Citation : 2012 Latest Caselaw 2853 Del
Judgement Date : 1 May, 2012
IN THE HIGH COURT OF DELHI AT NEW DELHI
(Not reportable)
CS (OS) 1242/1991 & IA No.13851 of 1992
Reserved on: April 19, 2012
Decision on: May 1, 2012
UNION OF INDIA ..... Plaintiff
Through: None.
Versus
PEECO HYDRAULIC PVT LTD. ..... Defendant
Through: Mr. Girish Aggarwal and
Mr. Y.R. Sharma, Advocates.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
01.05.2012
1. These are objections by Peeco Hydraulic Private Limited ('PHPL')
under Sections 30 and 33 of the Arbitration Act, 1940 ('Act') to an Award
dated 18th January 1991 passed by the sole Arbitrator in the disputes
between the parties arising out of an acceptance of a tender by the
Directorate General of Supplies & Disposal ('DGS&D') issued on 23rd
June 1980 whereunder PHPL was to supply an Oil Hydraulic Spring
Testing Machine.
2. According to the objector, Clause 14 of the tender documents
contained a question whether the tenderer agreed to sole arbitration by an
officer of Ministry of Law to be appointed by the DGS&D as provided in
Clause 24 of the General Conditions of Contract ('GCC') Form DGS&D-
68 (Revised). It was stated that omission to answer the question would be
deemed as acceptance to the Clause. PHPL answered the question in the
negative.
3. On 7th August 1992, the DGS&D cancelled the tender and invited fresh
tenders in which PHPL again was the lowest. DGS&D reinstated the old
tender of 30th December 1982 and cancelled it again on 14th June 1983.
4. One of the objections to the impugned Award by PHPL is that
inasmuch as it never consented to the arbitration by an officer appointed
by the Ministry of Law, the arbitration proceedings were bad in law. This
issue came to be decided against PHPL by this Court by an order dated
11th January 2002 of this Court. It was held in paras 17 and 18 as under:-
"17. The conclusions therefore from the aforesaid are clear and unambiguous. Under Section 7 of the Contract Act the acceptance of the offer has to be absolute but need not be conditional. However, if there is a conditional or counter offer and it is acted upon without protest and the acceptance has been conveyed subject to that, to which there is no dispute raised, this amount to a concluded contract.
18. With this backdrop one can refer back to the present case again. Even if while filling the document for tender the objector had stated that he does not agree
to arbitration but still when the contract was accepted and conveyed it contained an arbitration clause. Admittedly, the objector at no stage protested to it and acted on the same. In that view of the matter once acceptance contained an arbitration clause to which there was no protest an attempt was made to complete the contract. The conclusion would be that it was an accepted contract with the said stipulation pertaining to the agreement. It is too late in the day to rake up this plea at this stage in court for the first time. It must therefore be held in the peculiar fact of the present case that there was an arbitration agreement between the parties and it is decided accordingly."
5. Aggrieved by the above order, PHPL filed FAO (OS) No.53 of 2002
in which there was a stay granted of the further proceedings in the suit.
The appeal was disposed of by the Court ultimately on 5th January 2012
with the following order:
"After arguing for some time, learned counsel for the appellant does not press the appeal and the application and states that he will argue his objections on merit to the award before the learned Single Judge.
Dismissed as withdrawn.
Interim order dated 14.02.2002 stands vacated.
Parties to appear before the learned Single Judge in suit no.1242/1991 on 23.01.2012."
6. Consequently, the above objection to the impugned Award no longer
survives.
7. It is next submitted on behalf of PHPL that the first Arbitrator (earlier
to the one who passed the impugned Award) had passed on order dated
27th September 1989 adjourning the proceedings sine die after noting that
the time for pronouncing the Award had expired and that parties had to
seek extension of time. That Arbitrator continued till his resignation on
26th July 1990. It is submitted that thereafter only a competent court could
have appointed an arbitrator and not the persona designata in terms of
Clause 24 of the conditions of the Contract. Moreover, PHPL never
mutually agreed to extend the time as was contemplated in the order dated
27th September 1989.
