Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sunagro Seeds Pvt. Ltd vs National Seeds Corporation Ltd.
2015 Latest Caselaw 3639 Del

Citation : 2015 Latest Caselaw 3639 Del
Judgement Date : 6 May, 2015

Delhi High Court
Sunagro Seeds Pvt. Ltd vs National Seeds Corporation Ltd. on 6 May, 2015
Author: V. Kameswar Rao
*      IN THE HIGH COURT OF DELHI AT NEW DELHI
                                            Date of decision: May 06, 2015
+      O.M.P. 291/2015 & IA 9556/2015

       SUNAGRO SEEDS PVT. LTD
                                                       ..... Petitioner
                          Through:       Mr.Ratnakar Maltiyar, Adv.

                          versus

       NATIONAL SEEDS CORPORATION LTD.
                                                       ..... Respondent
                          Through:       Mr. Counsel
                                         (Appearance not given)

     CORAM:
      HON'BLE MR. JUSTICE V. KAMESWAR RAO
                   ORDER
      %            06.05.2015
IA 9556/2015

Exemption allowed, subject to all just exceptions.

Application stands disposed of.

O.M.P. 291/2015

1. The challenge in this petition is to the award dated February

16, 2015 passed by the Ld. Sole Arbitrator on issue no. 12 whereby

the Ld. Arbitrator has allowed the counter claim of the respondent

granting the respondent against the petitioner an amount of

Rs.1,38,58, 650/-. The counter claim of the respondent was in the

nature of damages sought against the petitioner for non- lifting of

onion seeds.

2. The undisputed facts are that a total quantity of 1075 quintals

of onion seeds were booked/indented by the petitioner. The details

of the booked/indented seeds are as under;

             S. No.        Date          Qty. in qtls.




                            Total            1075



3. It is an undisputed fact that the onion seeds booked between

the period May 9, 2011 to September 8, 2011 were to be governed

as per the terms and conditions provided in the Seed Dealership

Agreement dated July 23, 2007. Two relevant clauses in this

agreement are clause 20 and 21. The same are reproduced as under;

20. If the Dealer fails to either lift the quantity allotted within 15 days of NSC's intimation or to suggest a schedule of supply as envisaged in clause 18. NSC may in its discretion cancel the allotment and dispose off the relevant quantity of seed in any other manner and treat such lapses on the part of the Dealer as shortfall in lifting the committed quantities, for which the Dealer is liable to pay to NSC liquidated damage as per clause

21.

21. The Dealer would be free to restrict the ultimate purchase of seed to the extend of only 60 per cent of the quantity originally indented or the full quantity allotted by NSC whichever is less. If the Dealer fails to lift/accept the quantity allotted by NSC or 60

per cent of the original indent whichever is less the Dealer shall pay to NSC liquidated damage at the rate prescribed in the Schedule.

4. It may be noted here, as per clause 3.3 at page 138 of the

documents, the liquidated damages payable by the dealer to NSC is

3% of the cost of the seed not accepted lifted at the general sale

price applicable at the time of supply.

5. Out of the total 1075 quintals booked/indented onion seeds

only 394 quintals of onion seeds were lifted by the petitioner. In

other words, 681 quintals of seeds remained un-lifted. The

petitioner never communicated to the respondent that it will be

lifting only 60% of the booked/indented seeds an option which was

available to it as per clause 21 of the Sale Dealership Agreement

dated July 23, 2007.

6. The Learned Arbitrator in para 15.13.2 had posed for his

determination the following points;

i) Whether terms and conditions applicable on the booking/indenting of the Onion seed leading to non-lifting a portion thereof will be covered by the Seed Dealership Agreement of 23.07.2007 or subsequent agreement executed on 14.2.2012 (retrospectively w.e.f. 01.10.2012.

ii} Date on which breach of agreement occurred.

iii} Interpretation of Clause 20 and 21 of the Agreement dated 3.07.2007 and Clause 3.3. of the schedule attached to the agreement.

iv) Quantity of the seed which remained un-lifted for which Claimant is liable to pay liquidated damages.

v) Quantum of liquidated damages.

vi) Date on which Claimant has communicated its inability to lift the booked stock.

vii) Whether the Claimant has restricted the ultimate purchase to 60% of the quantity originally indented, if yes when and how?

7. The Learned Arbitrator has found that on July 8, 2011,

respondent has informed the petitioner that out of 475 quintals of

onion seeds booked/indented in May 2011 only 194 quintals have

been lifted. He also noted that respondent's letter dated July 8,

2011 refer to schedule of lifting agreed by the petitioner for the

balance un-lifted quantity in July, 2011. The petitioner agreed to

lift the balance quantity every week vide its letter dated July 21,

2011. The Arbitrator noted, as per clause 20 of the Seed Dealership

Agreement, dealer was required to lift the quantity allotted within

15 days of NSCs intimation. The petitioner failed to adhere to the

timelines which resulted in the breach of agreement.

8. Learned Arbitrator also noted that the petitioner failed to lift

the seeds as per the agreed schedule vide respondent's letter dated

July 8, 2011 and the petitioner's letter dated July 21, 2011. The

respondent's letter dated July 25, 2011 reminds the petitioner to

fulfil its obligation to lift the balanced onion seeds.

9. The Learned Arbitrator also noted that another lot of 600

quintals was booked/indented on August, 30, 2011 and September

8, 2011. A schedule of lifting of these 600 quintals seeds was from

October 8, 2011 to November 20, 2011 proposed by the petitioner

vide its letter dated September 8, 2011. However, seeds were not

lifted by the petitioner as per its own commitment as noted by the

Learned Arbitrator from the respondent's letter dated January 3,

2012. The Learned Arbitrator was of the view that there was again

a breach of agreement/contract. He noted that the petitioner had

only on January 17, 2012 communicated to the respondent its

inability to lift the un-lifted booked/indented onion seeds due to bad

market condition. He noted that the petitioner again vide its letter

dated April 27, 2012 retracted from its earlier stated position of

January 17, 2012 of its inability to lift the balance quantity of un-

lifted onion seeds and commenced fresh negotiations vide its letter

dated April 27, 2012 for reducing the dealer price to Rs.150/- per kg

from original price of RS.300/-.

10. Even, thereafter, the respondent had called upon the

petitioner vide its communications dated April 19, 2012, April 25,

2012, May 4, 2012 and May 9, 2012 to lift the balance quantity of

booked/indented quantity failing which the petitioner would be

responsible for the loss suffered by it. The petitioner again in

response to all these communications, vide its letter dated May 11,

2012 offered to lift 250 quintals of onion seeds. This offer was

accepted by the respondent. Further, the petitioner vide its letter

dated June 29, 2012 offered to lift 400 quintals. The respondent

responded to this offer by stating that the petitioner has failed to

meet its commitment to lift the booked/indented seeds in spite of the

repeated reminders and as such, now they had decided to invite

tenders to liquidate the unsold stocks indented/booked by the

petitioner. The Learned Arbitrator was of the following view;

(a) That Claimant has repeatedly failed to meet its

commitment to lift the booked/indented onion seed as required

under Clause 20 of the Seed Dealership Agreement.

(b) That the loss suffered by the Respondent is attributable to

the continuous unfulfilled promises and commitments made by

the Claimant from June/July 2011 onwards and extended till

as late as April/May, 2012. The facts on record clearly

establish that the Claimant has indulged in unfair trade

practice of keeping the Respondents on tenter-hook by

continuously renewing the schedule and not fulfilling

commitments repeatedly made. The Respondent has made all

efforts to accommodate the Claimant but misleading behavior

of the Claimant led to Joss suffered by the Respondent.

