Citation : 2014 Latest Caselaw 4994 Del
Judgement Date : 1 October, 2014
$~41
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.A. 25/2014
Judgment reserved on: 17.09.2014
% Judgment pronounced on: 01.10.2014
ARAVALI POWER COMPANY PVT LTD ..... Appellant
Through: Mr.Vikas Singh, Senior
Advocate with Mr. Bharat,
Ms. Deepika Kalia and
Ms. Anasuya Choudhary,
Advocates.
versus
M/S SUBHASH INFRA ENGINEERS LTD. .... Respondent
Through: Mr. Sandeep Sharma and
Mr.Vatsal Kumar, Advocates
CORAM:
HON'BLE MS. JUSTICE DEEPA SHARMA
JUDGMENT
1. The present petition has been filed against the orders dated
10.07.2014 and 08.08.2014 of learned arbitrator. It is submitted that
these orders are the interim order relating to the interim measures and
therefore, appeal is maintainable. It is further submitted that the order
of release of bank guarantee has been passed on the application of the
respondent dated 21.04.2014. It is further submitted that order dated
10.07.2014 regarding release of final bill payment, is bad in law as
there was no such request before the learned arbitrator in the
application dated 21.04.2014 filed by the respondent and therefore,
the said order is bad in law. It is further submitted that the order of
release of bank guarantee could not have been passed in violation of
Clause 9.7 of General Conditions of Contract (in short 'GCC') as it
was refundable on the expiry of defect liability period or on payment
of the amount of final bill in accordance with Clause 52, whichever is
later. Clause 52 of GCC clearly contemplates that the final bill
cannot be paid until the respondent records his unconditional
acceptance of the measurements and submits the final bill. It is
further submitted that although the period of defect liability had
expired on 14.01.2014, the respondent had not yet submitted the final
bill. It is submitted that the learned arbitrator has further erred in
holding that final bill had been submitted by the claimant/respondent
and that the same was processed by the appellant as 22nd RA bill (by
cutting the word final bill) especially when, admittedly, the 23rd and
24th RA bills were submitted thereafter by the respondent. It is further
submitted that the orders dated 10.07.2014 and 08.08.2014 be set
aside.
2. The application is contested by the respondent. They have filed
their written submissions although no reply has been filed. It is
argued on behalf of the respondent that the orders under challenge are
in the form of interim award and the same cannot be challenged under
Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter
referred to as 'the Act') by way of an appeal.
3. I have given careful consideration to the arguments of both the
parties.
4. The brief facts necessary for disposal of present appeal are
recorded hereinafter.
5. The appellant had entered into an agreement with the
respondent for Ash Dyke Package For Indira Gandhi Super Thermal
Power Project (IGSTPP), Jhajjar for a value of Rs.29,48,63,000/-.
Pursuant to Clause 8 of the Letter of Award (LOA), the respondent
was to submit the bank guarantee in the nature of security deposit for
execution of the contractual work. As per Clause 9.6 of GCC, 50 %
of the security deposit was to be released on the completion of the
said work. As per Clause 9.7 of GCC, the remaining amount of
security deposit was to be released on the expiry of the defect liability
period or on the payment of the amount of the final bill payable in
accordance with Clause 52 of GCC whichever is later. On completion
of work, the appellant had released 50 % of the security deposit in
terms of Clause 9.6 of GCC. Meanwhile, the dispute had arisen
between the parties and the claim petition was filed by the respondent.
During the pendency of the arbitral proceedings the period of defect
liability had expired and thereafter the respondent/claimant had
moved an application dated 21.04.2014 for release of the bank
guarantee on the ground that defect liability period had expired on
14.01.2014. Further issue was raised that in order to avoid the release
of the bank guarantee the appellant had issued, as an afterthought, a
letter dated 04.03.2014 wherein the appellant had alleged that the final
bill was ready since 16.10.2013. The respondent/claimant in this
application has also mentioned that though the final bill prepared by
the respondent/present appellant was without including other
payments but the present appellant had admitted entitlement for
payment. On these facts it was prayed that the bank guarantee be
released.
6. This application was taken up by the learned arbitrator on
10.07.2014 and following directions were issued:
"In view of the above and final bill being in positive and no claims raised by the respondent up to the expiry of the defect liability period, I decide to make immediate interim relief to the claimant through this order that the respondent to release the final bill payment as accepted by them as well as release of the bank guarantee before the next date of hearing.
The other claim of claimant as well as counter claim will be decided on its merits in final award after hearing the parties."
7. Subsequently, the appellant moved an application before the
learned arbitrator to keep the operation of the interim order for release
of bank guarantee pending till the end of September, 2014 and
accordingly, the learned arbitrator vide its order dated 08.08.2014
gave the respondent time to release the bank guarantee by 15.09.2014.
8. The sole contention of the respondent/claimant is that order
dated 10.07.2014 is in the form of interim award as by granting an
amount of Rs.401000/- towards final bill amount, the learned
arbitrator has given a finding on Claim 10 of the respondent/claimant.
It is further submitted that by the release of the bank guarantee the
arbitrator has granted the part of the relief of claim 6 of the
respondent/claimant. This argument is controverted by the appellant
stating therein that the order itself shows that "this order dispose of
the application dated 21.04.2014 and therefore this order cannot be
termed as an interim award but is an interim relief given to the
respondent." Learned counsel for the respondent/claimant has
submitted that observation of the learned arbitrator to the effect that
"the other claim of claimant as well as counter claim will be decided
on its merit in final award after hearing the parties", clearly shows
that this order is in the form of interim award.
9. The first controversy therefore is whether the orders dated
10.07.2014 and 08.08.2014 are in the form of an Award? Award has
not been defined anywhere in the Arbitration and Conciliation Act
except that the award includes the interim award. There is no dispute
to the settled law that an order of the arbitrator can be termed as an
award only when it determines the rights of the parties finally, on the
claims whether by way of interim award or by way of final award.
The question to be seen therefore is whether vide these orders the
learned arbitrator has finally determined the rights of the parties.
Contention of the respondent/claimant is that the findings of the
learned arbitrator to direct the respondent to pay an amount of
Rs.401000/- towards the final bill amount to a finding on Claim 10 of
the respondent. Two reliefs have been given to respondent/claimant
by the learned arbitrator vide his order dated 10.07.2014. First is
release of the final bill payment as accepted by them and other is
release of the bank guarantee.
10. As regards release of final bill payment is concerned, the
respondent/claimant had raised a demand of payment of final bill in
the form of Claim 10.
11. Claim 10 of the respondent/claimant is as follows:
CLAIM NO.10 - FINAL BILL The final bill amounting to Rs.410000/- which is admitted payment has not been released and is therefore required to be released with interest @ 18% per annum.
12. The appellant in his reply to this claim had taken the plea that
the claim was not tenable as the claimant had not submitted the final
bill and the final bill could not be paid till the claimant recorded his
unconditional acceptance of the measurement and submit the final
bill.
13. In the rejoinder, the respondent/claimant qua their Claim 10 had
alleged that there was no dispute in the measurement and that it was
on the accepted measurement that an amount of Rs.4,10,000/- is
payable by the claimant. It is further stated in the rejoinder that the
claimant had informed the appellant vide letter dated 20.12.2012 of
the completion of the work and had requested them to prepare the
final bill and release the payment. It is further submitted that the
letter dated 04.03.2014 had been issued with ill motive by the
appellant and that the claimant were entitled for this sum.
14. From this factual position it is clear that the release of the
money towards final bill was one of the claim and vide this order
dated 10.07.2014 the arbitrator has determined the said claim of the
respondent/claimant. The observation of the learned arbitrator to the
effect that the other claims of the claimant as well as counter claim
would be decided on this merit in final award further confirms that
this part of the order dated 10.07.2014 is by way of an interim award.
Hence, cannot be challenged by way of an appeal.
15. Vide this order dated 10.07.2014, the arbitrator has also ordered
release of the bank guarantee while disposing of an application of the
claimant dated 21.04.2014 for that relief. No claim has been made by
the respondent/claimant in his claim petition before the learned
arbitrator for release of the bank guarantee. The only claim qua bank
guarantee, which had been put up as claim 6 relates to claiming of
charges incurred on account of extension of bank guarantee.
16. In the rejoinder, however, the respondent/claimant has also
stated that the bank guarantee has been illegally withheld and
requested for issuance of necessary directions for release of bank
guarantee. Along with this rejoinder, the claimant had also moved a
separate application dated 21.04.2014 for release of the said bank
guarantee.
17. From the perusal of order dated 10.07.2014 it is apparent that
although the claimant had contended that withholding of a bank
guarantee is illegal, no finding had been given by the learned
arbitrator. The learned arbitrator has simply ordered for the release of
the bank guarantee. The entitlement of the claimant for charges on
account of the extension of the bank guarantee is also left to be
determined in the final award. No finding on Claim 6 of the claimant
has been given in this order. The order for release of the bank
guarantee is in the form of an interim order passed as an interim
measure on an application of the claimant, without determining the
claim and contentions of the parties. It is apparent that while moving
an application dated 21.04.2014, the claimant has not mentioned any
provision under which the said application had been moved. The title
of the application is simply for release of the bank guarantee on the
ground that defect liability period has expired. This part of the order
of the learned arbitrator therefore is not in the form of an award but is
an order in the form of interim measure. Both the directions of
learned arbitrator are separable as they are not interconnected. Hence,
challenging the findings relating to release of bank guarantee is
appealable under Section 37 (2) (b) of the Act.
18. It is argued on behalf of the appellant that the order for release
of bank guarantee is violative of Clause 9.7 read with Clause 52 of
GCC.
19. It is argued on behalf of the respondent/claimant that the order
of the learned arbitrator does not suffer with any infirmity as the same
has been passed in terms of the said clauses.
20. Clause 9.7 of GCC deals with the release of the bank guarantee.
The clause is reproduced as under:
"9.7 On expiry of the Defects Liability Period (referred to in Condition 33 hereof) or on payment of the amount of the Final bill in accordance with condition 52 whichever is later, the Engineer-in-Charge shall on demand from the Contractor, refund to him the remaining portion of the security deposit provided the Engineer-in-Charge is
satisfied that there is no demand outstanding against the contractor."
21. From the perusal of the relevant clause it is apparent that this
clause is in three parts i.e. (a) on expiry of defect liability period, (b)
on payment of amount of final bill in accordance with condition 52,
(c) whichever is later. The said clause also contains a 'proviso' which
clearly provided that "the engineer-in-charge is satisfied that there is
no demand outstanding against the contractor".
22. Learned arbitrator has defaulted in releasing the bank guarantee
on the ground that the defect liability period had expired and a final
bill had been issued by the engineer-in-charge and no claim raised till
expiry of period of defect liability. However, it is clear that there is
no certificate of the engineer-in-charge to the effect that there is no
demand outstanding against the contractor. It is not disputed that the
appellant has also filed a counter claim before the learned arbitrator,
which requires determination by the learned arbitrator during arbitral
proceedings. It, therefore, is clear that all the conditions of Clause 9.7
of GCC are not satisfied. From the order it is clear that bank
guarantee has been ordered to be released by the learned arbitrator
only on the submission of the claimant that there has been no demand
regarding any claim/amount due, without discussing the counter claim
of the appellant and also without giving any finding on this issue.
23. In view of this orders of the learned arbitrator dated 10.07.2014
and 08.08.2014 relating to release of the bank guarantee are hereby
set aside.
24. The relief for setting aside the order for payment of amount of
Rs.4,01,000/- towards payment of final bill cannot be granted in view
of the above discussion as the said part of the order is not appealable.
DEEPA SHARMA, J.
01st OCTOBER, 2014
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!