Thursday, 30, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Steel Authority Of India ... vs Primetals Technologies India ...
2020 Latest Caselaw 1574 Del

Citation : 2020 Latest Caselaw 1574 Del
Judgement Date : 12 March, 2020

Delhi High Court
Steel Authority Of India ... vs Primetals Technologies India ... on 12 March, 2020
                          $~
                          *    IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                              Date of Decision:- 12.03.2020


                          +     O.M.P. (COMM) 349/2020 & I.As 1862-64/2020
                                STEEL AUTHORITY OF INDIA LTD.(SAIL)
                                                                        ..... Petitioner
                                          Through: Mr.Sandeep Sethi, Sr.Adv with
                                          Mr.Puneeth Ganapathy, Ms.Ishita Mathur,
                                          Advs.

                                                    versus

                                PRIMETALS TECHNOLOGIES INDIA PVT. LTD.
                                (FORMERLY KNOWN AS SIEMENS VAI METALS
                                TECHNOLOGIES PVT.LTD)         ..... Respondent
                                        Through: Mr.P.C.Markanda, Sr.Adv with
                                        Mr.V.K.Sharma,    Mr.Rajesh      Markanda,
                                        Ms.Reema Soni, Advs.

                                CORAM:
                                HON'BLE MS. JUSTICE REKHA PALLI

                                REKHA PALLI, J (ORAL)

                               1.      The present petition under Section 34 of the
                               Arbitration and Conciliation Act, 1996 filed by Steel
                               Authority of India Limited, who was the respondent before
                               the learned Arbitrator, assails the arbitral award dated
                               15.10.2019 whereunder the claims of the respondent have
                               been allowed with actual costs of arbitration and interest @
                               14% per annum.
                               2.      The brief facts as emerge from the record are that the


Signature Not Verified
DigitallySigned                 OMP(COMM)349/2020                                 Page 1 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                           petitioner, which is engaged in the business of inter alia
                          manufacturing steel, awarded a contract for setting up a
                          Coupled Pickling Line and Tandem Cold Mill at Bokaro Steel
                          Plant to a consortium of M/s Siemens VAI Metals
                          Technologies         Pvt.   Ltd.,   M/s   Siemens   VAI    Metal
                          Technologies GmbH & Co, Austria and M/s McNally Bharat
                          Engineering Co. Ltd. The parties, therefore, entered into a
                          contract bearing No. TC/M/AGT-963 on 03.03.2008 which
                          specified the project commencement date as 03.03.2008 and
                          the date of completion as 03.09.2010. As per the terms of the
                          contract entered into between the parties, it was envisaged
                          that M/s Siemens VAI Metals Technologies Pvt. Ltd.
                          (hereinafter referred to as 'Siemens') would procure the
                          items, as set out in the contract, from such manufacturers as
                          identified by the petitioner and that the price of each item
                          would include a) Basic price, b) Excise Duty (ED) and c)
                          Central Sales Tax (CST). The parties had also agreed that
                          Siemens would pass on a minimum CENVAT credit of
                          Rs.33,06,70,252/- to the petitioner.        On 19.06.2015, the
                          contract was amended and Siemens was substituted by the
                          respondent and therefore the respondent also became bound
                          by the terms of the contract executed between the petitioner
                          and Siemens on 03.03.2008.
                          3.      While the work under the contract was still underway,
                          the respondent raised invoices towards the work done
                          wherein, besides seeking reimbursement of the input sales tax


Signature Not Verified
DigitallySigned            OMP(COMM)349/2020                                   Page 2 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                           paid by it towards purchase of items used for carrying out the
                          work under the contract, the respondent also sought
                          reimbursement of sales tax paid by its sub-contactors/vendors
                          while executing the contractual work. On 04.09.2015, the
                          respondent raised RA Bill No.34 for a total sum of
                          Rs.6,66,68,750/-      which was subsequently reduced to
                          Rs.5,93,64,168/-     towards   2.5%   milestone   against    the
                          completion certificate, in accordance with Article 2.1.4 of the
                          contract. As the CENVAT credit which the respondent
                          actually passed on to the petitioner was admittedly for an
                          amount of Rs.19,70,32,185/-, as against the guaranteed
                          amount of Rs.33,06,70,252/-, the petitioner refused to make
                          any payments to the respondent until necessary documents
                          were submitted by the respondent to show that the guaranteed
                          amount of Rs.33,06,70,252/- towards CENVAT credit would
                          be passed on to the petitioner. The respondent claimed that in
                          terms of the price schedule as set out in the contract, it was
                          entitled to deduct the shortfall in CENVAT credit from the
                          contract price at serial No.15 of the summary price schedule.
                          Per contra, the respondent's stand was that deductions to the
                          extent of shortfall in CENVAT credit could only be made
                          from the gross contract price at serial No.12 and not the net
                          contract price at serial No.15. As a result of these contrary
                          positions, the respondent invoked arbitration and the matter
                          was referred to the learned Sole Arbitrator by the Hon'ble
                          Supreme Court vide its order dated 14.09.2018 passed in


Signature Not Verified
DigitallySigned            OMP(COMM)349/2020                                  Page 3 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                           Arbitration Case(C) No.31/2018.
                          4.      Before the learned Arbitrator, the respondent raised
                          five claims and the petitioner raised two counter claims. The
                          learned Arbitrator, after noticing that the parties were ad idem
                          that work had been duly executed in terms of the contract, set
                          out that the disputes between these parties had to be
                          adjudicated in the following terms:-
                                  "1) non-reimbursement of Central Sales Tax (CST)
                                  amounting to Rs. 2,83,86,010.53/- to the Claimant by
                                  the Respondent (now reduced to Rs.1,90,56,702.38/-
                                  after the acknowledgement of receipt of
                                  Rs.92,16,537.03 by the Claimant.

                                  2)     non clearance of RA Bill No. 34 dated 04-09-
                                  2015 of the Claimant, for an amount of
                                  Rs.6,66,68,750/- (now reduced to Rs.5,93,64, 168/- in
                                  view of the Interim Award dated 06-03-2019 pursuant
                                  to which Rs. 73,04,582/- had been paid by the
                                  Respondent      on    12-04-2019)    pertaining    to
                                  commissioning activities, on account of difference in
                                  interpretation of the Contract covenants relating to
                                  shortfall in Minimum Guaranteed CENVAT Credit.

                                  3)      non clearance of RA Bill No. 43 dated 20-03-
                                  2017 of the Claimant of Rs 1,07,75,482.06/- (now
                                  reduced to Rs. 2,93,293.29/-, in view of payment of
                                  Rs.1,04,82,088.77/- on 05-12-2018 by the Respondent)
                                  pertaining to capital goods on account of difference in
                                  interpretation of the Contract covenants relating to
                                  shortfall in Minimum Guaranteed CENVAT Credit.
                                  4) Interest
                                  5) Cost"

                          5.      Before the learned Arbitrator, the plea of the
                          respondent was that once the summary price schedule
                          provided for two separate contract prices; one including the


Signature Not Verified
DigitallySigned            OMP(COMM)349/2020                                     Page 4 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                           minimum guaranteed CENVAT credit ('gross price') and the
                          other net of CENVAT and Input Tax Credit (ITC) on
                          VAT/Entry Tax ('net price'), the petitioner could make
                          deductions only out of the gross price at serial No.12 and not
                          from the net price at serial No.15, which did not include the
                          components of CENVAT credit and ITC. The respondent's
                          plea thus was that the shortfall of Rs.5,01,47,631/- in
                          CENVAT credit could be deducted only from the figure of
                          Rs.305,06,47,252/-, i.e., the gross price, and not from the net
                          price of Rs.271,99,77,000/-. The respondent also claimed
                          before the learned Arbitrator that once clause 11.2.1 of the
                          contract clearly provided for the reimbursement of all duties,
                          taxes & levies etc. to the respondent by the petitioner, subject
                          to a ceiling prescribed under the price schedule, the petitioner
                          could not refuse to reimburse the Central Sales Tax paid by
                          the respondent's sub-contractors/vendors for procurement of
                          material for execution of the contract which had been borne
                          by the respondent.
                          6.       On the other hand, the petitioner opposed the
                          respondent's claims by urging that once the respondent had
                          admittedly failed to fulfil its obligations under the contract by
                          not passing on the minimum guaranteed amount of CENVAT
                          credit to the respondent, the petitioner was fully justified in
                          making     deductions   from    the   net   contract    price     of
                          Rs.271,99,77,000/- on this ground. It was further claimed by
                          the petitioner that the CST was reimbursable to the


Signature Not Verified
DigitallySigned            OMP(COMM)349/2020                                     Page 5 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                           respondent only to the extent of the amount directly paid by
                          the respondent; reimbursement of the taxes paid by its sub-
                          contractors/vendors was not envisaged under the contract.
                          7.     In support of their respective stands, both parties led
                          evidence before the learned Arbitrator who, after considering
                          the pleadings, evidence and submissions of the parties, passed
                          the impugned award. The learned Arbitrator, while accepting
                          the respondent's claims and rejecting the petitioner's counter
                          claims, granted pre-award, pendente lite and post award
                          interest @ 14% per annum on the awarded sum, besides
                          directing the petitioner to pay the entire costs of arbitration to
                          the respondent.      The relevant directions of the learned
                          Arbitrator in the impugned award read as under:-
                                  "a) the claim of the principal amount
                                  Rs.2,82,73,811.35/- by way of reimbursement of CST
                                  is allowed. The sum of Rs.92,16,537.03/-, already
                                  paid by the Respondent on being adjusted against this
                                  amount, the Claimant is entitled to the payment of the
                                  balance amount of RS.1 ,90,56,702.38/- together with
                                  interest thereon @ 14% per annum, from the date on
                                  which it had fallen due in terms of Clause 12.1.6 of
                                  the GCC, till the date of actual payment. The counter
                                  claim of the Respondent for Rs.92,16,537.03/- is
                                  rejected.

                                  b)     the Claimant's claim of the principal amount
                                  Rs.6,66, 13,750/- against its RA Bill NO.34 dated
                                  04.09.2015 is allowed, together with interest thereon
                                  @ 14% per annum from 23.10.2015 till 12.04.2019.
                                  Further, the Claimant is also entitled to interest @
                                  14% per annum on the balance principal amount of
                                  Rs.5,93,64,168/- from 12.04.2019 till the date of
                                  actual payment. The counter claim of the Respondent



Signature Not Verified
DigitallySigned            OMP(COMM)349/2020                                     Page 6 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                                   for Rs.5,01 ,47,637/- is rejected.

                                  c)     the Claimant's claim of the principal amount
                                  of Rs.1,07,75,482.06/- against its RA Bill No.43 dated
                                  20.03.2017 is allowed together with interest @ 14%
                                  per annum thereon from 04.05.2017 till 05.12.2018.
                                  Further, the Claimant is also entitled to interest @
                                  14% per annum on the balance principal amount of
                                  Rs.2,93,293.29/- from 05.12.2018 till the date of
                                  actual payment.

                                  d) costs as above."

                          8.       Assailing the award, Mr.Sandeep Sethi, learned
                          Senior Counsel for the petitioner, besides reiterating the
                          submissions made before the learned Arbitrator qua the issue
                          of deduction of CENVAT credit and reimbursement of CST,
                          contends that the award of interest @ 14% per annum and
                          actual costs is wholly unwarranted.
                          9.      He submits that the learned Arbitrator, while allowing
                          the respondent's claim for release of the amount withheld by
                          the petitioner on account of its admitted failure to pass on the
                          guaranteed amount of CENVAT credit to the petitioner, has
                          re-written the terms of the contract and has in fact rendered
                          important clauses thereof absolutely redundant. He submits
                          that the learned Arbitrator has failed to appreciate that in
                          terms of the specific note at the bottom of the summary price
                          schedule, in lieu of the respondent's failure to provide the
                          guaranteed CENVAT credit to the petitioner under the
                          contract, the petitioner was entitled to deduct the amount due
                          from the net contract price. The respondent's failure to abide


Signature Not Verified
DigitallySigned            OMP(COMM)349/2020                                     Page 7 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                           by the terms of the contract could not simply be condoned by
                          directing that the said amount be deducted/reduced from the
                          CENVAT amount at serial No.15 of the summary price
                          schedule appended to the contract. As a consequence of the
                          respondent's failure to comply with the contractual terms, the
                          petitioner was entitled to make the requisite deductions from
                          the net contract price of Rs.2,71,99,77,000/- at serial No. 15.
                          He submits that since the note in the summary price schedule
                          clearly stated that deductions were to be made from the gross
                          contract price at serial no. 12, a necessary corollary thereof
                          would be that the deduction had to also be made from the net
                          contract price at serial No. 15. He thus contends that the
                          Arbitrator, having misread the unambiguous terms of the
                          Contract Agreement and the GCC, has interpreted the same in
                          a totally alien manner to pass the impugned award, which
                          violates public policy and is liable to be set aside.
                          10.     Mr.Sethi further submits that the learned Arbitrator's
                          directions to the petitioner to reimburse the CST paid by the
                          respondent's sub-contractors/vendors was beyond the terms
                          of the contract. By drawing my attention to clause 11.2.1 of
                          the GCC, he submits that the taxes which were reimbursable
                          to the respondent were only those which had been directly
                          paid by the respondent and not those paid by its sub-
                          contractors/vendors.     He further submits that as per the
                          contract, it was for the contractor to bear the taxes payable by
                          its sub-contractors/vendors. Thus, in essence, the contention


Signature Not Verified
DigitallySigned            OMP(COMM)349/2020                                      Page 8 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                           of Mr.Sethi is that the contract envisaged reimbursement of
                          only those taxes which were levied on the direct transactions
                          between the respondent and the petitioner and not those
                          which were levied on the respondent's transactions with third
                          parties, irrespective of whether those transactions were for the
                          purpose of executing any work under the contract; the
                          Arbitrator could not have awarded the same to the respondent
                          by blatantly overlooking the specific terms of the contract.
                          11.     Next, Mr.Sethi contends that even the award of
                          interest @ 14% per annum was wholly unjustified and unduly
                          harsh. He submits that the said rate is highly exorbitant and is
                          not in consonance with the prevailing rate of interest. By
                          placing reliance on the decision of the Supreme Court in
                          Vedanta Ltd. v. Shenzhen Shandong Nuclear Power
                          Construction Co. Ltd. (Civil Appeal No.10394/2018), he
                          prays that the rate of interest be reduced to 9 % per annum.
                          12.     Assailing the award of costs, Mr.Sethi submits that
                          the learned Arbitrator, while awarding an amount of
                          Rs.64,57,107/- towards costs of arbitration as claimed by the
                          respondent, has not only failed to give any reasons therefor
                          but has also failed to appreciate the plausibility of the
                          petitioner's defence by deeming it frivolous. He, therefore,
                          contends that the learned Arbitrator was not justified in
                          awarding the entire costs of arbitration in favour of the
                          respondent.
                          13.     Mr.Sethi finally submits that even though, as on date,


Signature Not Verified
DigitallySigned            OMP(COMM)349/2020                                   Page 9 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                           the total amount claimed by the respondent besides the
                          amount of Rs. 19,70,32,185/- towards CENVAT credit is
                          about Rs.267,09,84,999/-, the respondent is likely to raise
                          further claims towards escalation. This would not be
                          permissible in view of the prohibition contained in Article 4.2
                          of the contract which stipulates that in case the actual physical
                          quantities of civil work and weights of the mechanical
                          equipment differ from those indicated in the contract, the
                          contractor would not be entitled to get any additional price.
                          He, therefore, urges this Court to clarify that the respondent
                          will not be entitled to raise any further claims in this regard.
                          14.      On the other hand, Mr.P.C.Markanda, learned Senior
                          counsel appears on advance notice on behalf of the
                          respondent and supports the impugned award. He submits that
                          the claims made by the respondent before the learned
                          Arbitrator were strictly in accordance with the terms of the
                          contract and the GCC and have, therefore, been rightly
                          allowed under the impugned award. He submits that once the
                          contract and GCC provided a separate head for CENVAT
                          credit and specifically stipulated that the shortfall therein
                          would be deductible from the gross contract price of
                          Rs.305,06,47,252/- at serial No.12 of the summary price
                          schedule and not from the net contract price of Rs.
                          271,99,77,000/-, the petitioner could not arbitrarily and
                          unilaterally elect to deduct the same from the net contract
                          price.   He thus contends that the learned Arbitrator has


Signature Not Verified
DigitallySigned            OMP(COMM)349/2020                                     Page 10 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                           therefore rightly held that the deduction on account of
                          shortfall in CENVAT credit could be made only from the
                          gross contract price.
                          15.     Mr.Markanda takes a similar plea in respect of the
                          award of CST in favour of the respondent and submits that
                          under clause 11.2.1 of the GCC, though the respondent was
                          liable to bear the initial burden of the sales tax payable by its
                          sub contractors/vendors, the same had to be ultimately
                          reimbursed by the petitioner. Insofar as the grant of interest
                          at the rate of 14% per annum under the impugned award is
                          concerned, he submits that since the learned Arbitrator
                          exercised his discretion in this regard after considering the
                          entire facts and circumstances of the case, this Court ought
                          not to interfere with the same. With respect to the award of
                          actual costs of arbitration in favour of the respondent, he
                          contends that even though the same was fully justified, the
                          respondent is agreeable to modification of this direction to the
                          extent that instead of full costs, 50% of the costs be paid to
                          the respondent.
                          16.     I have heard learned counsel for the parties. It is well
                          settled that the scope of interference by this Court in a
                          petition under Section 34 of the Arbitration Act is extremely
                          limited, especially when the objections raised therein
                          primarily hinge on contractual interpretation. However, since
                          both parties have made extensive references to various
                          clauses of the contract, summary price schedule appended


Signature Not Verified
DigitallySigned            OMP(COMM)349/2020                                    Page 11 of 32
By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                           thereto and the GCC, I have carefully examined the same at
                          their instance. Therefore, before dealing with the rival
                          contentions of the parties, it would be appropriate to
                          reproduce the relevant contractual clauses which read as
                          under:-
                                            Contract dated 03.03.2008

                                    "4.2
                                    Should the actual physical quantities and weight
                                    differ from the indicated ones, neither the Contractor
                                    shall be entitled to get any additional price from the
                                    Employer not the Employer is entitled to deduct any
                                    amount from the Contract Price due to variation in
                                    physical quantities and weight.
                                    ...

11.2. The Contract Price shall comprise basic price (base price), Excise Duty, Sales Tax/VAT (including Sales Tax/VAT on Works Contract/works Contract Tax) for the Erection & Civil Work portion of the contract only, Octroi, Turn Over Tax (TOT), Service Tax, Education Cess and any other duties, taxes and levies, as may be applicable and prevailing on base date of the Contract. While the basic price will constitute the consideration under the Contract, the payment of duties, taxes, levies, etc., will be reimbursed (on actuals) against documentary evidence (except freight and Insurance which shall be paid limited to quoted amount incorporated in the Contract) to be produced by the Contractor, subject to a ceiling indicated in Price Schedule given in Appendix 1.

In no case the reimbursement towards duties and taxes, etc. shall exceed the amount indicated in Appendix 1 towards duties, taxes, levies, etc. except as indicated in Sub-Clause 14.6.1, hereof.

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 This clause is applicable for the portion for which prices have been quoted in Indian Rupees.

Entry Tax:

Entry Tax shall not be payable by the Contractor.

Service Tax and Excise Duty shall mean to cover applicable Education Cess any other surcharge thereon as applicable.

14.1 Except as otherwise specifically provided in the Contract, the Contractor shall bear and pay all taxes, duties, levies and charges assessed on the Contractor, its sub-contractors or their employees by Municipal State or Central Government Authorities.

However subject to stipulations of the Contract, the payment of duties taxes, levies etc, will be reimbursed (on actual) against documentary evidence to be produced by the Contractor, subject to a ceiling indicated in price schedule(s) of the Contract. In no case the reimbursement towards duties and taxes etc, shall exceed the amount indicated in price schedule(s) of the contract towards duties, taxes, levies etc, except on account of statutory variation in Taxes & Duties and/or imposition of new taxes and duties.

All taxes & duties payable outside India in respect of performance of the Contract shall be borne & paid by the Contractor. The Employer shall have no liability whatsoever on this account.

Entry Tax:

Entry Tax shall not be payable, by the Contractor.

14.5.3

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 Excise invoices for all indigenous plant, equipment & materials shall be made consigned to Steel Authority of India Limited - BOKARO Steel Plant for availing CENVAT Credit under relevant Rules and shall be furnished by the Contractor to the Employer for availing CENVAT credit.

14.5.6

Contactors to indicate Minimum Guaranteed CENVAT Credit that can be availed by the Employer against materials supplies for subject work. In case of any shortfall in CENVAT Credit from that Guaranteed by the Contractor the shortfall shall be deducted by the Employer from the Contractor. In case of excess of CENVAT, 50% of the excess CENVAT amount will be paid.

14.6.1

For the purpose of the Contract, it is agreed that the 'Contract Price' specified in Article 2 ("Contract Price" & "Terms of Payment") of the Contract Agreement is based on the taxes, duties, levies etc. and charges prevailing on Base date (hereinafter called "Tax" in this Sub-Clause 14.6 hereof). If any rate of tax is increased or decreased, a new tax is introduced, an existing tax is abolished, or any change in interpretation or application of any tax occurs in the course of the performance of Contract, which was or will be assessed on the Contractor, Sub Contractors or their employees in connection with performance of the Contract, an adjustment of the Contract Price shall be made as Sub-Clauses 14.6.2 & 14.6.3, hereof, by addition to the Contract Price or deduction therefrom, as the case may be.

14.6.1.1 The adjustment in the Contract Price towards variations in taxes shall be applicable for the

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 variations in the taxes enacted within the scheduled Contractual delivery/ execution period provided the Facilities are completed within the "Time, for completion" of the Contract. For any upward variations in taxes enacted after the Contractual delivery / execution period, the adjustment in the Contract Price shall not apply in case the reasons for delay are attributable to the Contractor not withstanding extension to the "Time for Completion" is granted. However, if the completion of the Facilities is delayed due to reasons attributable to the Employer and extension to the "Time for Completion" is granted variations in taxes enacted after the Contractual delivery/ execution period, the adjustment in the Contract Price shall be allowed within the extended" Time for Completion" of the Contract.

However, if the completion of facilities is delayed beyond scheduled date of the "Time for Completion" due to reasons attributable to both the parties, then the period for delay attributable to the Employer will be considered as initial delay and the price adjustment shall be applicable during this period as well.

14.6.1.2

The adjustment in the Contract Price towards imposition of new taxes or abrogation of existing taxes, shall be applicable only if the new tax is enacted or existing tax is abrogated within Contractual delivery/execution period. For any variation due to enactment of new tax after Contractual delivery/ execution period, adjustment in the Contract Price shall not apply in case the reasons for delay are attributable to the Contractor not withstanding extension to the "Time for Completion" is granted. However, if the completion of the Facilities is delayed due to reasons attributable to the Employer and extension to the "Time for Completion" is granted variations in taxes due to enactment of new tax or

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 abrogation of existing tax enacted after the Contractual delivery /execution period, the adjustment in the Contract Price shall be allowed within the extended "Time for Completion" of the Contract.

14.6.2

The adjustment in the Contract Price towards variation in the taxes shall be made by the Employer on production of the documentary evidences by the Contractor.

14.6.3

The Contract Price shall be adjusted towards variations in taxes in respect of only finished equipment supplied by the Contractor to the employer. No adjustment in the Contract price shall be made for variations in the taxes on raw materials, parts, component I intermediate components , assemblies/ sub-assemblies etc.

Summary Price Schedule

S.N Description Prices (Currency) o Foreign Portion Indian Portion (Euro) (INR) SVAI- SVAI MT MBE MT Linz India A B C D E 1 Design & Engineering a Imported (FOB) 7,085,91 --- ---

                                     (Refer Table-1)        6
                              b      Indigenous (At site)              127,707,2

                              2      Supply of Plant &
                                     Equipment
                              a      Imported (FOB)         51,813,3   ---          ---
                                     (Refer Table 4A &      84
                                     4B)



Signature Not Verified

By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                               b      Indigenous (At site)              2,372,225,    385,222,400
                                     (Refer Table 4A &                 000/-
                                     4B)
                              3      Supply of
                                     Refractories
                              a      Imported (FOB)         n.a        ---           ---
                                     (Refer Table 5)
                              b      Indigenous (At site)              n.a.          n.a.
                                     (Refer Table 6)
                              4      Supply of
                                     Commissioning
                                     Spares
                              a      Imported (FOB)         Included   ---           ---
                                     (Refer Table 7)        in Table

                              b      Indigenous (At site)              Included      Included in Table
                                     (Refer Table 6)                   in Table      4B
                                                                       4A
                              5      Civil Engineering      n.a.       n.a.          n.a.
                                     Work including
                                     supplies (Refer
                                     Table 9) Supply &
                                     Ejection of
                                     Fabricated Building
                                     Steel
                              6      Structures at site     n.a.       n.a.          n.a.
                                     including sheeting,
                                     glazing and final
                                     painting (Refer
                                     Table -10)
                              7      Storage, Handling,     ---        103,849,0     320,563,080

                                     Commissioning and
                                     P.G.Tests of Plant &
                                     Equipment (Ref
                                     Table 11)
                              8      Foreign Supervision    Included 303, 372,       ---
                                     Charges in India       in SVAI 000
                                     during Erection,       MT India
                                     Start up,              Price
                                     Commissioning and
                                     PG Tests of plant
                                     and Equipment
                                     (Refer Table 12)



Signature Not Verified

By:MANJU BHATT
Signing Date:16.03.2020
18:59:41
                               9      Training Charges     150,000    Included
                                     (Refer Table 13)                in Table
                                                                     11A
                              10.     Ocean          Freight n.a.    103,157,0      ---

                                      (excluding      Import
                                      Duty),             Port
                                      Clearance & Inland
                                      Transportation for
                                      imported
                                      items for which
                                      prices are quoted in
                                      foreign       currency
                                      (inclusive of Service
                                      Tax & Education
                                      Cess Rs. 11,347,000)
                              11.     Comprehensive           n.a.     40,337,00 ---

                                      Insurance        (Refer
                                      Clause no. 36 of
                                      GCC)       (Incl.    of
                                      Service Tax & Edu.
                                      Cess Rs4,437,000)

12. Total Contract Price 59,049,3 3,050,647, 705,785,480 (1 to 11) 00 252 Total Contract Price 59,048,3 3,756,432,732 (1 to 11) Total Euro 00 & INR Values

13. Guaranteed amount 330,670,2 87,669,480

on total contract pride

14. Guaranteed amount 14,816,000 of input tax credit on VAT

15. Total contract price 271,99,77, 603,300,000

input tax credit on VAT ENTRY TAX Total Contract Price (Net of CENVAT &VAT/ ENTRY TAX): Indian Currency (in words) (SVAI MT India Portion): Rupees Two hundred seventy one crore ninety nine lakh seventy seven thousand only. Indian Currency (in words) (Mchally Bharat Portion): Rupees Sixty crore thirty three lakh only.

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 Foreign Currency (in words) (SVAI MT Linz Portion): Euro Five crore ninety lakh forty nine thousands three hundred only.

Note: All the necessary documents for availing the CENVAT credit shall be furnished, else balance shortfall shall be deducted from the contract price item serial no.12 above.

Primetals Technologies India Pvt. Ltd. Sd/-"

17. Upon a perusal of the relevant clauses, more specifically Clause 14.5.6 of the contract, I find that the contract specifically envisages that in case of any shortfall in the CENVAT credit as against the minimum guaranteed CENVAT Credit, the same shall be deductible from the amount payable to the contractor. However, since this clause does not specify the amount from which the said shortfall would be deductible, the answer to this quandary lies in the note at the bottom of the summary price schedule appended to the contract. A plain reading of this note makes it evident that the only logical interpretation of the phrase 'contract price' for the purpose of Clause 14.5.6 of the contract is that any deduction on account of shortfall viz. the guaranteed CENVAT credit had to be made from the gross contract price at serial No.12 and not from the net contract price at serial No.15.

18. In the light of this position, I find no merit in Mr.Sethi's primary contention that the sum of Rs.5,01,47,631/- towards the admitted shortfall in CENVAT

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 credit was required to be deducted from the net contract price mentioned at serial no.15 of the summary price schedule and not from the gross contract price mentioned at serial no.12 thereof. In fact, the petitioner's submission that a deduction from the gross contract price at serial No.12 also contemplated deduction from the net contract price at serial no.15 is in the teeth of the plain language employed in the contract.

19. I find that the learned Arbitrator has, after considering the summary price schedule as also the terms of the contract, come to a categorical conclusion that the deduction could be made only from the gross contract price referred to at serial no.12. Thus, I have no hesitation in concurring with the findings of the learned Arbitrator that any shortfall in the CENVAT credit payable by the respondent, could be recovered only by making requisite deductions from the gross contract price mentioned at serial No.12 of the summary price schedule. The relevant observations of the learned Arbitrator in this regard reads as under:-

"61. CENVAT credit, conceptually is a credit in respect of Central Excise on inputs purchased for the manufacture or the duty paid in relation to manufacture of the final product. Authoritative texts elucidate, that CENVAT credit is also available in respect of duty paid on capital goods, which include machinery, plants, spare parts of machinery etc. CENVAT credit is thus comparable to a credit balance in bank account that can be adjusted towards the Excise Duty payable.

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41

62. As the discord patently, is traceable to the provisions of the Contract Agreement and the GCC, reference ought to be made to those relevant and extracted herein before. For ready reference, in addition, Article 1.2 and 1.3 of the Contract Agreement are set out herein below:

"Contract Agreement:

1.2 Contract Documents (Reference GCC Clause 2) The· followinq documents shall constitute the Contract between the Employer and the Contractor and each shall be read and construed as an integral part of the Contract.

(a)This Contract Agreement and Appendices hereto.

(b)General Conditions of Contract and Annexures hereto.

(c) Contract Technical Specifications.

(d)General Technical Specifications.

1.3 Order of Precedence (Reference GCC Clause 2) In the event of any ambiguity or conflict between the Contract Documents listed above) the order of precedence shall be the order in which the Contract Documents are listed in Article 1.2 (Contract Documents) above. (emphasis supplied)

A plain reading of the Articles of the Contract Agreement quoted hereinabove, testifies that the documents listed in Article 1.2, constitute the contract and are to be read and construed as an integral part thereof and that in the event of any ambiguity or conflict between these, the order of precedence for determining the primacy thereof would be the order in which these are listed in Article 1.2. In other words, in case of conflict between any provision of the Contract Agreement and the Appendices thereto and

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 that of the General Conditions of Contract and Annexures thereto, for an instance, surfaces, the provision in the Contract Agreement and the Appendices thereto, would prevail.

63. Whereas to reiterate, a combined reading of Article 2.1 of the Contract Agreement and Clauses 11.2.1, 14.1 and 14.1.1 quoted herein above, evinces that the Total Contract Price is inclusive of all taxes and duties as on the Base date and the Basic price constitutes the consideration under the contract. Clause 14.5.6, requires the Contractors to indicate Minimum Guaranteed CENVAT Credit that can be availed by the Employer, against materials supplies for subject work, so much so that in case of any shortfall in CENVAT credit from that guaranteed by the Contractor, the shortfall shall be deducted by the Employer from the Contractor and in case of excess of CENVAT, 50% of the excess CENVAT amount would be paid to the Contractor.

Clause 14.6 deals with variations in taxes and duties and Clause 14.6.1, 14.6.1.1 and 14.6.1.2 of the GCC comprehend adjustment in Contract Price on variation in the rate of taxi abolition of any taxi imposition of new tax. Clause 14.6.1 in particular reiterates, that the "Contract Price" specified in Article 2 of the Contract Agreement is based on the taxes, duties, levies etc., and charges prevailing on Base date and prescribes that, if any rate of tax is increased or decreased, a new tax is introduced and existing tax is abolished or any change in interpretation or application of any tax occurs in the course of performance of the contract, which was all to be assessed on the Contractor, sub-Contractor or their Employees in connection with the performance of the contract, an adjustment of Contract Price shall be made as per Clauses 14.6.2 and 14.6.3, by addition to the Contract Price or deduction therefrom as the case may be.

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 .......

71. The cognate provisions of the Contract Agreement and GCC on the issue as set out hereinabove, present a complete scheme, to be interpreted in a manner, to sustain the cohesiveness and the efficacy thereof, as intended by the parties. They ought not to be interpreted in isolation to be in conflict with each other and be mutually extinctive, making the Contract Agreement and the GCC unworkable. The 'Note' to the Summary Price Schedule, Clause 14.5.6 and 14.6 of the GCC and Clause 3 of the MOU, thus, have to be read with harmonious orientation. Apart from the fact that Clause 14.5.6 of the GCC and Clause 3 of the MOU, in the comprehension of the Tribunal, do not permit the deduction of the shortfall amount in minimum guaranteed CENVAT credit, otherwise than from the Total Contract Price, had the parties intended, such deduction from the Running Bills of the Contractor, these Clauses would have been expressly worded to that effect."

20. The petitioner's challenge to the learned Arbitrator's directions with respect to reimbursement of the CST paid by the respondent's sub-contractors/vendors to the respondent is equally meritless. I find that the learned Arbitrator has, after examining Clause 14.1 of the contract, concluded that the price agreed upon between the parties clearly includes all taxes to be reimbursed to the respondent. Therefore, merely because some input taxes were not paid directly by the respondent but by its sub-contractors/vendors in respect of goods used in the execution of the contract, the same could not be a ground for the petitioner to refuse reimbursement thereof to the respondent. In this regard, the learned

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 Arbitrator has observed as under:-

"44. On a combined consideration of all the materials on record, this Tribunal is of the view that the Claimant's remaining claim for reimbursement of CST for the amount of Rs.1,90,56,702.38 deserves to the allowed in full and the denial thereof by the Respondent on grounds urged by it, is wholly unsustainable in law and on facts. Further, the Respondent having made the payment of the Excise Duty component in the same sale transactions, its approach to deny reimbursement of the CST paid by the Claimants/Vendors in the first interstate sales, having regard to the entire conspectus of law, the contractual stipulations and the materials on record is wholly in defiance of logic. The materials on record evince, that the parties on a correct understanding of the terms and conditions thereof pertaining to the nature of sale transactions to be undertaken, did participate therein and in the process, the statutory form/certificate had been issued on due verification of all aspects and endorsed by the Tax authorities as well. The Respondent's specious plea of denying the reimbursement of CST to the Claimant on the ground that it did not charge CST on the sale value of the transaction of sale by it to the Respondent, flies in the face, not only of the statutory provisions involved and the judicial enunciation thereof as well as the contemporary documents on record including the letters dated 05.03.2010 and 25.06.2014 of the Respondent acknowledging the sales in favour of the Respondent as "Sale-in-Transit", the Respondent's demurer, that it being a predetermined buyer at the stage of the first interstate sale, the subsequent sale in its favour does not qualify for a sale in transit, is in view of the above referred judicial renderings, flawed and indefensible, as the law permits two successive sales and it is wholly inconsequential whether the ultimate buyer at the stage of first sale is known or not.

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 To reiterate, the Respondent having consciously acknowledged the sale in its favour to be a sale in transit, had issued Form "C" and had availed the concessional rate of tax of 2%, its plea against estoppel, in the facts and circumstances of the case also cannot be sustained. As a matter of fact, as is borne out by the records, the Respondent continued to issue such Form "C" pertaining to the subsequent sales in the Claimant's favour even after the letter dated 05.08.2014 of its expert, Mr.B.S.P. Roy. As the sales by the Claimant in favour of the Respondent, being sale-in-transit, were exempt from CST, the latter's contention that it was not liable to reimburse the CST as the same was not charged by the Claimant on such sales, is patently fallacious.

xxx

54. The plea of the Respondent, in the above overwhelming perspectives that as the Claimant has not raised CST invoice in respect of the sales made by the Claimant to it (Respondent) and that therefore, Section 9(1) of the Act is attracted, is to be mentioned only to be rejected. Such sales being in form and substance, sale-in-transit, as per Section 6(2) of Act, 1956, this contention is non est in law. Its avowal that the amount of CST paid by the vendors/Claimant in the first Interstate sale had been included in the cost price of the Claimant and that by seeking reimbursement thereof, it was endeavouring to reap undue benefits is also in the realm of speculation, more particularly in the face of categorical denial thereof by the Claimant in its rejoinder and the failure of the Respondent to discharge its burden with regard thereto. Even otherwise, a bare perusal of Table 4A, would unequivocally proclaim that ST/VAT/CST can by no means be a part of the Total Basic Price and is independent and severable therefrom. Mere reference of any commercial business practice by the Respondent to this effect does not, in the opinion of the Tribunal, prove this imputation against the Claimant.

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 The Respondent's plea that it did not stand to gain in the bargain, though CST at concessional rate of 2% had been charged on the first interstate sales and that the subsequent sales in its favour had been exempted therefrom, also belies logic and is on the face of records, unsound and unsustainable. Its plea, that the Claimant's invoices referring to the expression "Price Enhancement" though labelled as CST/Tax invoices, do not qualify for reimbursement of CST also, in the facts and circumstances of the case is untenable and is rejected.

xxx

56. The interstate sales referred to and proved by the Claimant in the instant proceedings and which form the basis of its claim for reimbursement of CST, do constitute "sale in transit" in terms of Section 6(2) of Act, 1956.

The supplies made by the Claimant to the Respondent, pursuant to the interstate sales involved, are in accordance with the Contract Agreement between the parties and the relevant clauses of the GCC more particularly Clause 33.2 of the GCC and having regard to the arrangement effected to execute the sale-in-transit, no separate/ fresh Contract between the Claimant and the Respondent was necessary after the interstate sales between the Claimant and its vendors. The interstate sales in succession between the Claimant and the vendors and the Respondent, in a progressive sequence in continuum, are valid in law and as contemplated by the parties.

Having regard to the scheme of the Contract Agreement and the GCC pertaining to "sale in transit", the fact that the Respondent was a predetermined buyer at the time of the first interstate sales between the Claimant and its vendors, is inconsequential and does not in any way render the sale in transit in the instant case, under Section 6 (2) of Act 1956, non est.

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 The Respondent's plea that it did not in any way participate in the sales in transit, in the face of the overwhelming materials on record to the contrary is negated. The Respondent, having consciously issued the declarations in Form 'C' qua the sales in transit after actively participating therein, being aware of all the relevant facts and circumstances and the significance of the sale dispatch documents involved, it cannot be permitted to take refuge under the cover of the plea of no 'estoppel against law'. It having issued the Form 'C' qua the sales in transit involved, in discharge of its statutory obligations and being fully cognizant of the significance and consequences thereof, if cannot be permitted wriggle out of its responsibilities on such plea. It having acted in accordance with law in issuing the Form „C‟ in terms of Act 1956 and the contractual stipulations, it cannot be allowed to retrace its path and avoid its obligations under the Contract. To reiterate, the Respondent's contention that the CST paid by the Claimant's vendors had been included in the Total Basic Price! Cost of the Claimant as per the normal commercial practice also does not commend for acceptance, in absence of pleadings or proof with regard thereto, and thus is wholly speculative warranting rejection thereof.

57. In view of the determination made hereinabove, the Claimant's claim of reimbursement of CST of Rs.2,82,73,811.35 is upheld. The payment of Rs. 92,16,537.03 by the Respondent towards this head is in accordance with the relevant contractual provisions and Act 1956, and the rules framed thereunder. Resultantly, the Claimant's claim for balance principle amount of Rs.1,90,56,702.38 is allowed, on a consideration of all aspects bearing on the issue. The Respondent's counter claim of Rs.92,16,537.03 is rejected."

21. It is thus evident that the learned Arbitrator has, after interpreting the various clauses of the contracts, including

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 clause 14.1 of the GCC, arrived at a categorical conclusion that the respondent was entitled to reimbursement of the CST paid by its sub-contractors/vendors, with which conclusion I find no reason to interfere. Even otherwise, when the findings of an award rest on an interpretation of the provisions of the contract between the parties, the Court, while examining the award under Section 34 of the Act, cannot interfere with the same, even if another interpretation is possible. In this regard, reference may be made to paragraph 22 of the decision of this Court in Union of India through Ministry of Youth Affairs and Sports Department of Sports CWG Delhi 2010 Cell vs. GL Litmus Events Private Limited OMP(COMM.)30/2020 dated 29.01.2020, which reads as under:-

"22. Even otherwise, the impugned award hinges upon the interpretation of Clauses 11.4 and 38 of the Agreement by the Tribunal; this must be considered in the light of the settled legal position that once the arbitrator interprets the provisions of an agreement between the parties, the Court while examining the award under Section 34 of the Act will not interfere with the same merely because another interpretation is possible. In any event, in the present case, I am of the view that the interpretation of Clause 38 by the Tribunal is not only correct but is the only possible interpretation. In this regard, reference may be made to the decision in National Highways Authority of India vs. ITD Cementation India Ltd. (2015) 14 SCC 21 wherein the Supreme Court was dealing with the question of interpreting the terms of a contract, which formed the basis of the dispute, and proceeded to reiterate the settled legal principles in that regard as under:-

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 "25. It is thus well settled that construction of the terms of a contract is primarily for an arbitrator to decide. He is entitled to take the view which he holds to be the correct one after considering the material before him and after interpreting the provisions of the contract. The Court while considering challenge to an arbitral award does not sit in appeal over the findings and decisions unless the arbitrator construes the contract in such a way that no fair-minded or reasonable person could do."

22. At this stage, reference may also be made to paragraph 17 of the GL Litmus Events Private Limited (supra) which reads as under:-

"17. Before I deal with the rival contentions of learned counsel for the parties, a reference may be made to a recent decision in Hindustan Construction Company Limited & Ors. Vs. Union of India & Ors. 2019 (16) SCALE 823 wherein the Supreme Court reiterated the scope and grounds of judicial interference in an arbitral award under Section 34 of the Act; the relevant paragraph reads as under:

"49. Further, this Court has repeatedly held that an application Under Section 34 of the Arbitration Act, 1996 is a summary proceeding not in the nature of a regular suit - see Canara Nidhi Ltd. v. M. Shashikala. As a result, a court reviewing an arbitral award Under Section 34 does not sit in appeal over the award, and if the view taken by the arbitrator is possible, no interference is called for - see Associated Construction v. Pawanhans Helicopters Ltd. (2008) 16 SCC 128 at paragraph 17.

50. Also, as has been held in the recent decision Ssangyong Engineering & Construction Co. Ltd. v.

NHAI 2019 SCC Online 677, after the 2015 Amendment Act, this Court cannot interfere with an

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 arbitral award on merits (see paragraph 28 and 76 therein). ...."

23. Mr.Sethi has also vehemently urged that the learned Arbitrator erred in awarding interest at an exorbitant rate of 14% per annum, for which purpose he has relied on Vedanta v. Shenzen Shadong Nucleur Power Construction Co. Ltd. Civil (2019) 11 SCC 465 wherein the Supreme Court held as under:-

"9. The discretion of the arbitrator to award interest must be exercised reasonably. An Arbitral Tribunal while making an award for interest must take into consideration a host of factors, such as: (i) the "loss of use" of the principal sum; (ii) the types of sums to which the interest must apply; (iii) the time period over which interest should be awarded; (iv) the internationally prevailing rates of interest; (v) whether simple or compound rate of interest is to be applied; (vi) whether the rate of interest awarded is commercially prudent from an economic standpoint;

(vii) the rates of inflation; (viii) proportionality of the count awarded as interest to the principal sums awarded.

xxx xxx xxx

16. The imposition of a high rate of interest @ 15% post-120 days is exorbitant, from an economic standpoint, and has no co-relation with the prevailing contemporary international rates of interest. The award-debtor cannot be subjected to a penal rate of interest, either during the period when he is entitled to exercise the statutory right to challenge the award, before a court of law, or later. Furthermore, the Arbitral Tribunal has not given any reason for imposing a 15% rate of interest post 120-days."

24. Though Mr.Markanda has tried to justify the award of

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 interest at the rate of 14% per annum by contending that the same was based on a consideration of the facts and circumstances of the present case, and therefore this Court should not interfere with the same. I, however, find that the learned Arbitrator, while awarding interest at the rate of 14%, per annum has given absolutely no reason for the same; which, admittedly, is much higher than the prevailing rates of interest. In this regard, Mr.Sethi's reliance on Vedanta (supra) is merited. I am, therefore, of the opinion that the award of interest @ 14% per annum by the learned Arbitrator is not only unreasoned but is, even otherwise, highly excessive and virtually in the nature of a penal interest when considered in the light of the prevailing rates. The grant of such a rate of interest in today's scenario is against public policy and, therefore, the same is liable to be reduced. Accordingly, the rate of interest awarded in favour of the respondent under the impugned award is reduced to 10% per annum, which is in tune with the prevailing market conditions, applicable for all the three periods, i.e., pre-award, pendente lite award and post-award periods.

25. Insofar as the petitioner's challenge to the costs of arbitration awarded in favour of the respondent is concerned, since the respondent has fairly expressed its willingness to accept 50% of the costs of arbitration, instead of full cost as granted under the impugned award, I need not delve into this aspect. Accordingly, the direction in this regard is modified

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41 and the petitioner is directed to pay 50% of the actual costs of arbitration amount incurred by the respondent as determined by the learned Arbitrator.

26. Before I conclude, I may note that Mr. Sethi has vehemently urged that in view of Clause 4.2 of the contract, the respondent is not entitled to claim any escalation or raise any future bills towards escalation qua the contract. However, since this issue was not the subject matter of the impugned award, I have consciously refrained from examining this aspect despite the petitioner's vehement arguments in this regard. It is, however, made clear that in case any claim is raised by the respondent in the future towards escalation, the same would be considered on its own merits.

27. The petition along with pending applications are, accordingly, disposed of in the aforesaid terms.

REKHA PALLI, J MARCH 12, 2020/sr

Signature Not Verified

By:MANJU BHATT Signing Date:16.03.2020 18:59:41

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter