Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Moni Traders vs Govt Of Nct Of Delhi
2017 Latest Caselaw 3832 Del

Citation : 2017 Latest Caselaw 3832 Del
Judgement Date : 1 August, 2017

Delhi High Court
M/S Moni Traders vs Govt Of Nct Of Delhi on 1 August, 2017
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

+                         FAO No. 325/2017
%                                                    1st August, 2017

M/S MONI TRADERS                                          ..... Appellant
                                   Through: Mr R. Rajappan, Advocate
                          versus

GOVT OF NCT OF DELHI                                   ..... Respondent

CORAM:

HON'BLE MR. JUSTICE VALMIKI J. MEHTA

To be referred to the Reporter or not?

VALMIKI J. MEHTA, J (ORAL)

CM No. 27241/2017 (for exemption)

Exemption allowed subject to all just exceptions.

CM stands disposed of.

FAO No. 325/2017

1. This first appeal under Section 37 of the Arbitration and

Conciliation Act, 1996 (hereinafter referred to as 'the Act') impugns

the judgment of the court below dated 05.04.2017, whereby the

objections filed by the appellant under Section 34 of the Act have been

dismissed and the Award dated 04.02.2016 of the arbitration tribunal

upheld.

2. By the Award, the respondent has been allowed to forfeit

the security deposit/performance guarantee which is the only aspect

which is argued before this Court.

3. The facts of the case are that a contract was entered into

between the appellant/contractor and the respondent for a sum of

Rs.67.62 lacs dated 20.11.2012 which was to commence on

04.12.2012 allowing six months time for completion of removal of

obstructions in the bed of NG drain like steel girders/RCC pipe,

dumped malba, building rubbish etc. and protection work on both

sides bank on the Mall Road bridge.

4. Appellant commenced the work but abandoned the work

on account of heavy seepage which could not be overcome despite

dewatering operations being carried out alleging impossibilities in

conditions of performance. Respondent rescinded the contract vide

letter dated 15.06.2013, that is, after the six months period of

completion of the contract. Respondent thereafter forfeited the earnest

money and the performance guarantee amount which was disputed by

the appellant as a claimant in the arbitration proceedings.

5. The issue argued before this Court on behalf of appellant

is that the earnest money and the performance guarantee could not be

forfeited unless losses were proved by respondent as required by

Section 74 of the Indian Contract Act, 1872. It is argued that the court

below ought to have relied upon the judgment of the Supreme Court in

the case of Hind Construction Contractors By Its Sole Proprietor

Bhikam-Chand Mulchand Jain (Dead) By LRs vs. State of

Maharashtra, AIR 1979 SC 720 which held that as the time was not

the essence of the contract, there cannot be forfeiture by invoking

Section 74 of the Contract Act. It is argued on behalf of appellant that

court below wrong relied upon the judgment of the Supreme Court in

the case of State of Gujarat vs. Dahyabhai Zaverbhai, AIR 1997 SC

2701 and which judgment approved the action of forfeiture of security

deposit as per clause of the contract on abandonment of work by the

contractor.

6. In my opinion, appellant cannot place reliance upon the

Hind Construction Contractors case (supra) inasmuch as in that case

the issue was of extension of time and consequently, once there was a

provision for extension of time hence disentitlement of the owner of

the project to rescind the contract, whereas in the present case the fact

of the matter is that appellant has been found to have abandoned the

contract. Further, the rescission of the contract by the respondent is

after the period of six months given in the contract as the six months

period commenced on 04.12.2012 and the rescission letter is dated

15.06.2013. In my opinion, therefore, the judgment in Dahyabhai

Zaverbhai's case (supra) squarely applies and which entitles the

forfeiture of the security deposit on account of abandonment of the

contract.

7. In my opinion there is another reason for rejecting the

argument urged on behalf of appellant inasmuch as whether the losses

have to be proved to have been caused or not depends on the nature of

the contract. If nature of the contract is such that losses which occur

cannot be proved, then there is no requirement of losses having to be

proved in order to forfeit the earnest money vide ONGC Ltd. vs. Saw

Pipes Ltd., (2003) 5 SCC 705 and Kailash Nath Associates vs. Delhi

Development Authority and Another, (2015) 4 SCC 136. In a

contract of cleaning a drain before the onset of the monsoon season

and which is not completed even after onset of monsoon season what

would be the loss of the respondent cannot be calculated in terms of

money and, therefore, keeping in mind the nature of the contract, the

respondent was entitled to forfeiture of security deposit/performance

guarantee. Accordingly, I reject the argument of the appellant that the

security deposit/performance guarantee could not have been forfeited

without proving of the losses.

8. There is no merit in the appeal. Dismissed.

AUGUST 01, 2017/SR                          VALMIKI J. MEHTA, J





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter