Citation : 2017 Latest Caselaw 6531 Del
Judgement Date : 17 November, 2017
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Reserved on: 06th November, 2017
Pronounced on: 17th November, 2017
+ EX.P. 47/2004, EX.AAPL.(OS) 377/2014
ECE INDUSTRIES ..... Decree Holder
Through : Mr.Amandeep Bawa, Advocate.
versus
DELHI POWER SUPPLY CO. & ORS ..... Judgment Debtors
Through : Mr.S.K.Dubey, Advocate with
Mr.Gaurav Gupta, Manager
(Legal) in person for judgment
Nos.1 & 2 in person.
Mr.Ravi Gupta, Sr Advocate with
Mr.Sunil Fernandes, Ms.Anju
Thomas, & Ms.Nupur Kumar,
Advocates judgment Nos.3 & 4.
Mr.Parnay Deep Shah and
Mr.Saurabh Shaw, Advocates for
non-applicant/TPDDL.
CORAM:
HON'BLE MR. JUSTICE YOGESH KHANNA
YOGESH KHANNA, J.
EA (OS) No.417/2012
1. This order shall decide an application moved by the judgment debtors No.3 & 4 under Order 1 Rule 10 read with Section 151 of the CPC for impleading of non-applicant/Tata Power Delhi Distribution
Limited (TPDDL) in the present execution proceedings as judgment debtor No.5.
2. The decree holder has sought execution of an arbitral award dated 09.04.2002 for recovery of `1,40,18,612.84/- along with interest @ 18% pa against the judgment debtor Nos.1 & 2. Vide an order dated 02.04.2007 the applicants viz judgment debtor Nos.3 & 4 were impleaded and they filed their respective affidavits.
3. The case of the decree holder, initially, was three purchase orders were placed by the Delhi Vidyut Board (DVB) for supply of 50, 110 and 135 KV Distribution Transformers. The same were duly supplied to the DVB and since they did not pay in terms of the purchase orders, the arbitration was invoked and subsequently award dated 09.04.2002 was passed against judgment debtors No.1 & 2.
4. In the year 1998 the Government of NCT of Delhi has started the process of bundling and privatization of the DVB and pursuant to such exercise, it was unbundled into six company i.e., a holding company; a generating company; a transmission company; and three distribution companies (DISCOMS). The provisions of the Delhi Electricity Reform (Transfer Scheme) Rules, 2001 came into force with effect from 01.07.2002 as notified by the notification dated 26.06.2002 and thus such rules are statutorily binding in nature. After the privatization, in place of the erstwhile DVB, six companies came into existence viz. holding company namely Delhi Power Company Limited; generating company namely GenCo; a transmission company namely Delhi Transco Limited;
and three distributions companies / DISCOMS viz BSES Rajdhani Power Limited; BSES Yamuna Power Limited; and Tata Power Delhi Distribution Limited (North Delhi Power Limited). The work related to the decree holder claimant, as contained in the statement of claim was undertaken and executed till 2002, but prior to the date of privatization. Despite there being no privity of contract between the judgment debtors Nos.3 & 4 and the decree holder, this Court vide an order dated 02.04.2007 had impleaded them being DISCOMS as subsequent to the Transfer Scheme came into existence with effect from 01.07.2002 three DISCOMS shared the responsibility for supply of electricity through transformers.
5. Hence, it is prayed that TPDDL formerly known as North Delhi Power Limited, a DISCOM, be also made a party to the present proceedings as under the transfer scheme it was entitle to equal assets and liabilities along with two other DISCOMS viz. judgment debtors No.3& 4. It is alleged there is nothing on record to suggest as to what happened to the transformers that were received by the judgment debtor Nos.3 & 4 and by the TPDDL. It is also alleged that TPDDL, if impleaded, would reveal as to how many transformers were supplied to them by erstwhile DVB which are lying in its possession or is using it for supply of electricity within the vicinity of Delhi. Hence TPDDL is necessary and proper party.
6. In reply TPDDL/DISCOM in para No.9 has alleged that all records relating to the transformer were within the sole custody of the Transco and therefore, it is the liability of the Transco to provide the details as to
whether any of the transformers relating to the present execution petition were ever delivered /transferred or is possessed by the non-applicant. Admittedly the dispute amongst the DISCOMS pertain only to 64 transformers.
7. Now Rule 8 (3) of the Delhi Electricity Reform (Transfer Scheme) Rules, 2001 notes as under:-
"8. Pending suits, Proceedings -
(1) xxx (2) xxx (3) Notwithstanding anything contained in these rules including the Schedules, the liabilities arising out of litigation, suits, claims, etc pending on the date of the transfer and / or arising due to events prior to the date of the transfer shall be borne by the relevant distribution company viz.
DISCOM 1, DISCOM 2, and DISCOM 3 respectively, subject to a maximum of Rs.1 Crore per annum. Any amount above this shall be to the account of the holding company in the event for any reason the Commission does not allow the amount to be included in the revenue requirement of the DISCOM."
8. Here I would also like to refer to the decision of the Supreme Court in North Delhi Power Limited vs. Government of NCT of Delhi & Ors (2010) 6 SCC 278, where it notes:-
"54. The learned counsel next contended that the High Court had erred in interpretation of Rule 8(3) of the transfer scheme. It was urged that if the Rule is construed widely, it will be arbitrary and affect the foundation of the privatisation which is mutual agreement. We do not think so. On the other hand, the purpose of sub-Rule (3) is to cap
any liability arising out of litigation, suits, claims etc. either pending on the date of transfer and/ or arising due to events prior to the date of transfer to be borne by the relevant DISCOM 1, DISCOM 2 or DISCOM 3, respectively. However, it will be subject to a maximum of rupees one crore per annum and any amount above this shall be to the account of the holding company and, even for any reason the Commission does not allow the amount to be included in the revenue requirements of the DISCOMS. The language is extremely clear. All that it obtains is capping of the liability. However, the nature of the liability and its being imposed on the DISCOMS alone is as clear as sunshine. To that extent, there can be no doubt that it includes all the liabilities including the liabilities on account of the personnel. Unlike Rule 3, Rule 8 (3) does not make any difference between the liabilities arising out of the transfer under Rule 4 or the liabilities contemplated in Rule 6. The contention is clearly incorrect.
55. It was suggested that the non obstante clause in Rule 8(3) if widely construed, would render the clause unconstitutional. We do not think that the clause can be rendered unconstitutional in any manner. The language is clear, unambiguous and must be given its natural meaning. If such a meaning is given, we do not think that any other interpretation is possible except the one rendered by the High Court. Shri Rao and Shir Patwalia relied on paragraphs 28 and 29 of the reported judgment in M. Rathinaswami & Ors. v. State of Tamil Nadu & Ors. [2009 (5) SCC 625]. In the said paragraphs, it is reiterated that in order to save a statutory provision from the vice of unconstitutionality sometimes a restricted or extended interpretation of the statute has to be
given. Since we don't agree that the clause can be rendered unconstitutional in any manner, in our opinion, the judgment is not apposite."
9. Hence, considering the provision of Rule 8(3) of the Electricity Reforms Act and decision in North Delhi Power Limited (supra), the non- applicant TPDDL cannot say that it would be illegal or unjustified to implead them as party to these proceedings.
10. It is matter of record that in order dated 21.11.2013 this Court notes three transformers have been transferred to BSES Yamuna Power Limited; seven to BSES Rajdhani Power Limited; but the details of 54 transformers was yet to be provided. In an affidavit dated 19.04.2014 on behalf of judgment debtor no.2 reference was made to failure of 10 transformers, of which deductions were given by the learned arbitrator. Moreso, the affidavit of Mr.Prakash Kumar Choudhary, on behalf of the judgment debtor No.1 averred about the Scheme of the Act more specifically under Rule 8(3) (supra) and deposed that on the basis of the discussions the decree holder had with the officials of DPCL a sum of `1,17,93,716/- was determined. The calculations were upto 31.01.2017. The affidavit further recorded the aforesaid sum is payable by the DISCOMS and not by DPCL, per Rule 8(3) (supra). He further reiterated that in view of above, the amount so calculated shall be payable by three DISCOMS viz BSES Rajdhani Power Limited; BSES Yamuna Power Limited; and Tata Power Delhi Distribution Limited in equal proportion of 1/3rd each of such amount in terms of Shared Facility Agreement dated 27.06.2002 effective from 01.07.2002 which is the part of the statutory
Transfer Scheme Rules, 2011 and the DISCOMS were legally bound by the same. The relevant portion of the schedule annexed to Share Facility Agreement dated 27.06.2002 read as under:-
"2. The DISCOMS will make arrangements for the procurement / acquisition of stores required by them. However, only for the existing stores and for the tenders already floated or orders placed, the following arrangements shall be applicable.
a) All civil works including buildings and facilities relating to stores situated at RPH Store (except Generation Store), Gazipur Store, Narela EHV Store, Lwarence Road Store, Okhla Store and Sri Niwaspuri Store (hereinafter jointly referred to as „Centralised Stores‟) shall vest in the relevant DISCOM, in whose area of supply the store is situated. The civil works including buildings and facilities of Mehruali Stroe and New Mehurali Store shall vest in TRANSCO. Each of the time of materials lying in the centralized stores pertaining to distribution functions shall be divided amongst the three DISCOMS in equal share with a right to the DISCOMS to adjust among themselves and vary the proportion of the stores based on their mutual agreement. Transco shall bill the DISCOMS for these stores on actual cost. The Transco will, however continue to provide services for stores at Centralised Stores for the benefit of the DISCOMS, at their option, for a period not exceeding one year. All the parties to this agreement shall, however, cooperate to ensure that the stores of distribution functions are divided and distributed within six months of the date of the transfer."
11. In view of the Shared Facility Agreement between Holding; Generating and Distribution companies and in view of Rule 8(3) of Delhi
Electricity Reforms (Transfer Scheme) Rules 2001, it shall be necessary to implead all DISCOMS. Since two of the DISCOMS have already been impleaded as judgment debtors no. 3 and 4 hence to resolve matter in controversy it is imperative to implead TPDDL, being necessary and proper party in these execution proceedings, hence is directed to be impleaded as judgment debtor No.5.
12. Amended memo of parties be filed by the decree holder within two weeks from today. The application stands disposed of.
EX.P. 47/2004, EX.AAPL.(OS) 377/2014
13. List for further directions before the learned Joint Registrar on 13.12.2017.
YOGESH KHANNA, J NOVEMBER 17, 2017 M/RS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!