8. In reply to the above averments, it is stated by the Union of India that
the Arbitrator succeeded the earlier Arbitrator who passed the order on
27th September 1989 was legally appointed was under the terms and
conditions of the contract. As regards the consent of the parties to the
extension of time, it is simply averred by the Union of India "it is only
with the mutual consent of the parties the arbitration proceedings
continued beyond a specified time and cannot be said that the defendant
never mutually agreed." This, of course, is vehemently denied in the
rejoinder where PHPL has reiterated that it had never consented to the
extension of time for passing the Award.
9. According to PHPL, the events that took place after the resignation of
Mr. R.K. Gupta as Arbitrator on 26th July 1990 were as under:
"1.37 That Shri C. Achuthan, the learned Arbitrator entered upon reference on 27th of September 1990 and it appears that ignoring the order dated 27th September 1989 passed by Shri R.K. Gupta as the Sole Arbitrator and without complying with the conditions laid down therein, directed the Defendant to file the counter-statement before him.
1.38 It is pertinent to note that the Defendant had never agreed for the mutual extension of time nor the Plaintiff had obtained any extension of time from a civil court nor for the appointment of Shri C. Achuthan as the Sole Arbitrator and the appointment of the learned Arbitrator remained without jurisdiction and unilateral."
10. In para 1.39 of the objections, it is stated by PHPL that a letter was
sent on 26th October 1990 by PHPL to the Arbitrator by registered post
stating that it had never agreed to extension of time. Another letter was
sent on 7th November 1990 to the learned Arbitrator by PHPL by
registered post. Copies of both letters have been enclosed with paras 1.39
and 1.41. The specific averment in para 1.42 is that the above
communications were ignored by the Arbitrator who fixed the hearing for
17th January 1991. Thereafter, on 18th January 1991 the learned Arbitrator
passed the impugned Award.
11. In reply to the above paragraph there is only a bald denial by the
DGS&D. It is asserted that the appointment of Shri Achuthan was legal
and that he had "every right to process the case the way it was considered
appropriate by him." Receipt of the two letters of PHPL by registered
post by the Arbitrator is not denied. The reply to both paras 1.39 as well
as 1.41 is that "this para needs no rejoinder (sic reply) it being a matter of
record".
12. The above submissions have been considered. The arbitral
proceedings were under the 1940 Act. The parties had to seek extension
of time for the Arbitrator to pass the Award. There is absolutely nothing
on record to show that the parties agreed to any extension of time. On the
other hand, the order dated 27th September 1989 passed by the earlier
Arbitrator makes the position clear. It reads as under:
"Shri Lal submits that the case should be proceeded with ex-parte as the contractor has not appeared for today's hearing. I am afraid, in the absence of a notice to proceed with ex-parte. Moreover, the claim statement has been filed by the Union of India only on 25.9.1989.
It is stated by Shri Lal that a copy of the statement is
being sent to the contractor. In the circumstances, it will be against all cannons of justice to proceed ex- parte.
Four months period is expiring on 30.9.89. Unless the parties agree for enlargement of the time or the claimant gets the time enlargement from the Civil Court, the case stands adjourned sine die."
13. The time fixed under Clause 3 of the Schedule to the Arbitration Act
1940 can be extended only by the Court and not by parties. The Arbitrator
had no jurisdiction to make an Award after the expiry of the time for
making the Award unless the parties sought extension by applying to the
Court under Section 28. [See H.K. Wattal v. V.N. Pandya (1973) 2 SCC
510 and State of Punjab v. Hardyal (1985) 2 SCC 629]. With there being
no consent of the parties for the extension of time, and no order of the
Court extending the time for making the Award, the entire arbitration
proceedings before the succeeding Arbitrator, Mr. Achuthan, stood
vitiated in law. The specific objection to this effect raised by PHPL
before the learned Arbitrator by two letters, as noted above, were not dealt
with by him. On this short ground, the impugned Award dated 18th
January 1991 is set aside.
14. The objections of PHPL in IA No.13851 of 1992 are accordingly
allowed.
15. The suit is disposed of in above terms.
S. MURALIDHAR, J MAY 1, 2012 s.pal
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!