Citation : 2014 Latest Caselaw 5657 Del
Judgement Date : 11 November, 2014
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ C.M.(M) Nos. 903/2004 & 904/2004
% 11th November, 2014
1. C.M.(M) No.903/2004
SH. MADAN LAL RADHU & ANR. ..... Petitioners
Through: Mr. Manoj Sharma, Advocate with
Ms. Lakshmi Gurung, Advocate.
versus
M/S. ATMA RAM PROPERTIES (P) LTD. ..... Respondent
Through: Mr. Amit Sethi, Advocate with Mr. Ishan Khanna, Advocate.
2. C.M.(M) No.904/2004
SH. MADAN LAL RADHU & ANR. ..... Petitioners
Through: Mr. Manoj Sharma, Advocate with
Ms. Lakshmi Gurung, Advocate.
versus
M/S. ATMA RAM PROPERTIES (P) LTD. ..... Respondent
Through: Mr. Amit Sethi, Advocate with Mr.
Ishan Khanna, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
To be referred to the Reporter or not? Yes
VALMIKI J. MEHTA, J (ORAL)
1. These two petitions are disposed of by this common judgment
inasmuch as the judgment of the first appellate court which is challenged in
both these petitions is a common judgment dated 11.5.2004. By the
judgment dated 11.5.2004, the first appellate court of the Additional Rent
Control Tribunal dismissed two appeals filed by the present
petitioners/tenants.
2(i) The first appeal which was filed was against the order dated
30.9.2002, a consequential order under Section 14(11) of the Delhi Rent
Control Act, 1958 (hereinafter referred to as 'the Act') directing eviction of
the petitioners for non-compliance of the directions passed in the main
judgment dated 7.2.2002 by which a decree was passed in favour of the
respondent/landlord under Section 14(1)(k) of the Act. As per Section
14(1)(k) of the Act, in case a tenant is found to be misusing the tenanted
premises against terms contained in the lease deed of L&DO/local authority
or using the tenanted premises against the user prescribed in the master
plan/zonal plan etc, then, such a tenant must stop the misuse and also pay the
penalty/misuser charges which are claimed by L&DO, failing which the
tenant is evicted pursuant to a consequential order passed under Section
14(11) of the Act.
(ii) The second appeal which was dismissed by the Additional Rent
Control Tribunal by the impugned judgment was an appeal filed against
dismissal of an application under Order IX Rule 13 of the Code of Civil
Procedure, 1908 (CPC) filed by the petitioners for setting aside the ex parte
judgment dated 7.2.2002 passing a decree under Section 14(1)(k) of the Act.
3. Let me at this stage, reproduce some relevant portions of the
main judgment dated 7.2.2002 which records that the petitioners were
proceeded ex parte not once but twice as they failed to appear in the
proceedings and thereafter respondent/landlord led evidence and proved its
case under Section 14(1)(k) of the Act and consequentially the petition under
Section 14(1)(k) of the Act was decreed. The relevant paras of the judgment
dated 7.2.2002 read as under:-
"8. In evidence petitioner examined Sh. Chattar Singh U.D.C.
L&DO as AW1 who proved letters dated 16.6.93 & 11.11.93 as Ex.AW1/1 and AW1/2. Sh. Arjun Singh overseer L&DO as AW3 deposed about having inspecting the suit premises on 31.8.86 and 5.2.93 and that demand was raised upon the lessee on the basis of breaches found during inspection. Sh. B.L. Nirman has appeared as AW4 as well as AW8 to prove perpetual lease deed as Ex.AW8/1 besides the letters Ex.AW1/1 & Ex.AW1/2. Sh. Mohan Singh Rawat as AW5 proved certificate of incorporation of present petitioner as Ex.AW5/1, Resolution dated 30.7.94 passed in the meeting of Boards of Directors of petitioner as Ex.AW5/2, site plan as Ex.AW5/3, and sale deed dated 31.3.94 as Ex.AW5/4. Sh. Vinod Mishra has partly been examined in chief as AW6. His testimony however cannot be read as it is in-complete. Sh. S.K. Jain, attorney of original petitioner
has appeared as AW2 as well as AW7. He generally deposed about the case and proved his power of attorney as Ex.AW7/1, copy of legal notice as Ex.AW7/2, A.D. Cards Ex.AW7/3 and Ex.AW7/4. Petitioners closed their evidence on 29.5.2000.
