Citation : 2021 Latest Caselaw 3347 Del
Judgement Date : 7 December, 2021
$~2
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 07.12.2021
+ ARB.P. 784/2021
SIMPLEX INFRASTRUCTURES LIMITED ..... Petitioner
Through Mr. Kirti Uppal, Sr. Adv. with Mr.
Ayush Aggarwala, Mr. Samrat
Sengupta, Ms. Riya Gulati and Mr.
Ishan Thakur, Advs.,
versus
DIRECTOR GENERAL MARRIED ACCOMMODATION
PROJECT ..... Respondent
Through Mr. Harish Vaidyanathan Shankar,
CGSC with Mr. Karan Chhibber and
Ms. S. Bushra Kazim, Advs.
CORAM:
HON'BLE MR. JUSTICE SURESH KUMAR KAIT
J U D G M E N T (oral)
1. The present petition has been filed under Section 11 of the Arbitration
and Conciliation Act, 1996 seeking appointment of sole Arbitrator to
adjudicate the disputes with respondent in terms of Clause 60 of the General
Conditions of Contracts for Lumpsum contracts and measurement contracts
entered into between the parties.
2. Petitioner is a company established in 1924 and is in business of
executing projects in several sectors like Transport, Energy & Power,
Mining, Buildings, Marine, Industrial Structures and Real Estate.
3. Respondent is Director General, Married Accommodation Project of
the Ministry of Defence and works under the aegis of the Engineer in chief
and has been entrusted with the task of constructing accommodation for
Married Personnel of the Armed Forces.
4. As per the averments made in the present petition, respondent issued a
tender for construction of residential accommodation for Army and Air
Force at Lucknow, Fatehgarh and Memaura on 28.06.2010. Petitioner
submitted its bid on 07.09.2010 for a lump-sum price of Rs.176,52,21,231/-.
By way of a separate letter, it also offered the respondent a rebate of 14% on
such quoted sum. Respondent issued a letter dated 16.09.2010 regarding
reviewing the rates quoted by the petitioner as it deemed the same to be
high. Thereafter, petitioner replied on 20.09.2010 that the rates were already
quite competitive and reducing it further was not possible. However, the
revised rates for certain sections were submitted to the respondent.
Eventually, the petitioner's bid was accepted and it was awarded the Project
on 21.09.2010 for the price of Rs.151,80,90,258.86/- after applying the
rebate of 14% offered by the petitioner. Pursuant to the same, parties
executed the Contract Documents. Subsequent to issuance of Letter of
Award and upon execution of the said agreement, the petitioner had
commenced mobilizing its equipment, funds and resources on the work site.
However, due to the various breaches and the disregard of the express terms
of the Contracts, as well as poor planning and management by the
respondent, the petitioner suffered significant time overrun as well as
additional costs and losses inter alia relating to increased overheads, interest,
unforeseen costs and unforeseen escalations attributable solely to the
unnatural prolongation of the contract periods but still completed 98% of the
works under the contract. Petitioner was accordingly compelled to invoke
Arbitration clause contained in Clause 60 of the General Conditions of
Contracts for lump-sum contracts and measurement contracts vide Letter
dated 12.06.2021 for adjudication of its claims and nominated its arbitrator
to decide the disputes and differences between the parties. However, the
respondent failed to appoint an arbitrator or show any cooperation for
settlement of dispute. Hence, the present petition has been filed.
5. Learned CGSC appearing on behalf of respondent submit that though
the averments made in the present petition are disputed, however, he has no
objection if sole Arbitrator is appointed by this Court for adjudication of
dispute between the parties.
6. In view of the above, the present petition is allowed. Accordingly,
Justice KG Balakrishnan, former Chief Justice of India
(Mobile:9717266700) is appointed sole Arbitrator to adjudicate the dispute
between the parties.
7. The fee of the learned Arbitrator shall be governed by the Fourth
Schedule of the Arbitration and Conciliation Act, 1996.
8. The learned Arbitrator shall ensure compliance of Section 12 of
Arbitration and Conciliation Act, 1996 before commencing the arbitration.
9. The present petition stands disposed of accordingly.
10. A copy of this order be sent to the learned Arbitrator for information.
(SURESH KUMAR KAIT) JUDGE DECEMBER 07, 2021 rk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!