Friday, 17, May, 2024
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Oil Industry Development Board vs Godrej And Boyce Mfg Co Ltd
2022 Latest Caselaw 335 Del

Citation : 2022 Latest Caselaw 335 Del
Judgement Date : 2 February, 2022

Delhi High Court
Oil Industry Development Board vs Godrej And Boyce Mfg Co Ltd on 2 February, 2022
$~5
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                            Date of decision: 02.02.2022
+     ARB.P. 1176/2021
      OIL INDUSTRY DEVELOPMENT BOARD                      ..... Petitioner
                          Through      Mr. K.R. Sasiprabhu and Mr. Tushar
                                       Bhardwaj, Advs.

                          versus

      GODREJ AND BOYCE MFG CO LTD           ..... Respondent
                   Through Mr. Sumit Chander and Mr. Gurdeep
                           Chauhan, Advs.

      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                         J U D G M E N T (oral)

1. The present petition has been filed under Section 11 (4) (a) of the

Arbitration and Conciliation Act, 1996 seeking appointment of sole

Arbitrator to adjudicate the disputes with respondent.

2. Petitioner is a statutory body established under the Oil Industry

Development Act, 1974. Respondent is company incorporated under the

Companies Act. Petitioner claims to have invited bids for interior works

(including internal electricals) for ground First, Second and Third Floor of G

+ 3 Block of the Oil Industry Development Board Office at Plot No.02,

Sector 73, Noida. Respondent participated in the said bid and was successful ARB.P. 1176/2021 Page 1 of 4 in the same. Subsequently, petitioner vide its letter dated 04.06.2008

accepted the respondent's bid and in furtherance thereof, an

Agreement/Contract dated 25.06.2008 was executed between the parties. As

per the said Contract, respondent was required to coordinate and consult

Engineers India Limited (EIL) for the proper execution of the project work.

However, there were gross delays in the execution of the contractual work

by the respondent due to which the petitioner had terminated the contract

and encashed the bank guarantees to realise Liquidated Damages, which

respondent was liable to pay to the petitioner in terms of the aforesaid

Agreement/Contract.

3. According to petitioner, respondent thereafter raised a dispute under

the Contract and in terms of clause 82.1 of the GCC sought settlement by

way of arbitration. Respondent vide letters dated 17.03.2011 and 29.04.2011

requested the respondent for appointment of an Arbitrator. However,

petitioner thereafter vide letter dated 18.05.2011 appointed the sole

Arbitrator and the proceedings commenced. Also, respondent filed petition

seeking appointment of Arbitrator before this Court being Arbitration

Petition No.74 of 2011, however, the said petition was dismissed as

infructuous vide Order dated 19.05.2011 passed by this Court. The learned ARB.P. 1176/2021 Page 2 of 4 sole Arbitrator conducted the Arbitration Proceedings and passed the Award

dated 25.06.2008. Nevertheless, the said Award was challenged by

petitioner before this Court vide OMP No.601 of 2012 inter alia on the

grounds that the learned sole Arbitrator had rejected the Counter Claims of

the petitioner on the only ground that those were never claimed prior to the

Arbitration Proceedings. The said OMP No.601/2012 was partially allowed

by this Court vide judgement dated 16.09.2019 wherein it was observed as

under:

"37. In view of the above, the Award insofar as it refuses to consider the counter-claim of the petitioner is set aside, leaving it open to the petitioner to agitate its claims in accordance with law."

4. In terms of the liberty granted by this Court vide judgement dated

16.09.2019, petitioner sent a letter dated 26.02.2020 to the learned sole

Arbitrator requesting to reconvene the proceedings and to decide its Counter

Claims. Learned sole Arbitrator vide email dated 04.03.2020 consented to

enter upon reference and decide counterclaims of OIDB as in terms of the

liberty granted by this Court. The first hearing through video conferencing

was held on 24.06.2020, wherein respondent also agreed to continue the

Arbitration and accordingly case was re-opened but due to ongoing ARB.P. 1176/2021 Page 3 of 4 pandemic, further hearing could not be held. Now, the learned sole

Arbitrator vide his email dated 7.10.2021 has expressed his inability to

conduct the arbitration proceedings and rescued himself from arbitration.

Hence, the present petition has been filed.

5. Learned counsel appearing on behalf of respondent has agreed to the

appointment of substituted sole Arbitrator by this Court for adjudication of

dispute between the parties.

6. In view of the above, the present petition is allowed. Accordingly,

Mr. Justice (Retd.) Indermeet Kaur (Mobile: 9910384614) is appointed

sole Arbitrator to adjudicate the dispute between the parties.

7. The fee of the learned Arbitrator shall be governed by the Fourth

Schedule of the Arbitration and Conciliation Act, 1996.

8. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration.

9. The present petition stands disposed of accordingly.

10. A copy of this order be sent to the learned Arbitrator for information.

(SURESH KUMAR KAIT) JUDGE FEBRUARY 02, 2022/rk ARB.P. 1176/2021 Page 4 of 4

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 
 
Latestlaws Newsletter
 
 
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2024

 

LatestLaws.com presents 'Lexidem Online Internship, 2024', Apply Now!

 
 
 
 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

Publish Your Article

Campus Ambassador

Media Partner

Campus Buzz