(c) That the Tribunal is of the opinion that claimant has failed

to exercise option of restricting the ultimate purchase of onion

seed to the extent of only 60% of the quantity originally

indented and as such not entitled to the benefit of clause 21 of

the Agreement dated 23.7.2007 and or Clause 3.3 of the

Schedule thereof. Tribunal is of the opinion that overt and

covert actions of the Claimant give no notice to the

Respondent about his intention of restricting lifting of

indented/booked seeds. In other words· restriction of

indented/booked seed quantity cannot be inferred from

misleading actions and unfair trade practices of the Claimant

and as such it is not legally tenable to allow the benefits of

clause 21 of the Agreement read with Clause3.3. of the

Schedule to the Claimant.

(d) That the liability of the Claimant will be to pay liquidated

damages on entire un-lifted 681 qtls. of seed.

11. In view of above, the liability of the Claimant was determined

by the learned Arbitrator as under:

A.      Total quantity of onion 1075 qtls. (A)
        seed booked/indented
B.      Quantity of Onion seed 394 qtls. (B)
        lifted
C.      Quantity un-lifted (A-B) 681 qtls. (C)

D.      Cost of the seed not lifted Rs.2,04,30,000.00
        68100 Kgs. @ Rs.300/-
        per Kg.                     (D)

E.      Discount of 15.5%          Rs.31,66,650.00

F.      Amount payable by M/s. Rs.1, 72,63,350.00
        Sun Agro Seeds Pvt. Ltd.
G.      Dues recovered from      Rs.34,05,000.00
        sales of Onion @ Rs.50/-
        per kg
H.      Balance payable (G-H)    Rs.1,38,58,650.00



12. The only submission made by Learned Counsel for the

petitioner is that even if the petitioner has failed to lift the onion

seeds, still the liability in terms of clause 20 and 21 read with clause

3.3 of the schedule, as reproduced above, cannot be over and above

Rs.1,65,600/-. He states, the liability having been prescribed in the

contract, Learned Arbitrator having gone beyond the contract and

determine the liability on a principles underlying in Section 73 of

the Contract Act is totally untenable. He relied upon the judgments

of this Court reported as 2012 (2) RAJ 390 Delhi Vishal Engineers

& Builders Vs. Indian Oil Corporation Ltd; 2007 (5) RAJ 608

(Delhi) to contend that the arbitrator being the creature of a contract

could not have gone beyond the contract. He also stated that the

respondent was required to prove the loss suffered by it in

consequence of breach of contract committed by the petitioner.

13. Having considered the submissions made by Learned Counsel

for the petitioner, suffice to state, meaningfully read the conclusion

of the Learned Arbitrator, was that the petitioner having not

expressed its intention to lift only 60% of the quantity at the outset

and even after prescribing the schedule, failed to lift the onion seeds

which resulted in a loss to the respondent, need to be compensated

by the petitioner. Insofar as the submission that in view of the

position of the contract in terms of clause 20 and 21, the liability

could not have exceeded beyond Rs.1,65,600/- is concerned, suffice

to state, the clause 20 and 21 would come into play only when the

dealer fails to lift the quantity allotted within 15 days of the

respondent's intimation or fails to suggest the schedule of supply as

envisaged in clause 18 and not where the party that is the petitioner

had repeatedly failed to meet its commitment/schedule to lift the

booked/indented onion seeds. In fact, it was concluded by the

Learned Arbitrator that the petitioner had continuously unfulfilled

promises and commitments made by it from June/July 2011

onwards till April/May, 2012. He was of the opinion that the

petitioner was not entitled to the benefit of clause 21 or clause 3.3 of

the schedule thereof. He worked out the liability in the manner

already reflected above. The view taken by the Learned Arbitrator

is a plausible view. Insofar as the judgments relied upon by

Learned counsel for the petitioner are concerned, the proposition of

law laid down in those judgments are well settled. However, the

same are not applicable on the facts of the case. I do not see any

merit in the petition.

14. The petition is accordingly dismissed.

V. KAMESWAR RAO, J MAY 06, 2015/ak

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter