Citation : 2013 Latest Caselaw 1257 Del
Judgement Date : 14 March, 2013
$~16 to 19
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on : March 12, 2013
Judgment pronounced on : March 14,2013
+ LPA 531/2012
UNION OF INDIA & ORS ..... Appellants
Through : Mr. Baldev Malik, Adv.
versus
KAMAL KUMAR ..... Respondent
Through : Mr. L.P.Dhir and Mr.Vikas
Nautiyal, Advs.
+ LPA 532/2012
UNION OF INDIA & ORS ..... Appellants
Through : Mr. Baldev Malik, Adv.
versus
KAMAL KUMAR ..... Respondent
Through : Mr. L.P.Dhir and Mr.Vikas
Nautiyal, Advs.
+ LPA 534/2012
UNION OF INDIA & ORS. .... Appellants
Through : Mr. Baldev Malik, Adv.
versus
RAMAN KUMAR ..... Respondent
Through : Mr. L.P.Dhir and Mr.Vikas
Nautiyal, Advs.
LPA 531/2012 Page 1 of 14
+ LPA 540/2012
UNION OF INDIA & ORS ..... Appellants
Through : Mr. Baldev Malik, Adv.
versus
KAMAL KUMAR L.R. ..... Respondent
Through : Mr. L.P.Dhir and Mr.Vikas
Nautiyal, Advs.
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE V.K. JAIN
ORDER
% 12.03.2013 CM 12463/2012(delay in filing the appeal for 136 days) CM 12469/2012(delay in filing the appeal for 136 days) CM 12481/2012(delay in filing the appeal for 136 days) CM 12763/2012(delay in filing the appeal for 136 days) CORAM:
HON'BLE THE CHIEF JUSTICE HON'BLE MR. JUSTICE V.K. JAIN
V.K. JAIN, J.
1. Certain writ petitions being W.P.(C) Nos.2276/1996, 302/1996,
303/1996 and 260/1995 were filed challenging the order dated
28th November, 1994 passed under Sections 7(1) and 7(3) of Smugglers
And Foreign Exchange Manipulators (Forfeiture of Property) Act, 1976
(SAFEMA), by the Competent Authority, the Appellate Tribunal's order
dated 8th March, 1996 and the rectification order dated 8th May, 1996.
The writ petitions were allowed vide common order dated 25th
November, 2011. LPA No.531/2012, 532/2012, 534/2012 and 540/2012
have been filed questioning the order passed in the writ petitions. Since
the appeals have been filed after expiry of the prescribed period of
limitation, the aforesaid applications have been filed seeking condonation
of delay of 139 days in filing the appeals.
2. Pursuant to our order dated February 22, 2013, the appellants have
filed a better affidavit explaining the delay in filing the appeals and the
delay is sought to be explained in paras 2 to 19 of the said affidavit.
3. A reply has been filed by the respondents, opposing the
applications, inter alia, on the ground that no action was taken by the
appellants for more than two months to file the appeals and no reasonable
and sufficient cause has been shown for condonation of delay in filing the
appeals. In support of their reply, the respondents have relied upon
certain documents obtained by them under RTI Act.
4. A perusal of the affidavit filed in support of the applications would
show that copy of the impugned order was received by the concerned
department after about four weeks, on 23rd December, 2011. Since, any
decision whether to accept the order passed by the learned Single Judge
or to challenge it by way of appeal could have been taken only after a
detailed analysis of the said order with the help of the relevant files
maintained in the concerned departments/Sections, the appellants cannot
be blamed for not initiating any action in the matter prior to 23rd
December, 2011. Since 24th December, 2011 and 25th December, 2011
were holidays, the order in question was received by the concerned
dealing officer on 26th December, 2011 and the file reached the
Competent Authority through proper channel, on 4th January, 2012.
Considering that the dealing officer could not have put up the file directly
to the Competent Authority and was, required to route the same through
his superior, it cannot be said that the appellants were inactive in taking
any action in the matter between 26th November, 2011 to 4th December,
2012. Immediately on the file being seen by the Competent Authority, a
legal opinion from the counsel who represented the appellants in the writ
petitions was sought vide letter dated 5th January, 2012. The appellants
were justified in seeking legal opinion before deciding whether to accept
the impugned order or to challenge it by way of appeal. The counsel also
took some time to give opinion sought by the Department, which was
received on 19th January, 2012. In the meanwhile, there was change of
Competent Authority and the previous Competent Authoirty Smt. Renu
Jauhri was replaced by Smt. Pragya S.Saxena. The opinion received from
the counsel was placed before the new Competent Authority on 18 th
January, 2012. The said opinion was received by the dealing officer on
27th January, 2012, on account of intervening holidays on 21 st, 22nd and
26th Januay, 2012. Since the office of the concerned department
remained closed on 21st January, 2012 and 29th January, 2012, the
approval to file appeal was sent to the counsel on 30th January, 2012.
Thus, within about one month and one week of receipt of the impugned
order, the concerned department had, obtained legal opinion from the
counsel and taken a decision to file the appeals. Upto this stage, we do
not find any laxity or inaction on the part of the appellants in processing
the matter.
5. The learned counsel for the respondents submitted that there is no
explanation for the delay for the whole of the month of February 2012.
This, however, was countered by the learned counsel for the appellants
referring to the letter dated 5th March, 2012 written by the Competent
Authority to the Under Secretary, Competent Authority Cell, Ministry of
Finance, which the respondents themselves have filed along with their
reply. A perusal of this document would show that the counsel took
about four weeks to draft the appeals and sent the same to the department
on 29th February, 2012. That explains the delay for the whole of the
month of February, 2012. This letter also shows that on 1 st March, 2012,
Shri Baldev Malik, counsel for the appellants, had telephonically
informed the concerned department that first he was required to get the
Brief Transmission Form(BTF) to be issued in his favour from Ministry
of Law & Justice, before the filing of LPA in this Court. It was because
of this requirement that a letter was sent by the Office of the Competent
Authority to the Ministry of Law & Justice seeking issue of requisite BTF
in favour of Shri Baldev Malik, Advocate, on priority basis. 3rd March,
2012 and 4th March, 2012 were holidays and on 5th March, 2012, the
abovereferred letter to the Under Secretary, Competent Authority was
sent seeking permission/advice at the earliest. A copy of the brief of the
case along with the LPA drafted by the counsel was enclosed to the said
letter. A perusal of the letter dated 28th March, 2012 written by Ministry
of Finance (Competent Authority Cell) to the Competent Authority would
show that on receipt of the letter dated 5th March, 2012 from him, the
matter was referred to Ministry of Law for the advice to file LPA against
the impugned order. It appears from the legal advice annexed to the letter
dated 28th March, 2012 that there was some delay on the part of the
Department of Revenue in seeking opinion of the Ministry of Law. The
opinion by the Law Ministry was sent on 26th March, 2012 and thereafter
there was no delay on the part of the Competent Authority Cell inasmuch
as the opinion of the Law Ministry was forwarded to the Competent
Authority on 28th March, 2012 itself, and was received by the said
Competent Authority on 29th March, 2012. The affidavit filed by the
appellants shows that on 30th March, 2012, a reply with brief facts and
ground for filing LPA was sent to the Ministry by FAX. 31st March,
2012 and 01st April, 2012 were holidays and on 02nd April, 2012, a letter
enclosing the brief note along with the grounds on which the impugned
order was considered to be bad in law and day-to-day reasons for the
delay in filing of the LPA, along with certified copy of the impugned
order, was sent by the Office of Competent Authority to the Competent
Authority Cell in the Ministry of Finance, with a request that Ministry of
Law & Justice may be requested for early approval for filing of the LPA.
It would thus be seen that once opinion from Law Ministry was received
by the Office of Competent Authority, there was no delay on its part in
processing the matters. The documents filed by the respondents would
show that about one week was taken by the Competent Authority Cell in
the Ministry of Finance in processing the file after receipt of letter dated
2nd April, 2012 from the Office of the Competent Authority and the
Deputy Legal Advisor gave his opinion on 26th April, 2012. The file was
sent to the Department of Revenue on 27th April, 2012 and from there it
was forwarded to the Office of the Competent Authority. The affidavit
filed by the appellants would show that the approval for filing the LPA
was received from the Ministry on 1st May, 2012 and it was put up to the
Competent Authority on the very next day. 5 th May, 2012 and 6th May,
2012 were holidays and on 7th May, 2012, a letter was sent to the counsel
conveying approval of the Competent Authority and the concerned
Ministry for filing the appeals. The appeals came to be filed on 9 th May,
2012.
6. Considering the detailed explanation given in the affidavit filed by
the appellants coupled with the documents comprising inter-departmental
correspondence and legal opinion filed by the respondents would show
that in the case before us, the concerned department has been diligently
pursuing the matters with the Competent Authority Cell of the Ministry
of Finance. We cannot be oblivious to the fact that under the procedure
of the Government, inter-Ministrial correspondence may not be
permissible below a particular level and that precisely seems to be the
reason why the Competent Authority instead of delaing directly with the
Ministry of Law & Justice had been routing the matter through the
Competent Authority Cell, the Ministry of Finance.
7. The learned counsel for the respondent, in support of his
contention, that the delay in filing the appeal ought not to be condoned,
has relied upon the decision of the Supreme Court in Office of The
Chief Post Master General and Ors. versus Living Media India Ltd. and
Anr., (2012)3 SCC 563, where the Apex Court after considering its
earlier decisions including the decisions in Collector, Land Acquisition,
Anantnag and Anr. v. Mst. Katiji and Ors. (1987) 2 SCC 107, G.
Ramegowda, Major and Ors. v. Special Land Acquisition Officer,
Bangalore (1988) 2 SCC 142, State of Haryana v. Chandra Mani and
Ors. (1996) 3 SCC 132, National Insurance Company Ltd. v. Giga Ram
and Ors. (2002) 10 SCC 176, State of Nagaland v. Lipok Ao and Ors.
(2005) 3 SCC 752, inter alia, held as under:-
"12) It is not in dispute that the person(s) concerned were well aware or conversant with the issues involved including the prescribed period of limitation for taking up the matter by way of filing a special leave petition in this Court. They cannot claim that they have a separate period of limitation when the Department was possessed with competent persons familiar with court proceedings. In the absence of plausible and acceptable explanation, we are posing a question why the delay is to be condoned mechanically merely because the Government or a wing of the Government is a party before us. Though we are conscious of the fact that in a matter of condonation of delay when there was no gross negligence or deliberate inaction or lack of bonafide, a liberal concession has to be adopted to advance substantial justice, we are of the view that in the facts and circumstances, the Department cannot take advantage of various earlier decisions. The claim on account of impersonal machinery and inherited bureaucratic methodology of making several notes cannot be accepted in view of the modern technologies being used and available.
The law of limitation undoubtedly binds everybody including the Government."
It would thus be seen that the State and its agencies have to offer
reasonable and acceptable explanation for the delay and show a bonafide
effort on their part and the usual explanation that the file was kept
pending for several months/years due to procedural red-tape cannot be
accepted. The Apex Court, however, did acknowledge that if it is shown
that there was no gross negligence or deliberate inaction or lack of
bonafide, a liberal approach in the matter could be adopted. It is not as if
delay cannot be condoned in any case. What is necessary is a bona fide
effort on the part of the appellant and a plausible and genunine
explanation for the delay in coming to the Court. Though red tapism and
what is usually termed as beurocratic delays inherent in an insensitive
government machinery cannot be a good ground for the condonation of
delay, if it is shown that the concerned department has been vigilant in
persuing the matter, a somewhat liberal approach in the matter can be
adopted considering the constraints and limitations which are inherent in
the functioning of a government department, bound by its own rules of
business and procedure. As observed by Supreme Court in Maniben
Devraj Shah vs. Municipal Corporation of Brihan, (2012) 5 SCC 157, if
the Court finds that there has been no negligence on the part of the
applicant and the cause shown for the delay does not lack bona fides,
then it may condone the delay. Of course, if the explanation given by the
applicant is found to be concocted or he is found to be thoroughly
negligent in prosecuting his cause, there would be no scope for
condonation of delay in coming to the Court.
In S. Ganesharaju (D) Thr. L.Rs. and Anr. versus Narasamma
(D) Thr. L.Rs. and Ors., 2012 (4) SCALE 152, condoning the delay of
53 days in filing a review petition, Supreme Court, inter alia, held as
under:-
"14. The expression "sufficient cause" as appearing in Section 5 of the Indian Limitation Act. 1963, has to be given a liberal construction so as to advance substantial justice.
15. Unless Respondents are able to show malafide in not approaching the court within the period of limitation, generally as a normal rule, delay should be condoned. The trend of the courts while dealing with the matter with regard to condonation of delay has tilted more towards condoning delay and directing the parties to contest the matter on merits, meaning thereby that such technicalities have been given a go-by.
16. Rules of limitation are not meant to destroy or foreclose the right of parties. They are meant to see that
parties do not resort to dilatory tactics but seek their remedy promptly.
17. We are aware of the fact that refusal to condone delay would result in foreclosing the suitor from putting forth his cause. There is no presumption that delay in approaching the court is always deliberate.
18. In fact, it is always just, fair and appropriate that matters should be heard on merits rather than shutting the doors of justice at the threshold. Since sufficient cause has not been defined, thus, the courts are left to exercise a discretion to come to the conclusion whether circumstances exist establishing sufficient cause. The only guiding principle to be seen is whether a party has acted with reasonable diligence and had not been negligent and callous in the prosecution of the matter. In the instant case, we find that Appellants have shown sufficient cause seeking condonation of delay and same has been explained satisfactorily."
8. The learned counsel for the respondents has also relied upon
Charan Lal Sahu v. Giani Zail Singh and Anr., AIR (1984) SC 309 and
Pundlik Jalam Patil (D) by Lrs. versus Exe. Eng. Jalgaon Medium
Project (2009) 5 SCC (Civ) 907. However, we do not find any such
proposition of law in either of these cases which would disentitle the
appellants from condonation of delay in filing these appeals. The learned
counsel for the respondents referred to the observation made by Supreme
Court in Ajit Singh Thakur Singh And Another v. State Of Gujarat,
(1981) 1 SCC 495 to the effect that when a party allows allows limitation
to expire and pleads sufficient cause for not filing the appeal earlier, such
cause must establish that because of some event or circumstance arising
before limitation expired it was not possible to file the appeal within time
and no event or circumstance arising after the expiry of limitation can
constitute sufficient cause. However, in the case before us, it cannot be
said that the appellants did not take any action in the matters during the
prescribed period of limitation. The matter was processed as soon as a
copy of the impugned order was received by the Competent Authority.
Therefore the observations made by Supreme Court in Ajit Singh Thakur
Singh (supra), do not apply to the case before us.
9. Since we are of the considered view that the delay on the part of
the appellants in approaching this Court stands substantially explained,
the applications are allowed and the delay in filing the appeals is
condoned subject to the payment of Rs.10,000/- each as costs in all the
four appeals.
V.K.JAIN, J
CHIEF JUSTICE
MARCH 14, 2013/'sn'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!