Citation : 2013 Latest Caselaw 313 Del
Judgement Date : 22 January, 2013
$~28
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of Judgment:21.01.2013
FAO(OS) No.40/2013
NATIONAL HIGHWAYS AUTHORITY OF INDIA .... Appellant
Through: Mr.Sudhir Nandrajog, Sr.
Advocate with Ms.Meenakshi
Sood, Ms.Padma Priya, and
Mr.Mukesh Kumar, Advocates.
versus
BEL- ACC (JV) .... Respondent
Through: Mr.Amit George and Mr.Abin
Mathew, Advocates.
CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON'BLE MS. JUSTICE INDERMEET KAUR
INDERMEET KAUR, J.
C.M. No.1122/2013 (for exemption)
Exemption is allowed subject to just exceptions.
FAO(OS) No.40/2013 & C. M.No.1121/2013 (for stay)
1. A contract dated 01.02.2001 had been entered into between the
National Highways Authority of India (hereinafter referred to as „the
petitioner) and M/s BEL- ACC (JV) (hereinafter referred to as „the
respondent‟) wherein the project of strengthening and four laning of the
existing two lane sections between 307.500 Km to 321.00 Km of
Etawah Bypass on NH-2 in Uttar Pradesh had been awarded to the
respondent. The work was to be completed by 03.10.2003 i.e. within a
period of two and half years. Delays were noted by the NHAI pursuant
to which notice dated 15.11.2001 had been issued to the respondent
followed by other correspondences evidencing that the work progress
was slow on account of various reasons which were attributable to the
respondent. Variations in the work contract were discussed in meetings
held between the parties on various occasions i.e. in the first meeting on
19.11.2001 followed by exchange of correspondence in the year 2002
which led to the revised date of completion which was accordingly fixed
for March, 2004. The date of completion was further enlarged in view
of the re-revised work programme dated 26.11.2003 up to January,
2006. The Variations Committee took a decision that the service road
be deleted; this decision was conveyed to the respondent only on 24th
and 26th June 2003. Submission of the respondent being that up to this
time he had already begun work on the construction of the service road
and by his reply letter dated 21.7.2003 he disputed the deletion of the
service road. A representation dated 09.3.2004 was also submitted by
the respondent to the Engineer of the NHAI against the decision to
exclude the service road.
2. The work progress still being slow, a show cause notice was
issued to the respondent on 31.8.2004 followed by a recommendation
dated 04.11.2004 of the Engineer of the NHAI recommending the
expulsion of the respondent and the completion of the balance work by
the NHAI. This was followed by the expulsion notice dated 05.4.2005
issued to the respondent and the balance work including work of the
service road was awarded to a new agency at the cost of the respondent.
Disputes arose between the parties; the arbitration clause was invoked
by the respondent. The Arbitral Tribunal by its majority Award dated
31.01.2009 noted that up to March 2001 i.e. till the time that the major
variations have been initiated by the NHAI (which was vide its letter
dated 19.11.2001) the progress of the work was slow which was
primarily the responsibility of the respondent, major variations having
been initiated by the NHAI on 19.11.2001 and which were conveyed to
the respondent only on 24-26.6.2003.
3. The relevant extract of these findings of the Arbitrator were
reproduced in the impugned order, which read as under:
(a) For the period from the date of the award of the work i.e. 6th March 2001 till the proposed major variations were initiated by NHAI (19th November 2001), the progress of the work was slow and the Respondent was solely responsible for this;
(b) For the period from the date on which proposal for major variation was initiated by NHAI (19th November 2001) till variation order was approved by the Engineer on 24th/26th June 2003 by excluding the service road, the Respondent could not be held responsible for any delay, since the decision had to be taken by NHAI. Therefore, both the parties were held responsible for slow progress of the work;
(c) The Engineer too was responsible for not operating the CA in proper manner. The Engineer had the authority to fix rate in accordance with General Conditions of Contract („GCC‟) Clause 52.1. The Engineer could have fixed provisional rates to enable work to progress. The parties could have objected to its decision and decided to go for arbitration;
(d) On the one hand, NHAI issued notice under Clause 46.1 and on the other hand, tried to find an alternative solution with the Respondent. This showed lack of clarity on the part of NHAI, for the course of action. The certificate dated 4th November 2004 of the Engineer lost its value with simultaneous efforts being made to find alternative solution;
(e) In case NHAI intended to terminate the contract then another certificate should have been issued by the Engineer giving a copy to the Respondent by referring to all that happened after earlier certificate. Thereafter, expulsion order could have been issued in reasonable time. The expulsion order of NHAI was "illegal, improper and not justified":
(f) Since, the termination order was not issued by the competent authority, it was illegal;
(g) Disputes arising on account of termination order issued by NHAI would be dealt with by AT-II and another dispute by AT-I.
(h) The varied works awarded to the Respondent included the service road. At much later stage on 26th July 2003, it was conveyed that service road had been taken out from the scope of the work. NHAI did not act in a proper manner by withdrawing the service road at a belated stage without any reasons. At the alternative of Engineer deciding on provisional rates and work of service road being allowed to be completed, a submission of the Respondent that contract was materially altered stood proved beyond any doubt.
5. Eleven claims had been raised by the claimant. Except for claim
No. 4 all claims were answered in favour of the respondent. It was held
that the variations noted in the contract did not define the rights and
obligation of the parties; the variations had in fact led to major changes
and it was unjust and unreasonable to expect the respondent to continue
the new work on the old rates and on the same terms and conditions, as
these amounted to a new work and not mere variations. The act of the
NHAI terminating the contract with the expulsion of the respondent in
these circumstances was held to be illegal.
6. Against this Award objections were filed by the NHAI under
Section 34 of the Arbitration and Conciliation Act (hereinafter referred
to as „the said Act). The impugned order dated 11.10.2012 had
dismissed these objections.
7. Learned counsel for the appellant has assailed the impugned order
on two grounds. His primary submission is that the Single Judge has
noted the variations in the work only in the year 2001 and 2002 and this
is evident from para 19 and 20 of the impugned order; there has been no
discussion in the impugned order about the variations made in the
subsequent years and which have been accepted by the respondent
which is clear from the correspondences exchanged between the parties
and in fact the respondent himself had agreed to the enlargement of time
to be granted to him to complete the work. Second submission being
that the work was to be executed in two phases; in the first phase the
respondent had to construct an additional lane by widening the existing
road whereas in the second phase new construction of four lanes had to
be done and there was no reason for delay in the second phase of the
work and both the submissions have remained unanswered by the
learned single Judge.
8. These submissions are ill-founded. Not only has the majority
award but the learned single Judge has also dealt with and answered
both these arguments. The fact finding of the Arbitrator was that the
correspondences exchanged between the parties showed that the works
which were awarded to the claimant in November 2001 stood varied but
this decision on the variation was conveyed to the claimant at a much
later stage i.e. on 26.7.2003 and it was accepted by the parties that in
case the service road had to be executed by the claimant the contract
would have been materially altered. The learned Arbitrator has noted
that for almost 20 months i.e. w.e.f. 2001 to July 2003 both the parties
had accepted that the contract was materially altered and this is evident
from the proposal of the engineer for revision of rates of work including
the service road but thereafter the decision had been taken at a belated
stage for the withdrawal of the work of the service road. This was
without any reason. A positive fact finding has been returned by the
Arbitrator in this regard which has been endorsed by the learned single
Judge. Learned single Judge had noted that the decision of the NHAI to
recommend termination of the contract after making the respondent
carry out the work of construction of service road for nearly two years
was neither reasonable and nor valid and as such the expulsion order
passed by the NHAI was illegal. This was a fact finding returned by the
Arbitral Tribunal and endorsed by the learned single Judge. The
termination of the contract by the NHAI being illegal the decision on the
individual claims was a necessary consequence and the awarded
amounts in favour of the claimant were rightly not interfered with.
9. The submission made by learned senior counsel before this Court
that the work was in fact being carried out in two phases and even if
there was a delay in the execution of work in relation to phase-I there
was no hurdle in the completion of work regarding phase-II which
submission was noted by the learned single Judge to have been taken for
the first time before him and was not an issue urged before the
Arbitrator. The terms of the contract also did not strengthen this
argument of the appellant.
10. Trite it is to state that the scope of objections under Section 34 of
the said Act are limited; the Award can be set aside only on any one of
the grounds enumerated therein. It is a reasoned Award. The
interpretation of the terms of the contract as adopted by the majority
Award and upheld by the learned single Judge is a plausible view, the
termination of the contract was rightly noted to be illegal. There is no
error apparent on the face of the record which calls for any interference
by this Court. In fact apart from the aforenoted two submissions as
argued before us there is no other argument which has been urged.
Although in the grounds of appeal it has been pleaded that this Award is
opposed to public policy but there has been no elaboration on this point.
11. In this conspectus we see no reason to interfere with the
impugned order. Appeal as also the stay application is dismissed.
INDERMEET KAUR, J.
SANJAY KISHAN KAUL, J.
JANUARY 21, 2013 nandan
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!