Citation : 2012 Latest Caselaw 2903 Del
Judgement Date : 2 May, 2012
IN THE HIGH COURT OF DELHI AT NEW DELHI
O.M.P. 490/2010
Reserved on: April 12, 2012
Decision on: May 2, 2012
INDIAN OIL CORPORATION LTD. ..... Petitioner
Through: Mr. M.M. Kalra with
Mr. Kunal Kalra, Advocates.
Versus
HONEYWELL AUTOMATION INDIA LTD. ..... Respondent
Through: Mr. Dhruv Mehta, Senior Advocate
with Mr. Ashish Wad, Ms. Kanika
Bhutani, Mr. Sameer Abhyanikar and
Mr. Sriram Krishna, Advocates.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
02.05.2012
1. The challenge in this petition under Section 34 of the Arbitration and
Conciliation Act, 1996 ('Act') by the Petitioner Indian Oil Corporation Ltd.
('IOCL') is to an Award dated 19th April 2010 of the sole Arbitrator in the
disputes between it and the Respondent Honeywell Automation India Ltd.
[earlier known as Tata Honeywell Ltd. ('THL')] arising out of a Work
Order dated 26th July 1999 in terms of which THL had to undertake the
work of design, manufacturing, testing, supply, installation, commissioning
and maintenance of Terminal Automation System works at the Jalandhar
Terminal of IOCL.
2. The stipulated date of commencement of the work was 10th August
1999. The stipulated date of mechanical completion was 9th May 2000 and
the stipulated date for system commissioning was 9th August 2000. Thus
the total period of completion of the work was 12 months.
3. According to the Respondent, the execution and mechanical completion
of the work got delayed till 20th December 2000 i.e. by 7 months and 11
days, as the work of other contractors engaged by the Petitioner was not
complete and due to non-availability of the site fronts and specific works
left incomplete by ICOL's other contractors. The other contractors, upon
the completion of whose activities the Respondent's progress of work was
dependent, could not complete their work earlier than December 2000.
4. The Respondent's grievance was that while those contractors were given
extension of time ('EOT') by IOCL, the Respondent was not. Further, even
for the extra work awarded to it, including re-working of 42 MOVs out of
the 100 MOVs in the pump house manifold area as late as on 4th December
2000, the Respondent was not given EOT for completion, although payment
for the additional/extra work was released. According to the Respondent
even after the stipulated period of mechanical completion expired on 9th
May 2000 IOCL directed it to execute extra work with variation and extra
items. It executed work worth Rs.479 lakhs up to May 2000 which was
92% of the total value of the work. However, the balance 8% work could
not be completed for reasons beyond the control of the Respondent.
5. The Respondent contended that IOCL had delayed payment for supplies
and services rendered by the Respondent. Mechanical completion was
achieved by the Respondent on 23rd December 2000. However, IOCL
failed to provide the clean product for carrying out calibration and stamping
of the meters. The Respondent further submitted that IOCL failed to
provide the requisite number of tank trucks for the trial runs and also failed
to provide the working conditions for proper operation of
instruments/systems. According to the Respondent, the system was handed
over by it to IOCL on 7th December 2001 after fulfilling all obligations.
However, IOCL withheld from the 7th Revised Running Bill a sum of
Rs.65,49,325 as provisional liquidated damages ('LD'). The Respondent
claims to have got watch and ward and other establishment at the site
during the extended period thereby suffering a loss of Rs.23,33,900. It
claimed Rs.62.50 lakhs being the loss suffered on account of its resources
remaining idle during the extended period of contract. It also claimed
interest and costs.
6. IOCL in its response denied the allegations. It was contended that it was
the Respondent who was responsible for the delay in the completion of the
work. The Respondent had admitted to this fact when it sought EOT till 30th
October 2000. IOCL contended that the Respondent was negligent in
executing the work. Barring the fronts for erection/installation of only FCU
for MOV, rest of the fronts were available for carrying out the work. The
non-completion of 8% of the work was due to the Respondent's own lapse
and negligence. Provisional LD was recovered "keeping in view the fact
first the complete case should be studied before levying the final LD".
7. On the basis of the pleadings of the parties the learned Arbitrator framed
the following issues:-
"(1) Whether the claimant are estopped from claiming the claims as claimed
in the claim petition in view of its accepting the payment of bills in full and
final settlement of claims?
(2) Whether the claimant is entitled to refund of liquidated damages of
Rs.65,49,325 as claimed by it as Claim No.1 in the statement of claim. If
yes, to what extent?
(3) Whether the claimant is entitled of sum of Rs.23,33,900/- as claimed by
it as extra cost incurred by it as claimed in Claim No.2 in the claim petition.
If yes, to what extent?