9. Respondents on their part produced Sh. Kamal Radhu as RW1 but the witness did not turn up for cross examination after 10.4.2001. Respondents were proceeded exparte on 17.9.2001. They filed an application U/O 9 Rule 7 CPC which was allowed on 17.10.2001. Respondents however did not turn up again nor paid subjective costs thereafter.
10.(a). xxxx xxxx xxxx xxxx (b). GROUND U/S 14(1)(k) OF D.R.C. ACT
No suggestion has been put to the witness to discredit that un- authorised shed on second floor in the back portion measuring 14ft.x10'9"exists in the suit premises. So far as un-authorised shed of 5ft.x5ft. is concerned notice Ex.AW1/1 itself specify that same was found removed hence there was no cause of action in respect of the small shed. True that un-authorised shed was already there when premises had been let out to respondents No.1 and 2 but provisions of Section 14(1)(k) of D.R.C. Act having been enacted to protect the covenents entered into by Government to maintain the sanctity of Master/Zonal Plans, the existence thereof is clearly in breach of Clause 2(5) of the perpetual lease deed Ex.AW8/1.
xxxx xxxx xxxx xxxx
12. In the said case the court was dealing with a matter wherein property demised for residential user in perpetual lease had been let out for commercial purposes by the landlord. The logical inference in the present context can legitimately be drawn that when tenant knew or had the opportunity of knowing that his tenancy premises are subject to the terms and conditions of perpetual lease deed Ex.AW8/1, the plea that he did not raise the un-authorised shed in the back portion on second floor of the property is inoccuaus. Once, it is shown that same has not been erected with specific permission of the paramount lessor." (underlining added)
4. Once the petitioners do not appear in the main petition under
Section 14(1)(k) of the Act and the respondent/landlord led evidence and
proved its case, and all aspects have been discussed in detail by the
Additional Rent Controller while passing the judgment dated 7.2.2002 as
reproduced above, then, in my opinion, no successful challenge can be laid
on merits by the petitioners to the judgment dated 7.2.2002. Obviously,
petitioners having led no evidence and the respondent/landlord having
proved its case by leading evidence, there cannot be any valid challenge on
merits either as a first appeal which was filed before the Additional Rent
Control Tribunal or as a second appeal in the form of a petition under Article
227 of the Constitution of India to the judgment dated 7.2.2002. Therefore,
so far as the petition being C.M.(M) No.904/2004 is concerned seeking
setting aside of the judgment dated 7.2.2002 on merits, there is no merit in
the same, much less for extraordinary jurisdiction under Article 227 of the
Constitution of India to be exercised.
5. That takes us to the second petition and through which two
aspects are pleaded. The first is that petitioners' application under Order IX
Rule 13 CPC should have been allowed and the second is that even if the
impugned judgment dated 7.2.2002 read with the consequential orders under
Section 14(11) dated 27.8.2002 and 30.9.2002 are sustained, since the
petitioners are ready to now pay the misuser charges, petitioners should be
allowed to pay the same and eviction should not be ordered.
6(i) The prayer for setting aside the judgment and decree dated
7.2.2002 on the basis of the application under Order IX Rule 13 CPC which
was filed on 10.2.2003 is without any merit for the reason that in an
application under Order IX Rule 13 CPC either the ex parte decree is prayed
for being set aside on the ground that there is no service of the present
petitioners in the eviction petition under Section 14(1)(k) of the Act or the
case set up is that the petitioners had sufficient cause for non-appearance.
(ii) The first aspect does not apply because petitioners were
admittedly served.
(iii) So far as the second aspect is concerned, petitioners having
been served and appeared through Advocate and were proceeded ex parte
not once but twice, petitioners cannot lay the blame of the fault on their
Advocate for simply claiming that they were not aware of the ex parte
judgment dated 7.2.2002 and hence have sufficient cause for non-
appearance. It is not believable that petitioners after instructing the
Advocate were never informed by the Advocate, and in any case if they
were not informed, yet the petitioners were duty bound to take steps for due
presentation of their defence by remaining in touch with their Advocate, and
in the facts of the present case there is no doubt that petitioners are guilty of
deliberately not pursuing of their defence in the eviction petition filed under
Section 14(1)(k) of the Act because after all petitioners were proceeded ex
parte not once but twice. There is therefore no reason, in my opinion, to
allow the application under Order IX Rule 13 CPC filed on 10.2.2003. Both
the courts below therefore have rightly dismissed the application under
Order IX Rule 13 CPC.
7. That takes us to the issue as to whether since the petitioners are
today ready and willing to deposit the amount of misuser charges and such
an offer also having been made before the first appellate court, whether the
petitioners should not be evicted from the suit premises being Flat No.106,
Plot No.1, H-Block, Connaught Circus, New Delhi and instead they should
be directed to pay the misuser charges. In this regard, it would be relevant to
refer to para 6 of the judgment of the Supreme Court in the case of Curewell
(India) Ltd. Vs. Sahib Singh (dead) by LRs. and Ors. 1993 Supp (1) SCC
507 which reads as under:-
"6. Sub-section (11) of Section 14 reads:
14.(11). No order for the recovery of possession of any premises shall be made on the ground specified in Clause (k) of the proviso to sub-section (1), if the tenant, within such time as may be specified in
this behalf by the Controller, complies with the condition imposed on the landlord by any of the authorities referred to in that clause or pays to the authority such amount by way of compensation as the Controller may direct."
This sub-section prevents eviction if the tenant has complied with the condition imposed on the landlord by the government. The sub- section also requires the person in possession, namely, the sub-lessee to pay to the authority such amount by way of compensation as the Controller may direct. It is not in dispute that the original lessee, upon receipt of notice from the government, had in turn issued notice to the sub-lessee, namely, the appellant calling upon him to stop misuser or vacate the premises. If the appellant has, as contended by him, stopped misuser, he is of course not liable to be evicted by reason of the protection given to him under sub-section (11). Nevertheless, for the past misuser, the appellant is liable to pay such charges as are payable in terms of the sub-section. The charges under the sub-section are such charges as are determined by the Controller.
The Controller must, therefore, after hearing the parties determine the amount payable by the person responsible for the misuser, namely, the appellant who is the tenant of the original lessee and determine the correct amount." (underlining added) 8(i) The aforesaid paragraph of the judgment of the Supreme Court
in the case of Curewell (India) Ltd. (supra) specifically holds, and which
ratio arises even from the language of the provisions of Sections 14(1)(k)
and 14(11) of the Act, that, it is not enough for a tenant to only stop misuse,
and tenant has to also in fact pay the misuser charges which are claimed by
the L&DO for the past misuse. Putting it in another words, removal of
illegal construction or stopping the misuse, it is not a panacea against
eviction of the tenant because the tenant has to very truthfully and
consciously pay whatever are the misuser charges which are claimed by the
L&DO with respect to the misuse of the tenanted premises against the terms
and conditions of the lease deed executed in favour of the landlord by the
L&DO.
(ii). Admittedly the judgment dated 7.2.2002 is final because
petitioners for no reason failed to appear and the Additional Rent Controller
therefore rightly decreed the petition filed under Section 14(1)(k) of the Act
by its judgment dated 7.2.2002. The petitioners admittedly did not comply
with the specific directions contained in para 15 of the judgment dated
7.2.2002 and the consequential orders dated 27.8.2002 & 30.9.2002 and
which read as under:-
A. "15. In view of the above reasons, petition is dismissed u/s 14(1)(j) while being.... Let notice U/S 14(11) of the D.R.C.Act be sent to L&DO for informing whether they... of damages for breach of the terms of lease deed. The respondents are directed to restore the tenanted premises to its original condition by demolishing the un- authorised construction/shed and by carrying out repairs to the damage caused while so doing within one month. Since the respondents are exparte, let a copy of judgment be sent to them at the address of suit premises through registered post as well as UPC for 18/3/2002.
B. Order dated 27.8.2002 Another adj. prayed on behalf of respondent for submitting objections.
Learned proxy counsel for respondent is not even aware as to whether cost imposed on the last date has been deposited or not. Respondent has already availed sufficient opportunities for this purpose. The request is only a pretext to further delay the disposal of case, given the
previous complacent attitude of respondent in this matter. Request is, therefore, declined.
I have heard the matter U/s 14(11) D.R.C. Act on behalf of petitioner and carefully perused the record. The paramount lessor has categorically refused to regularize the breach in the demised premises. There is nothing to perceive that respondents have dismantled the unauthorized shed measuring 14ft X 10.9" in the back portion of second floor of the demised premises in compliance of order dated 7.2.2002. It has been stressed on behalf of petitioner that said order has not been complied with so far. It can be perceived from the correspondence addressed to previous owner/landlord by the L&DO that the unauthorized shed was in existence prior to letting of the suit premises to respondent in 1988. The knowledge of the terms of paramount lease thus can be imputed to respondent only from the date of service of legal notice Ex.AW7/2. Respondent on this part did not comply with the condition of superior lease and thus incurred liability for existence of unauthorized shed in his tenancy premises as he was duty bound to remove the same on being objected to by the landlord as well as paramount lessor.
3. Despite having been offered adequate opportunities respondent did not file objection to the statement of damage charges submitted on behalf of L&DO. It has to be deemed that he has no reservation against the same. Petitioner has not represented against it either as such liability of respondent for damage charges is calculated from 1.1.94 onwards. Accordingly respondent is directed to deposit a sum of Rs.7,20,000/- including proportionate interest with L&DO directly within one month as regularization charges upto 30.9.2002. Rest of the liability assessed by the paramount lessor shall be borne by the petitioner. Needless to observe here is that in case of failure, passing of eviction order against respondent would become inevitable. Put up on 30.9.2002 for compliance report by the resptd. C. Order dated 30.9.2002 Sh. Singla has filed his affidavit affirming that respondents have not complied with order of deposit of damages, of the last date. Probably for the very same reason respondents have abandoned this matter. There is nothing to perceive otherwise. Consequently, eviction order
in respect of Flat No.H-106, Plot No.1, H-Block, Connaught Circus, New Delhi as morefully shown in site plan Ex.AW5/3 is hereby passed in favour of the petitioner and against the respondents U/S 14(1)(k) of D.R.C. Act. Petitioners are further held entitled to costs of the petition which is conservatively quantified at Rs.2000/-. File be consigned to record room."
9. Learned counsel for the respondent is justified in arguing that
though the Additional Rent Controller need not have directed sending of the
copy of the judgment dated 7.2.2002 to the petitioners because there is no
such provision of law and the petitioners were in fact duty bound after they
had appeared and contested the case necessarily to be aware of the final
judgment and the consequential orders which would be passed. Be that as it
may the judgment dated 7.2.2002 was sent by registered post AD and UPC
by the court of Additional Rent Controller suo moto to the petitioners and
which was duly served upon the petitioners as noted in the endorsement
made in the judicial record of the Additional Rent Controller besides the
order dated 7.2.2002. The endorsement appearing of the office of the
Additional Rent Controller besides the order dated 7.2.2002 records issuing
of the copy of the judgment dated 7.2.2002 to the petitioners and also receipt
of the same by the petitioners by registered AD post. Also there cannot be
any doubt that the judgment dated 7.2.2002 was received by the petitioners
because even in the application filed by the petitioners under Order IX Rule
13 CPC, petitioners have not categorically stated that they have not received
the judgment by the registered AD post and UPC as directed by the
Additional Rent Controller in its judgment dated 7.2.2002. Therefore,
petitioners failed to comply with the timelines specified in the directions
given in para 15 of the judgment dated 7.2.2002 of demolishing the
construction and more importantly of not paying the misuser charges within
a period of one month from 27.8.2002.
(iii) Learned counsel for the respondent rightly points out that
before passing of the operative orders on 7.2.2002 and 30.9.2002 decreeing
the eviction petition by directing eviction of the petitioners, there were five
dates of hearing before the ARC being 25.2.2002, 4.4.2002, 24.4.2002,
21.5.2002 and 8.8.2002 when presence of the counsel for the petitioners is
recorded. Though the counsel for the petitioners tried to argue that their
counsel did not inform the petitioners of the proceedings of the case, but
considering the facts of the present case where regular Kumbhkaran like
sleep of the petitioners is writ large on the face of record, this Court refuses
to believe that counsel who appeared for them after 7.2.2002, and till the
operative order was passed on 27.8.2002, did not inform the petitioners and
which stand is only a make believe story which I reject.
10(i) Learned counsel for the petitioners argues that petitioners have
removed the illegal construction and which was stated in para 11 of the
application under Order IX Rule 13 CPC but the stand of the petitioners is
not acceptable to this Court for various reasons.
(ii) The first reason is that the averments made in para 11 are only
self-serving averments and not supported by any documentary evidence of
removal of illegal construction. Even assuming the illegal construction was
removed and which I take for the sake of argument, then, it was necessary
for the petitioners to simultaneously inform the removal of the illegal
construction both to the court and to the L&DO because L&DO continues to
keep on charging misuser charges till intimation is received by them of
removal of the illegal construction. After notice is received by the L&DO
for removal of illegal construction, L&DO in fact conducts an inspection to
ensure that illegal construction is removed so that no future misuser charges
are payable, but in the absence of any notice by the petitioners either to the
court or to the L&DO no inspection would have been carried out by the
L&DO and therefore L&DO possibly may continue to claim further misuser
charges. On this aspect, however, I need not observe anything further
because even assuming the construction stands removed as stated in para 11,
admittedly the misuser charges which were payable in terms of the ratio of
the judgment in the case of Curewell (India) Ltd. (supra), have not been
paid by the petitioners till date.
11(i) The only other aspect which now remains is, as regards the
petitioners' prayer for now extending time for payment of misuser charges
and whether this Court should extend the period for the petitioners to deposit
the misuser charges so that there is no eviction order as against the
petitioners. Learned counsel for the petitioners very passionately argues that
petitioners have always been ready to deposit the misuser charges and which
was stated in para 11 of the application under Order IX Rule 13 CPC,
however, the classical expression that "put your money where your mouth
is" applies in the present case because except giving a lip service with
respect to showing readiness to deposit the amount, direction for payment of
which was made in August 2002, till today in the year 2014, petitioners have
not deposited the amount either with the court or with the L&DO with whom
it had to be deposited for the L&DO to stop claiming further interest and
penalty on the misuser charges amount. The issue of extension of time and
condonation of delay would only arise if actions of the tenants were
bonafide and their actions would have been bonafide only if the petitioners if
not within one month but within the next few months from August 2002,
would have actually deposited the misuser charges either in the court or to
the L&DO. But, what to talk of a few months, now over 12 years, except
making oral statements of willingness to deposit the misuser charges, the
deposit by the petitioners of the misuser charges has not seen light of the day
and which misuser charges of Rs.7,20,000/- payable as in August 2002,
would have as on date increased considerably by this date in the year 2014.
(ii) Learned counsel for the respondent is therefore justified in
placing reliance upon the direct judgment on this aspect of extension of time
passed by a learned Single Judge of this Court (Sh. Madan B. Lokur, J., as
he then was) in the case of M/s. Roneo Vickers India Ltd. Vs. Union of
India and Anr. 85 (2000) DLT 337 by which it was held that there should
not be condonation of delay and extension of time in routine with respect to
compliance of the order directing payment of misuser charges. Surely, and
as already stated above, some amount of delay could have been condoned,
but today there is no question after a period of 12 years after passing of the
judgment dated 7.2.2002 and the order dated 27.8.2002, of extending the
time for making the payment of the misuser charges alongwith further
interest and penalty thereon.
12. A summary of the aforesaid discussion makes the following
things crystal clear:-
(i) A decree under Section 14(1)(k) of the Act was passed against the
petitioners and which has to be treated as final because petitioners have no
reason for seeking setting aside of the ex parte judgment dated 7.2.2002
more so because petitioners were proceeded ex parte not once but twice in
these main proceedings under Section 14(1)(k) of the Act which concluded
with passing of the judgment dated 7.2.2002.
(ii) In terms of operative para 15 of the judgment dated 7.2.2002
petitioners had to demolish the illegal construction and had to pay the
misuser charges within one month in terms of the order dated 27.8.2002, but
admittedly till date except making oral requests the misuser charges which
were Rs. 7,20,000/- as in the year 2002 (and would be much much more
today) have not been deposited by the petitioners either with the courts or
with the L&DO. I must state that today we are in 2014, and the amount
which would be claimed by the L&DO from the respondent/landlord on
account of misuse of the illegal construction by the petitioners would be far
far more than Rs.7,20,000/- because L&DO will in addition to the amount of
Rs.7,20,000/- also claim interest and penalty on the same and may be even
further misuser charges because there is no communication to them of
removal of the offending construction.
(iii) In the facts of the present case, there does not arise any question of
extension of time being granted to the petitioners to deposit the misuser
charges amount with other charges towards interest and penalty, more so in
view of the direct ratio of the judgment of the learned Single Judge of this
Court in the case of Curewell (India) Ltd. (supra).
(iv) Petitioners have not only been grossly negligent but I would say
deliberately negligent in failing to appear in the main petition in 14(1)(k) of
the Act and in fact thereafter even in the proceedings which led to the
consequential orders being passed under Section 14(11) of the Act by the
Additional Rent Controller on 27.8.02 and 30.9.02, and petitioners seem to
believe that throwing a case on the negligence of their Advocate is enough
for them to walk away from their own inactions including of failing to
comply with operative para 15 of the judgment dated 7.2.2002 and the order
dated 27.8.2002.
13. In view of the above, there are no grounds for this Court to
interfere even as the first appellate court or the original court, leaving aside
exercising of jurisdiction under Article 227 of the Constitution of India
which is discretionary and extraordinary.
14. In view of the above, both these petitions are dismissed, leaving
the parties to bear their own costs.
VALMIKI J. MEHTA, J NOVEMBER 11, 2014 Ne
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!