Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gangotri Enterprises Ltd. vs National Thermal Power ...
2016 Latest Caselaw 7582 Del

Citation : 2016 Latest Caselaw 7582 Del
Judgement Date : 24 December, 2016

Delhi High Court
Gangotri Enterprises Ltd. vs National Thermal Power ... on 24 December, 2016
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

%                      Judgment Delivered on:     December 24, 2016

+     FAO(OS) COMM 149/2016

      GANGOTRI ENTERPRISES LTD.        ..... Appellant
                  Through   Ms. Chetna Bhalla, Advocate.

                          versus

      NATIONAL THERMAL POWER CORPORATION LTD.
                                   ..... Respondent
                   Through None

CORAM:
HON'BLE MS. JUSTICE INDIRA BANERJEE
HON'BLE MR. JUSTICE ANIL KUMAR CHAWLA

                            JUDGMENT

INDIRA BANERJEE, J (ORAL)

1. This appeal under Section 37 (1) (b) of the Arbitration and

Conciliation Act 1996, hereinafter referred to as the 1996 Act,

is against an order dated 22.12.2016 passed by the learned

Single Judge dismissing the application being OMP (1)

(COMM) No. 60/2015, filed by the appellant under Section 9 of

the 1996 Act.

=====================================================================

2. The respondent issued a Notice Inviting Tender (NIT) dated

16.02.2007 for Raw Water Reservoir Civil Works for National

Thermal Power Corporation (NTPC), Stage-II at Dadri in

Gautam Budh Nagar District in Uttar Pradesh.

3. In response to the said Notice Inviting Tender, the appellant

submitted its bid on 09.05.2007. The petitioner was declared

successful, after which a Letter of Award No. CS- 6130-319A-

9-CS-LOA-5053 dated 21.01.2008 was issued to the petitioner

for execution of the project for a total consideration of Rs

46,81,98,550/-.

4. A formal contract was executed between the petitioner and the

respondent on 12.03.2008. The Notice Inviting Tender, the

General Conditions of Contract of NTPC for civil works along

with its amendment, the Special Conditions of Contract and

other specified documents were made part of the contract.

5. In terms of the contract executed by and between the appellant

and the respondent, and in particular, clause 7 of the Letter of =====================================================================

Award, the project was to be completed within 24 months from

the date of receipt of the Letter of Award.

6. Clause 8.1.0 of the Letter of Award required the appellant to

make a security deposit Rs. 68,31000 by way of bank

guarantee. Accordingly, under cover of a forwarding letter

dated 12.03.2008, the Petitioner Furnished a Bank Guarantee

being BG No.4/08 dated 11.03.2008 issued by Canara Bank,

Hazratganj, Lucknow to the respondent. The Said Bank

Guarantee, was from time to time renewed, the last renewal

being till 10.12.2015.

7. Clause 14.1.0 of the Special Conditions of Contract required the

petitioner to deposit a Performance Guarantee security of Rs.

1,00,00,000/- by way of Bank Guarantee. Accordingly, the

petitioner, under cover of a forwarding letter dated 27.03.2008,

furnished a bank guarantee being BG No. 26/2008 dated

25.3.2008, issued by a Corporation Bank, Kaiserbagh,

Lucknow, to the respondent. The said bank guarantee was, from

=====================================================================

time to time renewed. The bank guarantee being BG

No.26/2008 is valid till 22.06.2017.

8. As per the Special Conditions of Contract the appellant was

also required to deposit a bank guarantee of Rs. 30,00,000/-

against material to be issued by the respondent. The appellant

accordingly furnished a Bank Guarantee being BG No. 39/2009

dated 17.12.2009 issued by Corporation Bank kaiserbag,

Lucknow, which was forwarded to the respondent under cover

of a forwarding letter dated 21.12.2009. The bank guarantee

was initially valid till 6.12.2010, but later renewed from time to

time. The bank guarantee is valid till 14.06.2017.

9. As per clause 13 of the General Conditions of Contract, the

execution of the project work was to commence on the 15th day

of the date of issuance by the respondent of written orders to

commence work. The appellant contends that no such notice or

order as contemplated in Clause 13 of the General Conditions

of Contract was issued to the appellant.

=====================================================================

10. It is alleged by the appellant, that the project work could not be

completed due to breaches and lapses on the part of the

respondent in performing its obligations under the contract.

According to the appellant, the appellant would have completed

the project within the stipulated time, but for the breaches and

lapses on the part of the respondent.

11. The appellant sought extension of time for completing the

work, and the respondent granted such extension. In the

meanwhile, by a letter dated 13.03.2010, the appellant penned

down its grievances with regard to failure of the respondents to

supply layout plan, construction drawings etc.

12. On 03.02.2011, the appellant again wrote to the respondents

explaining why the project work could not even be started.

Breaches and lapses were attributed to the respondents. The

respondents also raised claims to the tune of Rs. 41.67 crores

upon the respondent on account of alleged breaches and lapses

committed by the respondents.

=====================================================================

13. On 09.10.2012, the appellant invoked Clause 56 of the General

Conditions of Contract, that is, the arbitration clause, and

sought appointment of an independent arbitrator. The Chairman

and Managing Director of the respondent appointed an

arbitrator. The arbitrator entered into the reference.

14. By a letter dated 11.05.2015, the respondent alleged that the

project work had been stalled since 20.6.2014 and had not been

resumed by the appellant despite repeated requests informed

that after some investigation, it had been found that Rs. 139.50

lakhs was recoverable from the bills of the appellant. Thereafter

communication ensued between the parties

15. On 04.11.2015, the respondent served final notice to the

appellant in terms of Clause 41 of the General Conditions of

Contract, to resume the project work within 7 days, failing

which, the respondent would get the same executed at the risk

and cost of the appellant.

=====================================================================

16. The appellant has alleged that that the respondent all of a

sudden invoked the Bank Guarantees being BG Nos. 04/08,

26/2008 and 39/2009 by three letters issued on 07.12.2015 and

09.12.2015 respectively. The bankers of the appellant put the

appellant to notice of the demand and requested the appellant to

arrange funds to liquidate the bank guarantee amount

17. In the aforesaid circumstances, the petitioner filed an

application being OMP (1) (Comm) No. 60/2015 under Section

9 (1) of the 1996 Act, seeking an interim order restraining the

respondent from encashing the Bank Guarantees, or realising

the proceeds thereof. However, while the application was

pending, counsel for the respondent informed the Court that the

bank guarantee being BG No. 04/08 Rs. 4,68,31,000/- had

already been encashed.

18. On 14/12/2015, Counsel for the respondent submitted that the

Bank Guarantee being BG No. 26/2008 had not till then been

invoked. Insofar as BG No. 39/2009 was concerned the learned

=====================================================================

Judge granted stay and directed that the amount of Rs.

30,00,000/- should not be remitted to the respondent till the

next date of hearing

19. On 26.11.2016, the respondent terminated the contract in

question, as per Clause 41 of the General Conditions of

Contract. On 30 08/11/2016 an application of the appellant

being OMP (1) (Comm.) 10/2016 under Section 14(2) 0f the

1996 Act, questioning the authority of the sole arbitrator to

proceed with the reference, as also the application under

Section 9 of the 1996 Act being OMP (1) (Comm.) No. 60/2015

were heard by the learned Single Bench. The application under

Section 9 was directed to be listed on 22.12.2016 and the

interim orders were directed to continue till the next date of

hearing. On 22.12.2016, the learned Single Judge passed the

order under appeal, dismissing the application of the appellant

under Section 9 of the 1996 Act. It is not in dispute that the

Bank Guarantees in question were unconditional bank

guarantees invocable on demand =====================================================================

20. It is well settled that a Bank Guarantee constitutes an

independent contract between the bank which issues the Bank

Guarantee and the beneficiary of the Bank Guarantee. In the

matter of invocation of a bank guarantee, the merits of the

underlying disputes between the party at whose instance the

Bank Guarantee was furnished and the beneficiary of the Bank

Guarantee are of no relevance. It is only in exceptional cases of

egregious fraud or irretrievable injustice and/or special equity

that an injunction restraining the invocation of a Bank

Guarantee might be granted.

21. It is also well settled that if the bank cannot be restrained from

honouring a Bank Guarantee, the beneficiary of the Bank

Guarantee cannot also be restrained from invoking the Bank

Guarantee, for one cannot do indirectly, what one is not free to

do directly. This proposition is settled by the judgement of the

Supreme Court in UP Cooperative Federation Ltd. Vs. Singh

Consultants and Engineers Private Limited reported in (1988)

1 SCC 174.

=====================================================================

22. The bank was/is bound to honour its commitment under the

Bank Guarantees, irrespective of the merits of the disputes

between the appellant and the respondent. It is reiterated that

the Bank Guarantee is unconditional. It is not the case of the

appellant that the invocation was/is not in terms of the Bank

Guarantee. No case of fraud or special equity has been made

out.

23. The learned Single Judge rightly dismissed the application

under Section 9 of the 1996 Act. The appeal is without merit

and the same is dismissed. The appellant may proceed to press

its claim if any against the respondents in the arbitral

proceedings.

INDIRA BANERJEE, J

ANIL KUMAR CHAWLA, J December 24, 2016/ n

=====================================================================

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter