Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vinod Kumar Gupta vs South Delhi Municipal ...
2016 Latest Caselaw 6396 Del

Citation : 2016 Latest Caselaw 6396 Del
Judgement Date : 5 October, 2016

Delhi High Court
Vinod Kumar Gupta vs South Delhi Municipal ... on 5 October, 2016
$~40
*    IN THE HIGH COURT OF DELHI AT NEW DELHI


+                         LPA 329/2016

                                    Date of decision: 5th October, 2016


        VINOD KUMAR GUPTA                                ..... Appellant
                    Through:           Mr.Rajesh Tyagi, Advocate

                          versus

        SOUTH DELHI MUNICIPAL CORPORATION & ORS
                                                  ..... Respondent
                     Through: Ms.Puja Kalra, Advocate for R-1
                              Mr.Abhishek Kumar Rao and
                              Ms.Bavya Bharti, Advocates for R-3

        CORAM:
        HON'BLE MR. JUSTICE SANJIV KHANNA
        HON'BLE MS. JUSTICE SUNITA GUPTA

SANJIV KHANNA, J. (ORAL)

Confronted with the position that the respondent No.1-Corporation

has approved the application of the respondent No.3-Company for change of

user vide permission/approval dated 30th March, 2016, learned counsel for

the appellant states, on instructions, that he would challenge the order dated

30th March, 2016 in a fresh writ petition. It is submitted that the order

granting permission/approval dated 30th March, 2016 was passed by the

Corporation after the impugned order dated 21st March, 2016 was passed by

the single Judge in W.P. (C) No.806/2016, Vinod Kumar Gupta Vs. South

Delhi Municipal Corporation and Ors.

2. Learned counsel for the respondent No.3-Company, however, submits

that the appellant does not require the permission of the Appellate Court to

file a writ petition impugning the order granting approval/permission dated

30th March, 2016. He states that the petitioner is a rabble-rouser and had

filed W.P. (C) No.806/2016 to harass and harrow his brother. There are

multiple litigations inter se the two brothers.

3. In view of the order granting approval/permission dated 30 th March,

2016, the question of change of user would become infructuous. To this

extent we need not examine the issue of change of user in the present appeal

for the reason that the user has been regularised. If the regularization is not

in accordance with law and is contrary to the provisions of the Master Plan

of Delhi-2021 the appellant, subject to his right to challenge and question

the approval, would have to take recourse to appropriate proceedings in

accordance with law.

4. Bearing in mind the statement made by the learned counsel for

respondent No.1, it is open to the appellant to challenge and question the

order granting approval/permission dated 30th March, 2016. The said order

has been passed after the order dated 21st March, 2016 was passed by the

single Judge.

5. With regard to the unauthorised construction, the appellant has raised

the following five contentions.

(1) For category-6 plots admeasuring between 750 to 1000 Sq.

mtrs., as per Clause 4.4.3 of the Master Plan of Delhi, 2021, the

maximum ground coverage permissible is 50%. In the present

case, the respondent-corporation has permitted and allowed a

maximum ground coverage of 75% which is applicable to

category-5 plots admeasuring between 250 and 750 sq. Mts.

(2) The stilt parking height cannot exceed 2.4 mtrs. In the present

case, the height of the stilt parking is 2.92 mtrs.

(3) The height of the stilt level flooring is 2 ½ ft. from the road

level. As per the Bye-laws the height of stilt parking cannot be

more than six inches.

(4) The constructed building has been cladded and encircled with

glass panels, thereby closing the balconies. This is contrary to the

Bye-laws.

(5) The height of the building cannot exceed 15 mtrs. In the

present case, the respondents have constructed pillars and beams

without laying the ceiling. If the beams and pillars are counted, the

height of the building would exceed 15 mtrs.

6. Learned counsel for the respondent-corporation had drawn our

attention to Clause (ii) under the Heading 'Terms & Conditions' to Clause

4.4.3. As per the Corporation, the total coverage and FAR permissible in a

plot of any category shall not be less than that permissible to the largest plot

in the next lower category. The largest plot in category-5 is 750 sq. mtrs.

and the permitted FAR is 75%, i.e. 562.5 sq. mtrs. Thus the total ground

level coverage permissible in the present case is 562.5 sq. mtrs. Construction

on the ground floor is within the permissible limit. Faced with the aforesaid

factual position, the learned counsel for the appellant says that he is giving

up the first point.

7. On the maximum permissible height of the stilt parking, the

Corporation states that they are satisfied on this count. The stilt parking has

a false ceiling. The height, it is submitted, has to be counted till the base of

the false ceiling. Even otherwise, the floor to RCC ceiling height of the stilt

parking is 2.40 mtrs. As the respondent-Corporation is satisfied that the

height of the stilt parking is 2.40 mtrs. and has not been breached, we are not

impressed with the argument raised.

8. The plot in question is a corner plot and there are two roads adjoining

it. The roads have different levels. The respondent-Corporation has

considered the higher road, which is in front of the plot. The Corporation is

satisfied.

9. Regarding glass panels, it is pointed out that the balconies were not

constructed on the frontage of the building. The glass panels have been fixed

as a facade. The private respondents state that on the side balconies and

windows exist and open. The Corporation is again satisfied.

10. The photographs produced before us by the appellant would show that

a ceiling has not been casted and constructed. There are columns and beams

without any brick walls. This would not amount to a construction of a floor

above the second floor. The last violation as alleged, therefore does not, as

per the Corporation, have any merit.

11. We do not find any reason to waive off the cost imposed by the

learned Single Judge, for we find that the issues and contentions raised by

the appellant were wrong and incorrect. However, counsel for respondent

No.3-Company on instructions from the Managing Director, who is the

appellant's brother, states that he would not like the appellant to be burdened

with costs and the same may be waived. This statement is taken on record

and the cost imposed by the impugned order is waived.

The appeal is disposed of.

SANJIV KHANNA, J.

SUNITA GUPTA, J.

OCTOBER 05, 2016 NA/sv

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter