Citation : 2014 Latest Caselaw 2898 Del
Judgement Date : 2 July, 2014
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO No. 224/2003
% 2nd July , 2014
UNION OF INDIA ......Appellant
Through: Mr. Jasvinder Singh, Advocate.
VERSUS
M/S. J.D. CONSTRUCTION AND ANR. ...... Respondents
Through: Mr. Vikaram Nandrajog, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
To be referred to the Reporter or not?
VALMIKI J. MEHTA, J (ORAL)
1. This first appeal is filed under Section 37 of the Arbitration &
Conciliation Act, 1996 against the impugned judgment of the court below
dated 17.8.2002. By the impugned judgment, the court below has dismissed
the objections which were filed by the appellant/objector/Union of India
against the Award of the arbitrator dated 24.9.2001.
2. It may be noted that limited objections were filed by the
appellant/objector and the Award as a whole was not challenged. The Award
allowed certain claims of the respondent herein (claimant before the
Arbitrator) and certain amount towards the counter claim of the appellant
FAO No.224 /2003 Page 1 of 6
herein (who was the respondent and the counter claimant in the arbitration
proceedings).
3. The facts of the case are that the respondent no.1 was given a
contract for designing and construction of RCC overhead tank of 40,000 litre
capacity of NZP New Delhi. The total value of the contract was
Rs.5,32,520/-. Respondent no.1 completed construction of the overhead
tank but there were disputes and differences with respect to certain
incomplete and defective work. The appellant rescinded the contract acting
under clause 3 of the contract and got the minor incomplete work completed
and defective work rectified from another agency. The arbitrator has passed
the Award allowing various claims of the respondent herein and also
allowing counter claim of the appellant herein for a sum of Rs.36,572/-
towards the cost of doing minor incomplete work/rectification work.
4. The case of the appellant before the court below as also before
this Court was that in addition to the amount of the counter claim which was
awarded to the appellant for a sum of Rs.36,572/- towards small left over
items and rectification, appellant was also entitled to forfeit the security
deposit of Rs.53,253/-.
5. The issue which is called for decision thus is that whether the
appellant in addition to being allowed the claim of Rs.36,572/- towards
FAO No.224 /2003 Page 2 of 6
small left over items and rectification work can be allowed to forfeit the
amount of security deposit of Rs.53,253/-again towards the same heads of
works.
6. In order to appreciate the case of the appellant herein before the
arbitrator with respect to forfeiture of the security deposit, the following
paragraph of the reply to the claim petition requires to be referred to:-
"Claim No.10:- For Rs.54,000/- approx. for release of security
deposit.
Since the claimants did not carry out the work as per agreement,
and their agreement has been rescinded by the Govt., their full salary
deposit recoverable under the contract is liable to be forfeited.
Under clause 3 of the agreement when the contractor has made
himself liable for action for recision of his contract, then under clause
3(a) of the agreement the President of India shall have powers to
determine or rescind the contract as aforesaid of which termination or
rescission notice in writing to the contractor under the hand of the
Engineer-in-charge shall be conclusive evidence. Upon such
determination or rescission the full security deposit recoverable under
the contract shall be liable to be forfeited and shall be absolutely at the
disposal of the Government if any portion of the security deposit has
not been paid or received it would be called for and forfeited.
The security deposit money so far deducted from the bills of the
claimants is Rs.46863/-. Since the tendered amount is Rs.5,32,530/-
total security deposit to be recovered from the claimants is
Rs.53,253/- i.e a balance of the Rs.63900/- is yet to be recovered from
the claimants since their work has been rescinded by the Government
vide letter No.54(1)/CEDII/CCU/166 dt. 29.1.2001 (Exbt R14). As
such it may be seen that on the contrary the claimants are required to
deposit the balance amount of the security deposit with the
respondents which shall be recovered from their final bill. Hence, it is
prayed to the learned arbitrator that the claim of the claimants be
rejected." (underlining is added)
FAO No.224 /2003 Page 3 of 6
7. A reading of the aforesaid para shows that the appellant claims
forfeiture of the security deposit on account of rescinding of the contract
under clause 3. Effectively, therefore the claim was made for adjustment of
the security deposit on account of the defective work and incomplete work
having been got done from another agency.
8. The arbitrator awarded to the appellant/UOI its claim of cost of
execution of left over items and rectification by giving the following
conclusions:-
"............
14.Counterclaim- Respondents claim an amount of Rs.73,430/- for
balance work and rectification work. The claim was later
modified to Rs.35,532/-. The respondents further claim an
amount of Rs.50,000/- towards costs.
14.1 The claimants gave the details of the final bill as prepared by
them. They showed the recovery of Rs.53253 as recovery towards
levy of compensation under clause 2 and a recovery of a sum of
Rs.36,572 as the expenditure incurred on completion/rectification
through another agency. After making adjustments for other amounts
found payable, they arrived at the net figure of Rs.35532 as their
claim. While arriving at this figure, the respondents also took the
amount of security deposit of Rs.53253 recoverable as already
recovered.
14.1.1. There is ample evidence on record that the claimants did not
take the respondents' request for completing the balance small items
and for rectification of defects pointed out by respondents from time
to time and in the joint inspection on 24.8.2000, seriously. It has been
amply proved that the respondents had to resort to execution of those
items through another agency at the risk and cost of the claimants.
Respondents have further given the details of their expenditure by
FAO No.224 /2003 Page 4 of 6
way of payment to the other agency entrusted with this job of
execution of small left over items and for rectification. They have
given the details of a total expenditure of Rs.45,946/- out of which
they have preferred the claim for Rs.36,572/- as recoverable from the
claimants on this account.
14.1.2 I, accordingly, award the amount of Rs.36,572/- in
favour of the respondents on this account. ( I do not consider it
necessary to make a finer distinction between the amount spent on
rectification of defects in the original work and the extra items after
allowing the claim, as I did, for payment for extra items in favour of
claimants to the extent considered admissible and after taking note of
the fact that the respondents' claim is for an amount which is already
less than the total amount they spent by way of payment to the other
agency engaged under clause 3)."
9. It is trite that for the same heads of claims, amounts cannot be
awarded twice over. The appellant has already been awarded damages of
Rs.36,572/- on account of respondent herein not doing the work of certain
small left over items and rectification work. Hence, further amount of
Rs.53,253/- cannot be granted to the appellant under the same head in the
nature of forfeiture of the security deposit. Sections 73 and 74 of the
Contract Act, 1872 provide for damages in the alternative. Liquidated
damages under Section 74 of the Contract Act cannot be claimed in addition
to variable damages which are granted under Section 73 of the Contract Act
for the same head of damages. Once for the head of damages incomplete
work and defective work an amount of Rs.36,572/- is granted under Section
73 of the Contract Act, the appellant was not entitled to claim further
FAO No.224 /2003 Page 5 of 6
amount of liquidated damages under Section 74 of the Contract Act, 1872
for the sum of Rs.53,253/-.
10. At this stage, I may note that the appellant is satisfied by the
Award of Rs.36,572/- towards small left over items and for rectification
work as this part of the claim awarded in favour of the appellant by the
arbitrator has not been challenged i.e the appellant is not claiming an
enhancement to the counter claim allowed for the amount of Rs.36,572/- by
challenging the Award for this purpose.
11. In view of the above, I do not find any error in the judgment of
the court below dismissing the objections under Section 34 of the Act. The
appeal is therefore dismissed, leaving the parties to bear their own costs.
JULY 02, 2014 VALMIKI J. MEHTA, J.
Ne
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!