Thursday, 30, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gail India Ltd. & Ors. vs M/S Prerna Enterprises & Anr.
2017 Latest Caselaw 6030 Del

Citation : 2017 Latest Caselaw 6030 Del
Judgement Date : 31 October, 2017

Delhi High Court
Gail India Ltd. & Ors. vs M/S Prerna Enterprises & Anr. on 31 October, 2017
*            IN THE HIGH COURT OF DELHI AT NEW DELHI

+                         FAO No. 424/2017

%                                                   31st October, 2017

GAIL INDIA LTD. & ORS.                                  ..... Appellants
                    Through:             Mr. Sacchin Puri, Sr. Advocate
                                         with Mr. Vikrant Panchanda
                                         and Ms. Mehak, Advocates.

                          versus

M/s PRERNA ENTERPRISES & ANR.         ..... Respondents

Through: Mr. Aman Bhalla, Advocate.

CORAM:

HON'BLE MR. JUSTICE VALMIKI J.MEHTA

To be referred to the Reporter or not?

VALMIKI J. MEHTA, J (ORAL)

C.M. Appl. No. 39161/2017 (for exemption)

1. Exemption allowed, subject to all just exceptions.

The application stands disposed of.

C.M. Appl. No. 39160/2017 (for delay)

2. Considering that there are issues of huge monetary

liability upon the appellant, and delay is not of over one year, and is

only of 228 days, therefore, applying the ratio of the judgment of the

Supreme Court in the case of N. Balakrishnan Vs. M. Krishnamurthy

AIR 1998 SC 3222 delay of 228 days in filing the appeal is condoned

but subject to payment of costs of Rs.10,000/- to counsel for the

respondents within two weeks from today.

C.M. stands disposed of.

FAO No. 424/2017 and C.M. Appl. No. 39159/2017 (for stay)

3. This first appeal under Section 37 of the Arbitration and

Conciliation Act, 1996 (hereinafter referred to as 'the Act') is filed by

the appellant/objector impugning the judgment of the court below

dated 26.11.2016 by which objections filed by the appellant under

Section 34 of the Act have been dismissed whereby challenge was laid

to the Award of the Arbitrator dated 19.12.2014.

4. It is seen that the appellant had passed orders dated

7.2.2011, 11.4.2011, 9.3.2012, 20.9.2012 and 6/17.9.2012 whereby the

appellant had claimed amounts from the respondent no.1/house-

keeping service provider charges not only with respect to the extant

contract dated 20.2.2010 which was granted for a period of two years

with a three months extension, but also the appellant sought to recover

monies under an earlier contract dated 22.10.2007 which was for a

period of two years with one extension of four months. Total amounts

of Rs.88,000/-, Rs.2,00,000/-, Rs.2,54,889/- and Rs.4,40,432/- were

sought to be recovered from the respondent no.1 by the appellant. An

amount of Rs.4,40,432/- was already recovered by the appellant by

invoking and encashing a bank guarantee furnished by the respondent

no.1.

5.(i) So far as the challenge by the appellant with respect to its

entitlement of claim of deductions for the earlier contract dated

22.10.2007, the claim of the appellant was based on the charge against

the respondent no.1 that the respondent no.1 had provided a chef not

having requisite qualifications and that the staff of the respondent no.

1 was found sleeping in the guest house premises of the appellant.

(ii) In this regard the undisputed position which emerges on record

is that there is no clause of liquidated damages either under the

contract dated 22.10.2007 or the subsequent contract dated 20.2.2010

and appellant has not led any evidence to show that any loss was

caused to it by the breach of the contract of the respondent no.1 in not

providing a qualified chef or that it was found that the respondent

no.1's staff was sleeping on the premises, and therefore once neither

there is a clause of liquidated damages under Section 74 of the Indian

Contract Act, 1872 nor are the losses proved to have been caused to

the appellant, hence no adjustments or deductions or claims of the

appellant could have been allowed by non-payment on account of the

alleged dues of the respondent no.1 under the contract dated

22.10.2007.

6. So far as deduction made by the appellant under the

extant contract dated 20.2.2010, deductions were made on the ground

of alleged excess payment. Once again no evidence was led on behalf

of the appellant before the Arbitrator as to how the so called excess

payment was made to the respondent no.1. Therefore, Arbitrator

denied the claim of the appellant as there was nothing on record to

show how and in what manner excess payment was made to the

respondent no.1 by the appellant.

7. Accordingly, it is seen that there is no basis for sustaining

the impugned orders, and learned senior counsel for the appellants at

this stage during the course of arguments does not very seriously press

the appeal so far as these aspects are concerned.

8. Learned senior counsel for the appellant however very

emphatically questions the grant of high rate of interest by the

Arbitrator under the Award at 15% per annum. Learned senior

counsel for the appellants has placed reliance upon various judgments

of the Supreme Court which observe that since there is consistent fall

in the rate of interest courts could not award high rate of interest.

These judgments of the Supreme Court are Rajendra Construction

Co. v. Maharashtra Housing & Area Development Authority and

Others, (2005) 6 SCC 678, McDermott International Inc. v. Burn

Standard Co. Ltd. and Others, (2006) 11 SCC 181, Rajasthan State

Road Transport Corporation v. Indag Rubber Ltd., (2006) 7 SCC

700, Krishna Bhagya Jala Nigam Ltd. v. G. Harischandra Reddy

and Another, (2007) 2 SCC 720 & State of Rajasthan and Another

Vs. Ferro Concrete Construction Private Limited (2009) 12 SCC 1.

9. At this stage, learned counsel for the respondent no.1

states that the respondent no.1 if not be held entitled to 15% rate of

interest, it should yet be awarded a reasonable rate of interest which

should be much higher than 6% per annum as passed by the

appellants, and therefore in the facts of this case I am of the opinion,

and so agreed by counsels for both the parties, that the rate of interest

under the Award would stand reduced from 15% per annum to 9% per

annum, of course without in any manner interfering with the period for

which interest is payable by the appellant to the respondent no.1.

10. In view of the aforesaid discussion this appeal is disposed

of by sustaining the impugned judgment dated 26.11.2016 and the

Award of the Arbitrator dated 19.12.2014, except that the rate of

interest will stand reduced to 9% per annum simple.

11. The appeal is disposed of accordingly. Parties are left to

bear their own costs.

OCTOBER 31, 2017                             VALMIKI J. MEHTA, J
AK





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter