was entitled to additional toll in respect of the Mahanadi Bridge from the date of completion of the construction of the additional three lanes of the Mahanadi Bridge, and prior to issuance of the Provisional Completion Certificate/Completion Certificate under Clause 14 of the Concession Agreement.
43. The Arbitral tribunal (by majority) found in favour of SJE. It did not accept NHAI's contention that the claim of compensation on account of loss in collection of toll was barred under Clause 35 of the Concession Agreement. The Tribunal further held that the Concession Agreement permitted collection of toll for the Project Highway and in addition, for the permanent bridge or bypass or tunnel, costing over ₹50 crores. Since the cost of constructing the Mahanadi Bridge was in excess of the said amount, the Concession Agreement contemplated collection of additional toll in respect of the Mahanadi Bridge. The Arbitral Tribunal (by majority) held that the Fee Notification was
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 intended to effectuate the Concession Agreement and is, therefore, required to be construed accordingly.
44. In arriving at the conclusion, the majority examined the conduct of the parties before and after issuance of the Fee Notification. It found that the officials of NHAI had in their internal communications/notings accepted that SJE would be entitled to collect additional toll in respect of the Mahanadi Bridge on its completion (completion of the additional three lanes). Further, by a letter dated 23.02.2017, NHAI had permitted SJE to collect additional toll in respect of the Mahanadi Bridge with effect from 25.02.2017, even though the work regarding widening of the Project Highway was not completed as on that date.
45. Bearing the conduct of the parties, the Arbitral Tribunal (by majority) held that the clear import of the Fee Notification read with Schedule R of the Concession Agreement, is to allow additional tolling for the Mahanadi Bridge on its construction.
46. In view of the aforesaid finding, the Arbitral Tribunal awarded compensation for loss of toll revenue quantified at a sum of ₹90,33,30,660/- for the period up to June, 2016. In addition, the Arbitral Tribunal also awarded interest on the said sum quantified at ₹13,72,39,279/- (an aggregate amount of ₹104,05,69,939/-). The Arbitral Tribunal also held that SJE would be entitled to further compensation from June, 2016 to 25.02.2017. SJE had quantified the aggregate amount of compensation at ₹141,67,15,770/- (principal amount of ₹118,58,08,265/- and interest of ₹23,09,07,505/-). However,
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 NHAI had no occasion to examine the enhanced claim and therefore, the Arbitral Tribunal directed that subject to verification of the amount, NHAI would pay the balance amount for the period June 2016 to 25.02.2017.
47. In addition to the above, the Arbitral Tribunal also awarded pre- award interest at the prevailing bank rate plus 5% up to the date of the award and further, future interest at the prevailing bank rate plus 2%, till the date of payment. The Arbitral Tribunal also awarded costs of the arbitral proceedings in favour of SJE quantified at ₹45 lacs, which were directed to be included in the awarded sum for the purpose of computing future interest.
48. There is no cavil with the proposition that the scope of interference in an arbitral award is restricted to the grounds as set out in Section 34(2) of the A&C Act. In the context of the present petition, the question to be examined is whether the impugned award is in conflict with the public policy of India or is vitiated by patent illegality on the face of the award. It is well settled that if the arbitral award is contrary to the terms of the agreement, it would be amenable to challenge on the ground of patent illegality.
49. In the present case, one of the principal issues to be examined is whether the impugned award is contrary to the terms of the Fee Notification or the Concession Agreement.
50. Before proceeding further, it would be relevant to note certain clauses of the Concession Agreement.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
51. Clause 27 of the Concession Agreement contains provisions regarding 'User Fee'. In terms of Clause 27.1 of the Concession Agreement, SJE was vested with the sole and exclusive right to demand, collect and appropriate fee from users in accordance with the National Highway Fee (Determination of Rates and Collection) Rules, 2008. SJE and NHAI also acknowledged that a notification for levy and collection of fee would be issued by the Government under Section 8A of the National Highway Act, 1956. Clauses 27.1.1 and 27.1.2 of the Concession Agreement are relevant and set out below:
"27.1.1 On and from the COD till the Transfer Date, the Concessionaire shall have the sole and exclusive right to demand, collect and appropriate Fee from the Users subject to and in accordance with this Agreement and the National Highways Fee (Determination of Rates and Collection) Rules, 2008 (the "Fee Rules"); provided that for ease of payment and collection, such Fee shall be rounded off to the nearest 5 (five) rupees in accordance with the Fee Rules; provided further that the Concessionaire may determine and collect Fee at such lower rates at it may, by public notice to the Users, specify in respect of all or any category of Users or vehicles.
27.1.2 The Parties acknowledge that a notification for levy and collection of Fee shall be issued by the Government under Section 8A of the Act read with Rule 3 of the National Highways Fee (Determination of Rates and Collection) Rules, 2008 (the "Fee Notification") within 180 (One Hundred and eighty) days hereof, substantially in the form set forth in Schedule-R."
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
52. The relevant extract of Schedule R to the Concession Agreement is set out below:
"SCHEDULE-R
(See Clause 27.1.1)
FEE NOTIFICATION
MINISTRY OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS
(Department of Road Transport and Highways)
NOTIFICATION
New Delhi, the.........20............ S.O. .........................
And whereas,......................
Now, therefore, in exercise of the powers conferred by section 8A of the National Highways Act, 1956 (48 of 1956), read with Rule 3 of the of the National Highways Fee (Determination of Rates and Collection) Rules, 2008, the Central Government, having regard to the expenditure involved in building, maintenance, management and operation of the said section of the said national highway, interest on the capital invested, reasonable return, the volume of traffic and the period of said agreement between the Authority and the Concessionaire, hereby notifies that there shall be levied and collected fees on mechanical vehicles for the use of the section from Km 413.000 to km 418.000 and from km 0.000 to km 62,000 (Chandikhole
- Jagatpur - Bhubaneshwar) of National Highway No. 5 in the State of Orissa at the rate specified in the aforesaid Rules and authorises the said Concessionaire to collect and retain the said fees on and from the date of commercial operation of the said section of national highway, subject to and in accordance with the said Rules and the provisions of the aforesaid agreement. The fee levied and collected hereunder shall be due and payable at the following Toll Plazas for the distance for each such Toll Plaza:
S.No. Location of Toll Plaza Length (in km) for (Chainage) which Fee is payable 1 At km 40.50 of NH-5 67.000
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 In addition to the above, the fee levied and collected hereunder for the permanent bridges, bypass and tunnel, as the case may be, costing more than Rs.50 Cr. (Rupees fifty crore) or more as specified below shall be due and payable at the following Toll Plazas:
S. Location of Toll Plaza Nature of Cost (Rs.
chainage) structure Crore)
1 At km 40.50 of NH-5 Mahanadi Rs. 102.53
Bridge Crore
F.NO. RW/NH-.......................]
(Name)
Deputy Secretary
Government of India"
53. After SJE's bid was accepted and the parties had entered into the Concession Agreement, NHAI forwarded the draft of the Fee Notification dated 02.11.2010 proposed to be issued by the Central Government, to SJE. The relevant extract of the said Draft Fee Notification is set out below:
"[To be published in Part II, Section 3, Sub-section (ii) of the Gazette of India, Extraordinary] Government of India Ministry of Road Transport and Highways New Delhi, the,.................. , 2010
S.O. .........................
And whereas,...........
Now, therefore, in exercise of the powers conferred by section 8 A of the National Highways Act, 1956 (48 of 1956), read with the National Highways Fee (Determination of Rates and Collection) Rules, 2008, and in supersession of the notifications of the Government of India in the erstwhile Ministry of Shipping, Road Transport and Highways
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 (Department of Road Transport and Highways) number SO 1527 (E) dated the 18th September, 2006, SO 1774 (E) dated the 16th October, 2006 and SO 1392 (E) dated the 2nd June, 2008 except as respects things done or omitted to be done before such suppression, the Central Government, hereby notifies that there shall be levied and collected fees on category of mechanical vehicles specified in the following Tables, for the use of said section at the base rate specified thereof, and authorizes the said Concessionaire to collect and retain the fee subject to and in accordance with the said rules and the provisions of the said Concession Agreement on and form the date of commercial operation or publication of this notification in the Official Gazette, whichever is later, till the termination date, namely:-
Table I
xxxx xxxx xxxx
Table II
xxxx xxxx xxxx
Notes:-
1. For the purpose of this notification,-
(i) "actual fee" means the fees actually charged from the road users of the said section on the basis of-
(a) length of the project highway assigned to each fee plaza;
(b) base fee rates provided in the above Table duly indexed, and shall be rounded off to nearest Five rupee;
(ii) "date of commercial operation" means the date on which commercial operation of the said section begins after satisfying all Conditions Precedent in accordance with the said agreement;
(iii) "termination date" means the date on which the agreement entered into between the Authority and the Concessionaire expires pursuant to the provisions of the said agreement or is terminated by termination notice;
(iv) words and expressions used in this notification and not defined but defined in the agreement entered into between the Authority and the Concessionaire in respect of the said
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 section shall have the same meaning as assigned to them respectively in the said agreement.
2. The fee shall be collected at the following location of the Toll Plaza for the distance specified against the Toll Plaza:
A. During construction period.
S. No. Location of Toll Length (in km) for which Fee Plaza. payable.
1 Km 34.624 of NH-5 67.00
B. After completing of six laning. (This needs to be confirmed by the Tech Div) S. No. Location of Toll Length (in km) for which Fee Plaza. payable.
1 Km 40.50 of NH-5 Length of section shall be
confirmed by Tech Div and
for the bridge at Mahandi
River the estimated cost of
which is Rs 102.53 crores.
3. Exemption from payment of fee, rates of fee for overload vehicles, discounts in rates etc. shall be in accordance with the said Rules.
4. Upon request form any person for issue of 50 (fifty) or more one way tickets, the concessionaire shall issue such tickets valid for a period of one month, at a discounted rate equivalent to two-third of the fee payable for that category of vehicles.
5. The revision of fee shall not effected until a period of 6 (six) months has elapsed from the Commercial Operation Date.
(S S Gulia) Director to the Govt. of India [ F. No. NHAI/13013/571/10-11/CO/GC Bhubaneshwar (0.0-
62.0) BOT"
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
54. SJE responded by a letter dated 15.11.2010, requesting for certain amendments to the Draft Fee Notification. It, inter alia, sought deletion of the notes in the Draft Fee Notification and also sought replacement of the tables at point no.2 of the notes. The relevant extract of the amendments as sought by the SJE are set out below:
"The fee collected and levied hereunder shall be due and payable at the following Toll Plaza for the distance specified for the Toll Plaza:
SI Location of Toll Plaza (Chainage) Length ( in Km) for
No which fee is payable
1 At Km 40.50 of NH-5 (However exact 67.000
chainage will finalized in consultation with the IE & NHAI)
In addition to the above, the fee levied and collected hereunder for the permanent bridges, bypass and tunnel , as the case may be, costing more than ₹50 Cr ( Rupees Fifty crore) or more as specified below shall be due and payable at the following Toll Plaza:
SI Location of Toll Plaza Nature of Cost
No (Chainage) Structure (₹Crores)
1 At km 40.50 of NH-5 Mahanadi ₹102.53
(However exact chainage will Bridge Crores
finalized in consultation with
the IE& NHAI)
Instead of
1. The fee shall be collected at the following location of Toll Plaza for the distance specified against the Toll Plaza
A. During construction period.
SI Location of Toll Plaza. Length (in km) for which fee payable.
No
1 Km 34.624 of NH-5 67.00
Signature Not Verified
Digitally Signed
Signing Date:08.03.2022
SI Location of Toll Plaza. Length (in km) for which Fee payable.
No
1 At Km 40.50 of NH-5 Length of section shall be confirmed by
Tech Div and for the bridge at
Mahanadi River the estimated cost of
which is Rs 102.53 Crores"
55. Thereafter, SJE sent another letter dated 19.01.2011, inter alia, claiming that Schedule R of the Concession Agreement specified that the Concessionaire would be entitled to collect and retain fees from the COD and also permitted levy and collection of fees for permanent bridges, bypass and tunnels and therefore, the Fee Notification should have included the toll at Mahanadi Bridge from the date of COD, as the cost of the Mahanadi Bridge was more than ₹50 crores and Schedule R of the Concession Agreement specified so.
56. Admittedly, the suggestions made by SJE were not accepted by NHAI. NHAI once again forwarded a draft of the Fee Notification under the cover of the letter dated 29.04.2011, and sought consent of SJE. The draft of the Fee Notification annexed with the letter did not include any amendments as requested by SJE. SJE, by its letter dated 04.05.2011, protested against the proposed Fee Notification as it did not incorporate the suggested changes communicated by its letter dated 15.11.2010. SJE also reiterated its stand that the proposed Fee Notification was not in conformity with Schedule R of the Concession Agreement. The relevant extract of the said letter is reproduced below:
"The draft Fee Notification issued by yourself is not in conjunction with the "Concession Agreement" entered into with the Authority the reference of which needs to be included in para 2 of the Notification.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 Further, we once again bring to your notice that as per the Schedule R of the Concession Agreement executed with NHAI on August 6, 2010, the fee shall be collected by the Concessionaire as follows: "The fee levied and collected hereunder shall be due and payable at the following Toll Plazas for the distance specified for each such Toll Plaza:
S. Location of Toll Plaza Length (in Km) for which fee is
No. (Chainage) payble
1 At Km 34.800 of NH-S 67.000
In addition to the above, the fee levied and collected hereunder for the permanent bridges, bypass and tunnel, as the case may be, costing more than Rs. 50 Cr (Rupees Fifty crore) or more as specified below shall be due and payable at the following Toll Plazas:
S. Location of Toll Plaza Nature of Cost (Rs.
No. chainage) structure Crores)
1 At Km 34.800 of NH-5 Mahanadi Rs. 102.53
Bridge Crores"
There was no specific exclusion of totalling in either of these two locations during the construction phase as per Concession Agreement. Thus, it was imperative that the toll can be collected in both the locations during the construction phase.
However, in view of the delay in getting the COD pending the resolution of the above matter which is having adverse financial impact on us, we agree for issuance of this Fee Notification in the present form proposed by yourself (draft Fee Notification) reserving our right to seek suitable contractual remedies under the Concession Agreement, Applicable Laws and otherwise in respect of matters expressed above."