(4) Whether the claimant is entitled to claim and receive amount of
Rs.62,50,000 on account of idling charges as claimed by the claimant in
Claim No.3 in the claim petition. If yes, to what extent?
(5) Whether the claimant is entitled to claim and get interest @ 18% p.a. as
claimed by it?
(6) Whether the claimant is entitled to sum of Rs.2,50,000 towards cost of
arbitration and litigation, as claimed by it?"
8. The conclusions of the learned Arbitrator in the impugned Award on
each of the issues were as under:-
(i) It could not be said that on account of the endorsements on the 7th
Revised RA Bill or final bill the Respondent had accepted the withholding
of the LD amount.
(ii) Since the Respondent was not entirely responsible for the delay", the
contributing factors were lack of actions on the part of IOCL and/or its
contractors.
(iii) The levy of LD on the Respondent could not be sustained. Holding the
issue in favour of the Respondent it was opined that the Respondent was
entitled to a refund of Rs.65,49,325 which had been deducted from his 7th
Revised RA Bill as provisional LD.
(iv) In the absence of any documentary proof provided by the Respondent
issues No. 3 and 4 were decided against the Respondent.
(v) Under Issue No.5, the learned Arbitrator awarded interest at 9% per
annum on the awarded amount from the date the amount was withheld till
realization.
9. Mr. M.M. Kalra, learned counsel for the Petitioner first submitted that
the learned Arbitrator brushed aside the documentary proof which showed a
clear admission on the part of the Respondent that it was responsible for the
delay in completion of the work. The material which was required to be
fixed and fitted at the site did not reach the site in time. Reference was
made to the minutes of the meeting held on 21st August 2000 (RW1/6) in
which it was recorded that in spite of repeated requests by the Petitioner by
letters dated 31st May 2000, 2nd June 2000, 23rd June 2000 and 3rd August
2000 the Respondent had not adhered to the dates agreed by its
representatives for the completion of the balance jobs. It is next contended
that the learned Arbitrator mis-conducted the proceedings by ordering
refund of LD without examining the letter dated 13th September 2000
(Exhibit RW1/7) in which the Respondent had admitted that they had
started manufacturing of additional chassis console for TFMS. It was stated
that 85% of I&C activity was completed. The Respondent had sought EOT
till December 2000. This was the clear admission of its inability to
complete the work and of not having sufficient material and manpower at
the site. No engineer had been sent for software testing despite various
requests by IOCL. There was therefore a violation of Sections 21, 28 and
31(3) of the Act by the learned Arbitrator. It is pointed out that the
Respondent had accepted the payment against the 7th Revised RA Bill, from
which LD was deducted, without any protest. Reliance is placed on Oil
and Natural Gas Corporation v. Wig Brothers Builders and Engineers
Private Limited (2010) 13 SCC 377 to justify the imposition of the LD on
the Respondent in terms of the contract. The award of interest was also
assailed.
10. Mr. Dhruv Mehta, learned senior counsel for the Respondent contended
that the scope of interference with the impugned award under Section 34 of
the Act was limited. None of the grounds under Section 34 were attracted.
The Award could not be said to be suffering from any patent illegality. He
pointed out that there was no plea raised by the Petitioner under Section 34
of the Act that the finding of the learned Arbitrator that there was no
mention of any deduction of the LD in the final bill was erroneous. What
was withheld in the 7th Revised RA Bill was LD on provisional basis. Even
according to IOCL the case had to be studied further before the final bill
was prepared. However, that was never done. The plea that there was
complete satisfaction that the Respondent having accepted full and final
payment and therefore being estopped from protesting against the
withholding of the LD was not raised by IOCL before learned Arbitrator.
He pointed out that against the withholding of the LD the Respondent had
in fact written four letters dated 23rd June 2001, 16th August 2001, 26th
September 2001 and 1st October 2001. On the issue of delay Mr. Mehta
pointed out that if the delay was in fact caused by IOCL it was not justified
in withholding any sum from the bills. The fact that the EOT could be
granted in terms of the contract showed that time was not the essence of
contract. The passing observation that the Respondent could have also
contributed the delay did not take away from the main finding that IOCL
was responsible for delay in completing the work.
11. This Court has perused the "9th and Final" bill, a photocopy of which as
appended to the petition is illegible. If anything was written in the right
hand column of the payment certificate it is not visible at all. In any event
there is no clear indication of reduction of LD in the said bill. The copy of
the 7th Revised RA Bill, however, is more legible. It was dated 24th March
2001 and shows deduction of a provisional LD of Rs.66,94,325. The
remarks appended thereto by the Respondent reads: "I further certify the
amount of payment I shall be receiving on this bill will be full and final of
our claims, in respect of this work (except the refund of security deposit)
and we have no claim against the Corporation with regard to this work
order (applicable only in case of final bill)". As correctly observed by the
learned Arbitrator the above certification indicates the acceptance of the
amount but not of acceptance of any reduction of the provisional LD.
12. In the written statement of IOCL before the learned Arbitrator in para
1.9 it was stated as under:-
"That this paragraph of the claim petition is wrong and is denied. Provisional LD was recovered keeping in view the fact that first the complete case should be studied before providing the final LD."
13. There is nothing to indicate that IOCL first completely studied the case
before withholding the LD against the final bill. Therefore, by accepting
the payment of the final bill the Respondent did not waive its right to
challenge the withholding of the LD amount from the 7th Revised RA Bill.
14. The learned Arbitrator has in para 41 of the Award held that "in the
final bill no LD is indicated". This finding has not been challenged by
IOCL. It has not produced any document to dispel of the above finding of
the fact. This Court is unable to find any error having been committed by
the learned Arbitrator in holding that the Respondent was not estopped from
maintaining its claims only because it had accepted payment of bills in full
and final settlement of the claims.
15. At this stage this Court would like to refer to the recent decision of the
Supreme Court in National Insurance Company Limited v. Boghara
Polyfab Private Limited (2009) 1 SCC 267 where the law was explained as
under:
"52. Some illustrations (not exhaustive) as to when claims are arbitrable and when they are not, when discharge of contract by accord and satisfaction are disputed, to round up the discussion on this subject are:
(iii) A contractor executes the work and claims payment of say Rupees Ten Lakhs as due in terms of the contract. The employer admits the claim only for Rupees six lakhs and informs the contractor either in writing or orally that unless the contractor gives a discharge voucher in the prescribed format acknowledging receipt of Rupees Six Lakhs in full and final satisfaction of the contract, payment of the admitted amount will not be released. The contractor who is hard-pressed for funds and keen to get the admitted amount released, signs on the dotted line either in a printed form or otherwise, stating that the amount is received in full and final settlement. In such a case, the discharge is under economic duress on account of coercion employed by the employer. Obviously, the discharge voucher cannot be considered to be voluntary or as having resulted in discharge of the contract by accord and satisfaction. It will not be a bar to arbitration.
................
(v) A claimant makes a claim for a huge sum, by way of damages. The respondent disputes the claim. The claimant who is keen to have a settlement and avoid litigation, voluntarily reduces the claim and requests for settlement. The respondent agrees and settles the claim and obtains a full and final discharge voucher. Here even if the claimant might have agreed for settlement due to financial compulsions and commercial pressure or economic duress, the decision was his free choice. There was no threat, coercion or compulsion by the respondent. Therefore, the
accord and satisfaction is binding and valid and there cannot be any subsequent claim or reference to arbitration."
16. The above legal position was also noted by this Court in Gail (India)
Limited v. Hindustan Construction Corporation 2012 II AD (DELHI) 48.
17. In light of the above decisions it is not possible to agree with the
contention of IOCL that in the facts of the present case there was accord
and satisfaction of the claims of the Respondent and that its claims were not
arbitrable. The letters dated 23rd June 2001, 16th August 2001, 26th
September 2001 and 1st October 2001 and 6th November 2001 do indicate
the protest by the Respondent about deduction of the provisional LD. In the
circumstances, the decision of the learned Arbitrator as regards Issue No.1
calls for no interference.
18. As regards Issue No.2 the learned Arbitrator has discussed the evidence
at great length and has also noticed the legal position. If one reads the
Award as a whole then it is apparent that the finding of the learned
Arbitrator is that the Respondent cannot be held responsible for the delay.
Although in Paras 62 and 63 of the impugned Award there are observations
to the effect that there may have been "some contributory factors", for the
delay, the Award in fact answers Issue No.2 in favour of the Respondent
and holds it entitled to refund of the LD deducted. The attempt by learned
counsel for IOCL to urge that both parties were equally responsible for the
delay is not borne about by the above observations. As explained in Para 4
of the decision in Oil and Natural Gas Corporation v. Wig Brothers
Builders and Engineers Private Limited (2010) 13 SCC 377 this Court is
not expected to re-appreciate the evidence on record as an appellate Court.
19. The decision to grant the Respondent interest at 9% p.a. on the awarded
amount from the date of the withholding of the amounts till date of
realization does not suffer from any illegality and does not call for
interference by this Court.
20. For the above reasons it is held that no grounds have been made out for
interference with the impugned Award of the learned Sole Arbitrator.
21. The petition is dismissed with costs of Rs.25,000 to be paid by the
Petitioner to the Respondent within four weeks.
S. MURALIDHAR, J.
MAY 2, 2012 mm
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!