Citation : 2012 Latest Caselaw 6470 Del
Judgement Date : 5 November, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
#15 (Reportable)
+ O.M.P. 569 of 2012
M.L. DALMIYA & COMPANY LTD. ..... Petitioner
Through: Mr. Ram K. Watel, Advocate.
versus
THE CHAIRMAN & MANAGING DIRECTOR,
NATIONAL BUILDING CONSTRUCTION
CORPORATION LIMITED & ORS. ..... Respondents
Through: Mr. Sagar Bhatia, Advocate.
CORAM: JUSTICE S. MURALIDHAR
ORDER
% 05.11.2012
1. This is a petition under Section 14 of the Arbitration and Conciliation
Act, 1996 ('Act') for a direction to terminate the mandate of the
Respondent No. 4, who has been appointed by the Respondent, National
Building Construction Corporation Limited ('NBCC') (represented by
Respondents 1 to 3) to act as sole Arbitrator to adjudicate the disputes
between the Petitioner, M.L. Dalmiya & Company Ltd. and NBCC
arising out of the work of expansion and modification of the terminal
building and allied works at Patna Airport which was awarded to the
Petitioner by a letter dated 31st December 1993 and 3rd January 1994.
2. According to the Petitioner, it completed the work in all respects by
31st October 1998 but there were disputes concerning the payment of the
final bill, the security deposit and performance bank guarantee ('PBG').
The Petitioner invoked the arbitration clause by a letter dated 25th April
2002.
3. In terms of the arbitration clause, the Arbitrator was to be appointed
by the Chairman-cum-Managing Director ('CMD'), NBCC. By a letter
dated 18th June 2002, the CMD first appointed one Mr. S.K. Chatterjee,
Additional General Manager ('AGM'), NBCC as sole Arbitrator. The
Petitioner filed its statement of claim before Mr. Chatterjee. However,
NBCC failed to file its written statement despite several opportunities. In
anticipation of his retirement on 31st January 2004, Mr. Chatterjee had
resigned on 12th January 2004. He noted that the hearing in the arbitral
proceedings could not commence since NBCC had failed to submit its
counter claims.
4. Mr. Chatterjee was replaced by one Mr. A.K. Gupta, Deputy General
Manager ('DGM') on 1st May 2004. It is stated that without any
significant progress being made in the arbitral proceedings, Mr. Gupta
also resigned on 28th September 2007 stating that he was pre-occupied
with other commitments. The CMD, NBCC thereafter appointed one
Mr. S.K. Basandra, DGM, NBCC (Respondent No. 4 herein) as sole
Arbitrator by a letter dated 26th October 2007.
5. It is averred in the petition that after his appointment Mr. Basandra
held one hearing on 3rd June 2008 and for more than two years thereafter
he failed to fix any date for hearing. The copies of the letters dated 9th
December 2009 and 23rd February 2010 written by the Petitioner to
Respondent No. 4 have been placed on record. The Petitioner by a letter
dated 28th May 2010 informed Respondent No. 4 that since he had failed
to act without undue delay, his mandate stood terminated. A copy of the
said letter was also marked to NBCC. In response thereto by a letter
dated 9th/10th August 2010, Respondent No. 4 informed the parties that a
hearing had been fixed on 17th September 2010. At the request of the
Petitioner, Respondent No. 4 re-fixed the hearing date as 21st October
2010. On that date, the Arbitrator suggested that both parties should try
and reconcile their differences. At the instance of the Respondent No. 4,
the Petitioner by a letter dated 4th November 2010 sent the learned
Arbitrator a copy of the letter dated 14th January 1998 written by the
Chief Project Manager, NBCC to the Petitioner extending the time. It is
stated that thereafter no hearing was held by Respondent No. 4. By a
letter dated 12th May 2011, the Petitioner asked Respondent No. 4 to fix
a date for hearing. However, Respondent No. 4 failed to do so.
6. It is in the above circumstances that a letter was addressed by the
Petitioner to Respondent No. 4 on 27th April 2012 asking him to fix a
date for hearing within fifteen days failing which the Petitioner would
approach the Court. It is submitted by Mr. Ram K. Watel, learned
counsel appearing for the Petitioner that Respondent No. 4 having failed
to act without undue delay, he had lost his mandate in terms of Section
14(1)(a) of the Act. He further submits that the CMD, NBCC should
also be held to have forfeited his right to appoint an Arbitrator. Reliance
is placed on the decisions in Ariba India Private Ltd. v. Ispat Industries
Ltd. 2011(3) Arb. LR 163 (Delhi); Union of India v. Singh Builders
Syndicate 2009(2) Arb. LR 1 (SC); Northern Railway Administration,
Ministry of Railways, v. Patel Engineering Company Ltd. 2008(3) Arb.
LR 349 (SC); Bipromasz Bipron Trading SA v. Bharat Electronics
Limited (BEL) (2012) 6 SCC 384 and N.B.C.C. Ltd. v. J.G.
Engineering Pvt. Ltd. 2010(1) Arb. LR 165 (SC).
7. Mr. Sagar Bhatia, learned counsel appearing on behalf of the
Respondents 1 to 3 at the outset stated that the Respondents do not wish
to file any reply to the petition. He relied on the decision dated 4th
August 2009 of the Supreme Court in Civil Appeal No. 5075 of 2009
(Union of India v. Premier Files Ltd.) and a decision dated 23rd
December 2009 of this Court in OMP No. 451 of 2006 (Executive
Engineer v. M/s Nav Nirman Construction Co.). He submitted that
since the arbitration clause required the CMD to appoint an Arbitrator
then the choice of the Arbitrator had to be that of the CMD, NBCC. He
submitted that alternatively a time-frame may be fixed by the Court for
conclusion of the arbitral proceedings by Respondent No. 4.
8. The above submissions have been considered. This Court is satisfied
that the Respondent No. 4 has failed to act without undue delay resulting
in the termination of his mandate in terms of Section 14(1)(a) of the Act.
Despite letters written by the Petitioner to Respondent No. 4 requesting
him to expedite the arbitral proceedings as noted hereinbefore, the
Arbitrator has failed to do so. With the Respondents choosing not to file
any counter affidavit, the averments by the Petitioner on the failure of the
Arbitrator to act expeditiously remain uncontroverted. He has brought
about a situation where the "controversy remains" concerning his failure
to act without undue delay. Therefore, under Section 14(2) of the Act,
the Petitioner is entitled to approach this Court seeking termination of the
mandate of Respondent No. 4.
9. In Union of India v. Singh Builders Syndicate, the Supreme Court
observed that if the arbitral Tribunal is made non-functional on account
of the delay of one of the serving officers either by the frequent transfer
or by failure to take steps expeditiously then the Court should step in,
and appoint an Arbitrator. Again in Northern Railway Administration v.
Patel Engineering Company Ltd., the Supreme Court observed that it
was not powerless to make appropriate alternative arrangements where
the arbitral Tribunal is not functional. As regards appointing the named
Arbitrator, the Supreme Court in Bipromasz Bipron Trading SA v.
Bharat Electronics Limited, observed that if the facts so warrant, the
Court can appoint another person where it is of the view that the named
Arbitrator is not likely to be impartial. In N.B.C.C. Ltd. v. J.G.
Engineering Pvt. Ltd., the Supreme Court terminated the mandate of the
Arbitrator as there was undue delay in completing the arbitral
proceedings.
10. In the present case, the uncontroverted facts are that the arbitral
proceedings which commenced with the Petitioner invoking the
arbitration clause way back on 25th April 2002 are yet to conclude. There
have been three Arbitrators appointed by the CMD, NBCC in this long
period of over ten years with no significant progress being made in the
arbitral proceedings. The Court is, therefore satisfied that permitting the
CMD, NBCC to further appoint another Arbitrator to replace Respondent
No. 4 would be a futile exercise as the Arbitrators so far appointed have
not been able to carry on with the arbitral proceedings without undue
delay. This Court, therefore holds that in the facts and circumstances of
the case, the CMD, NBCC should be held to have forfeited his right to
appoint an Arbitrator in terms of the arbitration clause.
11. In the above circumstances, this Court terminates the mandate of
Respondent No. 4 as an Arbitrator.
12. Consequently, in exercise of its powers under Section 11 read with
Section 14(1)(a) and Section 14(2) of the Act, this Court appoints Mr.
Justice P.K. Bahri, a former Judge of this Court, residing at 171, Jor
Bagh, New Delhi-3 (Mob. 9818542737) as sole Arbitrator to adjudicate
the disputes between the parties. The learned Arbitrator will proceed
from the stage at which the arbitral proceedings were before Respondent
No. 4.
13. It will be the responsibility of the NBCC to ensure that the entire
arbitral record is collected from Respondent No. 4 within the next ten
days and placed before the learned Arbitrator appointed by this Court
forthwith. The fees of the learned Arbitrator would be in terms of the
Delhi High Court Arbitration Centre (Arbitrators' Fees) Rules.
14. The petition is disposed of in the above terms. A copy of this order
be delivered to the learned Arbitrator forthwith.
S. MURALIDHAR, J.
NOVEMBER 05, 2012 akg
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!