Citation : 2015 Latest Caselaw 4657 Del
Judgement Date : 3 July, 2015
$~15
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 03.07.2015
+ FAO (OS) 321/2015 & CM No.11285/2015 (stay)
M/S NATIONAL HIGHWAYS AUHTORITY OF INDIA .... Appellants
versus
M/S. KNR-PATEL (JV) ..... Respondent
Advocates who appeared in this case:
For the Appellants : Mr Trans Juris with Mr Rajiv Kapoor
and Mr Rahul Ranjan, Advocates.
For the Respondents : Mr Amit George, Advocate.
CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
HON'BLE MR JUSTICE SANJEEV SACHDEVA
JUDGMENT
BADAR DURREZ AHMED, J (ORAL)
CAV. 629/2015
The learned counsel for the respondent/Caveator is present
The caveat stands discharged.
CM No.11286/2015 (exemption) Exemption is allowed subject to all just exceptions.
FAO (OS) 321/2015 & CM No.11285/2015 (stay)
1. This appeal is directed against the judgment dated 27.04.2015
delivered by a learned Single Judge of this Court in OMP 51/2014 which
was a petition under Section 34 of the Arbitration & Conciliation Act,
1996 (hereinafter referred to as the 'the said Act') whereby the majority
award passed by the arbitral tribunal was challenged. We may point out
that the dissent was only in respect of claim Nos.5 & 6 and in respect of
rest of the claims, the award was unanimous.
2. The details of the contract between the NHAI and the respondent
are set out in the impugned judgment which we are reproducing herein
below:-
"2. The contract entered into between the NHAI and the Respondent, M/s. KNR-
Patel (JV) was regarding the rehabilitation and upgradation of existing 2 lane road to 4/6 lane divided carriageway configuration of NH-5 in the State of Andhra Pradesh from km 178 to km. 220 (Nellore to Kavali). The contract being a unit rate contract, the bidding documents contained a detailed document „Bill of Quantities („BOQ‟). The parties adopted the terms and conditions of contract as contained in the General Conditions of Contract („GCC‟) and Special Conditions of Contract modifying / amending the GCC clauses. The date of commencement for the work was 17th May 2001 and the intended date of completion for the first
milestone from km 189.5 to km. 198 was 22 months from the date of commencement; for second milestone from km. 178.2 to km. 189.5 was 27 months; and the third milestone from km 198 to km 222 was 33 months from the start date. The overall intended date for completion of the project was 16th February 2004. The work was finally concluded on 31st May 2005, i.e., after a delay of about 15.5 months. The extension of time was granted for the said period without imposition of any liquidated damages on the Respondent. On the completion of the work, the Engineer issued the taking over certificate on 31st May 2005 and the defect liability period ended on 31st May 2006."
3. It is evident on going through the impugned judgment and upon
hearing counsel for the parties that disputes had arisen and were referred
to the arbitral tribunal. These claims had been preferred by the
respondents. The argument raised before us by the learned counsel for
the appellant is that this was a case of no evidence. One of the main
points urged by him was that the idling with regard to machinery was
considered by the arbitral tribunal for a period which extended beyond
the original period. He submitted that there was no evidence provided on
record in respect of the extended period.
4. We have examined the impugned judgment as also the award and
find that there is ample evidence on this aspect of the matter. It is not so
much a case of no evidence but, as subsequently admitted by the learned
counsel for the appellant, a case of mis-appreciation of evidence. We
note that the learned single Judge, in paragraph 7, has rightly commented
that the learned counsel for NHAI invited the Court to re-appreciate the
evidence which has already been examined by the arbitral tribunal. The
learned Single Judge was right in observing that the Court is unable to
undertake such an exercise given the limited scope of the issue under
Section 34 of the said Act. Appreciation of evidence is within the
domain of the arbitral tribunal and the Court in exercise of its power
under Section 34 of the Act cannot embark upon re-appreciation of
evidence. It is, of course, a different matter if there was no evidence at all
or if the finding was so outlandish and could not at all be supported by
the evidence on record. This is not the case here. We also note that the
learned Single Judge had placed reliance on an earlier decision involving
the National Highway Authority of India itself in the case of National
Highways Authority of India v. Oriental Structural Engineers Pvt. Ltd.
- Gammon India Limited: (2013) 2 Arb LR 264 (Del) (DB) which,
according to the learned Single Judge, in similar circumstances had
declined to interfere with the award of the arbitral tribunal.
5. The other claims also and, particularly, the claim No.5 with regard
to the refund of excise duty paid by the respondent has also been
examined in detail by the learned Single Judge. That aspect of the matter
was also covered by an earlier decision of the learned Single Judge in
National Highways Authority of India v. ITD Cementation India
Limited: 197 (2013) DLT 650. A Division Bench upheld the same by its
order dated 06.03.2013 in FAO(OS) 137/2013. Therefore, the
conclusions on claim No.5 also do not warrant any interference. In other
respects also, no interference is called for inasmuch as we do not find any
perversity in the award. The learned Single Judge has correctly
appreciated the law and has applied the same to the facts of the case.
6. The appeal is dismissed. There shall be no order as to costs.
BADAR DURREZ AHMED, J
SANJEEV SACHDEVA, J JULY 03, 2015 st
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!