57. It is clear from the above that the issue regarding exclusion of tolling during the construction phase was raised by SJE at the material time. It sought to reserve its right to take 'suitable contractual remedies'. However, the same was not acceptable to NHAI; NHAI/MORTH required an unconditional consent from SJE that no litigation would be raised by it with respect to the Draft Fee Notification. NHAI
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 communicated this to SJE by its letter dated 10.06.2011 and called upon SJE to furnish its unconditional consent to the Draft Fee Notification. Thereafter, by a letter dated 16.06.2011, SJE communicated its unconditional consent to the Draft Fee Notification as enclosed. It also furnished an undertaking in the following terms:
"We hereby give an undertaking that we shall not raise any litigation in any court in regard to the Draft Fee Notification."
58. In view of the above, the Fee Notification was issued on 19.10.2011. The relevant extract of the Fee Notification is set out below:
"1. For the purpose of this notification
(i) "actual fee" means the fees actually charged from the road users of the said section on the basis of-
(a) length of the project highway assigned to each fee plaza;
(b) base fee rates provided in the above Table duly indexed; and shall be rounded off to nearest Five rupee;
(ii) "date of commercial operation" means the date on which commercial operation of the said section begins after satisfying all Conditions Precedent in accordance with the said agreement.
(iii) "termination date" means the date on which the agreement entered into between the Authority and the Concessionaire expires pursuant to the provisions of the said agreement or is terminated by termination notice;
(iv) words and expression used in this notification and not defined but defined in the agreement entered into between the Authority and the Concessionaire in respect of the said section shall have the same meaning as assigned to them respectively in the said agreement.
2. The fee shall be collected at the following location of the toll plaza for the distance specified against the toll plaza:
A. During construction period
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 S Location of Toll Plaza. Length (in Km) for No. which Fee payable.
1 Km 34.26 till the construction of fee 67.00 plaza at Km 40.50 of NH 5 or at a new location to be finalised in consultation with Independent Engineer and the Authority.
B. After competing of six laning.
S. Location of Toll Plaza Lenth (in Km) for which Fee
No. payable.
1 Km 34.624 till the construction of 64.75 Kilometeres and for the
fee plaza at Km 40.50 of NH 5 or at bridge at Mahanadi River of
a new location to be finalised in 225 Kms length, the estimated
consultation with Independent cost of which is Rs. 102.53
Engineer and the Authority. crores."
59. Although SJE had unconditionally accepted the Fee Notification, it claims that it is entitled to collect toll in respect of the Mahanadi Bridge on completion of the new Mahanadi Bridge notwithstanding that six-laning of the Project Highway was incomplete.
60. The definitions of the expressions 'Appointed Date'; 'Construction Period'; 'Project Completion Date' and 'Six-Laning' are relevant as the said expressions are used in the Fee Notification. The said expressions are not defined under the Fee Notification but they have been expressly defined under Clause 48 of the Concession Agreement as under:
"Appointed Date" means the date on which the Project enters into commercial service under Clause 15.1.1, and
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 shall be deemed to be the date of commencement of the Concession Period"
** ** ** ** ** "Construction Period" means the period beginning from the Appointed Date and ending on the Project Completion Date.
** ** ** ** ** "Project Completion Date" means the date on which the Completion Certificate or the Provisional Certificate, as the case may be, is issued under the provisions of Article 14.
** ** ** ** ** "Six-Laning" or "Six-Lane" means the construction and completion of all works included in or constituting a Six- lane Project Highway, as specified in Article 2 read with Schedule-B and Schedule-C.""
61. The definition of the expression 'Construction Period' is unambiguous. The said period commences from the 'Appointed Date' and ends with the 'Project Completion Date'. The term 'Appointed Date' is defined to mean the date on which the Project enters into commercial service under Clause 15.1.1 of the Concession Agreement
- the COD. In terms of Clause 15.1.1 of the Concession Agreement, COD is the date on which the Conditions Precedent, as specified in Clause 4 of the Concession Agreement, are complied with or waived.
62. The Project Completion Date is defined to mean the date on which the Completion Certificate or the Provisional Completion Certificate is issued under Clause 14 of the Concession Agreement. In the present case, the Provisional Completion Certificate of the Project
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 Highway was issued on 06.01.2017 and there is no dispute that SJE is entitled to collect additional toll thereafter. The definition of six-laning is also free from any ambiguity.
63. By virtue of Note 1(iv) of the Fee Notification, the expressions used in the Concession Agreement have been incorporated by reference to the Fee Notification.
64. Indisputably, on a literal reading of the Fee Notification, SJE was not entitled to charge any additional toll in respect of the Mahanadi Bridge till the completion of the 'Construction Period' as was expressly stated in Note 2 of the Fee Notification.
65. However, the Arbitral Tribunal was of the view that the Fee Notification was required to be read conjointly with Schedule R to the Concession Agreement. The Arbitral tribunal reasoned the Fee Notification differed from Schedule R and in terms of Clause 27.1.2 of the Concession Agreement, it was agreed that the Fee Notification would be "substantially in the form set forth in Schedule R."
66. As noticed above, Schedule R to the Concession Agreement includes two tables. The first table indicates that the user fee would be payable for 67.000 km at a toll plaza located at km 40.50 of NH-5. It further provides that in addition, fee levied and collected in respect of permanent bridges, bypass and tunnels as the case may be, costing ₹50 crores or more, would be due and payable on the toll plaza located at km 40.50 of NH-5 for the structure of Mahanadi Bridge with a cost of ₹102.53 crores.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
67. According to SJE, it was entitled to collect base toll for the entire stretch of 67 kms (including the Mahanadi Bridge) during the construction phase, but after completing the widening of the Mahanadi Bridge by adding three lanes. It would also be entitled to charge extra toll for the entire length of the bridge of 2.25 kms in addition to toll in respect of the balance stretch of 64.75 kms of the Project Highway.
68. NHAI contends to the contrary. According to NHAI, the expression "after completion of six-laning" is required to be construed as six-laning of the entire Project Highway. It claimed before the Arbitral Tribunal that after completion of six-laning of the Project Highway, the claimant (SJE) would be entitled to collect additional toll in respect of the new Mahanadi Bridge (the extant four lanes and three newly constructed lanes).
69. The Arbitral Tribunal (by majority) found in favor of SJE and held that in terms of Schedule R to the Concession Agreement, SJE was entitled to collect additional toll for the Mahanadi Bridge on its completion. This decision of the Arbitral Tribunal is founded, principally, on three findings. First, in terms of Schedule R to the Concession Agreement, SJE is entitled to collect additional toll for the Mahanadi Bridge. Since the Fee Notification was issued to give effect to the Concession Agreement, it is required to be construed keeping in mind the said object.
70. Second, the conduct of the parties indicated that that there was consensus between them that toll would be collected in respect of the
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 Mahanadi Bridge after its completion. The internal noting of the Chairman, NHAI indicated that a reference note had been placed before him at the material time. The possibility of SJE claiming that it was entitled to collect toll in respect of the Mahanadi Bridge even prior to it constructing the additional three lanes was considered. The Mahanadi Bridge was existing at the time the parties had entered into the Concession Agreement and a Fee Notification in the form of Schedule R construed literally could possibly be read as enabling the Concessionaire to collect additional toll in respect of the Mahanadi Bridge immediately from the Appointed Date (from the beginning of the Construction Period). It appears that in this context, the Chairman, NHAI had communicated his view that the additional tolling in respect of the Mahanadi Bridge could commence only after the completion (construction of the additional three lanes). The communication (letter dated 24.04.2014) sent by the Project Director to the Regional Officer, NHAI, which was marked to SJE as well, also indicates that a decision to that effect was taken by the Competent Authority at the material time.
71. Third, that SJE was permitted to toll the Mahanadi Bridge prior to completion of the Project, that is, prior to completion of the six-laning of the Project Highway. By a letter dated 23.02.2017, NHAI had approved the revised User Fee Rates, which included User Fee in respect of the Mahanadi Bridge (length of 2.25. Kms. costing ₹102.53 crores).
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
72. The said findings, which persuaded the Arbitral Tribunal to hold that SJE was entitled to collect toll in respect of the Mahanadi Bridge with effect from 08.04.2014, raises contentious issues.
73. SJE had, by its letter dated 16.06.2011, waived its objections to the Fee Notification. Admittedly, the Fee Notification was not in conformity with Schedule R to the Concession Agreement. SJE was aware of the same and had objected to it but, subsequently communicated its unconditional consent. Therefore, there is substance in the contention that the Fee Notification was not required to be read conjointly with Schedule R to the Concession Agreement.
74. The reasoning of the Arbitral Tribunal that the conduct of NHAI in permitting tolling of the Mahanadi Bridge with effect from 25.02.2017 indicates that the parties had understood that the toll in respect of the Project could be collected prior to completion of the six- laning of the Project Highway is, ex facie, erroneous. It was NHAI's case that collection of additional toll with respect to the Mahanadi Bridge was not permissible during the Construction Period. The said period commenced from the Appointed Date and ended on the Project Completion Date. The Project Completion Date is defined under the Concession Agreement to mean the date on which the Completion Certificate or Provisional Certificate is issued under the provisions of Clause 14 of the Concession Agreement. In this case, a Provisional Completion Certificate in terms of Clause 14 of the Concession Agreement was issued on 06.01.2017, while keeping the incomplete works in the Punch List. The conclusion of the Arbitral Tribunal that
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 the conduct of NHAI, to permit tolling of the Mahanadi Bridge after issuing Provisional Completion Certificate, is inconsistent with its stand that the tolling of the Mahanadi Bridge was not permissible during the construction period (that is period from the Appointed Date to Project Completion Date). On the contrary, NHAI's stand that additional toll in respect of the Mahanadi Bridge was permissible after the Construction Period is consistent with its conduct to permit collection of additional toll after issuance of the Completion Certificate in terms of Clause 14 of the Concession Agreement.
75. Having stated the above, this Court must necessarily bear in mind the narrow scope of examination under Section 34(2)(b)(ii) and Section 34(2A) of the A&C Act. The Arbitral Tribunal had construed the Fee Notification by applying the rule of purposive interpretation. Undeniably, there is material on record, which would support the view that the parties had understood that collection of additional toll in respect of Mahanadi Bridge was permissible after its completion. It is not impossible to read the expression 'six-laning' as used in the Fee Notification as referring particularly to Mahanadi Bridge (although the Mahanadi Bridge would be on seven lanes- four extent plus three construed by SJE) . If read in this manner, SJE would be entitled to collect toll for the length of 2.25 Kms. of the Mahanadi Bridge in addition to toll in respect of 64.75 Kms. road length (being the remaining Project Highway).
76. Given the limited scope of interference with an arbitral award, this Court is unable to accept that interference with the conclusion of
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 the Arbitral Tribunal (by majority) in regard to the interpretation of the Fee Notification, is permissible on the touchstone of Section 34(2)(b)(ii) and Section 34(2A) of the A&C Act.
77. The next question to be examined is whether the conclusion of the Arbitral Tribunal that NHAI is liable to compensation for the loss occasioned on account of non-collection of fees is contrary to Clause 35 of the Concession Agreement.
78. Clause 35.2 of the Concession Agreement, which is relied upon by NHAI, reads as under:
"35.2 Compensation for default by the
Authority
Subject to the provisions of Clause 35.6, in the event of the Authority being in material default or breach of this Agreement at any time after the Appointed Date, it shall pay to the Concessionaire by way of compensation, all direct costs suffered or incurred by the Concessionaire as a consequence of such material default within 30 (thirty) days of receipt of the demand supported by necessary particulars thereof; provided that no such compensation shall be payable for any breach or default in respect of which Damages have been expressly specified in this Agreement. For the avoidance of doubt, compensation payable may include interest payments on debt, O&M Expenses, any increase in capital costs on account of inflation and all other costs directly attributable to such material default but shall not include loss of Fee revenues, debt repayment obligations or other consequential losses, and for
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 determining such compensation, information contained in the Financial Package and the Financial Model may be relied upon to the extent it is relevant."
79. The said Clause expressly provides that in the event of NHAI being in breach of the Concession Agreement, it would be liable to pay compensation for all direct costs suffered or incurred by the concessionaire as a consequence of such material default. However, such compensation would not include "loss of Fee revenues, debt repayment obligations or other consequential losses".
80. The Arbitral Tribunal had concluded that Clause 35.2 of the Concession Agreement would only apply where there is a material breach leading to delay. Clause 35.2 of the Concession Agreement begins with the words "Subject to the provisions of Clause 35.6," which enjoins the affected party to take steps to mitigate costs. The Arbitral Tribunal reasoned that since there is no possibility of mitigation of loss in the present case, Clause 35.2 of the Concession Agreement is inapplicable.
81. Clause 35.6 of the Concession Agreement reads as under:
"35.6 Mitigation of costs and damage
The Affected Party shall make all reasonable efforts to mitigate or limit the costs and damage arising out of or as a result of breach of Agreement by the other Party."
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
82. There is merit in NHAI's contention that the aforesaid reasoning is manifestly erroneous. Clearly, if it is not possible for the affected party to mitigate the loss then its right to seek compensation under Clause 35.2 of the Concession Agreement, is not affected. The right of the affected party to claim compensation would be debilitated only if it was possible for the affected party to mitigate the loss but it had failed to do so as required under Clause 35.6 of the Concession Agreement. Justice (Retd.) Nanavati had expressly rejected the contention that Clause 35.2 of the Concession Agreement was restricted to breach of the Concession Agreement that led to delay in the construction activity. The language of Clause 35.2 of the Concession Agreement does not indicate any such restriction. It expressly provides that NHAI would be liable to pay compensation for all direct costs incurred resulting from the breach of the Concession Agreement on the part of NHAI.
83. Clause 35.2 of the Concession Agreement proscribes certain consequential losses including loss of Fee revenues. The Arbitral Tribunal has also indicated - although not in express words - that the loss claimed is not an indirect or inconsequential loss but a direct one. This view is a plausible one and therefore, the conclusion that Clause 35.2 of the Concession Agreement did not prohibit a claim for Fee for direct costs would not warrant any interference in these proceedings.
84. The last contention to be examined is whether the impugned award to the extent it accepts SJE's quantification of the claim is vitiated by patent illegality. NHAI claims that the claim as quantified was accepted without any material or evidence to prove the same.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
85. In its Statement of Claims, SJE had stated that it had lodged its claim for the first time on 08.07.2014 and had thereafter, updated and revised its claim at periodical intervals through various letters that were annexed as Annexure C-44 to Annexure C-61 to the Statement of Claims. SJE stated that the total amount reflected in the said letters till the month of June, 2016 was ₹104,05,69,939/- (Principal Amount- ₹90,33,30,660/- and interest amount-₹13,72,39,279/-). It further stated that since the breach was continuing, the amount claimed would continue to increase till the conclusion of the arbitral proceedings and therefore, it sought permission to amend the claim.
86. SJE claimed that it had calculated the amount as mentioned in the letters on the basis of the rates recommended by the Project Director, NHAI in its letter dated 24.04.2014. These rates were effective for the year 2014-15 and had been increased for the subsequent years according to the formula as provided in Schedule R of the Concession Agreement.
87. It is clear from the Statement of Claims that the only material relied upon by SJE for establishing the quantum of compensation was the letter dated 24.04.2014 sent by the Project Director, NHAI and the letters sent by SJE to NHAI raising its claims.
88. The letter dated 24.04.2014 was sent by the Project Director, NHAI to the Regional Officer, NHAI in reference to a letter dated 08.03.2014 sent by SJE, setting out tabular statement specifying the User Fee for various categories of vehicles for varying use (one way journey, return journey and for monthly pass for a maximum of fifty
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 one-way journeys). SJE had sought approval of the said fees and for further initiation of revision of the notified User Fee. The Project Director, NHAI had recommended the rates as specified in the letter. SJE had also appended a statement setting out the computation of the User Fees.
89. In view of the above, there is material on record to establish the enhanced User Fee that was payable in respect of different categories of vehicles and for different journeys.
90. SJE claimed that it had, on the basis of the said recommended rates, raised a claim by its letter dated 08.07.2014, which was updated periodically (Annexure C-44 to Annexure C-61). A reading of the said letters indicates that they contain a tabular statement of four columns: the first indicating the date; second the "Toll fees collectable on inclusion of fees for Mahanadi bridge completion"; the third the "Toll fees collectable on exclusion of fees for Mahanadi bridge completion"; and the fourth, stating difference of two figures under the preceding columns. The figures in the last column are claimed as the loss suffered by SJE for non-collection of fees for the Mahanadi Bridge. An extract of the said table set out in the letter dated 08.07.2014, indicating the structure of the tabular statement, is set out below:
Date(08.04.1 Toll fees Toll fees Loss to SJEPL 4-31.05.14) collectable on collectable on for non inclusion of fees exclusion of fees for collection of for Mahanadi Mahanadi bridge fees for bridge completion completion Mahanadi bridge(Rs) 8-Apr-14 3363300 2211830 1151470
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
91. There is no material on record to establish the basis for computation of the said figures mentioned in the table. As an illustration, a sum of ₹33,63,300/- is reflected as the toll fees collectible on 08.04.2014 by inclusion of fees for the Mahanadi Bridge and the sum of ₹22,11,830/- is reflected as the toll fees collectible on 08.04.2014 by exclusion of fees for the Mahanadi Bridge completion. According to SJE, the loss incurred on 08.04.2014 would thus be ₹11,51,470/-. As stated above, there is no evidence or material on record to indicate how these figures were computed. There is no material to establish that ₹33,63,300 would be collected on 08.04.2014 if collection of additional user fee for the Mahanadi Bridge was allowed on 08.04.2014. Similar tabular statements were claimed to have been forwarded by SJE on a monthly basis (C-44 to C-61).
92. NHAI, in its Statement of Defence, had denied the said claim. It had stated that the said claim is "false, frivolous, baseless, contrary to the terms and conditions of the Concession Agreement and is contrary to the said Fee Notification dated 19.10.2011".
93. Notwithstanding the fact that there was no material to substantiate the aforesaid calculation, the Arbitral Tribunal (by majority) accepted SJE's claims by referring to Section 19(1) of the A&C Act, which expressly provides that the Arbitral Tribunal would not be bound by the Code of Civil Procedure,1908 or the Indian Evidence Act,1872.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
94. The Arbitral Tribunal further reasoned that the claims made by SJE in its letters (Annexure C-44 to Annexure C-61) were not denied at the material time and NHAI's defence to the Statement of Claims was a bare denial.
95. According to SJE, NHAI had neither responded to any of its letters raising the claims (Annexure C-44 to Annexure C-61) nor denied the said claims and therefore, there was no dispute as to quantification of the amounts due. However, NHAI has specifically denied the claims made by SJE including quantification in its Statement of Defence. It was thus necessary for SJE to produce some material to establish the same. The burden to prove quantification of loss rested entirely on SJE. However, SJE did not produce any evidence to substantiate the quantum of its claim except the letters sent by it raising its claims on a periodical basis. Plainly, a letter raising a claim is not a proof thereof. It does not establish anything more than the fact that a claim was made.
96. The Arbitral Tribunal held that the claims made were on the basis of Schedule R of the Concession Agreement and the Wholesale Price Index. The Arbitral Tribunal had further observed that "A perusal of the detailed working contained in each claim document shows that the Claimant had taken the figures pertaining to volume of traffic from the daily records maintained at the tolling booth" and had sought additional toll calculated as per Schedule R and the wholesale price index for the said volume of traffic." This finding is, ex facie, contrary to the record. Annexure C-44 to Annexure C-61 neither reflects the volume of traffic nor any computation reflecting the enhanced toll
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 payable in respect of vehicles of a particular category included in the traffic. 'Traffic' is the movement of number of vehicles (of various categories) using the Project Highway. The toll collected in respect of the said traffic is a function of a number of vehicles of different categories for different categories of journey and the applicable User Fees. However, the claims made by SJE do not reflect the number of vehicles; their categories; or the kind of journey. The claims also did not reflect the actual toll collected but it mentioned the fee, which, according to SJE, was 'collectable' both by inclusion of additional toll for the Mahanadi Bridge and without including the same.
97. The Statement of Claims do not indicate any computation except the computation of the difference in two figures for each day, which according to SJE was the loss suffered by it. The Arbitral Tribunal thus had no material to verify or satisfy itself that the quantification of the claim made was a true estimate of the additional toll that would have been collected by SJE.
98. The Arbitral Tribunal proceeded on the assumption that NHAI had not disputed the quantification as it had made the following averments in its Statement of Defence: "When the claimant is not entitled to the alleged claim for additional toll, therefore the question of going in to quantification or its correctness thereof does not arise." This, according to SJE, reflected that NHAI did not dispute the quantification of the claims made. The said statement is required to be read in the context of the Statement of Claims. NHAI in its Statement
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 of Defence had denied the averments made in paragraphs 35 and 36 of the Statement of Claims as under:
35-36. Para No.35 and 36 of the Statement of Claim are not admitted and are denied. The Claimant wrongly raised the false and frivolous claim vide its letter dated 8.7.2014. All the alleged claims raised by the Claimant vide its letters dated 8.7.2014, 16.8.2014, 22.10.2014, 3.12.14, 1.1.2015, 14.2.2015, 31.3.2015, 24.4.2015, 30.5.2014, 1.8.2015, 7.9.15, 29.10.2015, 24.11.2015, 11.2.2016, 16.3.2016, 6.4.2016, 1.7.2016 and 19.7.2016 are not admitted and are denied. Annexure C-44 to C- 61 are not admitted and are denied. The total alleged claim raised by the Claimant till June 2016 for Rs.104,05,69,939/- is not admitted and is denied. The claimant is not entitled to the alleged amount, it is denied that the alleged breach is continuing. There is no breach. The claimant is not entitled for any alleged amendment. All the above alleged clams filed by the Claimant are false, frivolous, baseless, contrary to terms and conditions of the Concessionaire Agreement and are contrary to the said Fee Notification dated 19.10.2011 and the same are liable to be dismissed. The Claimant is not entitled to any amount. The Claimant is not entitled to any interest as such the alleged claim no.1 is liable to be dismissed.
The procedure adopted by the claimant for quantification of the alleged claim is not admitted and is denied. When the claimant is not entitled to the alleged claim for additional toll therefore the question of going in to quantification or its correctness thereof does not arise. The Claimant is not entitled to any
Signature Not Verified Digitally Signed
Signing Date:08.03.2022 amount. All the allegations to the contrary are not admitted and are denied."
99. NHAI's statement that SJE was not entitled to claim for additional toll and therefore, there was no question of going into quantification or correctness thereof, was in response to SJE's statement that NHAI had not disputed the quantification of loss in its letters. NHAI stated that it had denied SJE's entitlement to claim additional toll in terms of the Fee Notification, and therefore, there was no question of it examining the quantification. NHAI does not dispute that it had not examined the quantification of the claims as raised in the letters at the material time. However, it had denied the same in the arbitration. Indisputably, NHAI has disputed the claim as quantified by SJE, in its Statement of Defence.
100. It is well settled that this Court cannot re-appreciate / re-examine the evidence in proceedings under Section 34 of the A&C Act. However, in cases where it is found that there is no evidence to substantiate the claim, as in the present case, interference with the Arbitral Award is warranted.
101. The decision of the Arbitral Tribunal to accept SJE's claims of quantification clearly amounts to accepting the claim without any evidence to establish the amount of loss as claimed.
102. In view of the above, this Court is of the view that the impugned award is vitiated by patent illegality. The same is, accordingly, set aside.
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
103. The parties are left to bear their own costs.
104. The petition is accordingly disposed of.
VIBHU BAKHRU, J
MARCH 07, 2022 gsr, RK, pkv/v
Click here to check corrigendum, if any
Signature Not Verified Digitally Signed
Signing Date:08.03.2022
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!