Thursday, 30, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gvr Infra Projects Ltd. vs Natiional Highway Authority Of ...
2015 Latest Caselaw 6679 Del

Citation : 2015 Latest Caselaw 6679 Del
Judgement Date : 8 September, 2015

Delhi High Court
Gvr Infra Projects Ltd. vs Natiional Highway Authority Of ... on 8 September, 2015
Author: Rajiv Sahai Endlaw
           *IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                    Date of decision: 8th September, 2015

+           W.P.(C) No.2037/2012 & CM No.4421/2012 (for stay)

       GVR INFRA PROJECTS LTD.                     ..... Petitioner
                    Through: Mr. A.D.N. Rao, Mr. A. Venkatesh
                             and Ms. Neelam Jain, Advs.

                                Versus

    NATIIONAL HIGHWAY AUTHORITY OF INDIA
    AND ORS                                  ..... Respondents

Through: Ms. Meenakshi Sood, Adv. for NHAI.

Mr. Vikas Mahajan, CGSC with Mr. Rohan Gupta, Advs. for R-3.

CORAM:-

HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW

1. This petition was filed impugning the letters dated 13 th March, 2012

and 2nd April, 2012 of the respondents No.1&2 National Highways

Authority of India (NHAI), (respondent No.3 is Union of India) to the

petitioner notifying the petitioner that the bid submitted by it to the tender

for construction of new bridges / structures, repair of existing four lane

highway from Baleshwar to Kharagpur Section of NH-60 in the State of

Orissa / Odhisha & West Bengal was incomplete (non-responsive) and

asking the petitioner to, in terms of the tender conditions, deposit 5% of the

value of the bid security i.e. Rs.23.55 lakhs with the respondent No.1 NHAI

within seven days and threatening to otherwise partially encash the Bank

Guarantee (BG) submitted by the petitioner along with the bid.

2. The petition was entertained and referring to the judgment dated 10 th

March, 2011 of the Division Bench of this Court in W.P.(C) No.8418/2010

titled M/s. Madhucon Projects Ltd. Vs. National Highways Authority of

India, the encashment of BG by the respondents No.1&2 NHAI was stayed,

subject to the petitioner keeping the BG submitted alive to the extent of

Rs.23.55 lakhs.

3. The respondents No.1&2 NHAI has filed a counter affidavit. The

order dated 19th May, 2015 records that the Special Leave Petition (SLP)

preferred by the respondents No.1&2 NHAI against the judgment aforesaid

in M/s. Madhucon Projects Ltd. supra was dismissed by the Supreme Court

on 17th March, 2015.

4. The counsels have been heard.

5. Clause 3.2.2 of Volume No.I titled "Instruction to Bidders" of the

tender documents provided for the "Tests of Responsiveness" and Clause

2.20.7(a) under the head of "Bid Security" provided for the consequence of

payment of damages restricted to 5% of the value of the bid security for

submitting a non-responsive bid.

6. The respondents No.1&2 NHAI vide the impugned letter dated 13th

March, 2012 informed the petitioner that upon opening of the bids in the

presence of the representative of the petitioner, the online bid submitted by

the petitioner was found to be incomplete and vide impugned letter dated 2nd

April, 2012 asked the petitioner as aforesaid to deposit 5% of the value of

the bid security amounting to Rs.23.55 lakhs.

7. The counsel for the petitioner has raised two contentions. Firstly, it is

contended (i) that the bid, as per the tender conditions, was required to be

submitted in a hard copy as well as online; (ii) that no default was found in

the bid submitted by the petitioner in the form of hard copy; (iii) though the

petitioner had submitted the same bid online but the same, for reasons

beyond the control of the petitioner and owing to technical glitches,

remained to be received by the respondents No.1&2 NHAI; (iv) the

petitioner thus cannot be said to have submitted a non-responsive bid; and,

(v) that once the bids were required to be submitted in physical form as well

as online, even if the bid in the online form remained non-responsive, the

same was immaterial, since the same was only by way of abundant caution

and the bid submitted in physical form was enough. Reliance in this regard

is placed on Poddar Steel Corporation Vs. Ganesh Engineering Works

(1991) 3 SCC 273 in para 6 whereof it was held that as a matter of general

proposition, it cannot be said that an authority inviting tenders is bound to

give effect to every term mentioned in the notice in meticulous detail and is

not entitled to waive even a technical irregularity of little or no significance.

8. The second contention of the counsel for the petitioner is that the

Division Bench of this Court in M/s. Madhucon Projects Limited supra has

held the said clause of payment of 5% of the bid security for submitting a

non-responsive bid to be bad in law. However, the counsel has fairly stated

that the respondents No.1&2 NHAI in this regard is relying on the order

dated 18th March, 2015 of the Supreme Court in Civil Appeal No.3053/2015

titled National Highways Authority of India Vs. MEIL-EDB LLC (JV)

with respect to the same clause inter alia holding that the question whether

any damage has occurred to the respondents No.1&2 NHAI owing to

submission of non-responsive bid should be left to be considered by the

Civil Court and a Writ Court should refrain from adjudicating the said

controversy. The counsel for the petitioner thus fairly admits that the

judgment of the Division Bench of this Court in M/s. Madhucon Projects

Limited supra holding the said clause to be per se bad, can no longer be said

to be good law.

9. It thus follows, that if NHAI claims to have suffered a loss on account

of the bid submitted by petitioner being a non-responsive one and claims to

invoke the BG therefor and the petitioner controverts, the same question has

to be adjudicated in a Civil Court and not in a writ jurisdiction.

10. As far as the first of the aforesaid contentions of the petitioner is

concerned, in my view the adjudication thereof also would require

examination and cross-examination of witnesses, to determine whether the

bid submitted by the petitioner indeed was responsive or non-responsive.

Even otherwise, it is felt that once the claim is to be relegated to the Civil

Court, there should not be any piecemeal adjudication and the entire

controversy should be decided by the same Court. Such piecemeal

adjudication has always been deprecated. Reference in this regard can be

made to Moolchand Khairati Ram Hospital & Ayurvedic Research

Institute Vs. Secretary (Labour), GNCTD MANU/DE/1135/2001, Al-

Qahtani Pipe Coating Terminal Vs. Minerals Sales (P) Ltd.

MANU/MH/1278/2008, Claridges Hotel Pvt. Ltd. Vs. M.M. Bhagat & Co.

92 (2001) DLT 61 and also to D.P. Maheshwari Vs. Delhi Administration

(1983) 4 SCC 293. It will have to be determined, whether the requirement

of submitting the online bid was a superfluous requirement for the said

clause to be covered by the dicta of the Supreme Court in Poddar Steel

Corporation supra. Moreover, in Poddar Steel Corporation the question

was, whether the authority inviting the tender is entitled to vary the

non-essential terms thereof or not and whether the acceptance of the bid can

be challenged on this ground. Conspectus of the controversy in Poddar

Steel Corporation supra was thus in an entirely different context from as has

arisen in the present case. Here, it is not the respondents No.1&2 NHAI

which is seeking to tweak with the tender conditions but it is the bidder, who

after having agreeing to the tender terms and of submitting a bid, is now

wanting to contend that non-compliance with one of the conditions of the

tender would not invite the penal clause. I am therefore of the view that in

terms of the judgment of the Supreme Court in MEIL-EDB LLC (JV), the

parties, for adjudication of the said controversy also, are required to be

relegated to the Civil Court.

11. It is however found that the respondent NHAI, in the impugned letters

dated 13th March, 2012 and 2nd April, 2012, demanded the amount aforesaid

of Rs.23.55 lakhs being 5% of the value of Bid Security, merely in

accordance with Clause 2.20.7 of the tender document and without claiming

to have suffered any damage. Even in the counter affidavit filed to this

petition, no plea of having suffered any damage or to the extent of Rs.23.55

lakhs is to be found. Now, the Supreme Court, in MEIL-EDB LLC (JV)

supra has held that it is for the Civil Court to determine whether any damage

is suffered by NHAI and if so, whether deduction of 5% was a fair pre-

estimate or was punitive in nature. However, before the said adjudication is

relegated to the Civil Court, as done in the judgment supra, it is deemed

appropriate that first NHAI takes a decision in this respect in the light of the

said judgment of the Supreme Court. If NHAI itself, which till now was

claiming in the said amount under the belief that it was due under Clause

2.20.7 supra, decides that now, in the light of dicta of the Supreme Court it is

not to be claimed, there would be no need to relegate the parties to the Civil

Court.

12. Accordingly, this writ petition is disposed of with the following

directions:

A. NHAI to, on or before 31st October, 2015 take a decision afresh

on its claim for the aforesaid sum of Rs.23.55 lakhs against the

petitioner and if decides to persist in the claim, to communicate the

same, with reasons, to the petitioner before the said date; else the BG

furnished by the petitioner for the said amount be released /

discharged by the said date.

B. If the NHAI persists in its claim, the petitioner shall be entitled

to contest the same by instituting a suit / arbitration, as may be

applicable and if the said suit is instituted by the petitioner on or

before 4th December, 2015, the same shall be entertained on its merits

without going into the aspect of limitation.

C. The petitioner shall keep the BG, as was being kept alive during

the pendency of this petition, till 31st January, 2016.

D. The question, whether the petitioner is entitled to stay of

encashment of BG beyond 15th January, 2016 shall be decided in the

fora invoked by the petitioner.

E. If there is no stay after 15th January, 2016 against encashment

of BG, NHAI shall be entitled to invoke the same and realize monies

thereunder subject of course to decision in the proceedings aforesaid.

13. Needless to state that it having been held that this Court is not the

appropriate Court to adjudicate the lis, none of the observations contained in

this order would influence the decision in the proceedings aforesaid.

No costs.

RAJIV SAHAI ENDLAW, J.

SEPTEMBER 8, 2015 „bs‟

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter