Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

B K Structural Contracts Pvt. Ltd. vs Gati Kausar India Ltd.
2018 Latest Caselaw 6147 Del

Citation : 2018 Latest Caselaw 6147 Del
Judgement Date : 9 October, 2018

Delhi High Court
B K Structural Contracts Pvt. Ltd. vs Gati Kausar India Ltd. on 9 October, 2018
$~4
*      IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                 Date of Decision: 9.10.2018
+      ARB.P. 372/2018
       B K STRUCTURAL CONTRACTS PVT. LTD. ..... Petitioner
                    Through: Mr. L.B. Rai and Mr. Mohit Kumar
                             Sharma, Advs.

                           versus

       GATI KAUSAR INDIA LTD.                 ..... Respondent
                     Through: Mr. Koonal Tanwar, Adv.

CORAM:
HON'BLE MR. JUSTICE RAJIV SHAKDHER

RAJIV SHAKDHER, J. (ORAL)

1. This is a petition filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short '1996 Act') for appointment of an Arbitrator.

2. Notice in this petition was issued on 21.5.2018.

2.1    Notice was made returnable on 27.7.2018.
2.2    On that date, the respondent was given time to file a reply to the
petition.
2.3    Despite time having been given, no reply has been filed.
2.4    Mr. Tanwar, who, appears for the respondent, seeks another
opportunity to file a reply.
2.5    According to me, no further opportunity can be given as nearly five

(5) months have passed since notice was issued and nearly two and half (2½) months have passed since opportunity was given to file a reply.

3. The record shows that the respondent had invited a tender for construction of a Cold Storage Plant, which, appears, had to be constructed at Shamirpet, Hyderabad.

3.1 Pursuant to the tender, bids were invited by the respondent via its Architect, one, M/s. Aashray Design and Consultant Pvt. Ltd. (in short 'ADCL').

3.2 The bids were to be filed with ADCL at its office located at K-8, First Floor, South Extension, Part-I, New Delhi-110049.

4. The record shows that the petitioner was declared successful and, accordingly, a Letter of Intent (LOI) dated 26.11.2016 was issued in its favour.

4.1 The total value of the contract was pegged at Rs.3,50,00,000/-. The petitioner gave its formal acceptance vide communication dated 28.12.2016. 4.2 The record also shows that pursuant to the aforesaid steps having been taken an agreement dated 29.12.2016 was executed between the parties.

5. According to the petitioner, it was paid a sum of Rs.13 lacs against the 1st R.A. Bill raised for a sum of Rs.13,25,000/-.

6. The petitioner's grievance principally is that its 2nd R.A. Bill was not paid and that the respondent, instead, proceeded to terminate the contract.

7. To ventilate its grievance, the petitioner issued a legal notice dated 17.11.2017. Via this notice, demand for payment of outstanding amount is made.

7.1 The respondent, however, vide its reply dated 4.12.2017 disputed the demand raised by the petitioner.

7.2 The petitioner followed the aforementioned legal notice with another notice dated 13.12.2017 which was served on ADCL.

8. Since, as per the Clause 6.29 of the agreement obtaining between the parties, the notice had to be served on the Principal Architect i.e., M/s. Aarch Associates, Architects and Engineers. A fresh notice dated 3.3.2018 was taken out and served on the aforementioned Principal Architect. 8.1 It appears that the Principal Architect did not take the matter further. Being aggrieved, the petitioner approached this Court via the instant petition.

9. As indicated above, the respondent has chosen not to file a reply.

10. The respondent, however, is represented by Mr. Tanwar. 10.1 The learned counsel has raised two objections. 10.2 Mr Tanwar's first objection is pivoted on the provisions of Clause 6.12 of the agreement. It is submitted that the respondent had the right to terminate the uncompleted part of the Contract under the said clause and in case such a situation the petitioner was disentitled from claiming compensation.

10.3 Mr Tanwar's second objection is with regard to the jurisdiction of this Court to entertain the instant petition.

10.4 According to me, both the objections are untenable for the reason that Clause 6.12 only states that if in any unforeseen circumstance the owner decides to cancel/or postpone the execution of the project it would be entitled to terminate the contract for the uncompleted part without being in any way liable for the payment of compensation to the petitioner i.e., the contractor.

10.5. Furthermore, the clause says that the contractor shall prepare the final bill of all completed works and the work in progress for final settlement. The clause also says that the decision of the owner i.e., the respondent, in

such a situation shall be final and binding on the parties. 10.6 This clause, to my mind, cannot impede the appointment of an Arbitrator.

10.7 In my opinion all that can be said in favour of the respondent is that the aspect concerning the purported bar to claim for compensation under clause 6.12 of the agreement obtaining between the parties may form part of the defence that the respondent may likely take before the Arbitrator but surely it cannot come in way of the petitioner seeking relief from this Court that an Arbitrator ought to be appointed.

11. Insofar as the second objection is concerned, which is, that this Court has no jurisdiction, I may only advert to the averments made in paragraph 22 of the petition with regard to jurisdiction.

11.1 For the sake of convenience, the averments made therein are extracted hereafter:

"22. That the Petitioner submits that the tender was invited by the Architect of the Respondent at Delhi. The Petitioner participated in the tender at Delhi. The tender of the Respondent was accepted by the petitioner at Delhi, after detailed discussions with the Architect in his office at Delhi, after which the Architect gave the sanction for commencement of the work. The work was thus awarded to the Petitioner at Delhi. The office of the respondent is situated in Delhi. Therefore this Hon'ble Court has got jurisdiction to try and entertain the present Petition at Delhi."

11.2 The record shows, as indicated above, that the bids were, in fact, invited by the respondent via ADCL, which is located in Delhi. 11.3 The contract was also executed in Delhi as is evident from a bare reading of the agreement obtaining between the parties.

12. Under these circumstances, as indicated above, I have no hesitation in saying that this objection is also misconceived.

13. Accordingly, the petition is disposed of with the following directions:

(i) Mr. A.K. Garg, former Additional District Judge, (Cell no.9871158800) is appointed as an Arbitrator in the matter.

(ii) The learned Arbitrator will be paid a fee as per the provisions of the Fourth Schedule of the 1996 Act.

14. The Registry will dispatch a copy of this order to the learned Arbitrator.

RAJIV SHAKDHER, J OCTOBER 03, 2018 rb

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter